Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Chapter 10
Floodway Design
10
March 2010
i
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10
March 2010
ii
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Table of Contents
10.1 Introduction 10-1
10.2 Additional Considerations 10-1
10.3 Geometric and Safety Issues 10-1
10.4 Environmental Factors 10-2
10.5 Hydraulic Design 10-2
10.5.1 Floodway Terminology 10-2
10.5.2 Flow Over the Road 10-4
10.5.3 Full Floodway Design Calculations 10-4
10.6 Time of Submergence / Closure 10-8
10.6.1 Time of Submergence 10-9
10.6.2 Time of Closure 10-9
10.6.3 Issues Related to Times 10-9
10.6.4 Calculation of Time of Submergence or Closure 10-11
10.6.5 Procedure for Estimating AATOC / AATOS 10-12
10.7 Floodway Protection 10-13
10.7.1 Types of Protection 10-13
10.7.2 Floodways with Grassed Batters 10-13
10.7.3 Floodways with Other than Grassed Batters 10-14
10
10
March 2010
iii
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10
March 2010
iv
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Chapter 10
Floodway Design
March 2010
10-1
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Exceptions to the level grading in during times of flood, then a check should
Queensland occur where bridges have been be done on allowable flow velocities.
built significantly higher than the flooded
The procedures outlined in Section 9.7
approaches on both sides. The bridges have
should be followed for fauna passage
been built on the basis that the approaches
through culverts.
will be raised sometime in the future.
As noted above, floodways reduce the
Floodways should not be placed on
concentration of flow, compared to culverts
horizontal curves as:
or bridges, so the risk of scour damage to
there are problems in defining the waterway and surrounding land is reduced.
edge of the pavement for motorists;
10.5 Hydraulic Design
any superelevation may change the
normal flow distribution i.e. push 10.5.1 Floodway Terminology
more water to the non-
superelevated sections of road; and A floodway consists not only of the
roadway embankment to accommodate
the water depth will be deeper on flow over the road but also waterway
one side of the road than the other openings to provide for flow under the road.
in a superelevated section of road These openings may be required for one or
and there is the possibility of the more of the following functions:
high side being trafficable but not
the other, thus creating a safety reduce the afflux or rise in water
problem. level upstream due to the
obstruction (embankment);
Floodways should also not be located on
vertical curves to avoid variations in depths raise the tailwater level so that less
of flows. batter protection is required on the
downstream side e.g. grass instead
For further geometric requirements of of concrete; and/or
width, crossfall, vertical and horizontal
alignment, refer to the relevant chapters of act as anti-ponding structures for
the department’s Road Planning and low flow stream conditions.
Design Manual. Signage of the floodway is Flow over roadways may be:
also important and designers are referred to
free flow; or
the latest release of the Manual of Uniform
Traffic Control Devices for warrants / submerged flow.
10 guidance.
10.4 Environmental Factors
In the initial stages of overtopping a low
tailwater usually exists and free flow
occurs. Under these circumstances flow
For floodways that contain floodplain
passes through critical depth over the road
culverts (i.e. culverts located away from a
and the discharge is determined by flood
watercourse channel) only terrestrial
levels upstream.
movement generally needs to be
considered. However, if fish migration is
expected to occur across the floodplain
March 2010
10-2
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Free flow may be either: tailwater. This flow will have less
erosion potential downstream.
plunging flow which flows over the
shoulder and down the downstream Submerged flow occurs when the
face of the embankment. The flow discharge is controlled by the tailwater level
then penetrates the tailwater surface as well as the headwater levels. This occurs
producing a submerged hydraulic when the depth of flow over the road is
jump on the downstream slope. everywhere greater than the critical depth.
Velocities are likely to be high and
Typical velocities of flow over a floodway
erosive; or
are shown on Figure 10.5.1 as sourced from
surface flow which separates from Waterway Design (Austroads 1994) after
the surface of the road embankment Cameron and McNamara (1966).
and rides over the surface of the
March 2010
10-3
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Where:
10.5.2 Flow Over the Road
V2
The broad crested weir formula used for H h = Specific Head
2g
flow over a road is:
On Figure 10.5.2;
C
Q C f LH s
1.5 for H/l > 0.15 (usual case) Use
C
f curve B to obtain the free flow
Where: coefficient of discharge, Cf.
