PROJECT TITLE:
INTERLINKING OF ENOC FACILITIES WITH GULF REFINING COMPANY(GRC) BERTHS
6&11
CLIENT:
PROJECT MANAGER:
1
Method Statement & Risk Assessment
Approvals HEJP:
2
People Involved in The Project:
Designation
1. Project Manager
2. Sr. Project Engineer
3. Engineer
4. Supervisor
5. HSE Officer
6. QA/QC Engineer
7. Rigger
8. Surveyor
9. Carpenter
10. Steel fixer
11. Mason
12. Painter
13. Rigger
14. Helpers
15. Drivers & Operators
16. Soil testing technician
17. Drivers & Operators
3
1. Brief Description Of Work:
To establish safety guideline/method statement to carry out the excavation & civil works for laying
proposed jet fuel pipe line in HEJP Terminals (except road cross area near PLR), area as marked in
the drawings (ABE-670-PIP-GA-07-REV 2). The Construction work shall carry out by eliminating all
possible safety risks/hazards and confirm that installation is as per the project standards in HEJP
Terminals.
This method statement describes below works at HEJP Terminals for proposed Jet Fuel Pipeline.
1) Excavation for pipe trench
2) Backfilling with reinstatement works
4
4. Safety materials:
PPE ( cotton cover all, safety shoes, safety goggles, ear plugs, dust mask, apron )
1) Fire extinguisher (DCP) 9 kg 2nos
2) Vibration resistance Hand Gloves for Jack Hammer
3) Hand gloves for Hot works/Concreting
4) Face shield
5) Gas monitors
6) First aid kit
7) Gum boot
8) Cotton rags
9) Hand cleaner
10) Red cones
11) Warning tape
12) Hard barriers
13) Safety signage
5. Methodology
General:
1) Work permit shall be obtained from HEJP before starting any site activity.
2) Safety barricade shall be provided to warn others about possible hazards. Safety sign
boards also shall be displayed at works place.
3) Competent supervisor, Safety officer and Safety watcher shall be assigned for the site
activities.
4) Periodic Gas monitoring shall be ensured.
5) Safe access to the operational area shall be ensured.
6) Permanent bench mark & reference point shall be identified for cross verification of
levels/points.
7) QC inspections by all parties (ABE, ENOC and Trakhees) shall be carried out at
intermediate execution phases to ensure quality as per agreed QC standards.
8) Inward materials inspection & reporting shall be done as per approved ITP.
9) Proper material handling & stacking shall be ensured. Cranes will be used for unloading
the Precast Protection slab and other equipments.
5
1. Excavation for pipe trench
1) Excavation location to be identified and marked as per approved drawings( highlighted
in ABE-670-PIP-GA-07 REV 2)
2) All underground services will be rechecked in as built drawings and confirm with CAT
scanner before starting excavation.
3) Proper barricades and safety signage to be provided for excavation works.
4) Alternate access to be provided for operations as per HEJP requirements.
Road Crossing Area (Near Sampling Room)
5) Excavation trench at road cross area to be identified and marked.
6) Access will be closed for vehicle movement and temporary man crossing bridge made
by scaffolding materials shall be provided.
7) Proper barricades and safety signage to be provided for excavation works and diversion
8) Interlock shall be removed using crow bar and hand tools.
9) Removed interlocks shall be stored at designated area.
10) Existing Concrete to be removed using Electrical/ pneumatic Jack hammer.
11) All underground services shall be identified using CAT scanner before starting
excavation.
12) Shoring/benching/slope shall be provided below 1.2 mtr, which is applicable according
to the work area and excavation depth (details to be submitted prior to starting
shoring/benching/sloping)
13) The excavated soil to be kept at 1 mtr distance from excavation trench.
14) Confined space permit to be obtained after reaching 1 mtr depth of excavation.
15) After Completion of Excavation, trench will be inspected as per specification and
Approved ITP.
16) De-watering shall be arranged in-case of any ground water accumulation.
17) Pipe laying and Installations works shall be carried out as per approved Pipe line laying
MSRA.
Note: Excavation for the balance area & Road cross area (Near PLR) civil works amendment
will be submitted later
1) After lying of pipeline back filling and reinstatement work will start as follows. (MS RA
for Laying of pipeline will be submitted for approval separately.)
2) Survey works and setting out to be carried out on proposed RCC structures and survey
reports, as-built drawings to be submitted before starting backfilling.
3) Backfilling shall be carried out layer by layer and Compaction tests shall be taken as
per specifications and approved drawings.
4) Backfilling shall be done using Bobcat where ever possible.
5) U/G cable Duct to be provided for E & I cable laying works.
6) Compaction works shall be done using plate compactor.
6
7) Protection slab to be provided at Road crossing area as per approved drawings
(ABE‐670‐GEN‐SK‐36 Rev A).
8) Pre‐casted protection slab of size 2m x 1.5 m x .275 mm shall be shifted to site using
40’ trailer truck.
9) Pre‐casted protection slab shall be installed with the help of mobile crane.
10) Competent employees shall be deployed for activities.
11) Area of lifting will be properly barricaded.
