Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2 OTHERS - - - -
SUB - TOTAL (HEALTH AND SAFETY) - - -
V. SITEWORK-LAND DEVELOPMENT
1 Site Preparation - - - -
2 Earthworks & Retaining Structures - - - -
3 Site Drainage - - - -
4 Concrete Curbs, Gutters and Paved Walks - - - -
5 Road and Parking - - - -
6 Site Electrical and Transformers - - - -
7 Site Water Supply & Service Entrance - - - -
8 Termite Proofing - - - -
9 Integrated Pest Management - - - -
10 Hard Landscaping Permiable Parking - - - -
11 Soft Landscaping - - - -
12 Demobilization & Clearing - - - -
13 OTHERS - - - -
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT) - - -
VI. SITEWORKS-STRUCTURAL
1 Building Layout - - - -
2 Topsoil Stripping and Re-Use - - - -
3 Excavation - - - -
4 Fill/Backfill Compacted - - - -
5 Termite Treatment - - - -
6 OTHERS - - - -
SUB - TOTAL (SITEWORKS-STRUCTURAL) - - -
VII. CONCRETE WORKS
1 Forms, Scaffoldingd & Accessories - - - -
2 Footings - - - -
3 Grade Beams / Footing Tie Beams - - - -
4 Columns, Beams, Girder - - - -
5 Shear / Lower Ground Walls - - - -
6 Suspended Slabs - - - -
7 Lower Ground Floor Slabs & Slabs on Fill - - - -
8 Stairs - - - -
9 Cisterns (Potable & Rain Water) - - - -
10 Concrete Gutters, Parapet and Ledges - - - -
11 Equipment Pads - - - -
12 OTHERS - - - -
SUB - TOTAL (CONCRETE WORKS)
VIII. MASONRY WORKS
1 CHB & Other Masonry Walls - - - -
2 Cast Stone Sills, Thresholders, Walls - - - -
3 OTHERS - - - -
SUB - TOTAL (MASONRY WORKS) - - -
IX. METAL WORKS
1 Structural Steel
2 Misc. Structural Steel - - - -
3 Welding & Fasteners - - - -
4 Stainless Steel Hand & Grab Rail - - - -
5 Misc. Stainless Steel - - - -
6 Factory-Applied Metal Coatings - - - -
7 Aluminum Tube Railings - - - -
8 Aluminum Equipment Screen - - - -
9 Fiber Glass Grating - - - -
10 Architectural Joint Systems - - - -
11 OTHERS - - - -
SUB - TOTAL (ARCHITECTURAL) - - -
X. WOOD & PLASTIC
1 Miscellaneous Rough Lumber - - - -
2 Plastic Laminate - - - -
3 Wood Laminate - - - -
4 Sink Counters - - - -
5 Ground Floor Reception and Security Desk - - - -
6 OTHERS - - - -
SUB - TOTAL (PAINTING WORKS) - - -
XI. THERMAL & MOIST PROTECTION
1 Slab, Deck & Gutter Waterproofing -
2 Wall Waterproofing - - - -
3 Cistern Epoxy Waterproofing - - - -
4 Roofing Insulation - - - -
5 Roofing Materials and Accessories - - - -
6 Sheet Metal Flashing and Trim - - - -
7 Fluid-Applied Membrane Air Barriers - -
8 Sheet MetalRoofing - - - -
9 Exterior Metal Wall System - - -
10 Sprayed Fire-Resistive Materials - - -
11 Through-Penetration Firestop System - - - -
12 Fire-Resistive Joint System - - - -
13 Joint Sealant - - - -
14 Expansion Joint Covers - - - -
15 OTHERS - - -
SUB - TOTAL (THERMAL & MOIST PROTECTION) - - -
XII. DOORS AND WINDOWS
1 Metal Doors & Windows - - -
2 Metal Doors & Window Frames - - -
3 Stainless Steel Frames - - -
4 Interior Aluminum Frames - - -
5 Interior Glass Partition - - -
6 Flush Doors - - -
7 Access Doors and Frames - - -
8 Aluminum-Framed Entrance Door - - -
9 Aluminum Windows - - -
10 Hardware - - -
11 Door Hardware - - -
12 Finish Hardware - - -
13 Glased Aluminum Curtain Walls - - -
14 OTHERS - - -
SUB - TOTAL (DOORS AND WINDOWS) - - -
XIII. FINISHES
1 Plaster Walls - - -
2 FCB Ceiling on Light Gauge Metal Frame - - - -
3 Gypsum Wall Boards on FCBs on Light Guage - - - -
Metal Frame
4 FCB Wall Boards on Light Guage Metal Frames - - - -
1 Ventilation System - - - -
2 Dehumidification Systems - - - -
3 Floor Mounted ACU - - - -
4 Split Type ACU - - - -
5 Exhaust Fans - - - -
6 Centrifugal Fans - - - -
7 Computer Room ACU
8 OTHERS
SUB - TOTAL (VENTILATION SYSTEM (EXHAUST AND SUPPLY AIR) - -
XIV. ELECTRICAL WORKS
1 Overcurrent Protective Device Coordination - - - -
7 Electrical Identification - - - -
8 Conductors and Cables - - - -
9 Raceways - - - -
10 Cable Trays - - - -
11 Wiring Devices - - - -
12 Lighting Control - - - -
13 Package Engine Generator - - - -
14 Transient Voltage Suppression - - - -
15 Enclosed Swithes and Circuit Breakers - - - -
16 Transfer Switches - - - -
17 Electrical Distribution System - - - -
18 Switchboards - - - -
19 Panelboards - - - -
20 Enclosed Bus Assembles - - - -
21 Transformer - - - -
22 Fuses - - - -
23 Interior Lighting - - - -
24 Exterior Lighting - - - -
25 Voice and Data Communications (intercoms) - - - -
26 Security Systems - - - -
27 Fire Alarms - - - -
28 Pipes Rough-ins - - - -
29 OTHERS - - - -
SUB - TOTAL (ELECTRICAL WORKS) - - -
TOTAL COST per Unit
TOTAL PROJECT COST
Guard's podium 1 pcs. Laminated Woosd Finish
Multi-seater waiting area leather bench 2 pcs. Leather Finish
High Chair for guard 1 pcs. Synthetic Leather
Storage Cabinet 1 pcs.
OTHERS pcs.
Reception countertop, z-straight/multi-level 1 pcs. Laminated Woosd Finish
High chair for receptionists 3 pcs. Synthetic Leather
Storage Cabinet 1 pcs.
