Sei sulla pagina 1di 21

Department of Transport and Main Roads Chapter 10

Road Drainage Manual Floodway Design

Chapter 10
Floodway Design

10

March 2010
i
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Chapter 10 Amendments – Mar 2010


Revision Register
Issue/ Reference Description of Revision Authorised Date
Rev Section by
No.
1 - Initial Release of 2nd Ed of manual. Steering Mar
Committee 2010

10

March 2010
ii
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Table of Contents
10.1 Introduction 10-1
10.2 Additional Considerations 10-1
10.3 Geometric and Safety Issues 10-1
10.4 Environmental Factors 10-2
10.5 Hydraulic Design 10-2
10.5.1 Floodway Terminology 10-2
10.5.2 Flow Over the Road 10-4
10.5.3 Full Floodway Design Calculations 10-4
10.6 Time of Submergence / Closure 10-8
10.6.1 Time of Submergence 10-9
10.6.2 Time of Closure 10-9
10.6.3 Issues Related to Times 10-9
10.6.4 Calculation of Time of Submergence or Closure 10-11
10.6.5 Procedure for Estimating AATOC / AATOS 10-12
10.7 Floodway Protection 10-13
10.7.1 Types of Protection 10-13
10.7.2 Floodways with Grassed Batters 10-13
10.7.3 Floodways with Other than Grassed Batters 10-14

10

10

March 2010
iii
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

10

March 2010
iv
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Chapter 10
Floodway Design

10.1 Introduction requirements in the selection of final road


level.
Floodways are sections of roads which have
been designed to be overtopped by Floodways may offer environmental
floodwater during relatively low average advantages over culverts or bridges, since
recurrence interval (ARI) floods. An they will tend to spread flows more widely.
example of a flood is shown in Figure 10.1. This means that the risk of scour to
waterway and surrounding land is generally
reduced because flow is less concentrated.
It is also important that a floodway be
designed so that it is not covered by water
from ponding or backwater for any
significant period of time after a flood
event.
10.3 Geometric and Safety
Issues
It is important that adequate approach sight
Figure 10.1 - Little Annan River Floodway
distance be provided to allow drivers time
In Queensland, these overtopping floods are to recognise water over the road and to
usually in the ARI 10 to 20 year range stop. It is also important that the length of a
although some roads may be overtopped by floodway be limited at about 300 m so that
smaller flood events. drivers do not become disorientated when
confronted with wide open stretches of
Chapter 2 outlines many factors which
water. Where a proposed floodway would
should be considered before deciding on the
be longer than 300 m, it is recommended
design flood immunity for new road works.
that the proposed floodway be broken into
10.2 Additional shorter lengths by providing sections of
Considerations road that are raised above the maximum
Further to the requirements discussed in
Chapter 2, floodways may require costly
flood level.
As a general principle, floodways should be
10
batter protection and therefore a higher designed so that the depth of water over the
level road together with a larger culvert or road should be as uniform as possible over
bridge option may be more cost effective. the flooded section. Building a floodway
Floodways also have smaller waterway on a level grade avoids the possibility of a
(under road) requirements and may be more driver unexpectedly encountering deeper
prone to blockage by debris. These cost water and possibly stalling or being swept
related performance factors should be downstream.
considered as well as trafficability and other

March 2010
10-1
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Exceptions to the level grading in during times of flood, then a check should
Queensland occur where bridges have been be done on allowable flow velocities.
built significantly higher than the flooded
The procedures outlined in Section 9.7
approaches on both sides. The bridges have
should be followed for fauna passage
been built on the basis that the approaches
through culverts.
will be raised sometime in the future.
As noted above, floodways reduce the
Floodways should not be placed on
concentration of flow, compared to culverts
horizontal curves as:
or bridges, so the risk of scour damage to
 there are problems in defining the waterway and surrounding land is reduced.
edge of the pavement for motorists;
10.5 Hydraulic Design
 any superelevation may change the
normal flow distribution i.e. push 10.5.1 Floodway Terminology
more water to the non-
superelevated sections of road; and A floodway consists not only of the
roadway embankment to accommodate
 the water depth will be deeper on flow over the road but also waterway
one side of the road than the other openings to provide for flow under the road.
in a superelevated section of road These openings may be required for one or
and there is the possibility of the more of the following functions:
high side being trafficable but not
the other, thus creating a safety  reduce the afflux or rise in water
problem. level upstream due to the
obstruction (embankment);
Floodways should also not be located on
vertical curves to avoid variations in depths  raise the tailwater level so that less
of flows. batter protection is required on the
downstream side e.g. grass instead
For further geometric requirements of of concrete; and/or
width, crossfall, vertical and horizontal
alignment, refer to the relevant chapters of  act as anti-ponding structures for
the department’s Road Planning and low flow stream conditions.
Design Manual. Signage of the floodway is Flow over roadways may be:
also important and designers are referred to
 free flow; or
the latest release of the Manual of Uniform
Traffic Control Devices for warrants /  submerged flow.