12) Lifting plan will be submitted prior to lifting activity for Approval.
13) Existing gravel to be refilled after completion of Backfilling.
14) Interlock paving to be re‐instated at road crossing area after backfilling.
15) Base of kerbed stone to be concreted using Transit Mixer.
16) Interlock re‐instatement to be done as per procedure.
6. Responsibility Matrix:
SI # Activity Performed By
1. Gas Monitor ABE Safety
2. Clearance for Permit To Work PTW Receiving Authority
3. Communication With HEJP PTW Receiving Authority,
HSE Officer (ABE)
4. Issuing of PTW HEJP
5. Induction of Work Force PTW Receiving Authority,
HSE Officer (ABE)
6. Obtain PTW PTW Receiving Authority
7. Barricading the area PTW Receiving Authority,
HSE Officer (ABE)
8. Confined Space Entry PTW Receiving Authority,
HSE Officer (ABE)
9. Site Construction Activities PTW Receiving Authority
(ABE), Sr Engineer
7. Safety Precautions:
1. All workforces will attend induction training provided by HEJP terminal safety department.
2. Conduct a tool box meeting for all personnel assigned to the job prior to start activity on
daily basis and will be ensured to make them aware about potential hazards involved
within the work area and relevant safety measures to be taken.
3. Conduct a task risk assessment meeting to access the hazards involved and control
measures to be taken prior to start of activity and assign a safety officer for the job. All
control measures will be according to RA.
4. Gas testing shall be done as per HEJP guidelines and will be recorded.
7
5. All personnel have necessary PPEs.
6. Trained persons will be deployed for the job.
7. Obtain work permit from Horizon terminal, prior to commencing any activity.
8. Accident reporting as per safety procedure will be ensured.
9. First aid box with medicine shall be kept at site.
10. Ensure that the existing facilities are not disturbed during the work.
11. Supervise all operations by experienced supervisor/ foreman.
12. All vehicles/ diesel equipment entering into the site should be fitted with spark arrester and
inspection to be done by HEJP prior to enter the site.
13. Daily housekeeping should be done at work site inside the terminal. Debris and other
construction material shall be carted away and dumped to approve dumping area as
required.
14. Midsummer break times and Ramadan timings stipulated by Dubai Government will be
followed
15. No spark tool will be used
16. Petrol operated engine vehicles and equipment are not allowed inside HEJP area
17. Adequate earthing to be provided to the generator
8. Attachments:
1. Risk Assessments
2. Drawing References
ABE-670-PIP-GA-07 REV 2
ABE-670-GEN-SK-36-REV A
8
HORIZON EMIRATES JEBEL ALI TERMINAL [HEJT]
Process RISK ASSESSMENT FOR CIVIL WORKS FOR PROPOSED PIPELINE INSTALLATION AT HEJP AREA Location HEJP RA No ABE-J670-RA-30
Associated MS / WI /
Date & Rev No 05.04.2018 Rev. A Last Review Date Next Review Date
Procedure No
ABE-J670-MS-30
.Prior to mobilization Operatives shall receive HEJP EHS induction and PTW training
for job.
.Supervisor/Foreman/Engineer shall follow HEJP PTW Procedure and Obtain valid
permit before work commencement in HEJP terminal.
.Workers shall adhere to mandatory PPEs required on site.
.Lack of awareness in .Dedicated full time safety watch/safety officer shall be deployed .HEJP Emergency Preparedness and
live terminal .All related equipment’s to be used shall comply with HEJP EHS/Trakhees/ENOC Response Plan will be followed in case of
.Unauthorised Entry requirements any emergency.
.Uncontrolled vehicle .Equipment Daily/Weekly/Monthly inspection shall be conducted by respective .Ensure Equipment and vehicle shall be
Preparation and Site
movement supervisor/Maintenance Team. inspected by HEJP prior to entry into HEJP
Mobilization of Mobilization of workforce, .Personal injury Engineer/
.Over speeding .Barrication and appropriate safety signs shall be provide to prevent any area
1 workforce and equipment / vehicles .Environmental pollution 3 2 Y 6 3 1 Y 3 Supervisor /
.Spark unauthorized entry. .All Personnel involved in the works shall
equipment /trailer for offloading of .Property Damage Safety
.Unauthorised .Flagmen to be deployed. attend in-house Job Specific EHS training.
material by using crane Inspector
Operator .Follow Speed limit (10km/h) .Equipment to be colour coded / inspection
.Defective Equipment .Firefighting arrangements shall be kept nearby (DCP-9 kg 2 No’s) sticker has to be provided for the same by
.Oil Spillage .Ensure Authorised Drivers (with valid UAE license) for vehicles competent personnel.
.Fire .Ensure spark arrester for equipment / Vehicle
.HEJP EHS/Operation recommendation shall be taken into consideration and strictly
Comply with HEJP PTW Requirements .Only
diesel operated equipment / Vehicle allowed
.Ensure Cat scan shall be done for identifying any underground facility by referring
as built drawing.
.Fire blanket habitat to be provided for concrete chipping activities & periodical gas
monitoring shall be ensured.