OTHERS pcs.
a. b. c. Staff Desk 2 pcs. Laminated Wood Finish
b.
Midback Chair 2 pcs. Synthetic Leather
d.
Filing Cabinet/s pcs.
Clinic Bed 1 pcs.
OTHERS pcs.
4 ADMINISTRATION DIVISION
a. CHIEF ADMIN. OFFICER Carpeted Floor Finish
1 Executive Table
1 pc. Laminated Wood Finish
2 Executive Chair
3 Guest Chair 1 pc. Synthetic Leather
4 Staff Desk
5 Midback Chair 2 pcs. Synthetic Leather
6 Filing Cabinet/s 2 pcs. Laminated Wood Finish
7 OTHERS
2 pcs. Synthetic Leather
2 Executive Chair
3 Guest Chair
4 Staff Desk
5 Midback Chair
6 Filing Cabinet/s
7 OTHERS
a. CONFERENCE ROOM
1 Conference Table
1
2 Midback Chair
3 Projector 10
4 Projector Screen
6 OTHERS 1
1
II.
b. SECRETARY
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Finish
Finish
nish
Finish
Finish
Finish
nish
Finish
with arm rest
PROJECT :
LOCATION :
OWNER :
SUBJECT :
DATE :
1 Detailed A&E Design Fee Including specialized consultant for Laboratory Systems lot
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVEYS AND TESTS
1 Geodetic Survey lot
2 Soil Foundation Investigation lot
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS
1 Mobilization/ Demobilization lot
2 Permits and Licenses lot
3 Bonds & Insurances lot
4 Temporary Facilities lot
5 Temporary Utilities lot
6 Safety & Security lot
7 Material Testing lot
8 Construction Waste Management lot
9 As-Built Plans lot
10 Project Billboard lot
11 Site Management lot
SUB - TOTAL (GENERAL REQUIREMENTS)
IV. SITEWORK-LAND DEVELOPMENT
1 Site Preparation m²
2 Earthworks & Retaining Structures lot
3 Site Drainage lot
4 Concrete Curbs, Gutters and Paved Walks lm
5 Road and Parking m²
6 Termite Proofing lot
7 Integrated Pest Management lot
8 Clearing m²
9 Perimeter Fence m²
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT)
V. SITEWORKS-STRUCTURAL
1 Building Layout m²
2 Topsoil Stripping and Re-Use m²
3 Excavation m³
4 Fill/Backfill Compacted m³
5 Termite Treatment m²
6 OTHERS
SUB - TOTAL (SITEWORKS-STRUCTURAL)
CODE ITEM/DESCRIPTION QTY UNIT
Exterior Masonry
6" CHB m²
Interior Masonry
6" CHB m²
4" CHB m²
2 Stiffeners lm
3 Canopy m²
4 Ledge lm
3 Railings
Stair Railings lm
Ramp Railings lm
4 Grab Rail set
5 Countertops m²
6 OTHERS
Furnishings (see separate list) lot
HLURB Logo/Name, Bldg Name lot
Wayfinding & Room Signage System lot
Landscape m²
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
I. DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES
1 Detailed A&E Design Fee Including specialized consultant for Laboratory Systems 1.00 lot - - 390,000.00
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVEYS AND TESTS
1 Geodetic Survey 1.00 lot - - 75,000.00
2 Soil Foundation Investigation 1.00 lot - - 150,000.00
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS
1 Mobilization/ Demobilization 1.00 lot - - 100,000.00
2 Permits and Licenses 1.00 lot - - 213,003.20
3 Bonds & Insurances 1.00 lot - - 318,500.00
4 Temporary Facilities 1.00 lot 175,000.00 175,000.00 75,000.00
5 Temporary Utilities 1.00 lot 506,000.00 506,000.00 -
6 Safety & Security 1.00 lot - - 176,000.00
7 Material Testing 1.00 lot - - 50,000.00
8 Construction Waste Management 1.00 lot - - 42,000.00
9 As-Built Plans 1.00 lot 70,000.00 70,000.00 30,000.00
10 Project Billboard 1.00 lot 50,000.00 50,000.00
11 Site Management 1.00 lot - - 980,000.00
SUB - TOTAL (GENERAL REQUIREMENTS)
IV. SITEWORK-LAND DEVELOPMENT
1 Site Preparation 210.00 m² - - 50.00 50.00
2 Earthworks & Retaining Structures 1.00 lot - - 15,000.00 15,000.00
3 Site Drainage 1.00 lot - - 30,000.00 30,000.00
4 Concrete Curbs, Gutters and Paved Walks 21.00 lm 900.00 900.00 18,900.00 250.00 250.00
5 Road and Parking 150.00 m² 1,800.00 1,800.00 270,000.00 390.00 390.00
6 Termite Proofing 1.00 lot 3,000.00 3,000.00 3,000.00 6,000.00 6,000.00
7 Integrated Pest Management 1.00 lot 20,000.00 20,000.00 20,000.00 4,000.00 4,000.00
8 Clearing 630.00 m² - - 50.00 50.00
9 Perimeter Fence 44.55 m² 1,100.00 49,005.00 51.00 200.00
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT)
V. SITEWORKS-STRUCTURAL
1 Building Layout 1,229.03 m² - - 50.00 50.00
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
2 Topsoil Stripping and Re-Use 630.00 m² - - 35.00 35.00
3 Excavation 250.00 m³ - - 240.00 240.00
4 Fill/Backfill Compacted 378.00 m³ 250.00 250.00 94,500.00 160.00 160.00
5 Termite Treatment 630.00 m² 25.00 25.00 15,750.00 50.00 50.00
6 OTHERS
SUB - TOTAL (SITEWORKS-STRUCTURAL)
VI. CONCRETE WORKS
1 Forms, Scaffoldings & Accessories 2,408.00 m² 400.00 400.00 963,200.00 240.00 240.00
2 Footings - - -
Concrete 32.56 m³ 5,367.50 5,367.50 174,765.80 490.00 490.00
Rebar 1,965.00 kg 40.00 40.00 78,600.00 7.00 7.00
GI Wire 54.00 kg 80.00 80.00 4,320.00 7.00 7.00
3 Grade Beams / Footing Tie Beams - - -
Concrete 24.00 m³ 5,367.50 5,367.50 128,820.00 490.00 490.00
Rebar 4,200.00 kg 40.00 40.00 168,000.00 7.00 7.00
GI Wire 116.00 kg 80.00 80.00 9,280.00 7.00 7.00
4 Columns, Beams, Girder - - -