10 guidance.
10.4 Environmental Factors
In the initial stages of overtopping a low
tailwater usually exists and free flow
occurs. Under these circumstances flow
For floodways that contain floodplain
passes through critical depth over the road
culverts (i.e. culverts located away from a
and the discharge is determined by flood
watercourse channel) only terrestrial
levels upstream.
movement generally needs to be
considered. However, if fish migration is
expected to occur across the floodplain

March 2010
10-2
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Free flow may be either: tailwater. This flow will have less
erosion potential downstream.
 plunging flow which flows over the
shoulder and down the downstream Submerged flow occurs when the
face of the embankment. The flow discharge is controlled by the tailwater level
then penetrates the tailwater surface as well as the headwater levels. This occurs
producing a submerged hydraulic when the depth of flow over the road is
jump on the downstream slope. everywhere greater than the critical depth.
Velocities are likely to be high and
Typical velocities of flow over a floodway
erosive; or
are shown on Figure 10.5.1 as sourced from
 surface flow which separates from Waterway Design (Austroads 1994) after
the surface of the road embankment Cameron and McNamara (1966).
and rides over the surface of the

Q = 1.16m3/s (HEAD DROP = 1.77m)

Q = 1.16m3/s (HEAD DROP = 0.70m)

Q = 1.16m3/s (HEAD DROP = 0.36m)


10

Figure 10.5.1 - Indicative Velocities of Flow over a Typical Floodway

March 2010
10-3
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Where:
10.5.2 Flow Over the Road
V2
The broad crested weir formula used for H  h = Specific Head
2g
flow over a road is:
On Figure 10.5.2;
C 
Q  C f LH  s
1.5   for H/l > 0.15 (usual case) Use
C 
 f  curve B to obtain the free flow
Where: coefficient of discharge, Cf.

 Q = discharge over floodway  for H/l < 0.15 Use curve A to


(m³/s); obtain value of Cf.

 Cf = coefficient of discharge ‘free’  Calculate D/H x 100 and use curve


flow; C to obtain the submergence factor
Cs / Cf.
 Cs = coefficient of discharge flow
with submergence;  Calculate the discharge over the
road using the broad crested weir
 L = length of floodway (m); and
formula.
 H = specific head or specific
energy (m). 10.5.3 Full Floodway Design
Calculations
With reference to Figure 10.5.2:
 h = level difference between the Floodways incorporating culverts and
floodway crown and the upstream bridges will require calculations in addition
water surface (m); to those above.

 V = approach velocity of the stream The basic principle is that the total flow
(m/s); and over the road and through the waterway
structures equals the flow downstream in
 l = top width of road formation (m).
the unrestricted channel.
The flow over the floodway may be
Given the many combinations of headwater
calculated by means of the following design
and tailwater possible, it is necessary to fix
procedure:
at least one of these parameters for each
 Calculate the stage-discharge curve design calculation.
(height versus discharge) for the
With flow over the road, the issue of

10
unrestricted section, from open
whether or not road batter protection is
channel hydraulics (refer Chapter
needed becomes important as the
8);
calculations require the tailwater to be fixed
 Select a tailwater level and a when the flood is at the point of
headwater level (giving h and V) overtopping the road.
from the stage-discharge curve.
H
 Calculate
l

