Sei sulla pagina 1di 132

INTEGRATED

MINE
CLOSURE
Good Practice Guide, 2nd Edition
CONTENTS

Foreword 5 9. Success criteria 37

Executive summary 6 10. Progressive closure 39


Progressive closure and costs
1. Introduction 9 Tracking progressive closure

2. Integration into life of mine planning 13 11. Social transition 43


Planning for social transition to closure
3. Knowledge base 15 Social investment for closure
Risk assessment and the knowledge base Social transition costs
Operating with and without a regulatory
framework 12. Closure costs 47
Types of cost estimates
4. Closure vision, principles Calculating closure costs
and objectives 17
Closure vision 13. Closure execution plan 55
Closure principles
Closure objectives
14. Monitoring, maintenance and
Development and refinement of vision, management 57
principles and objectives
15. Relinquishment 59
5. Post-closure land use 21 Pathway to relinquishment

6. Engagement for closure 16. Temporary or sudden closure 61


plan development 25
Identification of stakeholders 17. Closure governance 63
Engagement on closure vision and post-closure Company closure standards
land use Closure committee
Engagement on success criteria
18. Definitions 67
7. Identifying and assessing risks and
opportunities 31

8. Closure activities 35

Publication: ©ICMM 2019, All rights reserved.

Cover image: ©Newmont

Every effort has been made to verify the accuracy of the information contained in this report. All information was
believed to be correct as of February 2019. International Council on Mining and Metals cannot accept responsibility for
the consequences of its use for other purposes or in other contexts.

2 Integrated mine closure: good practice guide


Tool 1 Abbreviations
The domain model 72
AR5 Fifth Assessment Report [of the IPCC]
Tool 2
ARD/ML acid rock drainage and metal leaching
Monitoring, measurement and inspections 76
CCM critical control management
Tool 3
Objective setting 80 CDA Canadian Dam Association

CEP closure execution plan


Tool 4
Screening alternatives for repurposing 86 EPCM engineering, procurement and
construction management
Tool 5
Key messages for social transition 88 ESIA environmental and social impact
assessment
Tool 6
GAAP Generally Accepted Accounting Principles
Social transition activities checklist 90
GARD Global Acid Rock Drainage [Guide]
Tool 7
Climate change and mine closure concerns 94 GIS geographic information system

ICMM International Council on Mining and


Tool 8
Metals
Risk/opportunity assessment and management 96
ICPS integrated closure planning system
Tool 9
Considerations in developing closure activities for IFRS International Financial Reporting
transversal issues 102 Standards

IPCC Intergovernmental Panel on Climate


Tool 10 Change
Considerations in developing closure activities
for domain-specific issues 111 LoA life of asset [includes post-closure period]

LoM life of mine [to end of productive mine life]


Tool 11
Social investment for closure 120 NGO non-governmental organisation

Tool 12 NPV net present value


Closure plan documentation 126
PTNMR PT Newmont Minahasa Raya

QA/QC quality assurance/quality control

RACI responsible, accountable, consulted,


informed

SMART specific, measurable, achievable,


relevant, timely

TEDWG Thompson Economic Diversification


Working Group

UHMD Upper Hunter Mining Dialogue

Integrated mine closure: good practice guide 3


©Anglo American

4 Integrated mine closure: good practice guide


FOREWORD

Our members are committed to sustainably


managing the natural resources of our planet and
enhancing the well-being of local communities.
ICMM members commit to enabling agreed closure and post-closure
commitments to be realised through planning, designing for and
implementing closure in consultation with relevant authorities, internal and
external stakeholders, and to make financial provision, in order to address
the environmental and social aspects of closure.

ICMM’s Integrated mine closure: good practice guide provides mining


companies with the guidance needed to effectively integrate closure across
the mining life cycle. This in turn creates the opportunity for companies to
be proactive in identifying and addressing risks early before they become
material with the potential to compromise eventual mine closure, as well as
to building stakeholder confidence. The guide is intended to support the goal
of delivering a positive legacy while balancing environmental protection and
social well-being with financial performance.

This guide is applicable to new mines, existing mines and legacy sites, and
is intended for use across the spectrum of mining companies, from major
multinationals to single asset junior mining companies. The guide is not
exhaustive but does establish the practices and expectations for closure
applicable at a broad variety of sites and can be used as guidance on the
standard of practice for sites in the absence of formal regulatory/government
requirements. It has been designed to be largely compatible with different
regulatory regimes and corporate guidelines.

The closure process has historically relied on the mining company’s


expertise to conceptualise and deliver results. In modern practice,
communities and governments also play a key role in creating successful
closure outcomes. As such, integrated closure planning and implementation
needs to capture and balance the views, concerns, aspirations, efforts,
knowledge and capacity of relevant internal and external stakeholders. The
goal is to achieve sustainable outcomes that are beneficial to the mining
company and its employees, the environment and host communities.

Tom Butler CEO

ICMM
December 2018

Integrated mine closure: good practice guide 5


EXECUTIVE SUMMARY

The Integrated mine closure: good practice guide provides ICMM members
and other responsible mining companies with guidance intended to promote
a disciplined approach to integrated closure planning and to increase the
uniformity of good practices across the sector.
This guide presents an updated and objectives is underpinned improve the legacy of benefits
version of ICMM’s 2008 Planning by considerations of potential from mining activities.
for integrated mine closure: toolkit. post-closure land use of the • Understanding of closure costs
Like the earlier version, guidance former mine site, and a formal for the purposes of planning,
is provided on critical aspects of identification and assessment of comparing alternatives,
mine closure focused on an iterative risks and opportunities throughout understanding financial liabilities
process, from the earliest stages of iterations of the closure plan. and complying with reporting and
knowledge gathering, engagement • Implementation of various closure financial assurance obligations.
and planning. The updated activities to implement closure, • Developing and updating a
guide provides emphasis on the both during the mine life as closure execution plan while
importance of social transitioning, progressive closure and as part ensuring adequate closure
progressive closure and strategies of final closure. These closure governance structures are in
for relinquishment and closure activities should be tied to meeting place to ensure closure planning
governance. The guide also includes specific closure objectives that is integrated into the life of mine
tools at the back of this document to have been defined and agreed. planning. The closure execution
help support planning for closure. Monitoring will be undertaken plan identifies actions and
to document and evaluate the resources required during the
Integrated mine closure is a dynamic effectiveness of the closure mine life to support planning and
and iterative process that takes into activities at meeting agreed closure implementation of closure, while
account environmental, social and objectives and the success criteria. appropriate governance ensures
economic considerations at an early The development of well-defined effective allocation of resources
stage of mine development. success criteria, with input and to closure across a range of
agreement with appropriate disciplines.
Fundamental to this process is stakeholders, are key to completing
the need to consider closure as an • Periodic evaluation of appropriate
closure works.
integral part of the mine operations’ ‘what-if’ scenarios during the
• Implementation of progressive mine life to help minimise the
core business. The structure of this
closure, which involves the disruption caused by such
guide reflects this process, providing
implementation of closure activities unplanned events. Unplanned
good practice guidance in delivering
during the operating life of a mine changes in circumstances can
key elements of mine closure
providing opportunities to test and result in temporary or sudden
planning and implementation,
demonstrate the effectiveness of closure of mines.
including:
closure activities, validate success
• Relinquishment of closed sites
• Integration into life of mine criteria and build trust with
to a third party, which may
planning and early definition of communities and the regulators. It
not always be possible, but it
the closure vision, principles and provides opportunities to generate
should be a desirable endpoint
objectives supported by both early learnings that can be incorporated
of the life of asset (the entire
engagement for closure plan into closure planning throughout
mining life cycle, including
development with stakeholders the mining life cycle.
post-closure). Detailed planning
and development of a knowledge • Planning and preparation for and robust execution of closure
base where data will be collected social transition to help reduce the throughout the mining life
and updated throughout the negative impacts of social change cycle can help increase the
mining life cycle. The definition for the workforce and communities probability of attaining successful
of the closure vision, principles connected to the mine site and relinquishment.

6 Integrated mine closure: good practice guide


This guide has been structured as Summary of tools
per the above process described.
However, in practice there are many Tool 1 The domain model
feedback loops that interconnect
each element – hence the need for Tool 2 Monitoring, measurement and inspections
an iterative process. Furthermore,
the guide provides good practices, Tool 3 Objective setting
case studies and a range of tools that
Tool 4 Screening alternatives for repurposing
can be utilised in formulating well-
considered decisions when planning Tool 5 Key messages for social transition
and executing closure.
Tool 6 Social transition activities checklist

Tool 7 Climate change and mine closure concerns

Tool 8 Risk/opportunity assessment and management

Tool 9 Considerations in developing closure activities for transversal


issues

Tool 10 Considerations in developing closure activities for domain-


specific issues

Tool 11 Social investment for closure

Tool 12 Closure plan documentation

©Teck

Integrated mine closure: good practice guide 7


©Rio Tinto

8 Integrated mine closure: good practice guide


1.INTRODUCTION

The International Council on Mining and Metals (ICMM) has developed


Integrated mine closure: good practice guide to support the needs of company
members and other responsible mining companies as they plan for closure.
This document is intended to promote a disciplined approach to integrated
closure planning and to increase the uniformity of good practices across the
sector. The concepts apply equally to both large and small mining companies.
The document is not intended to be across a range of considerations, • early identification of risks and
prescriptive. It provides guidelines, including health, safety, social, mitigation strategies.
good practices, case studies and a environmental, legal, governance • progressive reduction of liabilities.
range of tools that can be utilised and human resources.
• working towards an agreed-upon
in formulating well-considered
vision for the post-closure period.
decisions when planning and Effective closure planning results in:
executing closure. It uses a risk • a better social transition for
• consistent and transparent affected stakeholders as the mine
and opportunity-based process to
engagement with stakeholders. moves from operations to closure
guide the practitioner through the
iterative process of planning for • community participation in • opportunities for lasting benefits
final and progressive closure in a planning and implementing actions being recognised and planned for
considered manner, as well as tactics that underpin successful closure. adequately.
for considering sudden or temporary • stakeholder support of closure
closure. decisions. As shown in Figure 1, closure needs
• better management of closure to be considered throughout the life
A balanced closure approach fully throughout the mining life cycle. of asset (LoA). Designing for mine
incorporated into mine planning closure must be integrated into
• more accurate closure cost
activities will lead to better outcomes planning from the earliest stages of
estimates.

Figure 1: Mine closure framework


Final relinquishment

Design & permitting Construction Operations and progressive closure Closure Post-closure

Final closure
Monitoring,
Implementation maintenance &
Closure planning management
and design
Progressive closure

Monitoring & review

Monitoring & review

Stakeholder engagement

Planning and implementing social transition

Integrated mine closure: good practice guide 9


exploration and mine development.
Early consideration of mine closure
will make it easier and more cost-
effective to achieve final closure
objectives and can improve the
opportunities for relinquishment.

Some typical examples of designing


for closure throughout the LoA are:
• making areas available for
progressive closure in order to limit
closure impacts and liabilities at
final closure.
• sequencing the stripping

©Anglo American
and storage of topsoil during
development to facilitate direct
placement in areas to be reclaimed
– this reduces haul distances and
preserves topsoil quality.
• strategic placement of potentially
iterative process, with the closure 1. Integration into life of mine
reactive materials to facilitate their
plan refined and updated throughout planning: Closure should be
isolation and avoid groundwater
the LoA. Closure planning is cyclic integrated into the mine business
contamination.
as information relevant to closure plan, including the short, medium
• designing waste disposal facilities is updated and gathered. This and LoM planning processes,
with long-term physical stability information may come through many throughout the mine life. When
and maximised in-pit dumping, different sources, such as ongoing closure is fully embedded in LoM
minimising closure earthworks at engagement with communities and planning, there are better results as
closure. other stakeholders as ideas and expectations, risks and opportunities
expectations for closure evolve, can be proactively managed and
As the mine proceeds through studies are developed to address achieved for the mining company and
construction, operation, final closure gaps in the knowledge base, changes stakeholders.
and the post-closure period, various in technology, or learnings gained
domains or portions of the mine may through the implementation of 2. Knowledge base: The knowledge
be closed while operations continue progressive closure. The earliest base is the repository for information
(a process known as progressive progressive closure activities will that will be developed throughout the
closure), with final closure taking typically provide learnings that can LoA, with regular updates as data is
place at the end of the life of mine be incorporated into later progressive collected and reviewed. This is the
(LoM). As shown in Figure 1, closure activities and final closure. information that will inform site-
implementation of closure activities, specific closure planning, such as the
whether final or progressive, will Figure 2 illustrates key elements of environmental and socioeconomic
be preceded by the development of mine closure and a pathway through setting, environmental baseline data,
more detailed plans and designs. them aligned with the organisation operational data (such as volumes
This typically includes a progression in this guide, although the steps and types of waste currently and
through conceptual, pre-feasibility through the planning cycle will not planned to be deposited, waste
and detailed designs (although necessarily be sequential. In practice, characterisation), commitments and
the exact terminology for these there are many feedback loops that compliance requirements.
stages may vary between mining interconnect each element – hence
companies). the need for an iterative process. 3. Closure vision, principles
and objectives: These will be defined
While Figure 1 shows a linear Each of these elements for the early in the closure planning process
process for the implementation of planning process are summarised and refined throughout the LoA
closure, planning for closure is an below. with input from stakeholders and

10 Integrated mine closure: good practice guide


the knowledge base. The closure 4. Post-closure land use: Where 6. Identifying and assessing risks
vision is an aspirational description the use of the land after mining can and opportunities: A wide range
of what will be achieved with mine be defined, this greatly aids closure of risks and opportunities are
closure, compatible with regulatory planning. A defined post-closure associated with closure, covering
requirements. The vision will typically land use, or range of possible post- physical, social, economic and
incorporate an overview of the post- closure land uses and required land ecological considerations. Formal
closure land use and will evolve as capabilities, will inform all aspects identification and evaluation of
more information becomes available. of the closure plan, particularly the risks and opportunities helps to set
Closure principles are the common definition of both the closure vision priorities and shape many aspects
precepts that guide the basis of a and objectives. of the closure plan, including the
closure plan, such as promoting selection of closure activities.
physical and chemical stability, 5. Engagement for closure
meeting regulatory obligations plan development: Engagement 7. Closure activities: Specific
and facilitating social transition. with stakeholders will take place closure actions or works are
The closure objectives indicate in throughout the closure planning executed in the implementation of
concrete terms what is to be achieved process, with insight from that the closure plan, both at final closure
through implementation of the engagement used to shape key and progressively through the LoA.
closure activities. elements of the closure plan. Examples include installation of

Figure 2: Elements of closure planning

Integration into Life of Mine Planning

Engagement for closure plan development


Knowledge Post-closure
Relinquishment base land use

Monitoring, Closure vision,


maintenance and principles
management and objectives
gressi closure
on
ansiti

Closure Identifying and


ve

execution assessing risks


tr

plan and opportunities


cial
So
Pro

Closure Closure
costs activities
At each stage of the mine
life, there should be an
understanding of how
temporary or sudden Success
closure could affect the criteria
closure plan

Closure Governance

Integrated mine closure: good practice guide 11


a tailings cover, reshaping waste 13. Monitoring, maintenance This guide provides guidance on each
dumps, commissioning of a water and management: Following the of the above topics. The guide also
treatment plant and removal of completion of closure activities, includes supplementary information
contaminated soil. monitoring should be carried in the form of a series of tools to aid
out to document and evaluate the practitioner in developing closure
8. Success criteria: These are the effectiveness of the closure plans and carrying out activities in
developed as quantitative indicators activities at meeting agreed closure support of closure. The relevant tools
of successful closure activities. objectives and to demonstrate that are listed throughout the document.
Meeting success criteria can mark success criteria are being met, or
the end of the post-closure period on a pathway to be met. Monitoring The practice of mine closure
for a mine or part of a mine. This of sites against success criteria continues to evolve globally. Case
may be associated with the return of may lead to the identification of studies drawn from the experiences
the associated financial assurance maintenance needs. Rehabilitated of both ICMM member companies
amount to the mining company, an areas may also need to be managed and other mines are presented
opportunity for relinquishment of the as part of the broader ecosystem. throughout the document to illustrate
land to a third party, or both. recent, practical experience with
14. Relinquishment: Relinquishment mine closure at sites around the
9. Progressive closure: Progressive is not always the endpoint for the world. Practices such as repurposing
closure is the implementation LoA, but it is a stated objective mines at closure for beneficial uses
of closure activities during the for many mine sites. Attaining are now becoming commonplace,
operating LoM. There are many relinquishment requires careful and many mining companies are
benefits to implementing progressive planning and engagement with an seeking to integrate the social
closure, including the learnings that appropriate regulatory regime. component of closure planning into
can be integrated into the knowledge Where relinquishment is planned, how they do business, with ongoing
base. ongoing engagement with consultation throughout the planning
stakeholders will be required leading and implementation of operations
10. Social transition: This up to the eventual relinquishment, and closure.
encompasses the efforts that are with attention to developing agreed-
associated with transitioning of a upon success criteria. Good practice: Closure planning
community, including its workforce,
should be incorporated into the
towards closure of an operation. 15. Temporary or sudden closure:
earliest stages of mine planning,
These efforts take place throughout Various factors can result in the
including exploration, so closure
the LoM and into closure. temporary or unplanned closure of
risks and opportunities are captured
an operating mine. At each stage
from the start and proactively
11. Closure costs: A key part of of the mine life, there should be an
managed in order that closure is
the closure planning process is understanding of how temporary
fully considered in the mine design
estimating the cost of all aspects or sudden closure could affect the
and business plan.
of closure, and updating those closure plan. This understanding will
estimates as plans evolve and more need to be updated regularly over the
information becomes available. mine life.

12. Closure execution plan (CEP): 16. Closure governance:


A CEP will be developed and An overarching approach to
regularly updated through the closure governance is needed to
closure planning process. While ensure the effective allocation
the closure plan describes the of resources to closure planning
actions that will be carried out as from many disciplines across the
part of implementing site closure, mining company, including both site
a CEP identifies specific actions to resources and, where available,
be carried out during the mine life corporate support. Effective closure
in support of closure planning and governance will affect every aspect of
implementation of closure activities. closure planning at an operation.

12 Integrated mine closure: good practice guide


2.INTEGRATION INTO LIFE
OF MINE PLANNING

Designing for closure means integrating closure activities into the mine
business plan, including the short, medium and LoM planning processes,
throughout the mine life taking into account environmental, social and
economic considerations. Integrated mine closure should integrate stakeholder
involvement and community consultation throughout the mining life cycle.
The benefits of this integration can cycle. The earlier this approach in ensuring a positive social and
include the following: is followed in the life of a mine, environmental legacy is left behind
the greater the opportunity for post-closure. See BHP’s and Anglo
• closure decisions will be better
proactive planning. This provides American’s case study examples
supported by stakeholders.
a consistent approach over the life on integration of closure into LoM
• assets are designed and operated cycle of projects for reporting and planning.
with closure as a key input variable. management of long-term liabilities
• better understanding of closure
risks and knowledge gaps

CASE STUDY
throughout the business.
• value generation by realising
opportunities through the
operational phase. DELIVERING CLOSURE LANDFORMS THROUGH MINE
• liabilities progressively reduced or PLANNING IN WESTERN AUSTRALIA (BHP)
prevented, where practicable.
At BHP’s Western Australia Iron Ore, a closure and rehabilitation
• costs reduced through operational governance strategy specifically supported by guiding principles,
synergies. coupled with waste and landform design knowledge, has enabled LoM
• increased efficiency through planning to drive optimisations that target both operational production
reduction in double handling of and closure outcomes.
materials.
Western Australia Iron Ore disposal areas that would require
• minimise the risk of regulatory
experienced significant benefits rehabilitation, thus reducing
non-compliance.
from this approach to planning closure costs.
• adequate financial provisioning for waste disposal. A recent project • pit, waste disposal area and haul
closure is allocated. involved taking pre-feasibility road development sequences for
• reduce risk of an extended period (conceptual) level mine layouts and the whole mine life developed in a
of care and maintenance at the end schedules to a feasibility (detailed) manner that will reduce rework,
of the mine life due to inadequate level resulting (prior to mine optimise fleet utilisation and
closure planning. execution) in the following benefits: reduce capital expenditure.
• better understanding of closure • more than 50 per cent reduction • increased confidence in the
liabilities to inform change of in land disturbance by optimising ability to execute progressive
ownership decisions. in-pit dumping and haul road rehabilitation.
• improve accuracy of closure cost designs. • increased ability to manage
estimates. • more than 60 per cent increase closure risk through either
• recognise and adequately plan for in void backfilling, including avoidance or early mitigation of
post-mine land use opportunities. over a 30 per cent increase in risk issues – this reduces post-
progressive backfill of pits closure residual risks.
As with closure planning itself, where that backfill was needed • improved communication of
integrating closure into the LoM to manage potential post-closure closure and rehabilitation risks
plan is an iterative process that impacts. and proposed management
incorporates developing information • reduced number of waste measures to stakeholders.
and experience over the mining life

Integrated mine closure: good practice guide 13


Key questions to ask about
CASE STUDY integration into LoM planning

Has a multidisciplinary team


INTEGRATED CLOSURE PLANNING WITH OTHER provided input to the short,
MINE-PLANNING PROCESSES (ANGLO AMERICAN) medium and LoM planning
processes? Is there integration
Anglo American commenced the development of an integrated closure
between the closure, mine
planning system (ICPS) with the aim to provide a consistent approach
engineering/planning,
over the life cycle of projects for the reporting and management of
environment and community
long-term liabilities, to achieve their goal of ensuring that they leave a
teams in planning for closure?
positive and sustainable legacy post-closure.