V = approach velocity of the stream The basic principle is that the total flow
(m/s); and over the road and through the waterway
structures equals the flow downstream in
l = top width of road formation (m).
the unrestricted channel.
The flow over the floodway may be
Given the many combinations of headwater
calculated by means of the following design
and tailwater possible, it is necessary to fix
procedure:
at least one of these parameters for each
Calculate the stage-discharge curve design calculation.
(height versus discharge) for the
With flow over the road, the issue of
10
unrestricted section, from open
whether or not road batter protection is
channel hydraulics (refer Chapter
needed becomes important as the
8);
calculations require the tailwater to be fixed
Select a tailwater level and a when the flood is at the point of
headwater level (giving h and V) overtopping the road.
from the stage-discharge curve.
H
Calculate
l
March 2010
10-4
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10
March 2010
10-5
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Guidelines relating to the need for (c) Fix the headwater level at the crown of
protection are given in Section 10.7 with the road (or the highest edge if
the tailwater level generally in the range superelevated). Avoid the design of
0.4m to 0.6m below the crown of the road superelevated floodways, if possible, as
when the road is about to be overtopped. these can result in depth variations
laterally and surface debris on the
Full floodway design must satisfy Case A
floodway surface can compromise
and Case B conditions.
safety. Residual, silt and gravel on
Case A: When the flood is at the point of floodways after isolated rainfalls events
overtopping the road: can provide hazards on their own,
Tailwater level is not below the causing serious injury. Effective
level specified for the type of maintenance programs must be in place
protection to be adopted; and by relevant authorities and new designs
of new floodways need to minimise
Velocities through the bridges
risk.
and/or culverts are acceptable.
(Scouring velocities may be (d) Find the velocity Vx through a suitable
acceptable, if additional outlet major culvert / bridge with the
protection or the formation of scour headwater in (c) above and the tailwater
holes is acceptable). adopted for the type of floodway
protection to be adopted. Say this
The step by step design procedure for this
tailwater level is RLx on Figure 10.5.3
case follows:
Case A, corresponding to a total
Figure 10.5.3 illustrates results of discharge, Qx in the unrestricted
calculations performed using the steps (a) to channel.
(g) below for an actual floodway.
(e) With this velocity Vx find the total area
(a) Calculate the rating curve (height of waterway required from Total Area
versus discharge) for the unrestricted Required = Qx/Vx and select other
channel. culverts to give this total.
(b) Fix the level of the road as a first trial. (f) For the fixed headwater and the
The initial level of the road may be tailwater level, RLx, calculate the actual
based on trafficability eg for required flow through each culvert and bridge
trafficability in a ARI 20 year flood, the and total the discharges to give Qy
initial road level may be the level of the which may or may not be equal to Qx
March 2010
10-6
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
CASE A
CASE B
Note that the initial assumption of all the Note: The design velocities through
waterways having the same velocity is culverts are normally in the range 1.8 m/s
approximate only as different size and to 3.0 m/s with 2.4 m/s commonly adopted,
shape openings have different hydraulic depending on the scour resistance of the
10
efficiency. This is why the same head will surface material downstream. Higher and
give different velocities. lower velocities have been adopted.
Chapter 9 discusses the hydraulic design
The structures giving Qx are to be
of culverts and Chapters 7 & 13 methods
considered minimum requirements for the
of erosion control.
floodway regardless of the requirements
calculated for a peak flood above the
roadway, as all overtopping floods pass
through this stage.
March 2010
10-7
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Case B: At the peak of the flood above through the waterways. Similarly,
the floodway: Q3 etc may be obtained.
Velocities through the waterway Plot Q1, Q2, Q3 etc. against their
structures are acceptable; and respective headwater levels. Join
these points to make the curve
Afflux caused by the floodway is
shown on Figure 10.5.3 Case B.
acceptable.
From the curve, find the headwater
The step by step design procedure for this
which gives the required design
case follows:
flood discharge.