March 2010
10-4
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

10

Figure 10.5.2 - Discharge Coefficients for Flow over Floodways

March 2010
10-5
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Guidelines relating to the need for (c) Fix the headwater level at the crown of
protection are given in Section 10.7 with the road (or the highest edge if
the tailwater level generally in the range superelevated). Avoid the design of
0.4m to 0.6m below the crown of the road superelevated floodways, if possible, as
when the road is about to be overtopped. these can result in depth variations
laterally and surface debris on the
Full floodway design must satisfy Case A
floodway surface can compromise
and Case B conditions.
safety. Residual, silt and gravel on
Case A: When the flood is at the point of floodways after isolated rainfalls events
overtopping the road: can provide hazards on their own,
 Tailwater level is not below the causing serious injury. Effective
level specified for the type of maintenance programs must be in place
protection to be adopted; and by relevant authorities and new designs
of new floodways need to minimise
 Velocities through the bridges
risk.
and/or culverts are acceptable.
(Scouring velocities may be (d) Find the velocity Vx through a suitable
acceptable, if additional outlet major culvert / bridge with the
protection or the formation of scour headwater in (c) above and the tailwater
holes is acceptable). adopted for the type of floodway
protection to be adopted. Say this
The step by step design procedure for this
tailwater level is RLx on Figure 10.5.3
case follows:
Case A, corresponding to a total
Figure 10.5.3 illustrates results of discharge, Qx in the unrestricted
calculations performed using the steps (a) to channel.
(g) below for an actual floodway.
(e) With this velocity Vx find the total area
(a) Calculate the rating curve (height of waterway required from Total Area
versus discharge) for the unrestricted Required = Qx/Vx and select other
channel. culverts to give this total.
(b) Fix the level of the road as a first trial. (f) For the fixed headwater and the
The initial level of the road may be tailwater level, RLx, calculate the actual
based on trafficability eg for required flow through each culvert and bridge
trafficability in a ARI 20 year flood, the and total the discharges to give Qy
initial road level may be the level of the which may or may not be equal to Qx

10 ARI 20 year flood level in the


unrestricted channel. (This allows
culverts to be designed for a maximum
because of the different size openings.
(g) Adjust the culvert and bridge areas so
that with the fixed headwater and
head of 300 mm with the tailwater at
tailwater level, RLx, the total flow
the crown level of the road. It will be
equals Qx. (With progressive
found that a lower road level will give
adjustments the total discharge may be
less fill in the embankment, but require
Qy or Qz so on.)
more culverts under the road in the ARI
20 year flood.)

March 2010
10-6
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

CASE A

CASE B

Figure 10.5.3 – Example Floodway Calculations

Note that the initial assumption of all the Note: The design velocities through
waterways having the same velocity is culverts are normally in the range 1.8 m/s
approximate only as different size and to 3.0 m/s with 2.4 m/s commonly adopted,
shape openings have different hydraulic depending on the scour resistance of the

10
efficiency. This is why the same head will surface material downstream. Higher and
give different velocities. lower velocities have been adopted.
Chapter 9 discusses the hydraulic design
The structures giving Qx are to be
of culverts and Chapters 7 & 13 methods
considered minimum requirements for the
of erosion control.
floodway regardless of the requirements
calculated for a peak flood above the
roadway, as all overtopping floods pass
through this stage.

March 2010
10-7
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Case B: At the peak of the flood above through the waterways. Similarly,
the floodway: Q3 etc may be obtained.
 Velocities through the waterway  Plot Q1, Q2, Q3 etc. against their
structures are acceptable; and respective headwater levels. Join
these points to make the curve
 Afflux caused by the floodway is
shown on Figure 10.5.3 Case B.
acceptable.
 From the curve, find the headwater
The step by step design procedure for this
which gives the required design
case follows:
flood discharge.
At the peak of the overtopping flood,
 If the afflux is acceptable,
allowance for flow over the road must be
calculations are complete. If the
made and afflux calculated for the design
afflux is too high, additional bridge
flood (ARI 20 year in the example in Case
or culvert waterways are required.
A above).
Waterways from Case A are not to
The flow over the road is added to that be reduced.
through the culvert(s) and bridge(s) and the
 Calculate the afflux for the check
calculations initially include the structures
flood (usually of ARI 50 years).
from Case A. With reference to Figures
10.5.3 and Case A and Case B, the Because of flow over the road, maximum
procedure is: velocities are obtained from Case B.
 Find the tailwater level Both velocity and afflux requirements are to
corresponding to the design flood be met.
discharge from the rating curve for
10.6 Time of Submergence
the unrestricted channel.
/ Closure
 Select a headwater level slightly
Some of the following text and diagrams
above the tailwater level in (a), say
have been taken from Bridge Waterways
0.1 m above, and calculate the flow
Hydrology and Design (NAASRA 1989)
over the road and through each
and Waterway Design (Austroads 1994).
culvert and/or bridge with this
headwater - tailwater combination. Where a crossing is designed for
Add these flows together to obtain overtopping, it is usually important that an
a total flow, say Q1. estimate be made of the frequency and
duration of the periods during which the