To achieve this objective, focus on across the organisation; both Has the closure vision been
people, process and technology the LoA and shorter term mine clearly communicated to the
was required. The elements of planning processes had no clear LoM planners? Do LoM planners
the ICPS are planning (eg LoM, platform or process to facilitate understand the potential added
closure, short/medium-term closure planning interactions. This value of designing for closure?
mine, rehabilitation), financials finding reinforced the importance
(eg premature and LoM closure and emphasised the critical Are the roles and responsibilities
liability, operational expenditure, nature of the ‘people, process and of teams clearly defined in
guarantees), systems (eg closure technology’ elements. achieving the overall closure
toolboxes, geographic information vision?
systems, environmental Through application of a
management systems) and balanced scorecard, and Anglo Is there a platform/system in
requirements (eg internal/external American’s internal assessment place to ensure integration
standards, policy, regulation). of its operations across the globe, between teams and
potential pilot mine sites were incorporation of closure into the
The system involved identifying identified with low, moderate mine business plan?
the current state of processes, the and high levels of ICPS maturity,
target state of a fully integrated with associated high closure
process, developing a maturity risk or opportunities. Project
scorecard and identifying potential implementation plans were
technology solutions that may developed to increase the ICPS
assist in realising value at the maturity at the pilot sites to the
operational level. required level that will maximise
value realisation or minimise value
©Anglo American

In defining the current condition destruction from a mine closure


across the operations, it perspective.
became evident that roles and
responsibilities were not clear

Kolomela Iron Ore open pit, South Africa

14 Integrated mine closure: good practice guide


3.KNOWLEDGE Tool 1 The Domain model

BASE
Tool 2 Monitoring,
measurement
and inspections

The knowledge base is site-specific and domain-


specific information used in the closure plan.
The knowledge base typically covers looking evaluations of potential • identification of trends, in both
four areas: impacts and mitigation measures. environmental and socioeconomic
The construction of the mine will data.
• physical.
alter many aspects of the pre-mining • understanding of cumulative
• environmental.
characteristics. The plans to address impacts and changes that may
• social/socioeconomic.
gaps and uncertainties over the life of result from commissioning
• regulatory.
the mine should be incorporated into or decommissioning of other
the CEP and used to inform closure industries that have influence over
The information can also be organised
planning and implementation. the mine’s project area.
in domains, which consider the mine
site as an aggregation of specific • identification and assessment of
Throughout the mine life, monitoring
areas with related characteristics. possible closure-related impacts
will be conducted in each of the
Tool 1: The domain model can be and operational management or
areas covered by the knowledge
used to help organise information mitigation.
base. The data collected will be
for domains. The information • mitigation of some of the risk that
reviewed, assessed and incorporated
gathered for each area or domain comes from turnover of closure
into the knowledge base. For
should include its status, historical practitioners.
example, monitoring and inspection
information, technical information
of revegetation during progressive
(such as dimensions, concentrations, Risk assessment and the
closure could provide data on
environmental and social baseline
both vegetation growth rates and knowledge base
conditions and trends, and
maintenance issues encountered
chemical and hydrogeological No matter what kind of risk
while addressing erosion. Learnings
characterisations) and local and assessment is being carried out,
can be taken from review of this data
traditional knowledge, where the usefulness of the assessment
and incorporated into the knowledge
available and appropriate. Tool 2: will depend on the quality of
base for use in the refinement of
Monitoring, measurement and the information used. Gaps in
future closure activities.
inspections provides information the knowledge base may affect
relevant for collecting information confidence in a risk assessment.
This knowledge will inform all
to be added into the knowledge
aspects of the closure plan, from
base. Document control and quality Good practice: A knowledge base
setting the vision and objectives,
assurance/quality control (QA/ gap analysis should be undertaken
through to designing engagement
QC) are important to verify that the at regular intervals throughout the
programmes, evaluating risks,
information within the knowledge mine life (at least once per closure
selecting closure activities and
base is current, readily accessible and plan update) to identify further
defining success criteria. More
accurate. studies, research or trials that may
specifically, the information gathered
in the knowledge base allows: be required, as informed by the
The collection, updating, use and
risk assessment. These are then
review of the knowledge base in each • complexity of the environmental
incorporated into the CEP according
of these areas is an ongoing and and social setting to be better
to their time frame and significance.
iterative process over the mine life, understood.
used to inform the closure planning • identification and assessment of The risk assessment process will
process. Gaps and uncertainties closure risks and opportunities. highlight gaps in the knowledge base
will be identified over the mining
• identification of data gaps and and allow prioritisation of studies
life cycle, with studies, research
development of activities to close and activities to fill these gaps (see
and trials undertaken as needed to
them. section 7 on identifying and assessing
close knowledge gaps. Significant
• identification and assessment of risks and opportunities). If combined
development of the knowledge base
potential post-closure land uses. with a closure cost evaluation, the
typically takes place during the
risk assessment can focus attention
environmental assessment stage, • support for development of
not only on understanding the main
through baseline studies, and future- success criteria.
risks, but also on identifying and

Integrated mine closure: good practice guide 15


quantifying risks driving the overall international commitments, treaties, Code, and the International Financial
closure cost. investment agreement requirements, Reporting Standards (IFRS) or in
corporate commitments, disclosure the USA the Generally Accepted
As an example, knowledge gaps requirements and reporting related Accounting Principles (GAAP).
in the capping design of a tailings to standards such as National
facility are likely to have a significant Instrument 43-101 or the JORC
impact on the level of confidence in
final facility closure costing, which
can present a business risk. In this Key questions to ask about the knowledge base
case, enhancing the knowledge
base related to tailings cover could Have proper baseline and pre-mine data been collected? Is the data
become a priority. sufficient for evaluating closure needs? Does the data include proper
documented QA/QC information?
Operating with and without a
regulatory framework Is additional information for the knowledge base required?

Countries vary considerably in terms Are the tools and/or methodologies in place to obtain additional
of mine closure regulatory and information?
legislative requirements. In some
countries, detailed mine closure Are volumes and characteristics of waste being characterised as they
regulations are well established, are being planned, generated and paced with statistically significant
while in others there is limited (or no) sampling programmes?
applicable legislation. In countries
with new or changing regulatory Has spatial data been generated showing the mining operation and the
requirements, there can be a lack of associated communities, water resources, infrastructure and ecologically
regulatory experience. In countries sensitive or protected areas? Does this include clear definition of the
where limited or no mine closure surface water and groundwater watersheds?
regulations exist, mining companies
may need to manage uncertainty, and Have relevant regulations (mining and non-mining) been reviewed and
the knowledge base should consider understood, including proposed or foreseeable changes? Relevant
regional and national development non-mining regulations to consider include labour laws (as applicable
plans. to workforce retrenchment), water use regulations and environmental
regulations.
Good practice: In the absence
of country-specific mine closure Are relevant corporate standards incorporated?
regulations, mining companies
should consider applying Have commitments and legal obligations of the company to relevant
requirements for closure that are stakeholders been captured, as well as their expectations?
consistent with good practices
in more mature regulatory Has stakeholder consultation been conducted, with emphasis on
environments. Companies should identification of the closure risks and opportunities related to employees
engage regulators early in the and the community?
process to improve alignment on
expectations, understand regulator Have stakeholders been consulted on post-closure land use? Is there
objectives and communicate mine an existing land use or tenure plan that identifies expected post-closure
closure processes and objectives to land uses within the broader area of operations?
reduce uncertainty.
Are appropriate data management protocols in place to ensure that
In the absence of a clear local data from activities such as ongoing monitoring and field trials are
regulatory framework, there are incorporated into the knowledge base?
other sources of commitments
that should be considered in the Have commitments made through membership in organisations such as
knowledge base. These include ICMM been documented?

16 Integrated mine closure: good practice guide


4.CLOSURE VISION, Tool 3 Objective setting

PRINCIPLES AND
OBJECTIVES

The aims of the closure plan are set out through its underlying vision, principles
and objectives. Each of these are defined and discussed in further detail below.
Site-specific closure objectives are developed taking into consideration the
overall vision for the site and closure principles that may be applicable to a
broad range of sites. While different companies may use different terminology
for these concepts, the underlying approach is usually similar.
Closure vision a wide range of sites and conditions. • Chemical stability: to prevent
For example, the promotion of adverse effects on the local
The closure vision provides a high-
physical and chemical stability environmental quality by chemical
level aspirational description of
are universally accepted closure contamination arising from the
what an operation or company and
principles. While the terminology may site. Acid rock drainage and metal
stakeholders want to achieve through
be different, many mining companies leaching (ARD/ML) are common
implementation of the closure plan.
have their closure principles chemical stability issues, but there
This includes how the company
codified in their internal closure are a wide range of others that can
will be remembered, as the way
policies. The following are standard arise from site-specific conditions.
a company exits a mine site can
closure principles widely used and • Socioeconomic transition: to
impact positively or negatively on
considered good practice: promote, to the extent practical,
its reputation. Reputational impacts
can in turn affect the company’s • Safety: to promote physical safety a smooth transition from the
social licence to develop or operate of the closed mine site over time by socioeconomic conditions that
mines. The closure vision is a guiding the provision of closure activities to existed during mining activities
statement for the development of make safe (to human and animal) to the state that will be present
the closure plan. The closure vision any void or pit left after mining to after mining. Where practicable,
typically includes elements of post- prevent falls from height. the net socioeconomic impact
closure land use and must align with on the affected region should be
• Physical stability: to promote
regulatory obligations. It should be beneficial.
physical stability or the physical
endorsed by senior site or company sustainability of the closed mine • Ecological stability: to ensure
leadership. site over time, creating a physically the post-closure ecosystem at the
stable landscape that limits closed site is either stable, and
long-term erosion potential and remains in a sustainable state, or
Good practice: Begin with defining
environmental degradation in on a desired trajectory, compatible
a closure vision that articulates
the long term such that there is with the planned post-closure
what a company wants to achieve
little or no safety threat or risk land use. This may include goals
post-closure and the legacy it will
to personnel or the environment for biodiversity and for a self-
leave behind. Involve stakeholders
due to excessive movement sustaining ecosystem that will be
early in the development so that it
of permanent landforms. The viable in the long term without
can become a shared vision This
physical stability should be ongoing mining company support,
vision will serve as an overarching
compatible with access and the and compatible with the proposed
guide for the decisions and their
intended post-mining land use. land use.
implications throughout the mining
life cycle. There may be limitations to the • Risk limitation: to control risk to
practically achievable physical an acceptable level, in a number
stability of some landforms; of distinct areas (such as safety,
Closure principles
however, the closure design should environmental, financial, legal
Closure principles are general in be developed to manage safety risk compliance, social). Most mining
nature and are typically applicable to over prolonged periods. companies will look at closure

Integrated mine closure: good practice guide 17


through a risk assessment Development and refinement The development of the closure vision
framework, in which controlling of vision, principles and and objectives is usually greatly
risk is commonly an implicit or objectives shaped by post-closure land use
explicit principle. considerations. As an illustration, the
Establishing and then refining the example objective mentioned earlier
• Cost-effectiveness: to execute the
closure vision and objectives over (ie that water quality in a flooded pit is
closure activities cost-effectively,
the mine’s life cycle should be an safe for wildlife to drink) would likely
and efficiently use the technical,
integrated, multidisciplined and be developed considering a post-
financial and human resources
multi-stakeholder process. Engaging closure land use where wildlife is
required to implement closure.
and aligning internal and external expected to have access to the pit.
• Long-term care: to design the stakeholders will lead to more
closure plan to minimise or successful outcomes. As the closure
eliminate the need for long-term Good practice: Consider post-
principles are not site specific, they closure land use in the development
post-closure care and maintenance. are not expected to change over
This principle is closely tied of both the closure vision and site-
time, although new principles may specific closure objectives. Involve
with chemical, ecological and
be added as mine closure practices internal and external stakeholders
physical stability and may be tied
evolve. In contrast, the development early in the consideration of possible
with achieving relinquishment of
of the closure vision and objectives post-closure land uses.
the closed site where that is an
is typically an iterative process, and
objective.
both may evolve over the LoA.

Closure objectives Both the closure vision and closure


While the closure vision provides objectives should be informed by
overarching direction for closure, the knowledge base, particularly
and the principles provide a general the mine’s zone of influence,
framework, the closure objectives socioeconomic and environmental
provide concrete, site-specific and context, stakeholder relationships,
typically measurable statements of country-specific requirements and
what closure activities or measures other external drivers (such as
aim to achieve. Individual objectives alignment with the International
may be specific to mine domains such Finance Corporation’s Performance
as pits, infrastructure and waste Standards, the Sustainable
disposal facilities, or to aspects of Development Goals or other
closure. For instance, a site-specific requirements such as ICMM’s
objective could be that water quality performance expectations). Full
in a flooded pit is safe for wildlife to consideration of these factors should
drink. lead to a closure vision and closure
objectives that are aligned with the
The selection of closure objectives characteristics of the corporation
should be informed by consideration and the closing mine and appropriate
of risks and opportunities. Early to its socioeconomic setting. Figure
identification of risks associated with 3 illustrates the types of inputs
closure allows possible impacts to that are typically considered in the
be avoided or mitigated in a timely development of closure objectives.
manner, which ultimately reduces the Tool 3: Objective setting can
closure liabilities and improves post- help with developing the closure
closure benefits. objectives.

18 Integrated mine closure: good practice guide


Figure 3: Inputs to closure objectives

Company policies, guidelines,


resourcing, timing
Internal
considerations
Site constraints/achievability:
physical, technical,
environmental, workforce etc.

Closure
Socio-economic context, objectives
impacts and risks

International guidelines and External


regulatory requirements considerations

Stakeholder inputs, community


vision, public pressure

Key questions to ask about the closure vision and objectives

Has a long-term, overarching and site-specific closure vision been developed?

Does the closure vision consider environmental, community, workforce and financial concepts?

Did the development of the closure vision account for legal and health and safety constraints on land use?

Does the closure vision address the desired post-closure land use?

Has the closure vision been developed in consultation with internal and external stakeholders?

Does the closure vision match company, community and government needs, expectations, capacity and capability,
and will it be a closure vision that the future landholders support when the company has exited?

Is the vision feasible?

Have site-specific closure objectives been developed for each mine domain?

Do the planned closure activities correspond to the closure objectives?

Are the closure objectives measurable?

Are the closure objectives achievable in a timely and cost-effective manner?

Are the closure objectives feasible?

Are the closure objectives compatible with the closure vision and closure principles?

Have the closure objectives been developed in consultation with internal and external stakeholders?

Integrated mine closure: good practice guide 19


©Newmont

20 Integrated mine closure: good practice guide


5.POST-CLOSURE Tool 4 Screening alternatives
for repurposing

LAND USE

A clear definition of the post-closure land use greatly facilitates closure


planning. When the post-closure land use is understood, it aids not only the
definition of the closure vision and site-specific closure objectives, but also the
selection of closure activities and the definition of success criteria.
Understanding and planning for post- relinquishment, should be considered in place before closure. Sufficient
closure land use is challenging. The throughout the planning process. time needs to be allocated for local
possible and desired post-closure capacity building.
land use will be informed by several Post-closure, mined lands may be • Use the knowledge base:
factors, including: returned to pre-mining land use. This The information collected,
is not always desired or possible, organised and continually updated
• location of the assets (remote
due to alterations of the landscape in the knowledge base will provide
locations versus locations close
and socioeconomic context, but part of the basis for identifying and
to population).
should be evaluated. A wide variety evaluating post-closure land use
• pre-mining land use and the of alternative uses for mined lands options.
historical, current and future use is available. These could include
of surrounding lands. • Consider land capability: The land
adapting post-closure landscapes
use needs to be compatible with
• permanent alterations to the for forestry, agriculture or wildlife
the suitability of the land to sustain
landscape generated by mining habitat, or use of land as recreational
a type of land use permanently (ie
activities. areas.
soil types, depth, gradient, etc).
• land capabilities (defines feasible Post-closure land use will not be
land use). Some post-closure land uses
uniform over the entire site and
have the possibility of generating
• regulatory considerations/ will be affected by the post-closure
economic benefits. ‘Repurposing’ is a
obligations (may set requirements configuration of the mined lands
term often used to refer to activities
for post-closure land use). and waste disposal areas.
that have the possibility to generate
• the socioeconomic context, income from closure activities. This
including the desires of the may facilitate transfer of the site to Good practice: Develop maps of the
community and other external a third party for relinquishment or post-closure landscape and evaluate
stakeholders; this includes the provide an offset for ongoing post- post-closure land use for areas with
context as it evolves over time – closure operating and maintenance common capability. At the earlier
pre-mining, during mining and costs. stages of planning, these may be
post-mining. relatively large/coarse blocks of
• landownership – in many cases the There is no single process to plan land and broad categories of land
mining company is leasing the land, for post-closure land use. However, capability. As closure planning
and the owner may dictate future there are a number of principles that reaches more detailed levels,
land use if any. can be used to identify and evaluate additional detail on land capability
• economic feasibility. closure options: may be added as required. For
example, in the early stages a large
• regional plans. • Evaluate early: As post-closure
area may be identified as suitable for
land use will inform all aspects
agricultural use post-closure, and at
Relinquishment (transition of of closure, it should be taken into
the more detailed planning stages,
ownership and responsibility for consideration from the earliest
this area could be subdivided into
the land to a third party) is often stages of closure planning. Formal
different types of agricultural use
discussed in the context of post- structures for post-closure land
depending on capability.
closure land use. The type of use management and community
post-closure land use that may and business initiatives should be
facilitate relinquishment, and the considered from the early stages
compatibility of land use options with in approval and permitting, and

Integrated mine closure: good practice guide 21


• Involve stakeholders: Developing private landowners to obtain input As the mine approaches closure,
the post-closure land use on the potential land use options this map should become more
plan provides one of the most within the bounds of predicted land detailed to include post-closure
important opportunities to involve capability/suitability and company landform designs, surface
stakeholders. Further, a post- capacity. drainage designs, land capabilities,
closure land use that has been • Map the potential land use landscaping designs and key
developed with stakeholder options: Map potential land use features.
consultation and input will be for the various mining areas • Look for beneficial uses:
far more likely to succeed. based on the above assessments Repurposing approaches have
Engage with regulators and other (considering both the capability the potential to benefit mining
stakeholders including Indigenous of the land and the input from companies and stakeholders.
Peoples, government agencies, stakeholders). While not possible for all sites,
community organisations and repurposing options should be
identified and evaluated, starting
from the earliest stages of closure
CASE STUDY planning. Tool 4: Screening
alternatives for repurposing
provides an approach for the
PIONEERING SUSTAINABLE TRANSITION screening and evaluation of
TO POST-CLOSURE (TECK) repurposing alternatives.
Teck’s Sullivan mine near Kimberley, British Columbia, Canada • Be adaptable: While post-closure
operated for almost 100 years, and employed nearly 3,500 people land use will inform many aspects
at its peak – more than half of Kimberley’s population. of the closure plan, it is important
to realise that the post-closure
The city of Kimberley is now a communities as early as the late land use may evolve due to several
tourism and recreation destination, 1960s to co-create strategies factors. For example, the opinions
and Teck-owned lands were turned that would mitigate the economic or desires of stakeholders may
over to the city to expand the local impact of the pending closure. evolve over time, especially for
ski hill and recreational resorts. This included career transition mines with a lifespan that bridges
In addition, through a collaborative planning and training opportunities a generational change. Also,
partnership, a community solar for employees, the formation of innovative approaches may be
power plant was completed a multi-stakeholder committee developed or identified that modify
and began operating in 2015 on to provide community input into the planned land use.
reclaimed land at the Sullivan site. closure planning and transitioning • Consider the legislative
from mining to a tourism-based framework: Some jurisdictions
Teck focused on the inclusion of the economy. Rehabilitation after mine may have stipulations around
local community and Indigenous closure included tree replanting, post-closure land use or may
Peoples in planning for post- water collection and water have regional planning/policies
closure land use. At the Sullivan treatment system enhancements. that should be considered for
mine, Teck started engaging with
the development of post-closure
land use. This extends to the legal
framework around title transfer and
relinquishment to third parties.
• Identify and address failure
mechanisms: Not all attempts at
repurposing or transitioning assets
have worked. It is important to
consider in the evaluation of options
©Teck