Concrete 100.00 m³ 5,367.50 5,367.50 536,750.00 490.00 490.00
Rebar 29,457.00 kg 40.00 40.00 1,178,280.00 7.00 7.00
GI Wire 810.00 kg 80.00 80.00 64,800.00 7.00 7.00
5 Shear / Lower Ground Walls - - -
Concrete 8.50 m³ 5,367.50 5,367.50 45,623.75 490.00 490.00
Rebar 1,180.00 kg 40.00 40.00 47,200.00 7.00 7.00
GI Wire 30.00 kg 80.00 80.00 2,400.00 7.00 7.00
6 Suspended Slabs - - -
Concrete 107.00 m³ 5,367.50 5,367.50 574,322.50 490.00 490.00
Rebar 16,900.00 kg 40.00 40.00 676,000.00 7.00 7.00
GI Wire 464.00 kg 80.00 80.00 37,120.00 7.00 7.00
7 Lower Ground Floor Slabs & Slabs on Fill - - -
Concrete 45.00 m³ 5,367.50 5,367.50 241,537.50 490.00 490.00
Rebar 2,204.00 kg 40.00 40.00 88,160.00 7.00 7.00
GI Wire 60.00 kg 80.00 80.00 4,800.00 7.00 7.00
8 Stairs - - -
Concrete 14.00 m³ 5,367.50 5,367.50 75,145.00 490.00 490.00
Rebar 2,420.00 kg 40.00 40.00 96,800.00 7.00 7.00
GI Wire 60.00 kg 80.00 80.00 4,800.00 7.00 7.00
9 Watertank - - -
Concrete 14.00 m³ 5,367.50 5,367.50 75,145.00 490.00 490.00
Rebar 1,188.00 kg 40.00 40.00 47,520.00 7.00 7.00
GI Wire 29.00 kg 80.00 80.00 2,320.00 7.00 7.00
10 Equipment Pads
Concrete 2.00 m³ 5,367.50 5,367.50 10,735.00 490.00 490.00
Rebar 316.00 kg 40.00 40.00 12,640.00 7.00 7.00
GI Wire
SUB - TOTAL (CONCRETE WORKS) 8.00 kg 80.00 80.00 640.00 7.00 7.00
-
VII. METAL WORKS
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
1 Structural Steel 1.00 lot 526,224.00 526,224.00 526,224.00 105,244.80 105,244.80
75AT/100AF, 2P, 230V ECB 4.00 assy 3,500.00 3,500.00 14,000.00 2,000.00 2,000.00
60AT/100AF, 2P, 230V ECB 7.00 assy 3,500.00 3,500.00 24,500.00 2,000.00 2,000.00
50AT/50AF, 2P, 230V ECB 4.00 assy 2,500.00 2,500.00 10,000.00 2,000.00 2,000.00
40AT/50AF, 2P, 230V ECB 19.00 assy 2,500.00 2,500.00 47,500.00 2,000.00 2,000.00
Pull Box 1.00 assy 8,000.00 8,000.00 8,000.00 3,200.00 3,200.00
Sub Total :
1.0 Conduits & Fittings (Nichi Brand)
80mmØ PVC Pipe 10.00 pc/s 899.00 899.00 8,990.00 359.60 359.60
80mmØ RSC Pipe 20.00 pc/s 3,280.00 3,280.00 65,600.00 1,312.00 1,312.00
80mmØ RSC Coupling 40.00 pc/s 370.00 370.00 14,800.00 148.00 148.00
80mmØ RSC Locknut & Bushing 9.00 pc/s 122.00 122.00 1,098.00 48.80 48.80
80mmØ RSC Elbow 9.00 pc/s 1,486.00 1,486.00 13,374.00 594.40 594.40
50mmØ RSC Pipe 24.00 pc/s 1,580.00 1,580.00 37,920.00 632.00 632.00
50mmØ RSC Coupling 48.00 pc/s 110.00 110.00 5,280.00 44.00 44.00
50mmØ RSC Locknut & Bushing 6.00 pc/s 46.00 46.00 276.00 18.40 18.40
50mmØ RSC Elbow 6.00 pc/s 486.00 486.00 2,916.00 194.40 194.40
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
40mmØ RSC Pipe 5.00 pc/s 1,185.00 1,185.00 5,925.00 474.00 474.00
40mmØ RSC Coupling 10.00 pc/s 85.00 85.00 850.00 34.00 34.00
40mmØ RSC Locknut & Bushing 6.00 pc/s 39.00 39.00 234.00 15.60 15.60
40mmØ RSC Elbow 6.00 pc/s 290.00 290.00 1,740.00 116.00 116.00
32mmØ RSC Pipe 19.00 pc/s 978.00 978.00 18,582.00 391.20 391.20
32mmØ RSC Coupling 38.00 pc/s 73.00 73.00 2,774.00 29.20 29.20
32mmØ RSC Locknut & Bushing 6.00 pc/s 21.00 21.00 126.00 8.40 8.40
32mmØ RSC Elbow 6.00 pc/s 20.00 20.00 120.00 8.00 8.00
Sub Total :
2.0 Wires & Cables (Philflex Brand)
250 mm² THHN Wires 180.00 lm/s 1,310.00 1,310.00 235,800.00 524.00 524.00
80 mm² THHN Wires 98.00 lm/s 431.00 431.00 42,238.00 172.40 172.40
60 mm² THHN Wires 38.00 lm/s 342.00 342.00 12,996.00 136.80 136.80
50 mm² THHN Wires 106.00 lm/s 277.00 277.00 29,362.00 110.80 110.80
30 mm² THHN Wires 166.00 lm/s 172.00 172.00 28,552.00 68.80 68.80
60 mm² TW Wires (G) 113.00 lm/s 342.00 342.00 38,646.00 136.80 136.80
14 mm² TW Wires (G) 82.00 lm/s 75.00 75.00 6,150.00 30.00 30.00
8.0 mm² TW Wires (G) 56.00 lm/s 48.00 48.00 2,688.00 19.20 19.20
Sub Total :
B. LIGHTING LAYOUT
1.0 Conduits & Fittings (Emerald Brand)
20mm dia PVC Pipe 597.00 pc/s 72.00 72.00 42,984.00 28.80 28.80
20mm dia PVC Adapter 2,236.00 pc/s 10.00 10.00 22,360.00 4.00 4.00
20mm dia PVC Locknut & Bushing 2,236.00 pc/s 15.00 15.00 33,540.00 6.00 6.00
20mmØ PVC Elbow 895.00 pc/s 25.00 25.00 22,375.00 10.00 10.00
15mm dia Flexible Metallic Conduit 441.00 lm/s 20.00 20.00 8,820.00 8.00 8.00
15mm dia Flexible Metallic Straight Connector 678.00 pc/s 10.00 10.00 6,780.00 4.00 4.00
Junction Box 424.00 pc/s 50.00 50.00 21,200.00 20.00 20.00
Utility Box 103.00 pc/s 40.00 40.00 4,120.00 16.00 16.00
Square Box 32.00 pc/s 75.00 75.00 2,400.00 30.00 30.00
Sub Total :
2.0 Wires & Cables (Philflex Brand)
3.5 sq.mm. THHN 4,658.00 lm/s 22.00 22.00 102,476.00 8.80 8.80
3.5 sq.mm. THHN (G) 2,329.00 lm/s 22.00 22.00 51,238.00 8.80 8.80
Sub Total :
3.0 Lighting Fixtures (Firefly Brand)
2 X 40W Fluorescent Lamp Recessed Type 80.00 set/s 2,250.00 2,250.00 180,000.00 200.00 200.00
2 X 20W Fluorescent Lamp Grilled Type 38.00 set/s 2,050.00 2,050.00 77,900.00 200.00 200.00
Pinlight 163.00 set/s 600.00 600.00 97,800.00 200.00 200.00
Wall Lamp 8.00 set/s 2,100.00 2,100.00 16,800.00 200.00 200.00
Square Downlight 12.00 set/s 800.00 800.00 9,600.00 200.00 200.00