10  Compare this flow with the design


flood discharge. If Q1 is smaller, a
greater head / afflux is required to
crossing will be submerged as well as the
times it is closed to traffic due to flooding.
The time of submergence is of importance
ensure that the check flood is
with respect to stability of embankments
passed over the road and through
and pavements and consequent maintenance
the waterways.
costs. The time of closure is of importance
 Adopt a higher headwater and the in consideration of acceptable delays to
same tailwater level and obtain the traffic.
total Q2 for flow over the road and

March 2010
10-8
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

10.6.1 Time of Submergence close the road, though there may be some
hazard in travelling on the inundated road.
Time Of Submergence (TOS) is defined as
Different types of vehicles can travel on
the period of time that the road is inundated
roads with different amounts of inundation
by flood water, no matter the depth.
with large and heavy vehicles capable of
The time of submergence is expressed in travelling in water that is deeper and
one of two main ways. The first is the time flowing at a higher velocity than a light car.
of submergence during a major flood - for
Safety of vehicles in flood water is poorly
example, the number of hours of
understood and there has been considerable
submergence during the flood with an
research on the topic.
average recurrence interval of 50 years.
The second is as the Average Annual Time There are different definitions of the flow
Of Submergence, abbreviated as AATOS. conditions when the road is closed by flood
This is the average time per year that the waters. The normally adopted limit in the
road is submerged, expressed as hours per department is when the total head across the
year. road exceeds 0.3 m. That is:
Both expressions are an indication of the Total head (H) = d + v2/2g
frequency and duration of submergence.
Where:
For example a crossing that is submerged
frequently for short periods of time may  d = depth of inundation
have a similar AATOS as one that is  v = flow velocity
submerged less frequently for longer times.
 g = gravity (9.81m/s2)
To understand the concept and to compare
options, three parameters are needed, Similar to AATOS there is an Average
namely: Annual Time Of Closure, abbreviated as
AATOC
 Flood immunity;
 TOS for the ARI 50 year flood (or 10.6.3 Issues Related to Times
other large flood);
The concept of time of closure, in
 AATOS.
association with the time of submergence,
The absolute value of the time of adds some additional information to the
submergence is not particularly useful by question of flood immunity.
itself for a crossing, but it is useful to
Large and flat catchments will respond
compare several crossings or
options.
upgrading
more slowly than small and steep
catchments so the time of submergence for 10
these catchments will generally be longer
10.6.2 Time of Closure
for an equivalent flood immunity.
Time Of Closure (TOC) is similar to time In small steep catchments, where the
of submergence. However this parameter response time is short, the time of
takes account of the fact that some submergence will be low, even for a
inundation of the road may not necessarily crossing with low flood immunity.

March 2010
10-9
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

In small steep catchments, and also for unusual for state controlled roads in
urban catchments where the response time Queensland though it does occur on
is short, floods may occur and then recede interstate main roads and on more minor
very quickly. In this case the disruption to roads.
traffic may be short. Similarly in small
These situations can occur where the road is
catchments, the depth of inundation may be
inundated for months at a time during the
low even if the flood immunity is low. In
wet season or even sometimes the road may
this situation, the time of submergence may
be inundated by tides. The calculation in
be short so the cost of disruption may be
this case is very difficult and should use
very low and the additional cost of
either a stream gauge or calculated
providing for a higher level of flood
continuous discharge records.
immunity may not be justified.
Average time of submergence or closure
On the other hand, large catchments that
may be assessed for a range of selected
have a long response time may inundate the
grade levels and a plot of average time of
road for extended periods of time. In this
submergence against level may be produced
case the cost of disruption may be very high
as in Figure 10.6.3.
and a higher level of flood immunity may
be more easily justified.
There are occasions where the road crosses
a tributary close to the junction with a
major stream. If the road is inundated by
both the local catchment runoff and
backwater from the major stream, the time
of submergence may be quite different for
the two flood mechanisms. The local
catchment runoff, from a small catchment,
may have a short time of submergence,
while the larger catchment may inundate
the road for longer periods of time. Local
residents can often identify these two Figure 10.6.3 - Typical Deck Level / Time
sources of closure and they may be quite of Submergence Relationship
distinct.
When calculating the time of submergence
In many cases the plot will reveal a