©Teck

‘what could go wrong’ and develop


plans to address this.
Solar project and ski slope developed on
reclaimed Sullivan mine in Canada

22 Integrated mine closure: good practice guide


Some successful examples of
repurposing to provide economic
benefits following closure include
CASE STUDY
establishing a solar farm on closed
tailings areas, using rehabilitated GOLD MINE TURNED BOTANICAL GARDEN IS FIRST
areas to support agriculture and OF ITS KIND IN INDONESIA (NEWMONT)
developing parkland or visitor
attractions (see Teck’s, Newmont’s In 2011, after planting hundreds of thousands of trees on a former mine
and Orano’s case study examples on site in Southeast Minahasa, PT Newmont Minahasa Raya (PTNMR),
alternative post-closure land uses). Newmont’s Indonesian subsidiary, delivered 443 hectares (1,095 acres)
The post-closure land use plan of revegetated land to the Government of Indonesia. Today, the area is
should continue to be reviewed and a thriving forest of mahogany, teak, nyatoh and sengon trees, and the
updated throughout the LoM. future site of Indonesia’s newest botanical garden.
Reforestation of the former Indonesian Institute of Sciences,
PTNMR mine area, as well as the University of Sam Ratulangi,
several other initiatives to improve the North Sulawesi Sustainable
the long-term environmental, Development Foundation and
social and economic landscape of other local constituents, PTNMR
Southeast Minahasa, demonstrates succeeded in earning botanical
how responsible mining and garden designation for the former
closure can result in long-term mine site in 2014.
benefits to local communities.
The reforestation strategy was Both the reclaimed forest and
incorporated into PTNMR’s closure botanical garden have the potential
plan and Sustainable Development to create positive economic and
Program very early in the mine’s environmental conditions for local
lifecycle. Over time, it evolved to inhabitants. In addition, the site’s
include working with the Ministry of botanical garden designation
Forestry to designate 221 hectares ensures the habitats of hundreds
(546 acres) of the forest as a of species of plants, birds,
botanical garden. insects and other animals will be
protected.
Seeking botanical garden
designation is long and arduous The reclaimed forest also has
process, requiring approvals and become a model for carbon
endorsement from various local absorption – the first of its kind in
governments, as well as research Indonesia. And because of their
and analysis to assess a botanical rich biodiversity, the forest and
garden’s potential social, economic garden are expected to serve as an
and environmental impacts. outdoor classroom and laboratory
Working collaboratively with for environmental research and
the Department of Forestry, the education.
©Newmont

PTNMR rehabilitation in Indonesia now a botanic garden

Integrated mine closure: good practice guide 23


Key questions to ask about
CASE STUDY planning for post-closure
land use
FORMER MINING SITE HOSTS A LEISURE CENTRE Has there been engagement
WITH A FISHING LAKE (ORANO) on post-closure land use with
The former mining site of Puy de l’Age (Bersac-sur-Rivalier) in France external stakeholders and
today hosts a leisure centre with a fishing lake. The former mining site meaningful incorporation of
was remediated from 1992 to 1996. Each operation was carried out in feedback?
compliance with the environmental standards in force, in coordination
with the regional department for the environment, town and country What is the landownership
planning and housing and in consultation with local populations. situation, including formal
and customary landownership
The lake was created by aspects? Are there legal
impoundment of the old open Mining method restrictions on post-closure land
pit mine, with reprofiling works • In operation from 1977 to 1993 use options?
especially adapted to meet • Underground mine workings
spawning requirement of the fish • Open-cast mines Are there foreseeable
introduced after the remediation. socioeconomic or regulatory
The rest of the site has been changes that will affect post-
Production
revegetated as grassland. The site closure land use?
• 216,000 tonnes of ore extracted
is now home to a diverse fauna
• 421 tonnes of uranium If repurposing is pursued, how
and flora.
produced will revenues/landownership be
The site was monitored until addressed? How can the mining
1999. The measurements carried Remediated from 1991 to 1996 company evaluate the business
out showed an absence of any case for repurposing, including
environmental or health impact, Fish introduced into the capital investment (beyond that
and all inspections ceased on the impounded open-cast mine needed for closure), project
Puy de l’Age site by prefectural workings and lake profile evaluation and management?
order 99-266 of 17 May 1999. adapted for spawning
Have you explored or made
The Puy de l’Age lake is private and opportunities to support,
Recreational zone devoted
is now used as a recreational area, encourage, lead on and/
to fishing
especially for fly-fishing. or participate in developing
regional land use, watershed
use and/or socioeconomic
regional planning (strategies)?
Consider sectors such as
agriculture, tourism, renewable
energy, and industrial and
other types of natural resource
development (forestry, hydro,
gravel/sand – development
minerals).
©Orano

©Orano

Is the post-closure land


use compatible with
Puy de l’Age before closure and post-closure relinquishment? How will
residual liabilities be managed?

24 Integrated mine closure: good practice guide


6.ENGAGEMENT Tool 5 Key messages for
social transition

FOR CLOSURE PLAN Tool 6 Social transition


activities

DEVELOPMENT

Effective mine closure planning and implementation considers the views,


concerns, aspirations, efforts and knowledge of internal and external
stakeholders to identify mutually beneficial closure outcomes for the company
and its host communities. Stakeholder engagement serves as a critical aspect
of managing social risks of closure. Many jurisdictions and companies require
some level of stakeholder consultation during the design of the closure plan.
Opening the closure planning The stakeholders identified will
Good practice: Involve key affected
process and getting local community be involved in activities such as
stakeholders in the closure plan
members and other stakeholders social transition planning, as well
development, and keep broader
meaningfully involved in decisions as developing a vision, planning
external stakeholders informed
on mine closure, including feedback for economic diversification and
and updated on progress. Leaders,
on the closure vision, objectives, discussing community development
including government and
measures and criteria, can lead plans. While identifying stakeholders,
traditional or indigenous community
to more beneficial outcomes for the company will need to also
leaders, should be engaged in
the mining company and external assess the capacity and capability
the development of the plans as
stakeholders. Engagement on of people who want to be involved,
the ultimate aim is for community
closure should take place throughout and training requirements. For
members and relevant government
the mining life cycle and at the right example, if the local government is
stakeholders to develop and take
time, with a strategic approach that to take ownership of planning and
ownership of outcomes of closure.
involves and empowers the local implementation of social transition
community in the decision-making initiatives, it will need to have the
process. Identification of stakeholders capacity to manage budgets.
The involvement of stakeholders is
External stakeholders, the local key to the success of the closure The following is a list of key external
community in particular, have a plan and social transition after stakeholders and how they might
central role in planning for closure mining. In developing engagement be involved in the closure and social
and realising the social transition programmes, it is necessary to transition planning process. This list
at the end of mining and developing identify the appropriate external is not exhaustive and should be built
success criteria for closure. It is stakeholders. ICMM’s Community upon to reflect the influential and
the local community members who Development Toolkit provides useful impacted groups within the mine’s
will experience mine closure and tools on identifying stakeholders. zone of influence.
ultimately determine whether the
closure plan and social transition has Sustainable mine closure is a shared Community
been successful. endeavour, requiring collaboration • The communities within the
between industry, communities and mine’s zone of influence, which
governments to understand and may be extensive, are those that
address the environmental, social will be directly impacted by the
and economic aspects of closure. mine closure process. These
In support of this, representative communities should be identified
stakeholders must be identified and early in the permitting process.
engaged. The Upper Hunter Mining The promotion of community
Dialogue case study provides an engagement and involvement in
example of a multi-stakeholder all aspects of the social transition
engagement process. process is good practice, including

Integrated mine closure: good practice guide 25


in discussions on future land use unions should be kept aware they are aware of the measures
and social investment. of the planned LoM, as well as the mining company is taking to
retrenchment/downscaling address any requirements related
Good practice: Ensure that
associated with the cessation of to public participation.
community members participating
operations. This will ensure that • Identification of government
in the social transition planning
unrealistic expectations at closure stakeholders should consider
process are not limited to elected
are mitigated, thus minimising non-regulatory bodies, such
leaders, but include informal
potential social unrest. as conservation authorities or
and traditional representatives • Employees can also act as similar; boards, such as education,
of women, youth, community ambassadors for the closure health, economic development,
associations, vulnerable groups process when engaging with energy (renewables or other); and
and under-represented minorities. other employees or external cooperatives and associations,
Public forums and other broad stakeholders. such as those for tourism,
engagement opportunities can be agriculture and natural resources
facilitated so that consultation is Governments and regulators (eg forestry, fisheries, gravel/sand/
robust, and input does not reflect • Its input on mine planning and aggregate).
only the majority view. design, future land use and social
investment can be useful to making Industry peers
Indigenous Peoples/First Nations/ sure the social transition plan • Other current or planned mineral
traditional owners aligns with and builds on existing development projects in the
• In some jurisdictions, Indigenous processes and priorities for land region could represent alternative
Peoples will be present in the use and development in the area. economic drivers for the local
zone of influence and may have • Government plans may need to community, which would inform
rights over the land separate integrate consideration of, for the social transition for mine
from mining rights. There is an example, loss in tax revenue, closure. Other mine operators
additional level of consideration utilities and community services could also represent new partners
to be given to properly address when the mine closes. for the mining company as they
the rights of Indigenous Peoples may be open to collaborating on
• Regional and local government
and recognising these rights even regional planning exercises that
representatives may provide
where they are not fully enshrined would support social transitioning,
input and support on elements
in the dominant regulatory as well as opportunities for
related to the regional and local
structure of the jurisdiction. At a repurposing or transitioning land
economy and aspects related to
minimum, there is an additional and infrastructure.
the regional development plans,
onus to consult early in the or other sectors over which they
planning process, and to recognise have jurisdictional authority, Good practice: The presence of
that these groups may have a such as health, education and other mining projects is important
much deeper connection with the transportation. Regional and local to the external message. Where
land than more recent arrivals. land use strategies or economic possible, mining companies should
For further information refer to growth priorities may exist and engage with industry peers to develop
ICMM’s 2015 Indigenous Peoples should be integrated into the cohesive messaging on impacts
and mining: good practice guide, planning for social transition at and opportunities from mining, and
second edition. closure. The mining company must their commitment to sustainability
work with local authorities to make post-closure. There is an emerging
Workforce sure they understand the impacts trend for mining companies to share
• Engagement with mine employees of mine closure and how that will experiences with social transition,
to understand their concerns and impact their development agendas recognising the value in learning
visions for the future should be and plans (eg they may choose not from their collective experiences.
undertaken to assist companies to complete capital works if there This type of transparency and
in identifying appropriate is a likely decline in population or openness is fostering a community
opportunities in supporting change in community profile). of best practice that will lead to
employees to have a successful better outcomes for companies and
• Engagement with regulators on
employment transition. The communities.
the mine closure process ensures
workforce and representative

26 Integrated mine closure: good practice guide


©Anglo American
Community engagement for the Quellaveco project

Other sector contributors • It is expected that as part of the Media


• The social transition for mine social transition for mine closure, • Local media can be an important
closure will be informed by other ‘ownership’ of social investment vehicle to share information
economic drivers in the area programmes will transition on mine closure and promote
that may offer opportunities from the mining company to the participation in community
for diversification of the local communities, government and engagement efforts.
workforce and businesses or potential other partners, which is
may have use for redundant intended to ensure continuity and Engagement on closure vision
infrastructure, or alternative post- ongoing positive impact. and post-closure land use
mining land uses.
Academia The local community should be
• International or national NGOs can
• Trade schools, colleges and other involved in the development of the
provide insight and resources on
training institutions can play a closure vision and development of
large-scale development needs and
role in providing capacity-building post-closure land use. Involving the
opportunities. Local NGOs often
initiatives that support the local community in this process may take
have a unique understanding of and
communities in preparing for many forms, and different techniques
an existing relationship with local
and maximising opportunities are used in different cultural
stakeholders. They can therefore
throughout the social transition for contexts. Meaningful participation
serve as partners in implementing
mine closure. is critical to ensuring the local
social transition, including helping
community’s ownership of the
to mobilise community involvement • Academic research or publications
results. Upfront work is needed on
in the social transition planning relevant to the closure planning
the part of the mining companies to
process, social monitoring and social transition, such as
guide the conversations and provide
throughout the mine life, studies on economic or population
examples of realistic options for post-
implementing capacity-building trends, development patterns
closure land use, considering both
programmes that will be supported and priorities, social dynamics,
technical and economic feasibility.
through the mining company’s governance capacity, etc, can assist
The timing of the engagement
social investment programmes, in informing the closure planning
will also shape the discussion,
and communicating the company’s process.
with assessments likely to be less
progress with closure.

Integrated mine closure: good practice guide 27


in depth in the earlier stages of planning exercises, most local some cases, the company may
engagement. Tool 5: Key messages communities will not have a suggest and support a broader
for social transition and Tool 6: recent, comprehensive document regional planning process that
Social transition activities checklist outlining their vision for long-term provides a detailed map of
provide guidance for key messages development. In such cases, the economic growth patterns and
to share with stakeholders during company may choose to support opportunities. While these broader
the different stages of the LoA a process to help the community planning processes would require
and corresponding activities to articulate its development priorities. collaboration with multiple parties,
undertake. This process can be facilitated they have the potential to yield more
by a qualified non-governmental useful results and can be capacity-
While some jurisdictions may organisation (NGO), government building opportunities for the local
facilitate effective development official or external consultant. In communities involved.

CASE STUDY
ENGAGEMENT FOR THE HUNTER VALLEY REGION,
NEW SOUTH WALES, AUSTRALIA
The Upper Hunter Mining Dialogue (UHMD) provides an example of a multi- implemented – this should
stakeholder engagement process. The UHMD was established by the New include mining company
South Wales Minerals Council in response to community concerns around representatives with adequate
the cumulative impacts of mining operations within the Hunter Valley decision-making authority,
region in New South Wales, Australia. Industry realised that the concerns supportive voices and potential
raised were not specific to any one site and would need a collective opponents
response. Eight coal producers in the region engaged directly through the • provide information with an
UHMD with community, environmental and business groups, as well as honest and balanced view
local government.
• present monitoring results
Issues addressed by the group relevant government departments. and information in a way that
included the closure impacts and The UHMD is a key member is understandable for local
what alternative land use options of the working group and has community members
could be implemented to sustain supported them with stakeholder • provide clarity on issues of
the local communities after mining. identification. concern to avoid potentially
Through stakeholder engagement, incorrect assumptions
the UHMD has been instrumental in The UHMD has built a venue for
• update and revise regional plans
developing a vision of how the Upper multi-stakeholder dialogues, and
on a regular basis (± five years) to
Hunter will look post-mining. generated trust and support with
consider changes in the market,
communities, the government and
technology and policy – these
The UHMD encouraged appropriate mining companies. Through the
changes may affect decisions
ministries to update the Synoptic UHMD, community issues have
related to alternative land uses
Plan: Integrated Landscapes for been identified and addressed.
Coal Mine Rehabilitation in the • communicate updates so
Hunter Valley of NSW that had Some of the key learnings from that people know that work is
been developed in 1999 by the New the UHMD for multi-stakeholder progressing
South Wales Department of Mineral engagement on closure are: • engage all relevant government
Resources and that was out of departments in planning so that
• ensure the right people are
date. As a result, the Department all government plans are
at the table, to enable equal
of Premier and Cabinet is leading consistent.
opportunities to participate
a ‘whole of government’ approach
and share solutions to be
to reviewing the plan with other

28 Integrated mine closure: good practice guide


Engagement on success success of closure outcomes in management in all cases. Residual
criteria general and of relinquishment in risks may remain, and these should
particular. be clearly communicated and
Early and ongoing engagement understood. Engagement on success
with regulators and other external Figure 4 illustrates the success criteria therefore also needs to
stakeholders should be part of criteria engagement process and include engagement on residual risk.
the development and refinement how learnings from progressive
of success criteria (see section 9 closure can be incorporated into
for further information on success the refinement of these. Equally
criteria). Ongoing agreement on important, this figure identifies the
applicable criteria will facilitate role of residual risk identification and

Figure 4: Developing success criteria

Collaborative multi-stakeholder
consultation
Define closure success criteria aligned
to the closure goals and objectives

Assurance audit / monitor / Progressive closure Learnings / track records


trial Demonstrate effectiveness from other sites
Conduct to provide objective of success criteria
evidence of performance, and
data to modify designs and/or
criteria if needed
Residual risk management
Identify risk and consequence for
Assess residual risk each domain
Mechanisms required for
managing residual risk to
be devised

Collaborative multi-stakeholder
consultation
Assess residual risk
Obtain buy-in on final land use
Empower community

Close, (success criteria have


been met) and / or relinquish
(regulatory approval for closure
obtained)

Integrated mine closure: good practice guide 29


©Goldcorp

30 Integrated mine closure: good practice guide


7. IDENTIFYING AND Tool 7 Climate change and
mine closure concerns

ASSESSING RISKS AND Tool 8 Risk/opportunity


assessment and

OPPORTUNITIES management

Risk and opportunity assessments are deeply embedded in the management


of many aspects of mining, with well-established tools and methods for the
identification and evaluation of risks and opportunities. The intention of using
these tools is to minimise risk and maximise opportunity.
There are numerous potential Given these benefits, it is good basis incorporating changes to the
management benefits to embedding practice to embed risk assessment knowledge base such as changes
a structured risk/opportunity in closure management, with a in the mine plan, research results,
assessment process in closure formal risk assessment conducted learnings from progressive closure,
planning. These include: and documented early in the closure monitoring data and input from
planning process and revisited ongoing stakeholder consultation.
• attention and resources focused on
periodically as the closure plan
the risks and opportunities that are
evolves. Identified risks should be This risk assessment should consider
most important.
used as a management tool, as several different types of risk,
• identification of potential closure a basis for setting out tasks and associated with various categories of
cost savings. accountabilities for both preventing consequences. Categories typically
• closure objectives that are and mitigating risks. used in current practice may include
appropriate for the identified risks. the following:
• establishing metrics for success Figure 5 illustrates the key steps to
• Health and safety: impacts on
criteria. be taken in identifying risks as part
the well-being of people (injuries,
of the closure planning process.
• development of appropriate closure loss of life, as well as benefits
The risk assessment process
activities so that the identified risks such as better access to medical
should be undertaken on a regular
are mitigated to an acceptable level.
• communication of key risks
within an organisation and to
stakeholders.
• opportunity to engage a range
of stakeholders in the closure
process.
• considering the design life of
any engineered systems or
features that would require
ongoing maintenance or future
replacement.
• understanding and communication
of residual risks that will
remain after implementation
of closure activities, facilitating
relinquishment.
• improving likelihood that
opportunities for lasting benefits
are identified and put into action,
including opportunities for
©Teck

alternative post-closure land uses.

Greenhills operations, Canada

Integrated mine closure: good practice guide 31


care, improved contractor safety of influence of the mine, including other sites, and opportunities to
practices, etc). the workforce and cultural leave a positive legacy post-mining.
• Legal and regulatory: heritage, as well as the business
consequences associated with risk associated with workforce When undertaking the risk
non-compliance with regulatory uncertainties (ie safety and assessment, cumulative impacts or
statutes, including warnings, fines, financial liability impacts). risks should be considered, along
legal actions and imprisonment. • Financial: impacts on the mining with opportunities. For example,
company measured in financial risks considered in isolation may
• Environmental: impacts on air,
terms, including opportunities for have low consequences, but when
soil, water, and ecosystems, as
cost savings/offsets. considered in the context of multiple
well as opportunities such as
mining sites and industrial facilities
habitat creation and biodiversity • Reputational: impacts on the
in a given area producing similar
improvements. reputation of the mining company,
impacts, the risk to the company,
• Social: impacts on the well-being including the social licence to
environment, and community may
of the communities within the zone operate at the site in question and
significantly increase. Approaches to
managing and mitigating cumulative
risks and opportunities may also
significantly vary from approaches
Figure 5: Risk assessment process
for these risks in isolation, resulting
in potential greater closure costs
1. Identify risks and associated or lesser benefits if not properly
hazards that could affect mine captured during the initial risk/
closure opportunity assessment.