Exhaust Fan 15.00 set/s 4,500.00 4,500.00 67,500.00 1,100.00 1,100.00
Emergency Light 16.00 set/s 2,100.00 2,100.00 33,600.00 200.00 200.00
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
Special Lightings 4.00 set/s 10,000.00 10,000.00 40,000.00 1,500.00 1,500.00
C. POWER LAYOUT
1.0 Conduits & Fittings (Emerald Brand)
20mm dia PVC Pipe 404.00 pc/s 72.00 72.00 29,088.00 28.80 28.80
20mm dia PVC Adapter 908.00 pc/s 10.00 10.00 9,080.00 4.00 4.00
20mm dia PVC Locknut & Bushing 908.00 pc/s 15.00 15.00 13,620.00 6.00 6.00
20mmØ PVC Elbow 364.00 pc/s 25.00 25.00 9,100.00 10.00 10.00
Utility Box 227.00 pc/s 40.00 40.00 9,080.00 16.00 16.00
Sub Total :
2.0 Wires & Cables (Philflex Brand)
3.5 sq.mm. THHN 3,152.00 lm/s 22.00 22.00 69,344.00 8.80 8.80
3.5 sq.mm. THHN (G) 1,576.00 lm/s 22.00 22.00 34,672.00 8.80 8.80
Sub Total :
3.0 Wiring Devices (Royu Brand)
Duplex Convenience Outlet (Universal) 170.00 set/s 252.00 252.00 42,840.00 100.00 100.00
Special Purpose Outlet (Hand Dryer) 8.00 set/s 1,150.00 1,150.00 9,200.00 300.00 300.00
Sub Total :
D. HVAC LAYOUT
1.0 Conduits & Fittings (Emerald Brand)
32mm dia PVC Pipe 124.00 pc/s 160.00 160.00 19,840.00 64.00 64.00
32mm dia PVC Adapter 30.00 pc/s 20.00 20.00 600.00 8.00 8.00
32mm dia PVC Locknut & Bushing 30.00 pc/s 30.00 30.00 900.00 12.00 12.00
25mm dia PVC Pipe 187.00 pc/s 120.00 120.00 22,440.00 48.00 48.00
25mm dia PVC Adapter 50.00 pc/s 15.00 15.00 750.00 6.00 6.00
25mm dia PVC Locknut & Bushing 50.00 pc/s 22.50 22.50 1,125.00 9.00 9.00
Sub Total :
2.0 Wires & Cables (Philflex Brand)
22 sq.mm. THHN 497.00 lm/s 117.00 117.00 58,149.00 46.80 46.80
14 sq.mm. THHN 679.00 lm/s 75.00 75.00 50,925.00 30.00 30.00
8.0 sq.mm. THHN 1,451.00 lm/s 48.00 48.00 69,648.00 19.20 19.20
5.5 sq.mm. THHN 1,172.00 lm/s 32.00 32.00 37,504.00 12.80 12.80
8.0 sq.mm. THHN (G) 588.00 lm/s 48.00 48.00 28,224.00 19.20 19.20
5.5 sq.mm. THHN (G) 588.00 lm/s 32.00 32.00 18,816.00 12.80 12.80
E. 250KVA, 3P, 230V SILENT TYPE GENSET 1.00 lot 1,200,000.00 1,200,000.00 1,200,000.00 100,000.00 100,000.00
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
F. MISCELLANEOUS & CONSUMABLES 1.00 lot 50,000.00 50,000.00 50,000.00 20,000.00 20,000.00
Sub Total :
G. SUPPORTS & BRACKETS 1.00 lot 50,000.00 50,000.00 50,000.00 20,000.00 20,000.00
Sub Total :
H. TESTING & COMMISIONING 1.00 lot - - 150,000.00 150,000.00
Sub Total :
B INTERCOM SYSTEM
1.0 Conduits & Fittings
40mm dia PVC Pipe 8.00 pc/s 198.00 198.00 1,584.00 79.20 79.20
25mm dia PVC Pipe 589.00 pc/s 120.00 120.00 70,680.00 48.00 48.00
25mm dia PVC Adapter 516.00 pc/s 15.00 15.00 7,740.00 6.00 6.00
25mm dia PVC Locknut & Bushing 516.00 pc/s 22.50 22.50 11,610.00 9.00 9.00
25mmØ PVC Elbow 206.40 pc/s 34.00 34.00 7,017.60 13.60 13.60
Junction Box 10.00 pc/s 50.00 50.00 500.00 20.00 20.00
Utility Box 119.00 pc/s 40.00 40.00 4,760.00 16.00 16.00
Pull Box 1.00 pc/s 600.00 600.00 600.00 240.00 240.00
Sub Total :
2.0 WIRES & CABLES -
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
CAT 5E Cable, 4 pairs 2,329.00 lm/s 34.00 34.00 79,186.00 13.60 13.60
Telephone Cable 2,329.00 lm/s 30.00 30.00 69,870.00 12.00 12.00
Sub Total :
3.0 Telephone Equipment & Accessories
Two Gang Outlet for Telephone & Intercom 90.00 set/s 540.00 540.00 48,600.00 400.00 400.00
TTC 3.00 assy 32,000.00 32,000.00 96,000.00 15,000.00 15,000.00
PABX 1.00 assy 48,510.00 48,510.00 48,510.00 20,000.00 20,000.00
Sub Total :
C CCTV SYSTEM
1.0 Conduits & Fittings
40mm dia PVC Pipe 8.00 pc/s 198.00 198.00 1,584.00 79.20 79.20
20mm dia PVC Pipe 267.00 pc/s 72.00 72.00 19,224.00 28.80 28.80
20mm dia PVC Adapter 288.00 pc/s 10.00 10.00 2,880.00 4.00 4.00
20mm dia PVC Locknut & Bushing 288.00 pc/s 15.00 15.00 4,320.00 6.00 6.00
20mmØ PVC Elbow 116.00 pc/s 25.00 25.00 2,900.00 10.00 10.00
Junction Box 47.00 pc/s 50.00 50.00 2,350.00 20.00 20.00
Utility Box 10.00 pc/s 40.00 40.00 400.00 16.00 16.00
Square Box 15.00 pc/s 75.00 75.00 1,125.00 30.00 30.00
Pull Box 1.00 pc/s 600.00 600.00 600.00 240.00 240.00
Sub Total : -
2.0 WIRES & CABLES
CAT 5E Cable, 4 pairs 1,073.00 lm/s 34.00 34.00 36,482.00 13.60 13.60
Sub Total :
3.0 TV Equipment & Accessories
Dome Type Camera 20.00 set/s 8,500.00 8,500.00 170,000.00 1,500.00 1,500.00
Bullet Type Camera 1.00 set/s 12,000.00 12,000.00 12,000.00 2,000.00 2,000.00
Router 1.00 set/s 7,450.00 7,450.00 7,450.00 4,500.00 4,500.00
LED Monitor 1.00 set/s 24,000.00 24,000.00 24,000.00 2,500.00 2,500.00
DVR with HDD & Accessories 1.00 assy 148,200.00 148,200.00 148,200.00 34,000.00 34,000.00
Sub Total :
D MISCELLANEOUS & CONSUMABLES 1.00 lot 40,000.00 40,000.00 40,000.00 16,000.00 16,000.00
Sub Total :
E SUPPORTS & BRACKETS 1.00 lot 40,000.00 40,000.00 40,000.00 16,000.00 16,000.00
Sub Total :
F TESTING & COMMISIONING 1.00 lot - - 150,000.00 150,000.00
Sub Total :
TOTAL MISCELLANEOUS
TOTAL OF AUXILIARY WORKS
SUB - TOTAL (AUXILIARY WORKS)