10 or closure in these situations, the


calculation must consider both sources of
inundation as well as the risk that the
particular grade level above which a
relatively large increase in level will result
in only a small decrease in time of
inundation is independent, in which case
submergence, and a small reduction in level
the times must be added together.
results in a large increase in average time of
When the flood immunity is very low, the submergence. Such a level may be selected
time of closure may not be represented as a starting point for economic analysis.
accurately by the flood event hydrographs.
In this case, long term records may need to
be analysed, but this situation would be

March 2010
10-10
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

10.6.4 Calculation of Time of submergence) or close the road (for


Submergence or Closure time of closure).
 Calculate the total period of time
There are two approaches to calculating
where the road is submerged (or
TOS / TOC of a road by flooding. The first
closed) from the complete record of
approach is for the situation where there is a
the stream gauge.
stream gauge located at the bridge site,
which is not a common occurrence. The  Calculate the average duration per
second approach is based on analysis of year that the road is submerged (or
flood hydrographs, and is the method that is closed). This is the AATOS (or
most commonly adopted. AATOC).
Analysis with stream flow records is the  This procedure does not provide the
most reliable approach and is recommended duration of submergence (or
if there is a nearby station. However since closure) for a particular flood event.
this is often not the case, the theoretical
As with all hydrologic analysis, it is
approach is more commonly necessary.
important that the stream flow record is
If there is a stream gauge located on the sufficiently long to provide a representative
stream at or very near the bridge, this gauge sample of flow at the bridge. If the period
can be used to analyse the TOS / TOC. of record is too short, or the period of
Whilst this does not occur commonly, it is record is not representative, the result from
the most accurate method for calculating the calculation may not be reliable.
the TOS / TOC. Use of a stream gauge is
It is hard to define the period of record that
also useful since calculated hydrographs are
would be adequate for this analysis, since it
prepared considering the maximum
depends on the variability at the site as well
discharge and the length of the hydrograph
as other conditions. However it is likely
may often vary and longer duration floods
that if there is less than 20 years of record at
with a lower peak discharge may be more
the site, the result may not be reliable.
critical in consideration of time of
submergence or closure than the actual peak If there is only a short record, careful
discharge. analysis can be used to assess the best
means of extracting data from the record,
If there is no stream gauge located close to
and useful information can be extracted.
the crossing, it is possible to calculate a
continuous record of discharge from a It is much more likely that there will not no
stream gauge located near the bridge, and

10
hydrologic model and to use this sequence
of flows in the calculation of TOS / TOC in the theoretical method discussed here must
exactly the same way as a stream flow be used.
record would be used. The first step in this process is to calculate
The procedure for applying the stream design flood hydrographs for the crossing
gauge records is as follows: site. This can be done with a catchment
hydrologic model, such as RORB or
 Calculate the discharge that will
RAFTS™. It is noted that the Rational
just inundate the road (for time of
Method calculates only the flood peak
discharge so is not suitable for application

March 2010
10-11
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

of time of submergence or time of closure Step 1.


calculations.
Determine the ARI of the flood for which
It is also noted that the actual time of the stream crossing is trafficable, i.e.
inundation of the road depends on the flood floodway with or without culvert or bridge.
levels and not necessarily the discharge so
Step 2.
in some cases, especially on large flat
floodplains, the hydrographs of water levels Determine the times of closure ty for a
may not be exactly the same as the series of floods greater than the trafficable
hydrographs of flood discharges so this capacity flood, and the ARI’s of each of
issue may need to be considered at times. these floods.

However the normal procedure is to Estimate tmax by extrapolating a graph of


calculate flood hydrographs of discharge time of closure versus ARI or by estimating
with a catchment model and use these the probable maximum flood for the
directly for the calculation. catchment. It should be noted that the
probable maximum time of closure cannot
To calculate the time of submergence or
be disregarded in the calculation of the
time of closure the following is required:
AATOC.
 A hydrograph of the flood, which
Step 3.
may be obtained from actual
measurements at the stream Calculate the probability FT(t) of the road
crossing, or for ungauged streams, being closed for each ARI y year flood:
by the use of a runoff routing FT(t) = 1 – 1/y
method or synthetic hydrograph
Step 4.
method. (An experienced hydraulic
engineer is required to undertake Using the times of closure, ty and the
these analyses.) probability, FT(t) of the road being closed
for each ARI y year flood, draw the
 Flow capacity of the crossing at the
cumulative probability distribution.
point of submergence or closure.
This distribution gives the probability of the
 The time of submergence or closure
road being closed in any year for less than t
may then be calculated by drawing
hours.
a horizontal line on the hydrograph
at the flow capacity level and Step 5.
measuring the time for which the
Determine the probability density function:

10 flow is above this level.