One of the areas of risk evaluation


2. Rate the risks before where practice is evolving rapidly is
mitigation by determining the the consideration of climate change
level of impact in terms of impacts on closure and long-term
likelihood and consequence of
planning. Tool 7: Climate change
occurence (refer to Tool 8)
and mine closure concerns provides
an overview of the current state
Communications and Consultation

of addressing climate change risk


3. Devise appropriate closure in mine closure, and indication of
Monitor and review

activities or other actions to additional recommended resources.


mitigate the identified risks taking
into account appropriateness and
feasibilty of activities For the largest risks, the critical
control management (CCM) process
provides a practical approach to
providing control over large or
4. Rate risks post-mitigation potentially catastrophic events
assuming reasonable
effectiveness – mitigations that are identified through the
should reduce risk rating risk management approach. The
CCM approach provides clarity
on the controls that matter most
for such events, with a balanced
5. Refine closure costs to approach to both preventative and
implement devised closure
activities or process improvements mitigative measures. Clear guidance
on CCM can be found in ICMM’s
Critical control management:
implementation guide.
6. Implement actions

32 Integrated mine closure: good practice guide


Key questions to ask about the risk/opportunity assessment Many mining companies have
their own risk assessment
tools. In the absence of an ‘in-
Does the assessment capture the categories of risk that are important to house’ standard, Tool 8: Risk/
the mining company and stakeholders? opportunity assessment and
management provides a risk/
Were the right team members, representing the needed mix of
opportunity assessment process
disciplines, involved in identifying and ratifying the risks and
based on the risk management
opportunities?
standard developed by the Council of
Standards Australia and the Council
Was all relevant available information used to assess the risks, including
of Standards New Zealand, AS ISO
input from external stakeholders where applicable?
31000:2018 Risk management –
guidelines. This tool is applicable to
Are there data gaps that need to be addressed before risks can be
evaluating mine closure risks, as are
adequately assessed?
many other risk evaluation tools in
Have risks related to unplanned and temporary closures been use by ICMM members.
considered?

Have potential cumulative risks been assessed?

Has a stochastic (probabilistic) assessment of risks been considered?

Should success criteria or closure activities be refined based on the risk


assessment?

Are residual risks compatible with relinquishment and/or the identified


post-mine land use, and do all stakeholders understand the residual
risks?

Have risks been assessed both with all controls in place, and in the case
where the controls fail?

Have risks that could appear post-closure been included in the


evaluation?

Have the strategies been identified to mitigate the consequences of any


risks eventuating post-closure, and are measures being put in place to
deal with these consequences?
©Anglo American

Sishen mine open pit, South Africa

Integrated mine closure: good practice guide 33


©Goldcorp

34 Integrated mine closure: good practice guide


8.CLOSURE Tool 9 Considerations in developing
closure activities for

ACTIVITIES Tool 10
transversal issues

Considerations in developing
closure activities for domain-
specific issues

Closure activities are the physical works carried out to close the site.
These may be done during operations (progressive closure) or in the closure
and post-closure period. Closure activities are undertaken to achieve specific
closure objectives and satisfy success criteria.
For example, a closure objective • engineering designs and As the closure plan matures,
may state that buildings on the site optimisations. designs are refined, options further
should not pose a safety hazard • formal trade-off studies, multiple assessed, stakeholder input
post-closure. The appropriate accounts analysis and cost gathered, trials conducted and
closure activity to achieve this may analyses (including life- cycle cost definitive measures established.
be demolition of the site buildings, analysis). Research, engineering studies or
with the remnants either recycled experience with progressive closure
• resistance to climate change.
or disposed of in a landfill. This may be used to inform the selection
section presents approaches that • the results of research studies of closure activities and provide
are used to evaluate alternative and learnings from progressive greater confidence that the selected
closure activities and choose the rehabilitation. measures will provide the desired
option that will be implemented to • regulations or regulatory outcomes. For instance, active
achieve the objectives in the short commitments (such as those made water treatment may be considered
and long term. For more detail on during the environmental impact to manage impacted water at a
the technical aspects of measures assessment process). site in the early design stages. As
that are typically used, please see • standard industry practices (eg it is site-specific testing is carried out, it
Tool 9: Considerations in developing typical to demolish and remove all may be demonstrated that passive
closure activities for transversal buildings that will serve no purpose treatment options will be effective,
issues and Tool 10: Considerations following closure). or that source controls can eliminate
in developing closure activities for the need for treatment altogether.
• residual resourcing opportunities.
domain-specific issues.
• value of remaining assets (land, Not all closure activities will
At the simplest level, the closure plan water rights, infrastructure). be subject to the same level of
provides a description of the closure evaluation. Some will be relatively
options that will be implemented for Similar to the development of other standard and will not require
each domain that makes up the mine. projects, the level of design detail significant consideration of
The cost of carrying out these closure for closure activities usually evolves alternatives or may be a binary
activities is the basis for any estimate over the mining life cycle. At the choice between simple alternatives
of the overall cost of closure. earliest stages of closure design, (eg demolish or do not demolish).
measures are typically conceptual, In other cases, there may be many
For a given closure objective, there and it is common to carry forward alternatives considered, with
may be many feasible closure several different conceptual closure significant differences among
activities. The selection of closure activities for a given area. It is the options in terms of cost,
activities at the site may be informed typically necessary to identify an social acceptance, effectiveness,
by the following: option from the earliest stages as the opportunities, risk profile and other
most likely to succeed and integrate factors. In these cases, final selection
• risk assessments (which may also the cost estimate for that option in of the appropriate closure activities
inform the definition of objectives). the overall site closure cost estimate. may take years of effort, involving
• stakeholder input. Many companies can utilise their input from stakeholders, research
• chemical and physical capital projects framework for the programmes, design studies and
assessments. evaluation of closure activities. specific risk evaluations.

Integrated mine closure: good practice guide 35


The general approach is as parameters, such as cost or value. weightings placed on different
follows: This information can be used to parameters.
further narrow the list of options. • Formal risk evaluations may
• A preliminary ‘long list’ identifying Depending on the number of also be carried out on closure
potential closure activities is options, designs may be advanced alternatives to demonstrate their
generated. This list is typically to a conceptual or pre-feasibility effectiveness at risk reduction in
developed based on several inputs, level to further screen out various domains.
including professional experience, alternatives.
literature reviews and stakeholder
• Where multiple options remain Many variations on the above process
input.
at this stage, a multiple accounts are possible and it will be necessary
• An initial screening to eliminate analysis1 may be used to compare to adapt to site-specific conditions
options that are not feasible, either and rank options. While cost- and the complexity of available
on their own or in combination with benefit analyses are useful, a alternatives to meet closure
other measures. Formal ‘evaluation multiple accounts approach is objectives. The sophistication of the
parameters’ may be established at commonly used in closure design evaluation process used should be
this stage, which are quantitative as a way to incorporate disparate commensurate with the cost and
or qualitative considerations used elements such as cost or value, complexity of the measures under
to evaluate the options under environmental impacts, social consideration. The level of effort will
consideration. For example, social acceptance and technical risk, be dependent on the complexity of
acceptability would likely be a among others. analysis; best practice is to perform
qualitative parameter, while cost the analysis in stages. This process
• If a multiple accounts analysis is
would be quantitative. should be supported with ongoing
used, the options assessed will
• The options that have been be ranked. It is important for the updates to the relevant stakeholders
eliminated in the screening should scoring and weighting approaches (both internal and external) regarding
be documented, along with the to be well documented as the progress and status to ensure timely
rationale for their elimination. rankings will be a direct result of response to concerns and maintain
This documentation helps ensure these. engagement.
that decisions are traceable and
• At the completion of a multiple
facilitates coming back to ‘long list’ A formal project management
accounts analysis, sensitivity
options if conditions change. approach is recommended when
checks should be carried out
• Of remaining options, screening- completing closure activities due to
to evaluate the extent to which
level engineering designs or the magnitude of costs associated
rankings are affected by credible
technical evaluations may with closure.
ranges for either the inputs or the
help quantify the evaluation
©Goldcorp

Open pit backfilling at Marlin Mine, Guatemala

1. A multiple accounts analysis (also known as a multi-criteria analysis) establishes two or more ‘accounts’ that are weighted based on a qualitative and transparent
assessment of their relative importance to the decision. Various options can then be rated on a numerical scale in each account, and a weighted total calculated for
the option. There is no limit to the number of ‘accounts’ that are used. Typical accounts include cost, environmental impacts, social impact and technical risk.

36 Integrated mine closure: good practice guide


9.SUCCESS CRITERIA

Closure activities are implemented to meet specific closure objectives.


Success criteria are the specifications, measurements or requirements
that, if met, denote the success of the closure activities in meeting closure
objectives (also sometimes called ‘closure criteria’).
As an example, an objective might demonstrate to the regulator or
be to prevent an acidic seep from stakeholders that it has been met.
impacting water downstream of a While the method of measurement
mine waste facility, and the closure is usually obvious for numerical
activity implemented could be a criteria (such as concentrations
passive treatment system. One of or discharge flow rates), narrative
the criteria to demonstrate that criteria may require alternative
this measure is satisfying the forms of measurement (such
objective could be that discharge as completion of a given task
concentrations from the passive as confirmed through as-built
treatment system are maintained drawings or field inspections).
within a defined range, such as a pH Some objectives may require a
between 6 and 9. combination of qualitative and
quantitative measurement.

©Gold Fields
Meeting success criteria is a concrete • Achievable: If relinquishment
way to demonstrate that the closure or return of financial assurance
plan has been executed effectively, is to be attained, it is critical
assuming the correct criteria have that the criteria are realistic and Rehabilitated site at Damang mine, Ghana
been selected. It is usually necessary can be achieved. Unrealistic or
to demonstrate that success criteria poorly defined criteria can delay the agreement from the regulators
have been met before the associated or prevent relinquishment, or and other external stakeholders are
financial assurance will be released unnecessarily extend monitoring not meaningful. To ensure agreed
(where applicable), or relinquishment periods. criteria are developed, it is preferable
considered. Success criteria
• Relevant: Criteria should to engage on them early in closure
developed specifically to facilitate the
ultimately be aligned with planning, with full documentation of
relinquishment (legal and financial)
closure objectives and the social, agreements on applicable criteria.
of a property are often called
environmental and regulatory These agreements and approvals are
‘relinquishment criteria’.
context of the site. especially important if attempting to
• Timely: Criteria will have a time develop a clearly defined pathway to
The SMART approach (specific,
component, either explicitly or relinquishment.
measurable, achievable, relevant,
timely) is useful for developing and implicitly. Some can be considered
assessing success criteria. Key completed immediately after Good practice: The setting of the
considerations for each element of implementation of the associated success criteria should be done
SMART criteria are as follows: closure activities while others will with inputs from multiple disciplines
require a period of monitoring. across the operation. Involvement and
• Specific: Criteria should relate For the criteria that will require a understanding of the targets by the
directly to closure objectives and monitoring period, it is important local community and regulators should
individual closure activities. A to clarify early in planning how also be secured for ongoing alignment
closure activity or group of closure duration of monitoring will be and agreement on the endpoint for
activities without an associated defined. mine closure.
criterion indicates a gap; a criterion
without an associated measure In addition to the standard Some success criteria may be
or measures may indicate the SMART approach, the underlying relatively simple to define and can
criterion is too general. fundamental element in closure be clearly established at the earliest
• Measurable: If a criterion cannot is success criteria are ‘agreed’. stages of closure planning. As an
be measured, there is no way to Success criteria that do not have example, regulatory limits often

Integrated mine closure: good practice guide 37


provide clearly predefined success The continual refinement of success may be possible to secure regulator
criteria. Finalising other criteria will criteria over time highlights the and stakeholder agreement on less
require study and research and may iterative nature of closure planning, stringent criteria, which may permit a
require agreement on post-closure and the importance of ongoing change in the closure measure.
land use. This means that criteria monitoring and review. Changes in
may not be finalised until the final the planned post-closure land use Success criteria are most commonly
closure plan is developed. can drive changes in criteria. While developed for ‘lagging indicators’,
criteria are designed to evaluate the that is, indicators that demonstrate
Criteria development may require success of closure activities to meet that the task has been completed
site-specific studies and research closure objectives, changes in criteria in accordance with the objective.
plans. For example: may also drive changes in the closure However, for managing the closure
activities. For instance, where an process, leading indicators can be
• Multi-year revegetation studies
objective has been defined to avoid extremely useful to assess if closure
to refine the planned approach
adverse impacts on a downstream activities are on track for success.
to rehabilitation and applicable
ecosystem, active water treatment Examples of this include all wastes
success criteria are common.
may be selected as the approach characterised and managed as per
• Discharge criteria for impacted that can meet conservative criteria the plan as they are generated, and
mine waters may require selected prior to the completion of appropriate dumping records as they
studies for development – these site-specific studies. However, once are being generated.
studies could address a range site-specific studies are completed, it
of topics, including ecosystem
characterisation, evaluation
of assimilative capacity, anti- Key questions to ask about the success criteria
degradation standards and mixing
zones, etc.
Are the criteria related to the closure objectives? Criteria without
objectives or objectives without criteria indicate a gap in the closure plan.
Where the interactions are complex,
and longer-term studies are required
Are the criteria measurable or demonstrable, either through numerical
to develop criteria, it is common
assessment or inspection reports?
to start closure planning based on
conservative criteria, which are then
Are the criteria achievable in a reasonable time frame? Is the mining
refined as information is obtained
company willing to commit to achieving them, and have the appropriate
from research.
internal stakeholders been involved in making commitments to meet the
criteria?
Some criteria will be highly
dependent on the post-closure land
Do the criteria need a specific time frame, for example, meeting water
uses. For instance, water quality
quality over a five-year period?
criteria may be quite different if the
closure plan anticipates that water
Have regulators been involved in the development of success criteria or
may be used for agriculture or as
approved them? Is there a clear agreement that meeting the criteria will
an input to aquatic ecosystems. In
form the basis for a release of associated financial assurances and/or
many jurisdictions, both water and
permit relinquishment? Has this agreement been documented?
soil quality criteria are explicitly
related to land use in the regulatory
guidance, with different criteria Have external stakeholders been involved in the development of criteria?
applicable to industrial, agricultural Is there documented agreement with the criteria?
and residential uses. This means that
changes in planned land use may Once success criteria are met, what are the residual risks? Will these
change the applicable criteria. residual risks permit relinquishment?

Is it feasible to measure the criteria?

Have success criteria been developed for both leading and lagging
indicators?

38 Integrated mine closure: good practice guide


10. PROGRESSIVE CLOSURE

Progressive closure is the implementation of The term ‘progressive closure’


closure activities during the operating life of a mine. encompasses ongoing efforts to
advance closure activities during
The types of activities that can be implemented as construction and operation of
progressive closure are controlled by site-specific a mine.
conditions and mine plan.
Some of the most common
progressive closure works include:
• soil management (eg stripping,
stockpiling, placement).
• strategic placement of uneconomic
materials.
• diversion of unimpacted waters.
• revegetation.
• stabilisation works.
• cover placement.
• demolition of unneeded

©Newmont
infrastructure.
• improvements to water
management infrastructure.
Progressive rehabilitation at Batu Hijau Mine, Indonesia
• in-pit dumping of waste rock
material. of closure works are satisfactory. turn reduces the total liability as
• capping or encapsulation of tailings This can enhance the social licence considered in financial reporting,
waste rock material. to operate not only at the site under LoM planning and financial
consideration, but also at the assurance. Some jurisdictions
In some circumstances, the line operator’s other mines. provide mechanisms for reducing
between mining activities and • Experience/knowledge building: financial assurance amounts
progressive closure may blur. For Progressive closure provides the based on the extent of successful
example, where open pits are used opportunity to evaluate and refine progressive rehabilitation. Ideally,
for the disposal of mine waste, closure activities at a smaller this could be tied to progressive
backfilling activities can be seen as scale prior to final implementation. relinquishment for areas of the
progressive closure (pit filling and This can result in numerous site where closure has been
stabilisation) or operations (mine improvements in the closure completed.
waste disposal). plan, including risk reduction (due • Tax benefits: In some jurisdictions,
to more certainty in technical there may be a tax benefit with
The benefits of progressive closure
approaches), practical experience progressive closure. Progressive
are well documented. Some of the
to inform feasibility of closure closure activities are carried out
most important are:
activities and cost estimates, when the asset is generating
• Social licence and regulator and improvements to definitions revenue, and may facilitate tax
relations: Progressive closure of success criteria. Establishing reduction, but activities carried out
provides the opportunity to and testing success criteria in after closure typically do not offer
demonstrate the effectiveness collaboration with regulators the same type of benefit.
of closure activities at operating and other stakeholders helps
sites, as well as the overall with the development of realistic, All these benefits can be framed as
commitment to implementing experience-based agreements. a reduction of risk for the closure
closure. It provides stakeholders • Reduction of liability: Successful plan. Care should be taken to not
with evidence that the proposed progressive closure reduces the delay detailed closure planning
technologies are effective and that extent of disturbed lands, which in for sections or domains going
conditions after the implementation through progressive closure works.

Integrated mine closure: good practice guide 39


Implementing measures without should not be the only factor benefits such as reduced carrying
having completed detailed studies taken into consideration when costs or increased availability of
may lead to higher costs and often assessing progressive closure. credit for other investments.
long-term residual risks. In particular, an NPV analysis
typically assumes that the scope As shown in Figure 6, there is not
An evaluation of progressive closure of an activity will remain static just one pathway for the reduction of
risks and opportunities also requires if delayed, which is often not the liabilities through the implementation
consideration of the reasons why case with closure. of progressive closure. A ‘standard’
progressive closure has not been programme of progressive closure
implemented at sites where it may The business case for progressive may result in one level of reduction
appear technically feasible: closure should account for both in the provision whereas a more
the benefits of implementing intensive programme could result in
• Uncertainty in the mine plan:
progressive closure and the a significantly greater reduction in
While closure plans are developed
possible arguments against it. the provision.
based on a current mine plan,
mine plans typically evolve over Progressive closure and costs Another financial benefit of
time and at any given time there
Closure costs can be challenging progressive closure is in terms of
are usually several possible
to estimate correctly and there is cash flow. Progressive closure is an
modifications to the plan under
considerable industry experience operational cost, typically incurred
consideration. As an illustration,
where actual closure costs at a time when cash flow is positive,
a waste rock facility may appear
have differed considerably from while final closure occurs after
to be at its final extent and a
estimated values. This potential production, when cash flow for the
candidate for cover placement.
variation is a risk for the mining mine can be expected to be low or
However, there could be a mine
company. Progressive closure is negative. There may be benefits to
plan update under consideration
one of the most effective means incurring closure costs when cash
that would require expansion
to gain direct experience with the flow is positive, such as tax benefits
of the dump. If this change is
implementation of the closure in some jurisdictions.
implemented, rehabilitation
effort spent on the dump could works and accurately characterise
their true costs. Feeding this An NPV (or present value) analysis
be wasted. A building may be a
information back into future cost of costs is likely to suggest that
candidate for demolition, but there
estimates will reduce the risk of progressive closure is more
may also be a viable option under
inaccurate estimates. expensive, as the present value of
consideration to repurpose it for
any expenditure will be lower the
other mining uses.
Implementing progressive closure further in the future it is placed
• Competition for limited financial also provides the opportunity to (assuming no change in scope).
resources: Implementing reduce the total disturbance at any However, if progressive closure is
progressive closure typically given time, reducing the amount looked upon as an investment, a
requires expenditure above what of the financial provision for the more balanced analysis emerges.
is strictly necessary for operations company (see case study example The returns on an investment in
each year. If only financial factors on the value of progressive closure progressive closure typically include
are considered, progressive at the Rio Tinto operated Diavik both tangibles (improved book value
closure works may not be able to Diamond Mine). This can benefit the of the asset, reductions in costs
demonstrate a competitive rate of book value of the company. If the associated with provisions, improved
return on investment. Due to the reduction in the disturbance can cash flow, possible tax benefits,
time value of money, a net present be translated into a corresponding possible reduced carrying costs for
value (NPV) analysis may show reduction in the financial assurance financial assurance amounts, greater
a strong financial argument for held by the regulator, this can credit availability) and intangibles
pushing closure works to as late reduce the costs associated with (risk reduction, particularly through
a date as possible. It is important the financial assurance. Depending reduced risk of cost overruns and
to note that an NPV analysis is on the form of financial assurance through improved relations with
not a complete business case and required, this can translate into stakeholders including the likelihood

40 Integrated mine closure: good practice guide


of gaining approval for future Various kinds of indicators can be • mitigation of identified risks .
projects). Both the tangibles and used for completed closure work. • hectares/percentage of
intangibles should be considered Some common examples indicating rehabilitated land that meet the
when evaluating an investment into different stages of progressive final rehabilitation success criteria.
progressive closure. closure work include:
• project performance (cost and In some cases, it may be worthwhile
Tracking progressive closure schedule) of scheduled concurrent to use performance indicators to
The rate of progressive closure rehabilitation items. establish annual targets or for
and associated costs vary tracking progress.
• completion of rehabilitation work
widely according to site-specific as per plan and quality assurance
circumstances (complexity, climate/ requirements.
rainfall) and regulatory framework.
• percentage of salvaged topsoil
Even at sites where there are
directly placed.
opportunities for progressive closure,
there may be some years where • area of reshaped waste rock
progressive closure activity on the facilities.
ground is not possible given the mine • amount of reactive material
plan context or economic conditions. disposed of according to plan.