XVI. SANITARY & PLUMBING WORKS
1.0 Waste, Sewer & Vent System
1.1 PVC PIPES S-1000 ll
a. 150 mm Ø 8.00 length 1,530.00 1,530.00 12,240.00 612.00 612.00
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
b. 100 mm Ø 64.00 length 714.00 714.00 45,696.00 285.60 285.60
c. 50 mm Ø 24.00 length 250.00 250.00 6,000.00 100.00 100.00
1.2 PVC FITTINGS 1.00 lot 25,000.00 25,000.00 25,000.00 10,000.00 10,000.00
6.0 Hangers & Supports 1.00 lot 35,000.00 35,000.00 35,000.00 14,000.00 14,000.00
7.0 Miscellaneous & Consumables 1.00 lot 150,000.00 150,000.00 150,000.00 60,000.00 60,000.00
B. SECOND FLOOR
MATERIAL LABOR
CODE ITEM/DESCRIPTION QTY UNIT
1.00 UNIT COST AMOUNT 1.00 UNIT COST
B.1 SPLIT TYPE AIRCON UNITS
FCU1/ACCU1 2.00 sets 241,900.00 241,900.00 483,800.00 2,950.00 2,950.00
FCU2/ACCU2 1.00 sets 28,674.00 28,674.00 28,674.00 2,950.00 2,950.00
FCU3/ACCU3 1.00 sets 32,450.00 32,450.00 32,450.00 2,950.00 2,950.00
FCU4/ACCU4 2.00 sets 45,666.00 45,666.00 91,332.00 2,950.00 2,950.00
FCU5/ACCU5 1.00 sets 92,040.00 92,040.00 92,040.00 4,130.00 4,130.00
FCU6/ACCU6 2.00 sets 123,900.00 123,900.00 247,800.00 4,130.00 4,130.00
B.2 WINDOW TYPE AIRCON UNITS
WDO3 3.00 unit 23,594.10 23,594.10 70,782.30 2,950.00 2,950.00
160,786.80 160,786.80 160,786.80 107,191.20 107,191.20
1.00 lot
C. THIRD FLOOR
C.1 SPLIT TYPE AIRCON UNITS
FCU2/ACCU2 2.00 sets 28,674.00 28,674.00 57,348.00 2,950.00 2,950.00
FCU3/ACCU3 1.00 sets 32,450.00 32,450.00 32,450.00 2,950.00 2,950.00
FCU5/ACCU5 4.00 sets 92,040.00 92,040.00 368,160.00 4,130.00 4,130.00
FCU7/ACCU7 2.00 sets 128,620.00 128,620.00 257,240.00 4,130.00 4,130.00
2.00 VENTILATION SYSTEM INCLUDING DUCTWORKS
Scope of Works
1.0 Supply and Installation of brackets, hangers and supports.
2.0 Supply of all types of Toilet Exhaust Fan and machine connection of units to ducts.
3.0 Testing and Commissioning.
A. GROUND FLOOR
A.1 Ceiling Cassette Exhaust Fan for Toilet Exhaust “KDK”
CEF1 5.00 units 6,800.00 6,800.00 34,000.00 1,416.00 1,416.00
24,000.00 24,000.00 18,880.00 18,880.00
1.00 lot 24,000.00
B. SECOND FLOOR
B.1 Ceiling Cassette Exhaust Fan for Toilet Exhaust “KDK”
CEF1 4.00 units 6,800.00 6,800.00 27,200.00 1,416.00 1,416.00
19,200.00 19,200.00 15,104.00 15,104.00
1.00 lot 19,200.00
C. THIRD FLOOR
C.1 Ceiling Cassette Exhaust Fan for Toilet Exhaust “KDK”
CEF1 2.00 units 6,800.00 6,800.00 13,600.00 1,416.00 1,416.00
9,600.00 9,600.00 7,552.00 7,552.00
1.00 lot 9,600.00
3.00 ELEVATOR
1.0 10-person capacity Elevator 1.00 unit 1,800,000.00 1,800,000.00 1,800,000.00 200,000.00 200,000.00
345,731.50
631,468.80
8,035,696.25
- - -
1,677,023.07
4,581,405.47
1,236,471.75
865,318.40
- - -
3,000.00 18,400.00 55,200.00
3,000.00 17,400.00 52,200.00
3,000.00 16,400.00 49,200.00
- - -
600.00 6,100.00 6,100.00
6,000.00 3,100.00 31,000.00
- - -
12,000.00 7,400.00 88,800.00
11,000.00 7,400.00 81,400.00
18,000.00 7,400.00 133,200.00
1,000.00 7,800.00 7,800.00
- - -
2,500.00 40,750.00 40,750.00
2,500.00 29,050.00 29,050.00
2,500.00 33,190.00 33,190.00
2,500.00 23,875.00 23,875.00
- - -
- 87,900.00 87,900.00
- 20,500.00 123,000.00
- 37,500.00 75,000.00
- - -
- 7,420.00 14,840.00
- 3,920.00 31,360.00
- 3,360.00 6,720.00
- 9,360.00 131,040.00
- 5,280.00 10,560.00
LABOR TOTAL UNIT
AMOUNT
AMOUNT COST
- 5,880.00 5,880.00
1,118,065.00
- 26,000.00 364,000.00
- 5,500.00 44,000.00
- - -
- 3,500.00 172,200.00
- 3,000.00 54,900.00
- 1,500.00 1,500.00
9,573.75 3,900.00 41,486.25
3,576,730.00 3,576,730.00
50,000.00 50,000.00
50,000.00 50,000.00
1,350.00 1,650.00 14,850.00
4,369,666.25
13,847,949.94
- - -
4,981,612.00
4,981,612.00
1,956,111.04
1,956,111.04
1,610,938.65
1,610,938.65
5,077,098.50
9,447,544.15 39,659,261.62
2% 793,185.23
10% 3,965,926.16
LABOR TOTAL UNIT
AMOUNT
AMOUNT COST
7% 3,109,286.11
47,527,659.13
PROJECT : DESIGN AND BUILD OF THE THREE-STOREY HLURB-NTRFO BUILDING
LOCATION : Diosdado Macapagal Government Center, Brgy. Maimpis, City of San Fernando, Pampanga
OWNER : NORTHERN TAGALOG REGIONAL FIELD OFFICE