10.6.5 Procedure for Estimating


fT (t) = ∆ FT(t) / ∆t
This is the slope of the line connecting each
AATOC / AATOS
point on the cumulative probability
distribution.
The procedure for calculating the average
annual time of closure (AATOC) is as Step 6.
follows:
Determine AATOC as:

AATOC   p  t

March 2010
10-12
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Where: The tailwater level for floodways with other


than grassed batters is usually more than
 ∆p = area of each rectangle in the
300 mm and up to 600 mm or even 700 mm
probability density function; and
below the downstream edge of the road
 t = centroidal distance of each rectangle formation when overtopping first occurs.
from the fT(t) axis of the probability
Overtopping flows of long duration and at
density function.
frequent intervals may cause pavement
The same procedure is used for AATOS failures, and softening of the embankment,
except a lower flow is used to derive critical aggravating any tendency to scour. Even
flood level. with a high tailwater when the flood is at
the point of overtopping the road, the time
10.7 Floodway Protection
of submergence may indicate the need for
10.7.1 Types of Protection more elaborate protection other than natural
grass.
Selection of the form of protection of
floodways against scour is governed by: 10.7.2 Floodways with Grassed
Batters
 Whether flow across the floodway
is free or submerged; and Grass in this type of floodway is defined as
 Under free flow conditions, turf or seeded grass. Reinforced grass is
whether plunging or surface flow discussed in the Chapter 8.
occurs downstream from the Because the physical properties of grass
floodway. such as species, stiffness, cover density and
The tailwater level when the flood is at the rooting pattern varies with soil type and
point of overtopping the road usually climate, only general guidelines based on
controls the degree of protection required constructed floodways in Queensland are
for a particular floodway. Therefore, the possible.
cost of providing adequate bridge and/or Floodways with grassed batters should have
culvert waterways to raise the tailwater to a the following features:
high enough level to require minimum
 Bitumen seal or asphalt pavements
protection becomes a prime consideration
with concrete or other rigid margins
as well as the cost of the protection itself.
/ shoulders (stone pitching, cement
Floodway protection is considered in two stabilised gravel etc.) containing

10
categories: the bitumen in place;
 Minimum protection such as  As an alternative to (a) above,
grassed batters; and concrete blocks / nib walls along
 Other than grassed batters. the top edges of the formation with
bitumen seal or asphalt pavement
The tailwater level for floodways with
between them may be constructed.
grassed batters is usually not more than 300
These containing blocks may be as
mm below the downstream edge of the road
simple as 10% by volume cement
formation when overtopping first occurs.
stabilised gravel strips 600 mm
wide at the top by 180 mm deep;

March 2010
10-13
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

 Culverts under the floodway and savings in these areas should not be
section should raise the tailwater to considered.
not more than 300 mm below the
Five types of floodway which have
downstream edge of the road
performed satisfactorily are described in
formation when overtopping first
this section with their associated limitations
occurs;
specified. All these types of floodways
 Overtopping should occur for a should have the following general features:
period of less than 12 hours in a 50
 Culverts to raise the tailwater to not
year average recurrence interval
more than 600 mm below the
flood. However, the type of
downstream edge of the road
material in the embankment and its
formation when overtopping first
saturated strength may require
occurs (actual range 300 - 700
reduction of this allowable time of
mm). It is important to note that
submergence.
this afflux may not be acceptable in
Conversely there are some low floodways some areas and non-standard
that can withstand submergence for much additional outlet protection at
longer. culverts may also be necessary;
For this type of protection, it is desirable to  Full protection of the top surface of
have good grass cover when the the road formation, as for
overtopping flood occurs and this in turn floodways with grassed batters;
requires an ability to maintain grass cover
 Protection of at least the
during the dry season.
downstream batter. Although not
Concrete pavements if used instead of clearly defined, it appears that
bituminous types will, of course, cover the protection of the upstream batters
full width of the formation and not require may only be required in floodways
grass batter protection. of low flood immunity in major
streams. As a precaution where
10.7.3 Floodways with Other only downstream protection is
than Grassed Batters adopted, protection for a distance of
about 3 metres on each side of
There have been many types of floodways
major culverts on the upstream side
successfully constructed in Queensland
may be placed to offset possible
with other than grassed batters.
scour due to turbulence from the