Figure 6: Progressive closure – opportunity for liability reduction No rehabilitation


Standard progressive rehabilitation
Working smart – above and beyond

Operational
disturbance

Closure liability and


effort required at
Closure provision

closure

Initial disturbance
due to construction

Construction Operation Cessation Mine


commences commences of mining closure

Source: Anglo American

Integrated mine closure: good practice guide 41


Key questions to ask about progressive closure
CASE Has the business case for progressive closure been fully considered with
STUDY site leadership, considering the full range of benefits?

Have all opportunities for progressive closure been explored?


VALUE OF PROGRESSIVE
CLOSURE AT DIAVIK Have the appropriate internal stakeholders been considered in the
DIAMOND MINE evaluation of progressive closure opportunities and risk, with the
(RIO TINTO) corresponding sign-off?

The Diavik Diamond Mine is


Have resources required for progressive closure been included in short-
operated by Rio Tinto in the far
or medium-term plans (financial and physical resources)?
Northwest Territories in Canada
and produces gemstone quality
Is progressive closure aligned with and integrated into the LoM planning
diamonds. and closure planning?
The operations have considered
closure since inception in 2003, Is progressive closure aligned with post-closure land uses?
with closure objectives already
agreed by regulators and local Are lessons learned from progressive closure tracked and
First Nations. In 2018, Rio Tinto communicated? Are successes with progressive closure being
opened the fourth and final communicated with external stakeholders?
kimberlite pipe for mining. Rather
Are there opportunities to involve external stakeholders with the design,
than deposit waste rock on a
implementation or monitoring of progressive closure works?
short haul dump and rehandling
the waste to its final location as
Are costs fully tracked and compared to estimates? Are learnings on the
inert cover material at closure,
true costs of implementation incorporated into cost estimates?
the material is directly long
hauled and placed in final form to Are as-builts being sufficiently documented to facilitate lessons learned
meet closure criteria. and regulatory approval?

By implementing progressive Are reductions in liability accurately identified and incorporated into
closure, not only are net present closure cost estimates?
costs reduced by over 10 per cent
but final closure landforms are What incentives would be appropriate to encourage site leadership to
completed ahead of schedule, apply resources to progressive closure activities?
heavy mining equipment
utilisation is increased, acid rock
drainage risks are reduced and
visual amenity is increased.
©Rio Tinto

Diavik Diamond Mine

42 Integrated mine closure: good practice guide


11.SOCIAL TRANSITION Tool 5 Key messages for
social transition

Tool 11 Social investment


for closure

As with other closure management aspects, The term ‘social closure’ is more
proactive planning and management for the social commonly used in the industry
at present. However, it often
transition at closure is key for minimising negative has a negative connotation that
impacts and capturing benefits. Host communities can impede discussions with
that have grown dependent on mining operations stakeholders. As such, ICMM
suggests ‘social transition’ as a
will experience considerable socioeconomic more appropriate term.
impacts at closure.
This can be especially true for those foster economic diversification, and for socioeconomic development.
in remote areas or in developing when no efforts are made towards However, experience shows that
countries where the mine may facilitating the transition. investment in social transition can
become the primary local economic result in sustainable and resilient
driver and take on a de facto Good practice: Social transition
community outcomes when
leadership role that would otherwise for mine closure recognises risks
government, community and other
be the responsibility of government. associated with local dependence
partners share in the decision-
Governments in these scenarios often on the mine and consequently
making, responsibility and process of
have limited capacity or resources creates opportunities to encourage
closure.
and, in some cases, share the same the development of sustainable
expectations as the communities. post-closure options. The mine can Good practice: Social transition
build capacity of local communities for mine closure that considers
Figure 7 illustrates the development
and their governments to meet government-led development
of socioeconomic dependency on
their needs without the mine’s plans helps to reinforce the role of
mining activities over the life of the
involvement. government and enable ownership
operation. The figure illustrates
by the local community over social
the differing outcomes when
It can be challenging to define investment programmes in the long
social investment is strategically
boundaries of a mine’s responsibility term.
directed towards initiatives that

Figure 7: Social transition through the LoA (illustrative example) No social transitioning
Social transitioning

Planning and implementing social transition for closure


Socioeconomic dependency

Liability

Exploration Construction Operations Closure Post-closure

Integrated mine closure: good practice guide 43


Planning for social transition • how planned or unplanned • communication of closure internally
to closure developments such as mine (employees) and externally (local
expansion or construction of new communities, government, etc) –
Planning for social transition should infrastructure change the mine’s refer to Tool 5: Key messages for
be an integrated and iterative process zone of influence; this can result in social transition.
involving multiple mine departments changes to project stakeholders,
and stakeholders. This planning and the nature of the mine’s social Social investment for closure
process is incorporated into the and environmental setting.
overarching mine closure plan, either Social investment for closure
• the operating life of surrounding includes those aspects of social
through a dedicated social transition
mine operations and other investment that focus on generating
plan or through planning integrated
industries. post-closure economic and social
into the mine’s overall closure plan.
The iterative nature of planning for • implications of local procurement returns in local communities and
social transition is similar to the policies during operations and on building community resilience to
iterative nature of closure planning subsequent impacts on suppliers the impacts of mine closure. Refer
as a whole. post-closure. to Tool 11: Social investment for
• workforce recruitment and closure and case study example
retrenchment planning. on Vale’s approach to economic
Good practice: Social transition
diversification through strategic
planning should integrate the • interest, availability and capacity of
social investment for closure.
identification of social risks and local community representatives in
their mitigation measures into the participating in the social transition
Basic principles for social investment
earliest phases of mine planning. planning process and the type of
in support of social transition for
Incorporating the right specialists future leadership roles they can
mine closure are:
and stakeholders early in the take on.
selection of objectives can help • the impact of generational changes • Align social investment around
ensure that the closure plan includes over the LoA, and the resulting a shared vision of a post-mining
social transition objectives. evolution of needs and desires in future.
the community.
Figure 8 shows a five-step iterative
process. In the context of planning for
the social transition to closure, the
Figure 8: Iterative nature of social transition planning and management
initial ‘understand’ step links to the
knowledge base and understanding
Understand
the extent to which socioeconomic
dependence on the mine has
Baseline
developed (or is projected to develop). Zone of influence
In the ‘engage’ step, communication Closure goals
is undertaken to develop and Commitments
validate the approach to social Impacts
se

Eng
Revi

transition, while implementation Assess Validate


age

may include actions from securing Reconfigure Communicate


Recommend Align
funding and undertaking trials to Visioning
full implementation of programmes.
In the ‘measure’ step, results are
compared to the goals that were set Goals Contracts
for implementation. These results Key performance Stakeholders groups
are then used in the iterative process indicators Communication
Outcomes Funding
to revise and update the approach. Feedback Trials
M
t
en

ea
su em
The company’s approach to re pl
Im
social transitioning will require
consideration and management of:

44 Integrated mine closure: good practice guide


• Focus social investment for corporate aspects of the mine. • costs associated with
closure on building resilience – employee training or reskilling implementation of social transition.
– that is, building the long-term programmes. – stakeholder engagement and
capacity of stakeholders to grievance management.
– staff and contractor redundancy
transition through the changes
costs. – social investment
resulting from closure and to
– partnership costs (advisory implementation.
benefit from the presence of
mining. boards, fund management, etc). – relocation costs including
– communication and media planning and implementation,
• Start early in developing
planning and implementation. the latter of which may be
social investment for closure
and implement progressively
throughout the LoA. This process
cannot wait until closure is
imminent.
CASE STUDY
• Integrate and coordinate social
investment with other closure- ECONOMIC DIVERSIFICATION PLAN FOR THOMPSON,
related activities, both within the MANITOBA, CANADA (VALE)
company and with other local
Thompson, Manitoba has evolved as a diverse urban centre that functions
stakeholders.
as a regional service hub in Northern Manitoba, Canada. However,
• Develop a strategic, planned and economic volatility, coupled with an announcement by Vale in 2010
resourced approach to social that it was to close its smelter and refinery by 2015, prompted Vale to
investment for closure. support economic diversification of the region. The Thompson Economic
• Partner with others to identify Diversification Working Group (TEDWG) was formed following extensive
and prepare alternative long-term discussions that included the city and multiple stakeholders including
economic opportunities. indigenous rightsholders.
An agreement was adopted that fully engage in planning for the
Social transition costs identified specific funding in priority long-term sustainability of their
Estimating the cost and effect of the ‘streams’ to address infrastructure, community. It also highlighted how
social transition process for closure economic development and other practical tools, multi-stakeholder
planning presents specific challenges. operational needs articulated by dialogue and planning can
Unlike other elements of closure cost the TEDWG and city leadership. transform the challenges presented
estimation, social transition costs do The TEDWG process represents a by mining transition and changing
not typically have readily available, best practice in both procedural demographics into opportunities for
experience-based unit costs or and technical capacity building sustainable growth.
easily measurable quantities. There to ensure local stakeholders can
is considerable variability among
sites with respect to socioeconomic,
environmental and political settings,
stakeholder expectations, community
capacity, etc.

Social transition costs can include


factors such as:
• costs associated with updating
the knowledge base.
– social and health impact
assessments.
– community sensitivity analysis.
©Newmont

– economic diversification studies.


• costs associated with operational or
Stakeholder engagement at Yanacocha mine, Peru

Integrated mine closure: good practice guide 45


significantly different from initial under way, with the community and Key questions to ask about
costs depending on how well key stakeholders already mobilised managing social transition
migration, supply chain, etc have and implementing their community
been managed during the LoA. development plan, with limited need Has the knowledge base been
– final land use and infrastructure for ongoing support from mining updated for social transition?
companies.
costs to meet community or
government vision and their Has a socioeconomic impacts
It is important to ensure that there and opportunities assessment
requirements.
is a clear linkage between the been undertaken to understand
– post-closure monitoring, social transition costs and the other community capacity and
measurement and reporting. components of the closure cost. opportunities for economic
If the social transition cost is not diversification? Have partnering
Much of the expenditure towards embedded in the overall closure opportunities been explored?
effective social transition should cost estimate, there can be an
occur during operations, including incorrect accounting of true closure Has messaging around
projects that aim to support a cost (see case study example on closure been integrated into
sustainable local economy post- Anglo American’s approach to the stakeholder engagement
closure. At closure, social transition social transition planning at Landau programme? Has it been
activities should ideally be well colliery). included in the initial approval/
permitting?

Has a social investment


CASE STUDY programme been developed
with a focus on sustainable
post-closure programmes and
SOCIAL TRANSITION INTEGRATION IN PLANNING AT implemented during operations
LANDAU COLLIERY, SOUTH AFRICA (ANGLO AMERICAN) or as early as possible?
Anglo American completed the scoping, development and
Are training programmes in
implementation of a social transition plan for Landau colliery in
place to facilitate upskilling
Mpumalanga, South Africa during operations to reduce closure
employees for post-closure
liabilities. The plan followed a well-defined process and project
responsibilities and to improve
management approach to better define the scope. The work
their employability?
demonstrated that the following processes supported successful social
transition planning:
Has a retrenchment plan been
• Integrate the social transition assessment as living documents developed with consideration
plan into the overall mine closure and operational tools to be of staggering reduction in
plan (social transition is seen as updated, which will improve workforce and assigning post-
an operational activity). the social transition plan and closure responsibilities where
• Review and update existing estimate. possible?
operational processes in line with • Move from ‘our plan’ to ‘their
the plan. future’.
• Develop a detailed stakeholder
engagement plan. Anglo American incorporates social
transition into their operations. As
• Update and improve the
a corporation they have identified
current social transition plan by
that improving operational activities
implementing the stakeholder
will maximise the reduction of
engagement plan.
post-closure residual impacts and
• Use the basis of estimate obtain the best value from allocated
document and the risk resources and funds.

46 Integrated mine closure: good practice guide


12.CLOSURE COSTS

Mining companies, regulators and investors share a common interest in ensuring


the costs of implementing mine closure are accurately identified and clearly
communicated. The estimation and reporting of costs present a unique set of
challenges as closure costs may need to be estimated based on designs and
assumptions made prior to construction of the mine, and then updated regularly
over the LoA incorporating changing information.
These updates may occur over a span on the most recent version of the The LoA closure cost estimate
of years or even decades, prior to mine closure plan, the numerical includes the total cost of ownership
detailed design and implementation values are typically different as each expected to be incurred, including
of closure construction stages at the responds to different user needs and costs associated with all existing
end of the mine life. will be prepared under different sets facilities and mining features, as
of frameworks. Understanding the well as all those facilities not yet
This section provides an overview of differences and points in common constructed, land disturbances
the different types of cost estimates for these types of estimates is key to not yet incurred, mining not yet
that may be needed to respond to the efficient use of information and undertaken and progressive
the needs of mining companies, to providing useful estimates. A brief rehabilitation not yet undertaken
regulators, investors and other overview of each type of estimate is that have been included within the
stakeholders, followed by a summary provided in the following subsections. LoM business plan. It also includes
of recommended practices and For further information refer to monitoring and maintenance costs
considerations for developing all ICMM’s Financial concepts for mine over the anticipated post-closure
types of cost estimates. closure information document. period. This cost estimate should
be carried in a mining company’s
Types of cost estimates Life of asset cost estimate cash flow model for planning and
budgeting of capital and operational
Several types of cost estimates are The LoA cost estimate responds to
expenditures and ideally is fully
used to characterise the financial the internal planning needs of the
integrated and presented in the mine
aspects of closure. It is important mining company. While there are
business plan.
for mining companies to make clear variations in how each company
distinctions between the different defines these estimates (and the
Other common characteristics of
types of cost estimates as they serve terminology used), the estimates
the LoA closure cost estimate are as
different purposes. The basic types of address the full expected closure-
follows:
closure cost estimates are outlined in related costs that the company will
Figure 9. incur for a site that operates through • Owner costs (rather than third-
its full life and executes its planned party costs) are normally used
While much of the underlying mining activities to exhaust the where it is reasonable to assume
source information for each of mineral resources. that the owner would use its staff
these estimates should be based and equipment for executing

Figure 9: Closure cost estimate types

Regulatory estimate
LoA Financial liability Sudden closure (financial assurance)

Costs that the operator Estimated liability Cost to close the Costs that form the
expects to incur in the based on applicable operation in its current basis of a guarantee
context of the current accounting state provided to a
mine plan at the end of requirements regulatory body
the mine life

Integrated mine closure: good practice guide 47


the tasks. If the mine owner • The cost estimate is based on the • Mine owner execution rates or
does not propose to execute the present value of future costs of third-party rates may be used/
closure works using its staff and the current disturbed footprint required as applicable for closure
equipment, third-party costs that will be incurred over time to activities.
should be used to estimate the retire the asset and meet legal, • Obligations that will be required
cost. regulatory and agreed third- after decommissioning should be
• Credit for completed progressive party (including stakeholders) included, including long-term water
closure can be incorporated commitments, considering the management, monitoring and
directly into the estimate. current disturbance. Constructive maintenance, etc.
obligations and exclusions may vary
• The costs are normally calculated • The cost estimates are typically
in jurisdictions, but typically the
in accordance with the operational generated in partnership with a
financial liability cost estimate does
cost model. creditable independent third party
not include:
• Salvage value may be considered that provides expertise in mine
– closure and rehabilitation costs of closure.
where appropriate and internal
future environmental disturbance
business standards and guidelines • The cost estimates must be
or facilities yet to be installed/
permit. As salvage values are acceptable to corporate financial
constructed and any personnel
subject to wide variations, auditors.
severance-related costs.
conservative valuations should be
used, and should be supported by – potential salvage value for The amount considered in the
third-party quotes and evaluation. equipment and infrastructure. financial reporting will need review
• The discount rate used for present at each reporting period to ensure
Financial liability cost estimate value calculations is a pre-tax that the value continues to reflect the
rate(s) that reflects current market mining company’s obligations. As an
The financial liability closure cost
assessments of the time value of element of financial reporting, this
estimate must be developed to
money and the risks specific to the cost estimate is typically prepared
comply with accounting obligations
liability (except for risks reflected in under the direction of the company’s
and reporting principles, usually
the future cash flow estimates). executive management team and is
the IFRS, or in the USA the GAAP.
• The costs to be included in subject to third-party auditing.
The amount is also known as an
asset retirement obligation, closure the estimate are those where
environmental disturbance has Sudden closure cost estimate
provision or reclamation liability.
occurred, or facilities that have A sudden closure cost estimate is
The following are key characteristics been installed/constructed that typically developed and used for
of a financial liability cost estimate: require decommissioning and internal planning purposes to aid
rehabilitation. in options analysis and decision-
making. The estimated sudden
closure cost would reflect all costs
for immediately implementing
closure, with no exclusions.

Costs that would form a part of


the sudden closure cost estimate
include closure works, workforce
retrenchment costs, management,
studies, and care and maintenance
costs associated with deferring
closure works. The cost estimate
would also include post-closure
©Anglo American

costs such as those for maintenance


and monitoring. Not all companies
calculate this number and commonly
use the financial liability number.

Tumela mine, South Africa

48 Integrated mine closure: good practice guide


Regulatory cost estimate some set time limit or the • Similar to financial reporting
currently approved extent of final obligations, most jurisdictions with
In many, but not all, jurisdictions the
disturbance. financial assurance requirements
regulator may require some form of
• There is often a credit against do not allow for potential
financial assurance funds that will be
the financial assurance for salvage value for equipment and
available to complete closure works
satisfactorily completed infrastructure to be included.
in the event the mining company goes
bankrupt or otherwise abandons progressive closure works, to act • Internal mining company costs,
the site. This financial assurance is as an incentive for progressive such as employee severance costs,
sometimes known as a guarantee closure. Credit is typically not taxes and financing costs, are
or a closure bond. However, several granted for progressive closure not normally included in financial
other forms of acceptable financial until the relevant authorities have guarantees.
assurance exist. Laws requiring officially accepted the work as
financial assurance have arisen to complete and effective. There is considerable variation in
address a history of abandoned sites • Cost estimates usually must be the forms of financial assurance
in many jurisdictions. updated on a set schedule, or when accepted in different jurisdictions.
there are substantial changes to Each type has advantages and
There is considerable variation the mining operation. disadvantages, and the range of
among jurisdictions in how the feasible options should be considered
• There may be a requirement for
financial assurance amount is carefully in terms of their financial
third-party audits or certification
estimated and administered. Typical implications for the mining company.
of the cost estimates made to
characteristics include: Third-party guarantees, such as
establish the financial assurance.
irrevocable/unconditional bank
• The cost estimate is based on the • The cost estimate format may be guarantees and insurance bonds, are
closure activities presented in a specified by the regulator (ie there relatively common, as are renewable
closure plan that has received may be a standardised spreadsheet letters of credit. Cash deposits,
approval by the regulator. or other model used to present the trust funds, collateral and insurance
• Cost estimates consider third-party costs). policies are also used, as are a
costs, intended to be representative • The rules relating to present value variety of alternative options such as
of the cost the government would estimates vary greatly between parent company guarantees, balance
incur to implement the closure plan jurisdictions. If discounting of future sheet tests and financial strength
if the mine was abandoned. costs to present value is permitted, ratings.
• The cost estimate may be based the discount rates may be specified
on the current disturbance, by the regulator or subject to Calculating closure costs
the disturbance planned within negotiation.
The estimation of closure costs is
both challenging and of considerable
importance to mining companies.
Closure costs can have a material
impact on a mine’s book value and
therefore need to be adequately
accounted for at all phases of
planning and execution. Further, in
recent years, heightened attention
and scrutiny has been placed on
closure costs by company directors,
shareholders, regulators and the
general public, as these costs have
often been underestimated. This has
©Anglo American

in turn placed more emphasis on the


transparent communication of the
closure cost estimation process.

Community development project, South Africa

Integrated mine closure: good practice guide 49


• health and safety plans,
construction monitoring and QA/
QC.
• costs for management of closure
activities, including management
and supervision, power, water and
sewage services, fuel and supplies.
• closure planning activities.
• interim care and maintenance costs
(sometimes needed while closure
designs are being finalised).

