Building
Systems
PRECAST COMPONENT
Ground Floor Preparation
❑ Preparation of
foundation
❑ Casting of In-situ
column stumps
/ ground beams
with protruding
starter bars
ready to
receive Precast
Columns
❑ Before start
precast column
installation,
installer will mark
control line for
precast column
PRECAST COMPONENT
Column Installation
Installer will install require number of shim to make sure bottom of column level is correct
PRECAST COMPONENT
Protruding Column Installation
Starter Bars
❑ Installer
will install
require number
Precast
Column of shim to make
sure bottom of
column level is
correct
❑ Precast column
is slotted into
protruding starter
bar
PRECAST COMPONENT
Column Installation
Column is propped to the
required level and verticality
Propping
Of
Columns
PRECAST COMPONENT
Column Installation
Grouting
Of Starter
Column is
Bars
grouted
with high
strength
non-shrink Grouting
Of Starter
grout Bars
PRECAST COMPONENT
Beam Installation
Precast
Beam
PRECAST COMPONENT
Hollow Core Slab Installation
Precast Hollow Core
Slab is lifted onto Precast
Column
position by using
clamper or lifting belt
Precast
Precast Hollow
Beam Core Slab
PRECAST COMPONENT
Associated Works
Shear key joint is grouted
PRECAST COMPONENT
Associated Works
Beam top
concrete
casting
❑ Installation
of beam top rebar
❑ Beam top concrete casting
PRECAST COMPONENT
Associated Works
M&E M&E
services services
laying