SUBJECT : CONSTRUCTION SCHEDULE/ BAR CHART
DATE : 29-Jan-19
1 Detailed A7E Design Fee Including specialized consultant for Laboratory Systems 1.00 lot
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVSURVEYS AND TESTS 1.00 lot
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS 1.00 lot
SUB - TOTAL (GENERAL REQUIREMENTS)
IV. SITEWORK-LAND DEVELOPMENT 1.00 lot
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT)
V. EARTHWORKS 1.00 lot
SUB - TOTAL (SITEWORKS-STRUCTURAL)
VI. CONCRETE / STRUCTURAL
SUB - TOTAL (CONCRETE WORKS) WORKS 1.00 lot
-
VII. METAL WORKS 1.00 lot
SUB - TOTAL (METAL WORKS)
TOTAL - STRUCTURAL WORKS
VIII. MASONRY WORKS 1.00 lot
SUB - TOTAL (MASONRY WORKS)
IX. FINISHES
1 Wall Finishes 1.00 lot
2 Floor Finishes 1.00 lot
3 Ceiling Finishes 1.00 lot
SUB - TOTAL (FINISHES)
X. PAINTING WORKS 1.00 lot
SUB - TOTAL (PAINTING WORKS)
XI. THERMAL & MOIST PROTECTION 1.00 lot
SUB - TOTAL (THERMAL & MOIST PROTECTION)
XII. DOORS AND WINDOWS 1.00 lot
SUB - TOTAL (DOORS AND WINDOWS)
XIII. SPECIALTIES 1.00 lot
SUB - TOTAL (SPECIALTIES WORKS)
TOTAL - ARCHITECTURAL WORKS
XIV. ELECTRICAL WORKS 1.00 lot
SUB - TOTAL (ELECTRICAL WORKS)
XIV. AUXILIARY WORKS 1.00 lot
SUB - TOTAL (AUXILIARY WORKS)
XV. SANITARY & PLUMBING WORKS 1.00 lot
SUB - TOTAL (SANITARY & PLUMBING WORKS)
XVI. FIRE PROTECTION WORKS 1.00 lot
SUB - TOTAL FIRE PROTECTION WORKS)
XVI. MECHANICAL WORKS 1.00 lot
SUB - TOTAL (MECHANICAL)
TOTAL PROJECT COST
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509
Err:509 Err:509
Err:509
Err:509 Err:509
Err:509
Err:509 Err:509
Err:509
Err:509 Err:509
Err:509
Err:509
Err:509 Err:509 ### ### ### ###
Err:509
Err:509 Err:509 ### ###
Err:509
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
Err:509 Err:509
Err:509
Err:509 Err:509
Err:509
Err:509 Err:509
% ### ### ### ### ### ### ### ### ### ### ### ### ### ###
%
%
%
Php
Php
Php
Php
###
Err:509 Err:509
###
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
Err:509 Err:509
###
###
Err:509 Err:509
###
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
Err:509 Err:509
###
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
2019-2020
MONTH 4 MONTH 5 MONTH 6 MONTH 7
Err:509 Err:509
0 -
Err:509 Err:509
0 -
### ### ### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### Err:509 Err:509
0 -
Err:509 Err:509
0 -
### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### ### ### Err:509 Err:509
0 -
0 -
### ### ### ### ### ### ### ### Err:509 Err:509
0 -
0 -
### ### ### ### ### ### ### ### ### ### Err:509 Err:509
### ### ### ### ### ### ### Err:509 Err:509
### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### Err:509 Err:509
0 -
0 -
### ### ### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
### ### ### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
0 -
### ### ### ### ### ### ### ### ### ### ### ### Err:509 Err:509
### ### ### ### ### ### ### ### ### ### ### ### ### ###
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
Err:509 Err:509
###
###
Err:509 Err:509
###
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
Err:509 Err:509
###
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
###
Err:509 Err:509
Err:509
Err:509
Err:509
Err:509
###
Err:509 Err:509
Err:509 Err:509
###
PROJECT : DESIGN AND BUILD OF THE THREE-STOREY HLURB-NTRFO BUILDING
LOCATION : Diosdado Macapagal Government Center, Brgy. Maimpis, City of San Fernando, Pampanga
OWNER : NORTHERN TAGALOG REGIONAL FIELD OFFICE
SUBJECT : MANPOWER SCHEDULE
DATE : JANUARY 29, 2019
CODE ITEM/DESCRIPTION
MONTH 1
I. DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES
Detailed A7E Design Fee Including specialized consultant for Laboratory Systems
Principal Architect 1 1 1 1
Civl/ Structural Engineer 1 1 1 1
Design Architect 1 1 1 1
Professional Electrical Engineer 1 1 1 1
Quantity Cost Engineer/ Architect 1 1 1 1
Professional Mechanical Engineer 1 1 1 1
Sanitary Engineer 1 1 1 1
CAD Operator 2 2 2 2
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVEYS AND TESTS
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS
