Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
.
13.8kVLL VT Ratio = 14,440 / 120 = 120
a
Van=Vag
n=g ground a
vag=0
Van= -Vng
c b
Vbn=Vbg Vbn=Vbg Vcg Vbg
n
High
Impedance c b
Ground
Vcn Vbn
Software converts
(66.4V) voltages to
LG (66.5V)
LL (115V) quantities
Ipri nom = MVA*106 / 3*VLL
Ipri nom = 125*106/(1.732*13800)
Ipri nom = 5,230 A
Ct ratio is denoted as RC
RC = 8000/5 = 1600
Isec nom = I pri nom/RC
Isec nom = 5230/1600
Isec nom = 3.27 A
(used with 21, 51V)
Rating = 13,800 V
1.00
0.75
0.50
0.25
V
Nameplate
IS
VK > VS
•
100
Alarm Settings:
Definite Element #2
Pickup = 106% Definite time element #1
Time Delay = 3 sec Pickup = 135%
10
Time Delay = 4 sec
0.1
100 105 110 115 120 125 130 135 140 145
Values shown above are from
generator test sheet
•
•
Egen
I fault 12.75
MPU 6.67
I pickupVgen (%) 4.9(0.39)
MPU = 6.67
•
•
•
•
E gen 100
I MinFault 0.46 pu
Xd Xt 206.8 10
•
- loadability
- load swings
The fault appears farther than the actual location due to infeed.
Transformer Transformer Delta- Transformer Delta-
Direct Connected AC Connected AB Connected
•
•
•
•
•
Z2
Z1
85o
Z2 reach at
RPFA 1.64 31.8o)
ImpedanceLocus
1.0pu During Loss of Field Zone 1
Impedance Locus
Zone1
1.1Xd During Loss of Field
Xd
Zone2
-X
0
20
Overexcited
Real Power into the System
Reactive Power into the Generator
0
0 20 40 60 80 100 120 140
Underexcited
-20
MEL GCC
-40
SSSL
MEL
GCC
-60
SSSL
-80
10
MEL
GCC
SSSL
0
-30 -20 -10 0 10 20 30
-10
Zone 2 Zone 1
-20
-30
-40
-50
20
Overexcited
Real Power into the System
0
0 20 40 60 80 100 120 140
-20 Underexcited
GCC
MEL
Reactive Power into the Generator
SSSL
-40
MEL
GCC
-60 SSSL
Zone 2
-80
-100
-120 Zone 1
-140
x
x
10
Directional Element
0
-30 -20 -10 0 10 20 30
Zone 2
Zone 1
MEL -10
GCC
SSSL
-20
Dir Element
X -30
0 10
-10
-40
-50
20
Overexcited
Reactive Power into the Generator
Underexcited
-20
MEL GCC
Zone 2
-40
SSSL
MEL
GCC
-60
SSSL
Zone1
-80
•
•
•
•
Ensure fuse loss and
breaker position (52b)
are set to block.
104
600
92
120
127
600
173
•
•
•
•
•
Field Insulation
Real-Time Monitoring
-
-
Brushes
- Excitation systems have
capacitors installed between the
+/- field and ground for shaft
voltage and surge suppression. To
minimize this effect, injection
frequency may be adjusted
downwards at the expense of
response time.
Brush Voltage
- 64B pickup = unfaulted voltage + 0.5 (faulted brush voltage-
unfaulted brush voltage)
- 64B delay = 600 cycles