©Goldcorp
• ongoing dam safety inspections
and reviews.
Porcupine Dome mine, Canada
The above lists are not exhaustive,
and not all the above activities will
This section provides an overview surface and groundwater
be applicable at all sites or are
of the elements needed to develop management.
necessarily included in all types of
closure cost estimates, including • treatment of water, including water estimates.
anticipated scope of the cost treatment plant construction and
estimate, the information needed for operation.
its development and selecting the
Information needs
• liner installation or removal.
appropriate accuracy (or estimate A closure cost estimate will only be
class) for the conditions and • construction of seals on as good as the information used in its
closeness to closure of the site. underground mine openings to development. The quality and detail of
surface. the information used can be expected
Scope • post-closure monitoring and to increase as closure activities get
maintenance. closer to execution, either as part of
Cost estimates require a clearly
• access control and signage. ongoing investigations, research and
defined scope. While some aspects
• disposal cost. studies, progressive closure or final
of the scope will vary depending on
closure. Some of the information
what stage of the mine life the site • costs of funding the management
will be provided in the closure plan
is at and the final purpose of the of future or long-term activities
while other aspects will require the
cost estimate (as described in the related to residual risks.
input of the cost estimating team and
preceding section), the following are • closure planning and from the mining company’s closure
the kinds of direct costs typically decommissioning investigations management team.
included in closure cost estimates: and studies to inform and assist
• decommissioning and demolition in development of the closure The following types of information
of structures, and clean-up of designs. are needed to generate closure cost
contaminated sites. estimates:
Indirect costs and additional company
• earthworks, including re-sloping, • a closure plan with clear
costs that may not be addressed and
channel construction/expansion, descriptions of the type and scope
included in all types of closure cost
placement of erosion protection of physical closure activities to
estimates include:
material, relocating waste be implemented; where multiple
materials, cover construction and • mobilisation/demobilisation of options are under consideration,
borrow source development. contractors, consultants and other there should be a clear indication
• implementation of rehabilitation support services. of which option is to be taken as
measures, including seeding, • retrenchment of staff. the base case for use in the cost
planting, fertiliser placement, • socioeconomic programmes. estimate – assumptions around
maintenance and other related operating activities (such as
• engineering, procurement and
activities. progressive infill) should be clearly
construction management (EPCM)
• water management, including identified.
costs.

50 Integrated mine closure: good practice guide


• established basis of design and government guidance (or implementation plan. There may
engineering standards to be requirements) and contractor be site-specific drivers to spread
adopted. quotations. the closure activities of a site over
• clear descriptions of the scope and • financial planning variables a longer period.
duration of activities planned for such as exchange rates and the • During the post-closure period:
facilitating social transition and rate of inflation and the discount Monitoring and maintenance
workforce retrenchment. rates to be used for any present costs will occur over a duration
• a register of the facilities and value calculations – for financial that can vary from a few years to
infrastructure to be closed, assurance estimates, specific costs that will be ongoing for the
including (but not limited to) plants rates may be established by the foreseeable future. Regulators
and processing facilities, camps, regulatory authority. may set minimum monitoring and
power, water, waste management maintenance periods.
and temporary infrastructure As indicated above, the closure
equipment – early in the LoA, this schedule is an input to the cost Estimate accuracy
information may be indicative, estimate. Typically, closure costs
One of the most important
but in the years prior to closure need to be realistically distributed
differences between closure
detailed registers will be needed over the closure schedule for
cost estimates and other types of
with sufficient information on planning purposes and for present
cost estimates in typical mining
dimensions and types of material to value calculations. Closure costs
applications is that closure costs
support demolition estimates. will typically be incurred over the
frequently need to be estimated
following three periods:
• unit quantities, areas and volumes for the implementation of closure
of mining features and closure • During the LoM (progressive activities many years or even
domains such as open pits, waste closure): The duration of this decades in the future. In this context,
rock facilities, tailings storage period will depend on the LoM it is important to be realistic about
facilities, water containment and the nature of the mining the achievable accuracy of cost
facilities and heap leach piles, operation as some operations estimates.
including volumes of material that present more opportunities for
will need to be moved for activities progressive closure than others. The risk of underestimated closure
such as re-sloping and capping. • During the implementation of costs underlies any discussion of
• schedule of closure activities, closure activities: Typically, this estimate accuracy. More detailed
including durations of planned will be a few years, although this estimates are generally desired to
or required monitoring and can vary greatly not only with reduce this risk. Cost estimates
maintenance activities and the the size and complexity of the for capital investments typically
proposed closure execution site but also with the closure progress through different estimate
strategy (EPCM, engineering,
procurement and construction,
owner or third party, etc).
• register of formal commitments
with associated financial obligations
not captured in the above, such as
technical commitments made in
approvals documentation.
• the third-party equipment and
infrastructure required to support
closure activities, recognising that
some of this may not exist on-site at
the time of closure, or may need to
be replaced.
©Newmont

• unit rates for individual closure


activities or supplies required –
the unit rates used to be based
on on-site or industry experience, Yanacocha mine, Peru

Integrated mine closure: good practice guide 51


classes as designs progress detailed estimates (Class 4 or • the LoM – mine lives of five years
towards maturity and the level of similar) may be more appropriate to or less will immediately begin
detail in the estimate increases. screen alternative closure activities. with a more precise estimate than
While terminology and definitions With a greater level of detail in mines with greater mine lives.
of estimate classes vary among closure planning, especially for high- • the probability of significant
organisations, AACE International risk items such as water treatment, changes in the mine plan.
(Association for the Advancement of associated security, and general and
• the probability of major changes
Cost Engineering) defines five levels administrative expenses, the overall
in the preferred closure activities,
of cost estimate, from Class 5 to mine design can be influenced
particularly considering planned
Class 1, with the highest accuracy to a greater degree and focus on
research, studies or design work.
expected for a Class 1 estimate. reducing this type of long-term
liability. Once disturbance occurs, • the probability of changes in the
The question often arises in closure financial reporting needs typically mine schedule.
cost estimating, what class of cost trigger a requirement for a greater • the cost of rework – more detailed
estimate is needed? When closure level of accuracy, at least for the cost estimates will be costlier to
works are imminent, the answer is base case option. The closure plan update or redo than less detailed
usually clear. Most mining companies revisions through the mining life ones.
have well-defined processes for cycle should incorporate the most • the availability of information to
evaluating and approving capital recent alternative screening and cost inform the cost estimate.
investments, with stage gates estimate.
• the risk of a false sense of
or similar decision points, and
accuracy – when mine closure is
clarity on the timelines needed for The progression over the LoA from
distant, a very detailed estimate
approval. These procedures are Class 4 estimates to more precise
may convey an unrealistic sense
generally applicable to imminent costing is normally a decision for
of accuracy, given the changes in
closure works. There is, however, the closure management team and/
mine plan that can reasonably be
one important difference between or company policies and procedures
expected.
closure and other types of capital that will require the weighing
investments: with closure, ‘do of various factors. Some of the • the risk of poorly informed
nothing’ will not be an option for factors that should be taken into decisions where insufficient data
consideration. consideration when evaluating the is available.
appropriate level of cost estimate
At the very earliest stages of are: It is expected that closure costs will
planning, prior to disturbance (and become more certain over the LoM
• regulatory requirements or as the project operations develop,
the associated financial reporting
expectations – regulators may knowledge is gained, designs and
requirements) very high-level (often
request a higher level of estimate studies are advanced and site-
referred to as Order of Magnitude)
than might be chosen for mine specific experience with cost is
cost estimates (Class 5 or similar)
planning needs. developed. This experience would
are generated. However, more
include experience gained through
field trials and progressive closure.

For deterministic cost estimates, the


value is expressed as a single point
estimate. A contingency amount
may be added to partially address
the risk that costs are greater than
the estimated value. Contingencies
are usually calculated as a fixed
percentage of the total direct and
indirect costs, with the amount of
©Goldcorp

the percentage reduced as the class


of the cost estimate is increased.
Contingencies are used to address
Eleonore mine, Canada

52 Integrated mine closure: good practice guide


additional costs that are not known Key questions to ask about closure cost estimates
at the time of making the estimate
but that can be reasonably expected Are cost estimates built to a level of detail that is appropriate for
to occur based on experience. They the anticipated mine life remaining until closure and for regulatory
do not address all risks, and in requirements in the jurisdiction?
particular do not cover costs that
could be incurred due to significant Is the closure cost estimate documented fully in a way that can
changes in scope or extraordinary be audited by a third party? Are changes auditable? Is the costing
events such as natural disasters. spreadsheet/database easily navigated? Can the integrity of the model be
Regulatory authorities may require demonstrated?
a contingency to be added to the
amounts estimated for financial Are assumptions realistic and defensible? Are there major data gaps
assurance. Contingencies are not preventing good assumptions?
required to be included on closure
liabilities on the balance sheet. Are all major assumptions fully documented? Do they require agreement
from internal stakeholders? Have the assumptions been sourced from the
As indicated in the previous section, right people?
the quality of a closure cost estimate
(accuracy and completeness) is Are cost estimates built from an up-to-date LoM plan and closure plan?
strongly influenced by the quality of
the information used in developing Have all potential costs required to close a mine been captured, including
the estimate. A probabilistic physical costs of implementing closure works, decommissioning, post-
approach to cost estimating can be closure monitoring and maintenance, and site management/support
used to present transparently the through closure implementation and post-closure?
confidence in each input to the cost
estimate, and the impact of that
Have costs for implementing the planned social transition been included?
confidence on the final estimated
amount.
Is a uniform approach to closure cost estimation applied across the
business, including a process for internal and external audits?
In the probabilistic method, a
possible range and likelihood of
Are there up-to-date unit rates that are appropriate to the class of
costs for each activity is assigned
estimate, and the site/location?
and a statistical model is used to
express the estimate as distribution
Are discount rates and inflation rates used properly and validated
of probable costs. The result of
internally, or (in the case of financial assurance) calculated in a way that is
a probabilistic cost estimate is
acceptable to the regulator?
expressed as a combination of costs
and probabilities, such as ‘There is a
Are contingency amounts appropriate for the estimate class or other
50% likelihood (P50) the closure cost
requirements?
estimate will be up to or less than
USD 85,000,000 (and 50% chance
Do estimates account for risks, uncertainties and opportunities in
costs will exceed the estimate) and
successfully executing the planned work and achieving the desired
an 85% likelihood (P85) the closure
outcomes?
cost estimate will be up to or less
than (and a 15% chance of exceeding)
Have the appropriate skills and expertise been involved in the
USD 117,000,000.’ While this method
development of the cost estimates?
provides considerable transparency,
it can result in some difficulty in
terms of identifying what is the Are adequate funding mechanisms being made available to meet closure
correct value to use in reporting. The obligations?
method is also more labour intensive
to apply. Is there a system in place to track actual versus projected costs, and
incorporate learnings?

Integrated mine closure: good practice guide 53


©Rio Tinto

54 Integrated mine closure: good practice guide


13.CLOSURE Tool 1 The domain model

EXECUTION PLAN
Tool 12 Closure plan
documentation

While the closure plan describes the actions that will be carried out as part of
implementing site closure (see Tool 12: Closure plan documentation), a CEP
identifies specific actions to be carried out during the LoA in support of closure
planning and implementation of closure activities.
During the earlier stages of the • the required engineering, Having a formal execution plan with
LoA, it may be targeted towards environmental or socioeconomic clear responsibilities makes it far
closing gaps in the knowledge base, studies, trials, assessments and more likely that the above actions
executing studies/research, refining monitoring to fill key gaps in the will be embedded in ongoing mine
closure objectives and criteria, knowledge base and ascertain planning, with costs allocated and
integrating agreed aspects of the closure risks and mitigation achievable scopes and timelines
closure plan into the mine plan, measures. defined and regularly updated based
carrying out progressive closure, • the communication of the closure on the outcomes of previous actions.
conducting monitoring/inspections strategies/objectives so that key Closure becomes part of what the
and reviewing the data collected. stakeholders are kept informed mining operation does, embedded in
As the mine nears closure or as and engaged in the process. the mine planning function.
major progressive closure works
• progressive closure opportunities/
are undertaken, the execution plan Execution plans can be developed to
activities.
will evolve into a full implementation address specific domains described
plan, with a detailed execution • review of monitoring and inspection in Tool 1: The domain model,
schedule. data, with incorporation in the such as applicable legislation, risk
knowledge base of relevant assessments, mitigation and post-
During the mining life cycle, the CEP learnings that will inform future closure land use for each domain.
will have various elements, covering closure planning.
both the short term (the coming year • determining the point in time at
or similar) and longer-range planning which having a final executable
(up to the entire LoA). The plan may closure plan is necessary.
be addressed through one or more
documents. CEPs will be dynamic
internal planning documents, Key questions to ask when developing the CEP
regularly updated or redeveloped
over the mine life to reflect changing What is to be done to support closure planning in the short and long term?
needs, changing conditions and new
information. For the tasks to be completed, when should they be started and finished?

The CEP should establish clear What is the estimated cost to complete each action?
lines of authority and responsibility
for implementing actions. The What other resources are required to complete the action?
most detailed portion of the plan
will address actions for the near
Have risks been assessed based on current controls or future
term, with budget and staffing
controls? In the risk assessment, has the maximum foreseeable
requirements identified. Actions
loss been assessed?
might include:
Has a process for change management been identified?

Integrated mine closure: good practice guide 55


56 Integrated mine closure: good practice guide
©Teck
14.MONITORING, Tool 2 Monitoring,
measurement and

MAINTENANCE AND inspections

MANAGEMENT

Following the completion of closure activities, monitoring (including


measurement and inspections) is undertaken to document and evaluate the
effectiveness of the closure activities at meeting agreed closure objectives and
the success criteria. Monitoring is carried out with a focus on structures and
facilities that remain post-closure, and on areas where there is an expectation
or risk of impacts.
Where there is a pathway to inspections, to be considered when or frequency of monitoring events
relinquishment of the site, post- developing programmes for closure reduced as data is collected and
closure monitoring provides the and post-closure monitoring. trends documented. Some types of
information needed to demonstrate monitoring will be a one-time post-
that success criteria are being met, At most sites, monitoring that closure event, such as inspections
or on a pathway to be met. See is conducted before and during to confirm that specific works have
case study example on Glencore’s operations (including areas of been carried out. In some cases, the
Westside mine monitoring progressive closure) will provide post-closure characteristics of the
programme in confirmining that the experience and data needed to site may require permanent or very
success criteria have been met. develop an appropriate and effective long periods of ongoing monitoring.
post-closure monitoring programme. This is often the case for closure
Monitoring could be conducted for Typically, the post-closure monitoring configurations that include large
various reasons to achieve different programme will be a version of the water-retaining dams, or active
outcomes. Some of the most operational monitoring programmes, treatment of ARD/ML.
common needs include: refined and optimised for post-
closure. As such, it will integrate with The development of post-closure
• Performance/success monitoring:
existing baseline and operational monitoring programmes will involve
to determine whether specific pre-
monitoring data as well as traditional input from regulators and other
set targets/criteria are being met/
knowledge, where available, to place stakeholders, both on what is to
attained, typically the success with
the post-closure data within a longer- be monitored and for how long. In
site success criteria.
term context. The refinement of jurisdictions with developed closure
• Information gathering operational monitoring programmes policies, post-closure monitoring
monitoring: to obtain baseline for post-closure may include the plans will need to be approved by
information to populate/augment addition or removal of monitoring the corresponding authority, and
the closure knowledge base, locations, changes in the frequency results from the monitoring reported
typically to obtain data to a greater of measurement and reporting, and regularly.
resolution to calibrate numerical potentially adding or removing types
groundwater model. of monitoring. Monitoring of sites against success
criteria may lead to the identification
The focus of post-closure monitoring The required duration of post- of maintenance needs where
is primarily on performance/ closure monitoring is dependent on success criteria are not met.
success monitoring and compliance site-specific conditions (including Common maintenance activities
monitoring. Refer to Tool 2: regulatory requirements) and include repairing or armouring
Monitoring, measurement and cannot be generalised. Post-closure areas of erosion, addressing areas
inspections, which provides an monitoring programmes are often where vegetation efforts have not
overview of typical needs for phased out over time, with the been successful, and repairs or
monitoring, measurement and number of monitoring locations replacement of signage or access

Integrated mine closure: good practice guide 57


controls. Rehabilitated areas may
also need to be managed as part of
the broader ecosystem. This might
CASE STUDY
include fire management through
controlled burns, removal and WESTSIDE DEMONSTRATES A WELL-PLANNED AND
control of weeds and control of illegal EXECUTED MINE CLOSURE STRATEGY (GLENCORE)
access onto the site.
Rehabilitation of the Westside open cut coal mine near Lake Macquarie
Maintenance and management in New South Wales was completed in April 2012, just two months after
activities should be documented mining operations ceased. It is managed by Oceanic Coal Australia
describing any ongoing activities, Limited and is owned by Glencore.
as well as providing any historical
The closure plan for the mine once sustainable vegetation has
site information for the responsible
divided the site into a number of been established and agreed
party to which the closed site
different rehabilitation domains closure criteria have been met.
may be transferred as part of the
with different completion criteria Oceanic Coal Australia Limited has
relinquishment process.
developed for each area and used sophisticated and innovative
included a void that has been monitoring methods to ensure
retained as a permanent lake. objectives are being met and have
employed a proactive management
Extensive surface preparation approach to optimise ecological
activities for rehabilitated areas outcomes for the site.
commenced as soon as possible
following the completion of The land has been successfully
mining activities. This followed returned to high-quality native
a programme of progressive vegetation and is home to a diverse
rehabilitation across the life of the range of flora and fauna.
mine.
Recent monitoring found nine
Rigorous rehabilitation monitoring threatened species on the
programmes have been in place at rehabilitated site, including grey-
the Westside mine for many years. headed flying fox, masked owl,
The Westside mine closure plan greater broad-nosed bat, little
has been carefully implemented bent-wing bat, powerful owl, large-
with a clear goal of achieving eared pied bat and squirrel glider.
relinquishment in a staged manner,
©Glencore

Rehabilitated Westside open cut coal mine, Australia

58 Integrated mine closure: good practice guide


15.RELINQUISHMENT

Relinquishment occurs when ownership, residual liabilities and responsibility


for a former mine site can be returned to the corresponding jurisdiction or
original owner, or transferred to a third party, following completion of closure
activities and satisfying the agreed success criteria. If ongoing maintenance
and management is required, the responsibility for this under relinquishment
would also transition to the new responsible party.
Relinquishment may be either total, a closure plan that will set the site relinquishment and possible
where the entire property is turned on a pathway to relinquishment. The impediments (ie laws that will
over to a third party, or partial, where business case for relinquishment prevent relinquishment).
parts of the property are turned must be balanced rationally, with • Involve regulators in discussions
over following completion of closure the ongoing costs and liabilities about relinquishment and
activities. Partial relinquishment of maintaining ownership of a understand their concerns.
may also be part of a progressive site weighed against the cost and
• Monitor the state of practice
relinquishment plan, where the difficulty of securing relinquishment. and learnings from successful
expectation is to achieve total Relinquishment may not always be relinquishment, especially in the
relinquishment in a stepwise process. the preferred outcome. jurisdiction under consideration.
• Engage with communities and
Responsibly executed, Pathway to relinquishment
relinquishment can be the final stakeholders early on the topic of
The probability of achieving a relinquishment and see if a pathway
step in a successful mining life
successful relinquishment can be can be developed that is compatible
cycle. It marks the final transition
enhanced by adopting a pathway with their needs and desires. If the
of the site to its post-closure use,
approach, with management, end land use is desirable to them,
with the formal completion of a
planning and communication look for opportunities to ensure
mining company’s involvement.
throughout the mining life cycle that feedback reaches regulators.
Relinquishment is not necessary for
designed to achieve relinquishment • Look at the development of specific,
a successful mining life cycle, as in
or improve the possibility of achieving measurable success criteria that
some instances the desired post-
it. Relinquishment plans and criteria are clear, with input and agreement
mining land use may be achieved
may be developed over a long period from regulators and stakeholders.
without relinquishment.
of time. During this time, changes in • Look at partial or progressive
The concept and practice of government, changes in policies and relinquishment to demonstrate the
relinquishing a company’s obligations shifting stakeholder opinions may all concept and help regulators and
on a closed mine is influenced by make relinquishment more (or less) stakeholders gain confidence.
local laws as well as global and local difficult.
• Identify and communicate residual
community expectations. The clarity risks clearly and openly. Discuss
Good closure planning practice
of a pathway to relinquishment varies acceptable risk thresholds.
can help with setting a site on
widely between jurisdictions and may Investigate a residual risk fund or
the pathway to relinquishment.
even vary between mines in a single similar mechanism to facilitate the
Specific actions that will improve the
jurisdiction. acceptance and transfer of residual
possibility of relinquishment are as
risk.
While responsible relinquishment is follows:
• Periodically re-evaluate and
in the interest of mining companies, • Evaluate relinquishment options refine relinquishment options and
and is widely desired, there are from the earliest stages of closure the pathway to relinquishment,
several impediments that should be planning. incorporating the knowledge
understood if a realistic, effective • In evaluating post-closure land use, gained throughout the mining life
pathway to relinquishment is to consider the compatibility of land cycle.
be developed. For the evaluation use options with relinquishment. • Track the business case for
of relinquishment options, these
• Evaluate the legal structure in the relinquishment and be prepared to
challenges must be considered fully
jurisdiction and understand both abandon the concept if it does not
to maximise the chance of developing make economic sense.
the elements that could support