At the peak of the overtopping flood,
If the afflux is acceptable,
allowance for flow over the road must be
calculations are complete. If the
made and afflux calculated for the design
afflux is too high, additional bridge
flood (ARI 20 year in the example in Case
or culvert waterways are required.
A above).
Waterways from Case A are not to
The flow over the road is added to that be reduced.
through the culvert(s) and bridge(s) and the
Calculate the afflux for the check
calculations initially include the structures
flood (usually of ARI 50 years).
from Case A. With reference to Figures
10.5.3 and Case A and Case B, the Because of flow over the road, maximum
procedure is: velocities are obtained from Case B.
Find the tailwater level Both velocity and afflux requirements are to
corresponding to the design flood be met.
discharge from the rating curve for
10.6 Time of Submergence
the unrestricted channel.
/ Closure
Select a headwater level slightly
Some of the following text and diagrams
above the tailwater level in (a), say
have been taken from Bridge Waterways
0.1 m above, and calculate the flow
Hydrology and Design (NAASRA 1989)
over the road and through each
and Waterway Design (Austroads 1994).
culvert and/or bridge with this
headwater - tailwater combination. Where a crossing is designed for
Add these flows together to obtain overtopping, it is usually important that an
a total flow, say Q1. estimate be made of the frequency and
duration of the periods during which the
March 2010
10-8
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10.6.1 Time of Submergence close the road, though there may be some
hazard in travelling on the inundated road.
Time Of Submergence (TOS) is defined as
Different types of vehicles can travel on
the period of time that the road is inundated
roads with different amounts of inundation
by flood water, no matter the depth.
with large and heavy vehicles capable of
The time of submergence is expressed in travelling in water that is deeper and
one of two main ways. The first is the time flowing at a higher velocity than a light car.
of submergence during a major flood - for
Safety of vehicles in flood water is poorly
example, the number of hours of
understood and there has been considerable
submergence during the flood with an
research on the topic.
average recurrence interval of 50 years.
The second is as the Average Annual Time There are different definitions of the flow
Of Submergence, abbreviated as AATOS. conditions when the road is closed by flood
This is the average time per year that the waters. The normally adopted limit in the
road is submerged, expressed as hours per department is when the total head across the
year. road exceeds 0.3 m. That is:
Both expressions are an indication of the Total head (H) = d + v2/2g
frequency and duration of submergence.
Where:
For example a crossing that is submerged
frequently for short periods of time may d = depth of inundation
have a similar AATOS as one that is v = flow velocity
submerged less frequently for longer times.
g = gravity (9.81m/s2)
To understand the concept and to compare
options, three parameters are needed, Similar to AATOS there is an Average
namely: Annual Time Of Closure, abbreviated as
AATOC
Flood immunity;
TOS for the ARI 50 year flood (or 10.6.3 Issues Related to Times
other large flood);
The concept of time of closure, in
AATOS.
association with the time of submergence,
The absolute value of the time of adds some additional information to the
submergence is not particularly useful by question of flood immunity.
itself for a crossing, but it is useful to
Large and flat catchments will respond
compare several crossings or
options.
upgrading
more slowly than small and steep
catchments so the time of submergence for 10
these catchments will generally be longer
10.6.2 Time of Closure
for an equivalent flood immunity.
Time Of Closure (TOC) is similar to time In small steep catchments, where the
of submergence. However this parameter response time is short, the time of
takes account of the fact that some submergence will be low, even for a
inundation of the road may not necessarily crossing with low flood immunity.
March 2010
10-9
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
In small steep catchments, and also for unusual for state controlled roads in
urban catchments where the response time Queensland though it does occur on
is short, floods may occur and then recede interstate main roads and on more minor
very quickly. In this case the disruption to roads.
traffic may be short. Similarly in small
These situations can occur where the road is
catchments, the depth of inundation may be
inundated for months at a time during the
low even if the flood immunity is low. In
wet season or even sometimes the road may
this situation, the time of submergence may
be inundated by tides. The calculation in
be short so the cost of disruption may be
this case is very difficult and should use
very low and the additional cost of
either a stream gauge or calculated
providing for a higher level of flood
continuous discharge records.
immunity may not be justified.