Project Manager 1 1 1 1
Project Architect/ Engineer 1 1 1 1
Quantity Surveyor/ Engineer 1 1 1 1
Electrical Engineer
Mechanical Engineer
Sanitary Engineer
Site Engineer 2 2 2 2
Safety Officer 1 1 1 1
SUB - TOTAL (GENERAL REQUIREMENTS)
IV. SITEWORK-LAND DEVELOPMENT
Surveyor
Construction Foreman
Skilled Workers
Laborer
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT)
V. EARTHWORKS
Surveyor 1 1
Construction Foreman 1 1
Skilled Workers 5 10
Laborer 10 15
SUB - TOTAL (SITEWORKS-STRUCTURAL)
VI. STRUCTURAL WORKS
Construction Foreman
Skilled Laborer (Mason/Steelman/Carpenter)
Laborer
SUB - TOTAL (CONCRETE WORKS)
-
VII. METAL WORKS
Construction Foreman
Welder
Helper
SUB - TOTAL (METAL WORKS)
TOTAL - STRUCTURAL WORKS
VIII. ARCHITECTURAL & FINISHING WORKS
Construction Foreman
Skilled Laborer (Mason/Carpenter/Finisher)
Laborer
TOTAL - ARCHITECTURAL WORKS
XIV. ELECTRICAL WORKS
Construction Foreman
Electrician
Laborer
SUB - TOTAL (ELECTRICAL WORKS)
XIV. AUXILIARY WORKS
Construction Foreman
Electrician
Laborer
SUB - TOTAL (AUXILIARY WORKS)
XV. SANITARY & PLUMBING WORKS
Construction Foreman
Plumber
Laborer
SUB - TOTAL (SANITARY & PLUMBING WORKS)
XVI. FIRE PROTECTION WORKS
Construction Foreman
Skilled Worker
Laborer
SUB - TOTAL FIRE PROTECTION WORKS)
XVI. MECHANICAL WORKS
Construction Foreman
Skilled Worker
Laborer
SUB - TOTAL (MECHANICAL)
By:
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1
1 1
5 5
8 8
1 1 1 1 1 1
1 1 1 1 1 1
10 10 10 10 10 10
15 15 15 15 15 15
1 1 1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 15 15 15 35 35 35 35
7 7 7 7 7 7 22 22 22 50 50 50 50
1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5 5
3 3 3 3 3 3 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 40 40 40 40 40 40 40
10 10 10 10 10 60 60 60 60 60 60 60
1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5 5 5 5 5 5 5
10 10 10 10 10 10 10 10 10 10 10 10 10 10
1 1 1 1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 4 4
7 7 7 7 7 7 7 7 7 7 7 7
1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5 5 5 5 5 5 5
10 10 10 10 10 10 10 10 10 10 10 10 10 10
1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5
7 7 7 7 7 7 7 7
1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5
7 7 7 7 7 7 7 7
MONTH 7
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
2 2 2 2
1 1 1 1
0 #REF!
0 #REF!
1 1 1 1
1 1 1 1
5 5 5 5
8 8 8 8
0 #REF!
0 #REF!
0 #REF!
0 #REF!
13 #REF!
215 #REF!
308 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
1 1 1 1
40 40 40 40
60 60 60 60
0 #REF!
0 #REF!
1 1 1 1
5 5 5 3
10 10 10 5
0 #REF!
0 #REF!
1 1 1 1
4 4 4 2
7 7 7 4
0 #REF!
0 #REF!
1 1 1 1
5 5 5 3
10 10 10 5
0 #REF!
0 #REF!
1 1 1 1
5 5 5 2
7 7 7 3
0 #REF!
0 #REF!
1 1 1 1
5 5 5 2
7 7 7 3
PROJECT : DESIGN AND BUILD OF THE THREE-STOREY HLURB-NTRFO BUILDING
LOCATION : Diosdado Macapagal Government Center, Brgy. Maimpis, City of San Fernando, Pampanga
OWNER : NORTHERN TAGALOG REGIONAL FIELD OFFICE
SUBJECT : EQUIPMENT UTILIZATION SCHEDULE
DATE : JANUARY 29, 2019
CODE ITEM/DESCRIPTION
MONTH 1 MONTH 2
I. DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVEYS AND TESTS
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS
Emergency Lighting System 5 5 5 5 5 5
Cutoff Machine 1 1 1 1 1 1
Tonner Walk Behind 1 1 1 1 1 1
Submersible Pump 2 2 2 2 2 2
Welding Machine
SUB - TOTAL (METAL WORKS)
TOTAL - STRUCTURAL WORKS
VIII. ARCHITECTURAL & FINISHING WORKS
By:
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1
1 1 1 1
2 2 2 2
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
1 1 1 1
2 2 2 2
1 1 1 1
1 1 1 1
1 1 1 1
2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2
4 4 4 4 4 4 4 4 4 4 4
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
MONTH 7
0 #REF!
0 #REF!
0 #REF!
0 #REF!
5 5
1 1
1 1
2 2
0 #REF!
0 #REF!
1 1
1 1
2 2
1 1
0 #REF!
0 #REF!
0 #REF!
0 #REF!
26 #REF!
26 #REF!
26 #REF!
52 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
0 #REF!
1 1
1 1
1 1
0 #REF!
0 #REF!
0 #REF!
0 #REF!
1 1
0 #REF!
0 #REF!
1 1
1 1
0 #REF!
0 #REF!