Integrated mine closure: good practice guide 59


CASE STUDIES
While there are challenges to achieving relinquishment, it has been attained AUSTRALIA
in a number of jurisdictions. The following examples illustrate cases and (RELINQUISHMENT
locations where relinquishment has been attained. For the examples in the PROCESSES)
USA and Canada, it should be noted that even after relinquishment, the legal
structure does not permit full relinquishment. If environmental impacts Similar to Canada, the Australian
attributable to mining activities should be discovered after completion of the mining industry is governed at a
relinquishment, the mining company would remain liable. state or territory level with each
jurisdiction having its own closure-
USA (COAL INDUSTRY) with the liability for the treatment specific obligations as part of the
transferred to the third party. mine approvals process, which fall
For coal mining in the USA, the
under overarching Commonwealth
path to relinquishment is clear,
CANADA (SASKATCHEWAN) law principles. Most mining approvals
specific and highly regulated. Coal
and tenement conditions are framed
mining in the USA is governed In Canada, mining is largely governed
in such a way that in theory, control
under the federal Surface Mining at a provincial or territorial level,
of the mine site is returned to the
Control and Reclamation Act of although there are applicable federal state or territory, discharging the
1977, which lays out the pathway regulations. Relinquishment has company from all future maintenance
to relinquishment. While there been undertaken in the province and monitoring obligations. General
is variation in the specifics of the of Saskatchewan. The province guidance on the mine closure
application in different states, in developed the Institutional Control process, including relinquishment,
general terms there is a financial Program. Through this programme, is described in the Leading Practice
assurance requirement. The mining companies can relinquish a Sustainable Development Program
financial assurance is released as site through a process that involves for the Mining Industry,2 which aims to
rehabilitation is completed. After making deposits into separate funds identify issues and potential solutions
completion of rehabilitation activities that account for both the NPV of the for sustainable development of the
and a set monitoring period (typically ongoing monitoring and maintenance Australian mining industry.
5–10 years), a Phase 3 bond release needs for the site, and a fund to
is granted, and the mining company address unexpected costs (residual Over the past 25 years, however, 70
may sell the land, release it back risks). These funds are managed per cent of mines in Australia have
to the original owner or otherwise separately from the province’s undergone unplanned closures for
release ownership, effectively general revenues. various reasons, including economic,
relinquishing the land. If there is a technical, regulatory, social and
need for ongoing activities, such as As of March 2017, six sites were other unforeseen circumstances,
a water treatment plant, this can under the management of the leaving few examples of successful
be addressed as a funded liability, Institutional Control Program. relinquishment.

Key questions to ask about relinquishment

Is relinquishment a realistic endpoint for the mine site?

Is relinquishment an objective of the mine closure plan?

Are there SMART success criteria agreed with regulators and stakeholders?

Is there a community engagement strategy that addresses relinquishment?

Are the long-term monitoring requirements and the implications of those requirements understood?

2. Source: https://archive.industry.gov.au/resource/Programs/LPSD/Pages/LPSDhandbooks.aspx

60 Integrated mine closure: good practice guide


16.TEMPORARY OR
SUDDEN CLOSURE

While the expectation is that mines will continue uninterrupted operation from
start-up to the completion of the economic extraction of the ore, temporary or
sudden closure of mines can occur. Both have implications for closure planning.
Temporary closure is a suspension
of mining activities for a limited
period. During temporary closure,
the site is maintained. This is also
called a ‘care and maintenance
phase’. In sudden closure, a mine
goes into final closure ahead of the
previously planned timeline.

Operations may go into temporary


closure or sudden closure for a
variety of reasons. Typical reasons

©Newmont
include:
• financial pressures (market
conditions).
• environmental incidents (floods,
earthquakes, force majeure).
A temporary closure may last for Sudden closure typically
• social incidents (major health months or even years until the site presents several challenges for
epidemics or civil action). returns to active production. On the implementation of the closure plan.
• regulatory authority actions or other hand, temporary closure may These include:
changes. be a precursor to final closure of the
• Closure designs may be at the
• structural failures (tailings facility site (due to financial or regulatory
conceptual or pre-feasibility stage
failures, open pit slope failures). considerations). For this reason,
and may need to be advanced on an
temporary closure often triggers
accelerated schedule.
During temporary closure, regulatory scrutiny to confirm that
financial assurances are adequate • The configurations of mine facilities
maintenance works are carried out
and that the mining company has may be different from the final
in anticipation of the site returning
appropriate plans and resources in configuration considered as a
to active production. Equipment
place to implement final closure if basis for closure designs. This may
and staff will remain on-site, with
needed. Depending on the require rework, or major revisions
appropriate care taken of all site
jurisdiction and the cause of the to design concepts.
infrastructure, including ongoing
monitoring of mine waste facilities temporary closure, updates to • Studies that were in progress
and the environment. From a the closure plan and the financial to support closure may not be
regulatory and closure planning assurance amount may be complete. The impact on closure
point of view, many aspects of requested. The mining company designs of completing or not
temporary closure should be may need to develop a detailed care completing the designs will need to
indistinguishable from regular and maintenance plan, documenting be considered.
operations. All environmental the work that will be done to • Schedules for the implementation
controls will remain active, keep the site in compliance with of the closure plan will likely need
discharge limits will be unchanged applicable regulations. The care to be re-evaluated and adjusted.
and financial assurances will be and maintenance plan is outside
• Alternative contracting approaches,
maintained in place (or possibly even of the scope of the closure plan,
such as design-build, may need to
reduced if progressive closure works although some jurisdictions require a
be considered for some closure
continue to be carried out during the simplified care and maintenance plan
works.
care and maintenance phase). to be included in the closure plan.

Integrated mine closure: good practice guide 61


• Engaging with the regulator will By the nature of these closure Key questions to ask about
likely be necessary to ensure that events, there may be very little temporary or sudden closure
necessary permissions are in place time to communicate with external
for the implementation of closure stakeholders in advance. Either event Has a risk assessment been
works. For works that respond to is stressful for mine employees, conducted to determine which
critical safety or environmental contractors and suppliers. assets in the mining company’s
concerns, accelerated permissions portfolio (as appropriate) are
are usually possible. The strategy for mitigating the
most at risk of sudden closure?
• Factors that led to the sudden socioeconomic impacts will
closure may also affect the vary greatly depending on the
Is there a plan for sudden
financial resources available for cause of the closure and on the
closure, appropriate to the
implementation of the closure socioeconomic setting. In all cases,
current state of the mine
works. clear communication is beneficial,
development?
and a communication strategy
• Availability of third-party
and engagement plan to keep
contractors to execute the Is there a plan addressing care
stakeholders informed is important.
proposed work may need to be and maintenance needs for the
It is good practice to have a high-level
considered. site in the case of temporary
contingency plan in place to guide
closure, or high-level guidance
actions, and to keep the plan updated
At each stage of the mine life, it is for developing one?
as the relation between the mine and
good practice to have a contingency
the stakeholders evolves.
closure plan in place for sudden Are there contingency plans in
closure that identifies the key areas place for communications and
The social transition plan in the
of the site closure plan that will engagement with stakeholders
event of a sudden closure may be a
require modification in the event of a (including workers) in the case
modified version of the plan that was
sudden closure. of either a temporary or sudden
developed in the principal closure
closure?
plan. Managing social transition
The socioeconomic impacts of both
in the case of a temporary closure
temporary and sudden closure Is there a clear line of
will likely require a case-specific
are difficult to manage. Either can communication to ensure that
approach as one of the most
occur at a time when plans for the teams involved in closure
important variables (the duration of
facilitating social transition are not planning are informed with the
the temporary closure) is unknown.
fully developed or implemented. maximum possible anticipation
of a temporary or sudden
closure?

Is there appropriate security


at the site to manage risks
associated with theft, vandalism
or unauthorised access?

How will regulatory expectations


be managed and by whom?
©Anglo American

62 Integrated mine closure: good practice guide


17.CLOSURE GOVERNANCE

Effective planning and implementation of mine closure will involve resources


from many disciplines across a mining company and directly affect its financial
performance. As such, closure governance involves reconciling the roles and
relationships of numerous stakeholders within the mining company (and joint
venture partners and/or parent corporation, where applicable), as well as the
goals of closure with the overall goals of the organisation. Corporate and
closure governance will relate directly to the process of decision-making and
the interactions between the stakeholders involved in solving the collective
closure challenges.
All publicly listed mining companies will maximise value through addressed by generating an
are required to have clearly defined managing risks and opportunities. ‘internal’ plan, or a version of
governance structures, with a board the external plan that contains
of directors that is responsible for Some of the topics that may be additional chapters to address
corporate governance. The decision- addressed in the standards include: corporate requirements.
making required in planning and • providing guidelines so that
• documenting the approach to
implementing closure will take place closure planning advances in a
closure governance.
at different levels throughout the timely manner to the level of detail
corporate governance structure. • defining site-specific closure
required – this is particularly
Ideally, decisions will take place at obligations.
important to avoid costly periods of
levels that are commensurate with • specifying the approach to care and maintenance after the end
their impact and importance. identifying, managing, reviewing of operations while closure designs
and documenting closure-related are being completed or approved.
To ensure an adequate level risks and opportunities.
• providing guidance on:
of closure governance, it is • identifying controls and standards
recommended to establish the – the integration of progressive
for incorporating mine closure
following: closure during operations.
planning into the initial mine
assessment process. – estimating closure costs for
• company policies or standards for
different final uses, including the
closure to establish expectations, • defining expectations for
differences in cost assumptions
roles and responsibilities in a form incorporating closure requirements
for financial reporting obligations
that is compatible with corporate in business plans.
(governed by applicable
structure. • defining the level of detail/accuracy accounting practices), financial
• a closure committee to coordinate required for closure plans and assurance (governed by
the closure planning process and costs at each stage in the mine life. jurisdictional regulations) and
its integration into operational • defining requirements for LoM planning (governed by
planning. regular updates to closure plans internal corporate practices).
throughout operations so that the – requirements for the frequency of
These are described in more detail in plans reflect the current mine updates to closure cost estimates.
the following subsections. plan and the level of information
– these may need to be updated
available.
Company closure standards more often than the full closure
• outlining specifications on the plan due to needs for internal/
The establishment and contents of the closure plan: external financial reporting or
implementation of company policies – these may differ from closure regulatory obligations.
and/or standards that include closure plan requirements as specified by – requirements for stakeholder
is imperative for mining companies. the regulator. engagement as an integral part of
Such standards provide a consistent
– where there are differences, closure planning.
approach to closure across
these differences may be
operations, and fully implemented

Integrated mine closure: good practice guide 63


• providing guidance on site function, with support from will include succession planning
environmental, social and safety a corporate level. The committee so that for each role there are one
expectations. will typically be a site function, with or more defined successors in the
• providing guidance for managing support from a corporate level. Table organisation. Other steps that can
sudden or temporary closure. 1 provides examples of key roles help with change management are:
and responsibilities that may be
• providing guidance on the pathway • providing documentation of trade-
identified for a closure committee.
to relinquishment, including off studies and risk assessments
The role of the closure champion
approaches to engagement conducted during the mine life.
in this committee is critical, as the
with regulatory entities and • making sure that documentation
champion will be responsible for
stakeholders. identifies not only the reasons for
liaising with other key leaders within
the organisation. The role should be the selection of chosen closure
The company guidance may exist as activities but also the reasons that
implemented from the early stages of
a single document or across several other measures were not carried
the mine life.
related documents. forward.
A RACI (responsible, accountable, • monitoring data from operations
The company guidance may exist
consulted, informed) matrix and closure that should be
as a single document or across
should be developed by or with managed in searchable data bases
several related documents. Where
the closure committee to identify with various site staff familiar with
a single comprehensive document
the key roles, including both their operation.
is prepared to address closure, it
the committee members and • keeping detailed records of all
is likely to have linkages to other
relevant stakeholders outside progressive closure, including
corporate policies (such as those for
of the committee. In developing areas closed, methodologies
project definition, sustainability and
the RACI matrix, consideration used and monitoring data; the
community relations). Those linkages
should be given to stakeholders in records should include tracking of
should be explicitly identified in the
corporate governance structures, reclaimed areas in a geographic
closure guidance.
including the board of directors, information system (GIS).
company management, executives,
Good practice: Have a • preparing as-built drawings of all
shareholders and employees.
comprehensive mine closure mine facilities and closure works.
External stakeholders may also be
standard that addresses the full included in the matrix. Establishing a
range of corporate policies related to
In addition to the committee roles
RACI chart for external stakeholders
closure. This document will link with
identified in Table 1, it may be useful
is also helpful as it can assist to
other corporate policy documents.
to establish a stakeholder forum.
clarify accountabilities and is a useful
This forum provides means for the
insight into stakeholder perspective
operations to effectively consult with
Closure committee of their role in the closure activities.
key stakeholders throughout the
Establishing a closure committee mining life cycle and develop joint
While closure has historically
for implementation at the asset level strategies and plans for addressing
been an environment function at
has emerged as best practice to closure-related issues. This forum
many mine sites, making closure a
confirm that the closure planning would typically be championed by
planning function can help ensure
process is carried out in accordance the committee lead for community
that closure planning is appropriately
with company standards and legal liaison and development, with
incorporated into overall mine
requirements, and that it is fully support from other committee
planning.
incorporated into operational members.
planning.
Change management
The make-up and organisation of the Management accountable for mine
closure committee will vary between operations will change during the life
companies and will be closely related of an operation. While there will be
to each company’s overall approach some unavoidable loss of knowledge
to corporate governance, as well as and continuity with these changes,
the size and number of operations. steps can be taken to minimise
The committee will typically be a the loss of knowledge. Part of this

64 Integrated mine closure: good practice guide


Table 1: Centralised closure committee roles and responsibilities

Role Responsibilities

Closure champion • leads the development of the closure • ensures the CEP is implemented as per
process the specified timelines
• engages leadership throughout the • facilitates a multidisciplinary
organisation on closure planning, collaboration of key mine personnel
including corporate, management and (such as mine planners, engineers,
operational leads finance, corporate, and social and
• implements rigorous planning and environmental teams) for the closure
project management processes so that plan implementation
the closure plan is incorporated into the • leads the implementation of the closure
LoM plan plan
• ensures that closure plans are updated • leads regulatory engagement on the
as circumstances change or as closure plan
knowledge improves • monitors performance against agreed
• makes sure that the closure cost criteria
estimate is updated and communicated • facilitates financial liability reporting

Community liaison • facilitates and manages stakeholder • develops strategies and plans to
and development input into the development of the minimise job losses and mitigate
closure plan adverse effects on communities and the
• maintains consultation and local economy
communication with government, • implements training programmes and
community, employees and other social legacy projects
interested parties • assesses and reports on the
• leads local community engagements success and progress of all job loss
• leads or provides input to social and retrenchment management
investment programmes programmes planned and implemented
• evaluates mechanisms for transfer of
infrastructure to community

Human resources • owns the workforce transition strategy • develops strategies and plans to
minimise job losses and mitigate
adverse effects on workforce

Technical specialists • coordinates design and research studies • leads progressive closure
– mine engineering, where needed to address data gaps or • provides or coordinates adequate
rehabilitation manager, key uncertainties training for community takeover of
geotechnical, water, • guides the implementation of existing infrastructure (eg operation of
etc (in-house or appropriate closure activities boreholes/wellfields)
contractor/consultant)

Finance/accounting • ensures provision of funds for • reports liabilities in accordance with


progressive and final closure execution financial reporting standards

Operational leadership • facilitates formation of committee • approves/allocates resources

Integrated mine closure: good practice guide 65


©Gold Fields

66 Integrated mine closure: good practice guide


18.DEFINITIONS

The following terms are defined for purposes of this document:


Acid rock drainage/metal leaching Closure risk assessment: Financial assurance: Funds that
(ARD/ML): Acidic drainage from mine The closure risk assessment will be available to complete closure
wastes resulting from the oxidation assesses the risks and opportunities works, even if the mining company
of sulphides such as pyrite and from associated specifically with closure goes bankrupt or otherwise abandons
contact with water. Often associated and post-closure. the site. This financial assurance is
with metal leaching generating sometimes known as a guarantee
elevated concentrations of metals in Closure vision: High-level description or a closure bond. Required by
the drainage. Metal leaching may also of what a company wants to achieve government authorities in many
occur without acid conditions. Also through implementation of the closure jurisdictions.
known as acid mine drainage. plan, which guides the overall closure
strategy and selection of closure Heap leach: Using chemicals to
Closed mine: Mine at which all mining objectives. dissolve minerals or metals out of an
activities have ceased but in respect ore spread out as a lined/impervious
of which the owner, agent, manager Decommissioning: This is the process pad. The solution percolates through
or permittee remains responsible for of taking infrastructure out of active the crushed ore, leaching out the ore.
compliance with regulations and the service, which begins at the end of
mine owner’s obligations under the its utility for site activities and ends Knowledge base: The collection of
permit for the mine. with the removal of all unwanted site-specific information that will
infrastructure and services. inform the closure plan, including
Closure activities: Definitive actions physical, environmental, social and
that will be carried out during Decontamination: Removal of regulatory information. Initiated
implementation of the closure plan. contaminants from buildings or other with baseline data and updated
infrastructure. May involve activities with additional information as it is
Closure domains: Domains such as asbestos abatement, collected.
comprising site features that have pipeline cleaning and general
similar closure requirements. An cleaning/washing. Often required as Life of asset (LoA): The length of time
asset can be divided into a number of preparation for recycling or reuse of an asset (including but not limited to
physically or socially distinct domains. assets. mine, processing facilities, refineries,
smelters, rail, port, utilities, towns
Closure execution plan (CEP): Demolition/deconstruction: and associated infrastructure) is
The plan that identifies specific This is the process of physically owned, operated and closed by the
actions to be carried out during taking apart infrastructure and may mining company up until divestment
the mine life in support of closure involve disassembly of some or all or relinquishment. This LoA period
planning and implementation of of the structures, or destruction of includes exploration, development,
closure activities. infrastructure with heavy equipment operations, closure and post-closure.
or explosives.
Closure objectives: A qualitative Life of mine (LoM): The length of
description of what is to be achieved Divestment: Process by which time a mine is, or is planned to be,
through the implementation of the the company sells part or all of its in production. Based on a mine plan
closure activities. The objectives are assets. This can occur during any developed in consideration of the
site specific and may be specific to stage of a mining project, and entails available capital and the ore reserves
individual mine domains, or aspects of a process of transfer of ownership, or a reasonable and justifiable
closure. Closure objectives are derived infrastructure, liabilities and closure extension of the reserve estimate.
from the overall closure vision and responsibility.
closure principles. Local community: Refers to
Engagement: Interactions between communities that will be impacted
Closure principles: Common people, often a company and its directly and indirectly by the mine and
precepts that form the basis of and stakeholders. Can involve but will be most affected by closure.
guide selected closure activities, such not restricted to consultation,
as physical and chemical stability. communication, education and public
participation.