Average time of submergence or closure
On the other hand, large catchments that
may be assessed for a range of selected
have a long response time may inundate the
grade levels and a plot of average time of
road for extended periods of time. In this
submergence against level may be produced
case the cost of disruption may be very high
as in Figure 10.6.3.
and a higher level of flood immunity may
be more easily justified.
There are occasions where the road crosses
a tributary close to the junction with a
major stream. If the road is inundated by
both the local catchment runoff and
backwater from the major stream, the time
of submergence may be quite different for
the two flood mechanisms. The local
catchment runoff, from a small catchment,
may have a short time of submergence,
while the larger catchment may inundate
the road for longer periods of time. Local
residents can often identify these two Figure 10.6.3 - Typical Deck Level / Time
sources of closure and they may be quite of Submergence Relationship
distinct.
When calculating the time of submergence
In many cases the plot will reveal a
March 2010
10-10
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10
hydrologic model and to use this sequence
of flows in the calculation of TOS / TOC in the theoretical method discussed here must
exactly the same way as a stream flow be used.
record would be used. The first step in this process is to calculate
The procedure for applying the stream design flood hydrographs for the crossing
gauge records is as follows: site. This can be done with a catchment
hydrologic model, such as RORB or
Calculate the discharge that will
RAFTS™. It is noted that the Rational
just inundate the road (for time of
Method calculates only the flood peak
discharge so is not suitable for application
March 2010
10-11
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
AATOC p t
March 2010
10-12
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
10
categories: the bitumen in place;
Minimum protection such as As an alternative to (a) above,
grassed batters; and concrete blocks / nib walls along
Other than grassed batters. the top edges of the formation with
bitumen seal or asphalt pavement
The tailwater level for floodways with
between them may be constructed.
grassed batters is usually not more than 300
These containing blocks may be as
mm below the downstream edge of the road
simple as 10% by volume cement
formation when overtopping first occurs.
stabilised gravel strips 600 mm
wide at the top by 180 mm deep;
March 2010
10-13
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Culverts under the floodway and savings in these areas should not be
section should raise the tailwater to considered.
not more than 300 mm below the
Five types of floodway which have
downstream edge of the road
performed satisfactorily are described in
formation when overtopping first
this section with their associated limitations
occurs;
specified. All these types of floodways
Overtopping should occur for a should have the following general features:
period of less than 12 hours in a 50
Culverts to raise the tailwater to not
year average recurrence interval
more than 600 mm below the
flood. However, the type of
downstream edge of the road
material in the embankment and its
formation when overtopping first
saturated strength may require
occurs (actual range 300 - 700
reduction of this allowable time of
mm). It is important to note that
submergence.
this afflux may not be acceptable in
Conversely there are some low floodways some areas and non-standard
that can withstand submergence for much additional outlet protection at
longer. culverts may also be necessary;
For this type of protection, it is desirable to Full protection of the top surface of
have good grass cover when the the road formation, as for
overtopping flood occurs and this in turn floodways with grassed batters;
requires an ability to maintain grass cover
Protection of at least the
during the dry season.
downstream batter. Although not
Concrete pavements if used instead of clearly defined, it appears that
bituminous types will, of course, cover the protection of the upstream batters
full width of the formation and not require may only be required in floodways
grass batter protection. of low flood immunity in major
streams. As a precaution where
10.7.3 Floodways with Other only downstream protection is
than Grassed Batters adopted, protection for a distance of
about 3 metres on each side of
There have been many types of floodways
major culverts on the upstream side
successfully constructed in Queensland
may be placed to offset possible
with other than grassed batters.
scour due to turbulence from the
March 2010
10-14
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
March 2010
10-15
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
March 2010
10-16
Department of Transport and Main Roads Chapter 10
Road Drainage Manual Floodway Design
Type 7 Floodway
This floodway was designed for use in
Western Australia and is described in
Waterways Design (Aust roads 1994).
As the riprap consists of rock with grading
requirements, it may have limited
application in Queensland where supplies
of such rock are scarce where floodways
are constructed.
Further details of the required grading and
riprap thickness may be obtained from the
reference.
March 2010
10-17