1 1
1 1
PROJECT : DESIGN AND BUILD OF THE THREE-STOREY HLURB-NTRFO BUILDING
LOCATION : Diosdado Macapagal Government Center, Brgy. Maimpis, City of San Fernando, Pampanga
OWNER : NORTHERN TAGALOG REGIONAL FIELD OFFICE
SUBJECT : PAYMENT SCHEDULE
DATE : JANUARY 29, 2019
1 Detailed A7E Design Fee Including specialized consultant for Laboratory Systems 1.00 lot
SUB - TOTAL (DESIGN DEV'T, INCLUSIVE PROFESSIONAL FEES)
II. SURVSURVEYS AND TESTS 1.00 lot
SUB - TOTAL (SURVEYS AND TESTS)
III. GENERAL REQUIREMENTS 1.00 lot
SUB - TOTAL (GENERAL REQUIREMENTS)
IV. SITEWORK-LAND DEVELOPMENT 1.00 lot
SUB - TOTAL (SITEWORKS-LAND DEVELOPMENT)
V. EARTHWORKS 1.00 lot
SUB - TOTAL (SITEWORKS-STRUCTURAL)
VI. CONCRETE / STRUCTURAL
SUB - TOTAL (CONCRETE WORKS) WORKS 1.00 lot
-
VII. METAL WORKS 1.00 lot
SUB - TOTAL (METAL WORKS)
TOTAL - STRUCTURAL WORKS
VIII. MASONRY WORKS 1.00 lot
SUB - TOTAL (MASONRY WORKS)
IX. FINISHES
1 Wall Finishes 1.00 lot
2 Floor Finishes 1.00 lot
3 Ceiling Finishes 1.00 lot
SUB - TOTAL (FINISHES)
X. PAINTING WORKS 1.00 lot
SUB - TOTAL (PAINTING WORKS)
XI. THERMAL & MOIST PROTECTION 1.00 lot
SUB - TOTAL (THERMAL & MOIST PROTECTION)
XII. DOORS AND WINDOWS 1.00 lot
SUB - TOTAL (DOORS AND WINDOWS)
XIII. SPECIALTIES 1.00 lot
SUB - TOTAL (SPECIALTIES WORKS)
TOTAL - ARCHITECTURAL WORKS
XIV. ELECTRICAL WORKS 1.00 lot
SUB - TOTAL (ELECTRICAL WORKS)
XIV. AUXILIARY WORKS 1.00 lot
SUB - TOTAL (AUXILIARY WORKS)
XV. SANITARY & PLUMBING WORKS 1.00 lot
SUB - TOTAL (SANITARY & PLUMBING WORKS)
XVI. FIRE PROTECTION WORKS 1.00 lot
SUB - TOTAL FIRE PROTECTION WORKS)
XVI. MECHANICAL WORKS 1.00 lot
SUB - TOTAL (MECHANICAL)
TOTAL PROJECT COST
1,858,996.06
1,816,263.51
901,332.78
4,576,592.35
1,474,619.57
1,474,619.57
989,860.43
989,860.43
2,199,274.31
2,199,274.31
933,255.93
933,255.93
12,898,029.54
4,645,997.46 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056
4,645,997.46
2,571,503.05 0.0035 0.0035 0.0035 0.0035
2,571,503.05
1,947,785.92 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023
1,947,785.92
906,041.54
906,041.54
7,347,819.80
7,347,819.80
46,227,863.38
0.0094 0.0094 0.0077 0.0077 0.019 0.019 0.019 0.019 0.019 0.019 0.0253 0.0253 0.0347 0.0368 0.0368 0.0368
1%
435,427.28 435,427.28
870,854.55 435,427.28
2%
3.43%
3.43%
3%
1,227,773.68 356,919.13
1,584,692.81
1,584,692.81
3%
1,584,692.81 356,919.13
5%
2,461,325.19 876,632.38
7%
3,337,957.58 876,632.38
7.59%
11.01%
19.87%
19.87%
9%
4,214,589.96 876,632.38
5,091,222.35
3,506,529.54
11%
5,091,222.35 876,632.38
13%
5,967,854.73 876,632.38
15%
6,844,487.12 876,632.38
8.86%
19.87%
17%
8,014,811.45 1,170,324.33
9,185,135.78
4,093,913.43
9,185,135.78
9,185,135.78
20%
9,185,135.78 1,170,324.33
23%
10,788,621.75 1,603,485.97
27%
12,489,313.71 1,700,691.97
34.37%
14.51%
31%
14,190,005.68 1,700,691.97
15,890,697.65
6,705,561.87
34%
15,890,697.65 1,700,691.97
80.07%
60.20%
-2020
MONTH 5 MONTH 6 MONTH 7
0.0102005363 -
0 -
0.0065388053 -
0 -
0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.0036 0.1007892292 -
0 -
0.0026 0.0026 0.0026 0.0026 0.0026 0.0026 0.0158539874 -
0 -
0.0125689309 -
0 -
0.0138 0.1793032596 -
0 -
0.0021 0.0021 0.0021 0.0021 0.0021 0.0021 0.0189248197 -
0 -
0 -
0.0059 0.0059 0.0059 0.0059 0.0059 0.0059 0.0589347369 -
0 -
0 -
0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.0402137568 -
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.0392893673 -
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.0194976085 -
0 -
0.0053 0.0053 0.0053 0.0053 0.0053 0.0053 0.0318989341 -
0 -
0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0031 0.0214126363 -
0 -
0.0079 0.0079 0.0079 0.0079 0.0079 0.0079 0.0475746476 -
0 -
0.005 0.005 0.005 0.005 0.0201881692 -
0 -
0 -
0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.0056 0.1005021024 -
0 -
0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0035 0.0556266904 -
0 -
0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.042134457 -
0 -
0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0195994683 -
0 -
0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.1589478565 -
0.0576 0.0525 0.0525 0.0525 0.0604 0.0604 0.0604 0.0604 0.0568 0.0568 0.0429 0.0429
40%
18,555,244.27 2,664,546.63
45%
20,983,065.24 2,427,820.97
80.07%
60.20%
55.89%
21.52%
23,410,886.21 51% 2,427,820.97
25,838,707.18
9,948,009.54
56%
25,838,707.18 2,427,820.97
62%
28,633,073.87 2,794,366.69
68%
31,427,440.56 2,794,366.69
80.07%
24.17%
74%
34,220,077.81 2,792,637.25
11,174,007.87
37,012,715.06
27,827,579.28
37,012,715.06
80%
37,012,715.06 2,792,637.25
86%
39,637,791.44 2,625,076.38
91%
42,262,867.82 2,625,076.38
19.93%
19.93%
100.00%
100.00%
44,245,365.60 1,982,497.78
46,227,863.38
9,215,148.33
46,227,863.38
9,215,148.33
96% 100%
46,227,863.38 1,982,497.78