.Safe Distance shall be maintained from existing facilities and ensure access and
egress are maintained free from any obstructions.
.ABE shall strictly adherence to the HEJP PTW requirements.
.Daily tool box talk shall conducted with entire working crew.
.Electricity .Firefighting arrangements shall be kept nearby (DCP-9 kg 2 No’s).
.Dust .Physical Injury .All demolished material shall be kept at designated area allotted by HEJP before
.Improper posture .Fatigue, closing the permit on daily basis.
.Hand tools .Injuries due to Failure of .Only competent personnel shall perform the task
.Flying particles. Power Tools .Power tool shall be inspected & apply colour code
.Ensure Equipment shall be inspected by Site
.Access/egress .Damage to the property .Flying objects protection measures to be in place.(Fire blanket/temporary
PCC breaking using hoardings) HEJP Engineer/
.Existing services .Electrocution
4 PCC breaking Power Tools (Electrical .Ensure the usage of appropriate hearing protection measures by all personnel 3 2 Y 6 .Fire hose kept charged while performing 3 1 Y 3 Supervisor /
.Sparks .Noise induced hearing
Jack Hammer, chisel etc.) working in the vicinity of demolition activity demolition activity. Safety
.incompetent loss.
.No loose clothing will be worn by operatives. .Any Inspector
personnel .Entanglement
damage tools shall return to store and Put tag "Do not Use”. .Safe manual .Ensure to check as built drawings to
.Noise .Hand/Arm Vibration
handling measures has to be followed. identify underground facilities.
.Fire Syndrome (HAVS)
.Ensure all power connection through ELCB
.Cement
.Concrete truck pre- site entry inspection shall be conducted by ABE safety officer
.Slip/trip
.Skin irritation to ensure meeting HEJP/ENOC requirements.
.Failure of support
.personal injury .Concrete truck / operator shall have valid Driver’s licence.
system / platform
.Chemical burn due to .Concrete delivery truck(s) to be fitted with spark arrester
.Failure of concrete
concrete corrosively .Toolbox talk to be conducted with entire crew. Proper PPE shall be provided .concrete vehicle truck drivers shall be
truck
.loss of property / facility .Polythene sheets shall be used when necessary to prevent direct contamination of attending HEJP induction.
.Pressure Supervisor /
Concrete Pouring of PCC manually damage soil. .All drivers for delivery must be aware of
8 .Vehicle Collison with 3 2 Y 6 3 1 Y 3 Safety
Pouring / with cement mix truck .Environmental .Area to be properly barricaded and signs to be displayed. approved route, speed limit and other road
other vehicle and Inspector
degradation due to wet .Flagmen to be station to assist vehicular movement user instructions as per HEJP terminal.
existing facility
concrete -concrete .Appropriate PPEs to be used. (Rubber hand glove, disposable coverall, gum boot)
.Environmental
spillage .Speed limit must be followed. (10 km/hr)
Spillage
. .Firefighting arrangements shall be kept nearby (2 no’s of 9kg DCP)
.Over speeding
.No washing or cleaning of concrete vehicle allowed at site
.Sparks
.Fire
.All debris / unused materials at the civil work area shall be removed and stacked at
safe distance on daily basis prior to permit closure.
.injury due to trip or slip .Housekeeping shall remain a continuous
.Removal of unwanted .Trip / Slip .Cable management shall prevail at all times
.Fall of wrongly stacked activity at the site.
debris .Improper material .All walkway, access and egress shall be kept free of material that can induce
11 Housekeeping material. 2 3 N 6 .Inspection on housekeeping shall be done 2 1 Y 2
.Waste disposal stacking trip/slip or obstruction
on a daily basis.
.Barricading /Signs for material storage shall be ensured.
.Housekeeping shall remain a collective responsibility
.Materials shall be properly stacked
Date Page
Form No Revision No 8-Mar-12 1 OF 2
EHSMS-F0-3A 03
20 to 25 STOP VERY HIGH Do not take the risk
10 to 16 ALERT HIGH Reduce to at least Medium Risk Level
5 to 9 CAUTION MED Reduce / Demonstrate Risk Level to ALARP
2 to 4 SAFE LOW Proceed carefully, with continual improvement
1 NEGLIBLE VERY LOW Safe to proceed
Practically impossible Not likely to occur Possibility of isolated Possibility to occur Possibility of
incidents sometimes repeated incidents
Never heard of this Has occurred within Has occurred Occassionally occurs Frequently occurs
occuring within our our industry but not infrequently within our within our company within our company or
industry within an ENOC or company industry
HTL Group of
Companies
SEVERITY
Impact 1
Btw 2k to 200K
(Non-hazardous)
Moderate
LTI > 100 & < 500 or Considerable Impact 3 6 9 12 15
3
between 200 to 1k
(hazardous)
Btw 200k to 2M
LTI with (Non-hazardous) Major
> 500 & < 1000 National Impact 4 8 12 16 20
Hospitalisation or 4
1K to 200k (hazardous)
Over 2M
(Non-hazardous)
Fatality or Permanent Catastrophic
> 1000 or International Impact 5 10 15 20 25
Total Disabilities 5
200k
(hazardous)