COD - Commercial Operation Date Kuwait 6 Days Week 0 COD - Commercial Operat
639
Emergency sea outfall (ESO)
Kuwait 6 Days Week 314
Design
Design Kuwait 6 Days Week 314
703
Electrical Special Facilities (ESF)
Kuwait 6 Days Week 182
Design
Design Kuwait 6 Days Week 182
Milestones and
a Key Dates 808
MS1000 Closing Date of PPP Contract 0
MS1200 Approval for construction 0
MS5090 Commercial operation date (COD) 0
Project Management
Mana 962
PM0200 Start of Project incl. preparation works 0
General Items 671
PM1000 Overall time schedule (preliminary) 20
PM1010 Overall time schedule (final) 40
PM1020 List of subcontractors /manufacturers (preliminary) 15
PM1030 List of subcontractors /manufacturers (final) 30
PM1040 Proposed inspection and testing (preliminary) 20
PM1050 Proposed inspection and testing (final) 20
PM1060 Detailed program for commissioning (preliminary) 30
PM1070 Detailed program for commissioning (final) 40
PM1090 Training program (final) 40
PM1100 O & M Manual (preliminary) 30
PM1110 O & M Manual (final) 40
PM1130 As-built documentation (final) 56
Authority Engineering
Engin 112
AE1000 Application Documents for Building permit 70
AE1120 Completion of permit application documents 0
AE1130 Completion of the EIA report and associated studies/investigation 0
DS2020 Completion of permit application documents 0
DS2050 Approval for construction 0
WWTP UAH 963
Design 195
Milestones 155
DS-M100 Completion of Process Design 0
DS-M110 Completion of mechanical, electrical and I&C design 0
DS-M120 Completion of civil and structural design 0
Basic Design 128
DS2000 Design work 128
EN1000 Project Kick-off Meeting 1
EN1360 Finish of Basic Design 0
Hydraulical Design
Des 26
EN1010 Hydraulical calculation 16
EN1020 Hydraulical Cross Section 26
Process Design 39
EN1030 Process Design calculation 15
EN1040 Process Design Report 30
Ex-Zone conceptual
concep design 15
EN1050 Ex-Zone drawings 15
Mechanical Design
Des 88
DS2010 Basic design for mechanical and electrical equipment 87
EN1060 Corrosion Protection Concept 44
EN1070 Establishment of plant identification code 44
d) Acceptance
Acceptanc of Commercial Operation Test Report 52
COM1650 Preparation of Draft Commercial Test Report 47
COM1660 Review of Draft Commercial Test Report by the Buyer 5
COM1670 Acceptance of Commercial Test Report for Sludge Treatment 0
Sludge Composting
Compost Plant 233
COM1830 Completion of the Plant (Ready for introduction of sludge) 0
Pre-Commissioning (Dry Commissioning)
Pre-Commissio 93
COM1820 Inspection and Testing of Plant Equipment 56
a) Equipment Validation
V 92
COM1730 Pre-Commissioning (On-Site) Testing 92
COM1740 Construction inspections and testing at site 92
COM1750 Tests on part completion 55
Hydrostatic Validation
Va 92
COM1770 (a) Hydrostatic testing of the water retaining structures 92
COM1780 (b) Standard Oxygen Transfer Rate - SOTRTest of the aeration system 92
COM1790 c) Flux test of the Membrane units (if applicable); 92
COM1800 (d) Pressure test for all pressure pipes and elements of pressure systems 92
COM1810 e) Functional test of all electromechanical and safety equipment (like 92
screens,
COM1960 b) the Project Company shall have suitably qualified and experienced 38
technicians at the Sludge Composting Plant as requi
COM1970 c) the Project Company shall monitor and check all equipment at regular 38
intervals in accordance with the checklists esta
COM1980 d) as required by the test program, equipment may be stopped and the 38
function may be taken over by stand-by equipment; s
c) Performance
Performanc Test for Sludge Composting Plant (SCP) 38
COM2000 Demonstration of a) the operational integrity of the Anaerobic Sludge Diges 38
COM2010 Demonstration of d) for the SCP the ability to produce composted Sludge a 38
d) Acceptance
Acceptanc of Commercial Operation Test Report 52
COM2030 Preparation of Draft Commercial Test Report 47
COM2040 Review of Draft Commercial Test Report by the Buyer 5
COM2050 Acceptance of Commercial Test Report for Sludge Composting Plant 0
COD / Plant Acceptance
Acce Certificate 0
COM2060 COD - Commercial Operation Date 0
Emergency sea
s outfall (ESO) 639
Design 262
ESO1010 Geotechnical Investigations 33
ESO1020 Approval 0
Procurement 183
ESO2000 Procurement 183
Execution 325
Site Preparation 284
ESO3000 Site installation trenched pipe 223
ESO3010 Site installation Micro tunneling road 40 39
ESO3020 Site installation sea outlet Micro tunneling 59
Construction 325
ESO3030 Trenched pipe (onshore, 3,7 km underground pipes) 223
ESO3040 Microtunneling sea outlet (offshore, ca. 2km) 245
ESO3050 Microtunneling crossing road 40 (250 m highway cross) 38
ESO3060 Finish of ESO 0
Electrical Special
Spe Facilities (ESF) 703
Design 182
ESF1000 Design work 150
ESF1010 Geotechnical Investigations 39
ESF1020 Approval 0
Procurement 179
ESF2000 Procurement 179
Construction and
an Installation 545