10 Recommended types of protection are


described and illustrated in this section and
the selection of the type of protection would
mixing of longitudinal and direct
flows at the culvert inlets;

be based on a cost comparison of  Adequate downstream aprons. For


recommended types considered suitable to height of road embankment, H,
that locality. equal or more than 2.0 m, the
downstream apron should extend at
Most failure of floodways with downstream
least 1.5H metres away from the
batter protection in the past commenced by
toe of the embankment. For H less
scouring at the downstream aprons and/or
than 2.0 m, the downstream apron
the downstream edge of the road formation

March 2010
10-14
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

should extend at least H away from Type 1 Floodway


the toe of the embankment unless
This type of reinforced concrete floodway
other specified; and
has been constructed in many areas of the
 Weepholes in the downstream rigid State, particularly in the west. The
protection to relieve hydrostatic reinforcement selected should not only
pressure. These weepholes are satisfy strength requirements, but also
normally about 90 mm diameter at prevent temperature and shrinkage cracks.
1.8 m (maximum) centres with 300
Where cut-off walls have been used without
x 300 x 150 no-fines concrete
the downstream apron, failures have
blocks behind the weepholes. The
occurred.
weepholes should be placed about
300 mm above the apron level or With a suitable width of downstream apron
just above long standing water level and weepholes, the Type 1 Floodway is
if higher. The more porous types of recommended as suitable for all crossings
protection such as rock on filter where other than grass protection is
cloths or layers and some cement required, cost permitting.
stabilised gravels, depending on the Type 2 Floodway
grading, do not require weepholes.
This is an example of a reinforced concrete
A brief description of the five successful floodway where the tailwater depth is
types of floodway protection follows and uncertain but probably quite low (perhaps
sectional details of these types are shown in 700 mm or more below the downstream
Figures 10.7.3(a) and 10.7.3(b). These edge of the formation when the flood
types are not in any order of preference and begins to overtop the road). No adverse
comparative cost comparisons should be reports are known. Costs are higher than
made where more than one suitable Type 1 floodways.
protection is considered.
Type 3 Floodway
A brief mention of reinforced grass, or a
This previously used type is no longer
type of geotextile protection as it is also
recommended.
known in the USA, is given in Other Types.
Although it appears to have been successful Type 4 Floodway
in some stream channels, little is known
This is considered by some to be an
about its performance in floods overtopping
improvement on Type 3. The increased use
embankments.
of stone mattresses and gabions has given
confidence to this type of construction.
10

March 2010
10-15
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Most common type.


Widely Used.

TYPE 1 – Concrete Protection

Type performs well, but


need to justify cost.
Requires specialist
design.

TYPE 2 – Concrete Protection


An improvement over
previous Type 3.
Mattresses must be
pinned / anchored.
Consider a cutoff wall.
Cut off walls may not be
necessary as mattresses,
usually achieve their
optimum position with a
little scour by dropping
into a scour proof position
TYPE 4 – Rock Mattress Protection
Figure 10.7.3(a) - Downstream Floodway Protection (Types 1,2 & 4)

Type 5 Floodway  Time of submergence is small


(hours).
This type of protection incorporating a

10 bituminous seal is probably the lowest cost


of the types shown, but its use is limited.
Rock fill with size 70 - 100 mm and median
diameter 85 mm would be adequate for
most uses.
It should only be used only where:
Type 6 Floodway
 Fill height is not higher than 900
mm; This previously used type is no longer
recommended.
 Tailwater at overtopping is not
more than 300 mm below the
crown of the road; and

March 2010
10-16
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design

Type 7 Floodway
This floodway was designed for use in
Western Australia and is described in
Waterways Design (Aust roads 1994).
As the riprap consists of rock with grading
requirements, it may have limited
application in Queensland where supplies
of such rock are scarce where floodways
are constructed.
Further details of the required grading and
riprap thickness may be obtained from the
reference.

Common, low cost type.


Suitable for low velocities
over floodway situations
only.

TYPE 5 – Bitumen Seal Protection

Variation to Type 4 where


mattresses are not
readily available.
Consider a cutoff wall.

TYPE 7 – Dumped Rock (RipRap) Protection


10
Figure 10.7.3(b) - Downstream Floodway Protection (Types 5 & 7)

March 2010
10-17

Potrebbero piacerti anche