Integrated mine closure: good practice guide 67


Mine waste facilities: General Post-closure land use: Refers to Reactive materials: Term used to
term for installations designed and the use of mined lands after the refer to mine wastes that may change
constructed for the storage of wastes completion of extractive mining and characteristics when exposed to
generated by mining and processing closure activities. air and/or water. Typically used to
activities, including tailings facilities, refer to tailings or waste rock that
waste rock facilities, spent heap Post-closure maintenance and is susceptible to generating acid
leach piles, slag heaps and process management: Includes activities drainage when exposed to air and
residues. Does not include domestic required to maintain and manage water but may be used for other
landfills or non-mining hazardous infrastructure and rehabilitation until material types.
waste areas. relinquishment is possible, or on an
ongoing basis if not. Rehabilitation: The return of land
Mining life cycle: This is the full to a stable productive and self-
period of the mining process. Typically Post-closure monitoring: Includes sustaining condition, after taking into
includes exploration, development, monitoring after closure, including account beneficial uses of the site and
operations, closure and post-closure. socioeconomic, water quality, water surrounding land. Reinstatement of
Synonymous with the LoA. quantity, terrain, ecological and degrees of ecosystems and function
air quality monitoring. Results are where restoration is not the objective.
Multiple accounts analysis: A multiple compared to success criteria.
accounts analysis (also known as a Relinquishment: The end of site
multi-criteria analysis) establishes Post-mining land use: Refers to ownership by the mining company
two or more ‘accounts’ that are the use of mined lands once active and of their responsibility for the
weighted based on a qualitative and mining is complete. This may include site, with transition of ownership and
transparent assessment of their land use during the period when the residual liability to the jurisdictional
relative importance to the decision. site is undergoing closure activities, authority or a third party. Implies
Various options can then be rated on particularly when closure activities that the mining company has
a numerical scale in each account, stretch over many years or decades completed all obligations outlined in
and a weighted total calculated for the (such as during water treatment). the closure plan to the satisfaction
option. Differs from post-closure land use of the authorities (and possibly other
in that it includes land use that may stakeholders).
Net present value (NPV): The occur before the completion of closure
difference between the present value activities. Repurposing: Beneficial reuse of a
of cash inflows and the present value closed mining operation, whether
of cash outflows over a period, taking Progressive closure: A broad term through value-added reuse of the land
into account the time value of money, that encompasses ongoing efforts (eg energy generation or residential),
with future values discounted to the throughout the mine operations that reuse of infrastructure at another site
present day considering compound seek to advance closure activities or derivative business opportunities to
interest over the time period. during construction and operation. create positive economic activity.
Examples of progressive closure
Partial relinquishment: Where part activities include disturbed land Residual risk: The risk that a
of the site is transferred to a third rehabilitation and revegetation, rehabilitated area (or closed mine),
party, and the remaining area or areas decommissioning and demolition of in the foreseeable future, fails
remain the responsibility of the mining unused infrastructure. to perform as predicted and the
company. See also relinquishment. consequence of the failure will result
Progressive relinquishment: in the need for repair, replacement
Post-closure: General term referring Relinquishment of a site in a stepwise or maintenance works, and thus
to the period after the completion of fashion, typically over a number of associated costs.
all works needed to implement the years as discrete portions of the site
closure of the site. Sometimes used are closed and brought to a condition Restoration: Re-establishment of
to refer only to a period of monitoring suitable for relinquishment. See also ecosystem structure and function to
and maintenance leading up to relinquishment. an image of its prior near-natural
relinquishment but may include a state or replication of a desired
period in which ongoing activity (such reference ecosystem.
as the operation of a water treatment
plant) is needed.

68 Integrated mine closure: good practice guide


Revegetation: The introduction and Temporary mine closure: Mine
establishment of new vegetation closure where the site is secured and
following land disturbance by seeding, activities are carried out to reduce the
planting or natural colonisation. potential of environmental impacts
for the period of time before closure
Social investment: Defined as operations occur or mine reopens.
the provision and use of company
resources – in addition to those Waste characterisation: This is the
resources for core business activities process by which the composition of
and mitigation of negative impacts different waste streams is analysed.
– to generate or enhance positive
economic and social returns in local Waste rock facility: Mine waste
communities. or spoil materials disposal areas,
specific to mineral waste, not landfill
Social licence: The level of acceptance or ‘non-mineral’ waste. Also known
a population has for an operation, as waste dumps, waste piles, waste
company or industry. rock dumps, waste residue dumps.
Overburden piles are where low-grade
Social transition: The planning, stockpiles remain at closure – these
considerations and activities are often treated effectively as waste
undertaken throughout the LoA rock facilities.
to develop and implement the
transition of a community, including Zone of influence: Represents the
its workforce, towards closure of an geographic area within which firstly,
operation. direct socioeconomic impacts can be
attributable to a mining operation,
Stakeholder: A person or group that inclusive of its activities (and those
is influenced by, or can influence, an of its contractors), facilities, labour-
operation. sending areas and procurement of
goods and services; and secondly,
Success criteria: Specifications/ indirect impacts, including those
measurements/requirements that, on ecosystem services or where
if met, denote the success of the secondary or knock-on economic
closure activities in meeting closure impacts are experienced.
objectives. Success criteria may be
numerical or narrative. They may
have a time component and may also
be linked to specific management or
monitoring activities.

Sudden mine closure: Occurs when


unexpected changes in conditions
result in operations at the mine
ending ahead of the date in the
current mine plan.

Tailings storage facility: Area


where tailings are stored. Typically,
a permanent facility. Facilities may
©Anglo American

include dams or other structures to


retain tailings. Also called tailings
landforms, tailings impoundments,
tailings management facilities and
integrated tailings facilities.

Integrated mine closure: good practice guide 69


70 Integrated mine closure: good practice guide
TOOLS

Integrated mine closure: good practice guide 71


©Teck
TOOL 1: THE DOMAIN MODEL

This tool provides a set of templates to be used when developing


a plan for each of the domains.
A useful approach to dividing up • control of erosion – slag and process residue
the closure plan is to segregate the • a rehabilitation plan • infrastructure
mine into specific areas or domains. – buildings
• monitoring
Each domain is treated as a separate – roads
detailed entity within an overall plan • cost estimates
– pipelines, powerlines
that deals with common issues like • research. – fuel storage facilities
drainage and site monitoring. – water management infrastructure
Each domain should have its own plan (including process and raw water
The following factors should be (see template provided). Assumptions, facilities).
considered when developing a plan for inclusions and exclusions should
each domain: be documented throughout the While the domain approach will not be
operational life. optimal for all sites, it is often useful.
• the amount and area of disturbance In some cases, sub-areas within a
• applicable legislation Examples of domains at a mine are: given domain may require a different
• hazardous areas and risk treatment, depending on interactions
• mine voids with other domains.
assessments
– open pits
• a plan for deconstruction and – underground mines For accuracy, the operation should
decommissioning
• mine waste facilities use GIS digital terrain models and
• contamination and mitigation – tailings facilities aerial photos to illustrate the domain
• post-closure land use – waste rock facilities features and boundaries; 3-D models
• required earthworks and capping – spent heap leach piles of voids and mine waste facilities are
also useful.

©BHP

Escondida mine open pit, Chile

72 Integrated mine closure: good practice guide


XX AREA

Description

Area of disturbance Void xx hectares; waste rock facilities xx hectares

Status Active

Closure date xx void and waste rock facilities will be closed in 20xx

Infrastructure to be retained Final void

OBLIGATIONS RELATING TO CLOSURE

Subject Obligation Relationship to closure

Regulatory Progressive rehabilitation must commence when areas Incorporating details and
condition – become available within the operational land requirements for leaving voids safe
rehabilitation and stable after closure

xx xx xx

Final land use Void


objectives (a) Safe with minimal risk to the public, native fauna and livestock
(b) Conceptual land use options include water bodies or partially filled
water bodies. A decision will be based on the results of detailed geochemical and hydrological
studies

Examples Waste rock facility


(a) Provide an acceptable post-disturbance land use capability/suitability
(b) Provide acceptable, stable post-disturbance landforms
(c) Protect surface and groundwater quality on-site when leaving the mining lease
(d) Close using technically effective and cost-effective methods and proven engineering practices to
ensure that no long-term maintenance is required beyond the post-closure phase of five years
(e) Make the area safe with minimal risk to the public, native fauna and livestock

xx xx

CLOSURE COMPLETION CRITERIA

Description xx void Area (ha) xx Photo no Photo xx Timing 20xx–xx

Closure activities
(a) Excavate and haul waste rock material to construct perimeter bund walls
(b) Fencing of void perimeters
(c) Purchase and erect warning signs
(d) Final pit water balance and groundwater models
(e) Geotechnical stability assessment for long-term pit wall stability

Integrated mine closure: good practice guide 73


Statutory sign-off

No Yes Date Document reference no

√ xx xx

Description xx waste Area (ha) xx Photo no Photo xx Timing 20xx–xx


facilities

Closure activities
(a) Selective handling of acidic rock on outer waste rock facility face of xx facility – dispose of on top surface
(b) Re-profile xx stockpile to drain towards final void
(c) Re-profile central waste rock facility to drain towards final void
(d) xx stockpile – stable, minor leaching, no activities
(e) Excavate, load and haul inert oxide waste to the reshaped xx facilities
(f) Moderate earthworks to place store-and-release cover system (inert oxide rock) over potential acid-generating
rock, reshape facility surface and revegetate
(g) Re-profile and deep rip the balance of the waste rock facility surface
(h) Minor erosion control works and seeding on the balance of the waste rock facility surface
(i) Geotechnical assessment to demonstrate long-term stability of facility

Statutory sign-off

No Yes Date Document reference no

√ xx xx

Post-closure activities Void


(a) Continue surface and groundwater quality monitoring until a stable state is achieved,
including void water qualities and monitoring void water levels

Examples Waste rock facilities


Monitoring and maintenance of:
(a) Revegetation works
(b) Soil erosion and soil erosion control structures
(c) Weed control in and around the rehabilitation area
(d) Surface water quality in leachate collection ponds as per current monitoring schedules

Specific closure Void


assumptions (a) The void will not be backfilled
(b) The void will be allowed to flood naturally
(c) Bunding and fencing will occur at closure
(d) There will be no impact on groundwater as a result of water accumulating in the final void
(e) The closure strategy adopted for this closure plan will be accepted by all
stakeholders

Examples Waste rock facilities


(a) Geochemical test work of the waste rock facilities will confirm the applicability of
proposed closure methods

74 Integrated mine closure: good practice guide


Closure material sources Void
(a) 4,500 m3 of inert waste rock to construct 2 m high perimeter bund walls
(b) 2,500 m of fencing
(c) 50 warning signs

Examples Waste rock facilities


(a) Selective handling machinery for acidic outer facility waste rock face
(b) 80,000 m3 of inert waste rock from xx facility
(c) Seed and fertiliser to rehabilitate 28 ha

Waste disposal sites Not applicable

Other issues None identified

REHABILITATION COSTS ($)

Engineering and $500,000


rehabilitation cost

Closure $20,000
administration cost

Post-closure $10,000
management cost

Total $530,000

Costs not included Consultant investigations on additional geochemical test work

Cost-saving opportunities (a) There may be an opportunity to generate additional cash flow by processing the
stockpile at the same time as reducing existing liabilities that would otherwise require
re-profiling and rehabilitation
(b) Reduce existing liability by aiming to gain sign-off of the xx waste rock facility and
final void as soon as regulators finalise the progressive rehabilitation policy

Further investigations/ Long-term water quality and groundwater impacts will be needed, as well as
studies required investigations on geotechnical stability of the outer dump face and verification of cover
depth to restrict infiltration, before regulators accept the final landforms as they are

Liabilities/risks/hazards (a) The encapsulation method may not be effective in reducing acid leachate generation
to acceptable levels
(b) ‘Hot spots’ of potentially ARD/ML material may develop as acidic rock is exposed
during any waste rock re-profiling

Integrated mine closure: good practice guide 75


TOOL 2: MONITORING,
MEASUREMENT AND INSPECTIONS

This tool provides an overview of the typical needs for monitoring,


measurement and inspections, to be considered when developing
programmes for closure and post-closure monitoring.
There are numerous ways to organise – earnings by individual/household closure and post-closure. Methods
the types of monitoring that may be compared to pre-operation, can include stakeholder perception
carried out post-closure. For the during operations and post- surveys, household surveys, community
purposes of this tool, the following closure consultation meetings and analysis of
categories have been defined: – proportion of households in trends in community grievances.
affected communities generating
• socioeconomic alternative incomes Socioeconomic monitoring may be
• water carried out by the mining company.
• economic diversification
However, given the lowered presence
• terrain – proportion of households
of company representatives at the
• ecological in affected communities
mine site post-closure, and to bolster
participating in alternative
• air quality. ownership by the local community of
livelihoods
the social transition, monitoring can be
– employment rate of former
A brief overview of the typical undertaken by one or a combination of:
employees and suppliers
components of monitoring for
– proportion of businesses
consideration for each of these • Government: Involving government
operating post-closure
categories is provided below. can help to ensure a monitoring
– proportion of new businesses
programme is consistent with
Socioeconomic monitoring • post-closure land use/rehabilitation development plans and that
attainment monitoring results are considered in
Socioeconomic conditions will – proportion of lost land restored to future planning decisions.
need to be monitored following a productive capacity
closure, for both former workforce • NGOs: Organisations active
– changes in yield or productivity of in the local area often have
and communities transitioning crops
to a post-closure economy. existing relationships with the
This monitoring is required in • social investment programme local communities; understand
part because social investment performance the local socioeconomic issues,
programmes targeted at post-closure – proportion of social investment needs and capacity; and may have
socioeconomic opportunities can take programmes continuing post- ongoing community development
time to establish, become sustainable closure, disaggregated by programmes that meet the
and reach an acceptable level of community and by programme, as company’s social investment and
residual risk. well as by gender and age where social transition objectives and
applicable programmes.
The indicators used in socioeconomic – local migration trend • Community members: Involving
monitoring should consider indicators • traditional harvest economy metrics community members in the
agreed upon through community – land available for hunting, fishing monitoring process would require
visioning or regional planning and trapping capacity building and training during
processes. They should also consider – productivity measures for hunting, the operations or pre-closure
the mining company’s internal fishing, trapping and traditional phase to facilitate their participation
objectives and targets set for social food/medicine plant sources. in social transition monitoring
transition. activities. In some cases, it may be
Methods for monitoring and appropriate for company employees
Example monitoring indicators can evaluation in closure and post- who are also resident in the local
include: closure typically involve social community to participate in the
monitoring tools that were used ongoing measurement and reporting
• income generation and financial during operations, adjusted as needed requirements. However, this would
well-being to reflect needs and capacities in need to be considered on a case-by-

76 Integrated mine closure: good practice guide


©Anglo American
Water monitoring at Barro Alto, Brazil

case basis to ensure the monitoring Water monitoring • estimates based on stream velocity
and reporting process remains measurements, cross-section
Water monitoring in closure can be
transparent. characteristics and water elevation
divided into measurements related to
The nature and duration of the quantity and quality. • visual estimates based on visible
socioeconomic monitoring period flows
post-closure should be established Quantity-related measurements • information inferred from
through collaboration with regulators include both measurements of flow hydrogeological data (eg aquifer
and stakeholders. These should be rates and levels. Common approaches transmissivity and gradient
the same parties that were involved for flow rate measurements include: calculations for groundwater well
in developing social investment
level monitoring)
programmes. • flow meters on discharge pipes
• information inferred from water
Socioeconomic monitoring will • pumping records (including balance calculations – rainfall
generate results to be compared with estimates based on pump monitoring at a representative
the project’s socioeconomic baseline characteristics and operating time) weather station is standard practice
data. This baseline must include data • discharge weirs (with either manual to inform water balances in
that characterises the socioeconomic or automated measurement of operations and closure.
conditions while the mine is at full water levels over the weir)
production and the supply chain has Water levels may need to be
• changes in water level over
been fully established. If possible, the monitored for geotechnical purposes,
time from impounds of known
data set should also include the pre- erosion considerations or water use
characteristics (using stage-volume
mining baseline conditions. considerations, or to provide data for
curves)
flow estimates. It is good practice to

Integrated mine closure: good practice guide 77


are commonly inspected for some
years following closure include dump
slopes, covers, pit walls and other
geotechnical structures. Large dams
that retain water and tailings will
typically need regular inspections
on an ongoing basis (with additional
inspections after extreme rainfall
or seismic events), while other
inspections may have the possibility of
being phased out as ongoing stability
is demonstrated.

Surveys: Surveys are used regularly


in post-closure to supplement

©Newmont
visual inspections. Surveys may be
conducted to evaluate settlement
(particularly of dam crests) or quantify
other types of movement of the
Rehabilitation monitoring at Tanami Mine, Australia
ground surface.

tie all water level measurements back Water quality measurements Instrumentation: Geotechnical
to a common reference elevation. include those taken on both surface instrumentation, such as slope
A common elevation reference and groundwater samples. The indicators, lasers, extensometers
point is usually established prior to methods for the correct collection of and settlement plates, may be
the start of operations and should water samples, their handling and used to quantify ground movement.
be maintained as the basis for transportation, and analysis protocols Where frozen ground conditions are
measurements through closure and are well codified. important for ground stability or other
post-closure. This facilitates the aspects of closure, thermistor strings
comparison of measurements over a Water quality monitoring programmes are used to provide measurements of
long period of time. for closure typically include a range of ground temperature.
parameters that have been selected
Groundwater levels are typically based on the contaminants of concern Soils analysis: Laboratory and
monitored with standpipe piezometers specific to the mining operations. field analysis of soil quality may be
or vibrating wire piezometers. required during the implementation of
Standpipe piezometers have the Terrain monitoring closure works and in the post-closure
advantage of permitting sampling period. This includes soil monitoring
Monitoring of the terrain includes
of the groundwater for water quality that is linked to the assessment
monitoring that is usually carried out
measurements, while vibrating wire of rehabilitation success, with
to evaluate the physical stability of the
piezometers facilitate remote data measurements of parameters such
site, with visual inspections, surveys,
collection using telemetry. as available nutrients, salt content,
instrumentation, soils analysis and
remote sensing. organics content and changes over
Surface water levels can be measured time in bulk density or texture class.
through different techniques. Soil monitoring may also be carried
Visual inspections: These are typically
Traditional survey methods provide out for the assessment of soil
conducted by a qualified professional
reliable, accurate measurements of contamination. During operations
or designated person to identify
surface water level, as do manual or the closure period, this may be
signs of instability and erosion. For
readings of calibrated surface done to evaluate if soil contamination
dams that retain water and tailings,
water level gauges. There are also is present, and then to confirm
this will include a regular site visit
approaches available for remote the success of remedial efforts. If
by a geotechnical engineer who will
measurements, including automated there is a mechanism or suspected
check the dam signs of instability
pressure transducers and radar mechanism for recontamination of the
such as slumps, cracks, seeps and
measurement of water elevation. soil, then there may be a requirement
erosion features. Other areas that

78 Integrated mine closure: good practice guide


for ongoing resampling and analysis • Terrestrial flora: often undertaken • Chemical uptake: evaluating the
over a set period. As with water quality to monitor the progression of concentrations of contaminants of
monitoring, soil sample collection revegetation with tracking of concern in one or more species.
and analysis methods are fully changing of vegetation density and A common area of concern is the
standardised (see, for example, the distribution of species diversity. uptake of contaminants in the
applicable ASTM standards). • Terrestrial fauna and avifauna: plants used for revegetation, and
most commonly undertaken to subsequent bioaccumulation of
Remote sensing: Remote sensing, monitor the recovery of biodiversity those contaminants in animals or
with satellite, drone or aircraft- in an area following the completion humans.
based sensor technology is used in a of closure works.
variety of fields to collect information. Ecological monitoring will generally
• Aquatic flora: typically undertaken
In mining applications, the use of be referenced to baseline data and/or
to evaluate the impact of closure
Lidar technology to collect ground data from reference sites.
works and mine water discharges
information is well established.
on aquatic vegetation.
Technologies are available that allow Air quality monitoring
for the characterisation of a wide • Aquatic fauna: often undertaken
to evaluate the impact of mine Post-closure monitoring can include
variety of ground characteristics that
water discharges to a receiving monitoring for air quality, which may
may be useful in closure applications,
environment. include ambient air quality and dust
from changes in vegetation to
monitoring. Such programmes are
evaporation characteristics.
Ecological monitoring programmes almost always based on an extension
generally focus on evaluating one or of monitoring programmes in place
Ecological monitoring
more of the following parameters: to address air quality concerns
Ecological monitoring includes a during operations and closure.
wide range of activities designed to • Species populations: evaluating the Dust generation is likely to continue
monitor the conditions of organisms abundance and diversity of species through closure activities such as
living on the closed mine site in a given area. A common example demolition and rehabilitation.
following the completed closure would be measures of plant cover
activities. Ecological monitoring can on a reclaimed area. The completion of closure almost
be organised into the monitoring of always results in a dramatic reduction
• Biodiversity: characterisation of
terrestrial and aquatic flora and fauna. or elimination of many potential
the different types of species in a
These programmes typically share the sources of impacts to air quality,
given area, including identification
need to develop formal field sampling such as blasting, truck traffic and
of invasive species.
plans and QA/QC procedures. processing.

Post-closure air quality concerns


typically relate to dust generation
from tailings facilities or other
areas of fine-grained deposits. As
the technologies for the control of
dust generation post-closure are
typically robust and effective, it is
usually possible to demonstrate
improvements in air quality rapidly
after completion of closure and limit
the duration of the post-closure air
quality monitoring.
©Newmont

Ecological monitoring at Boddington Gold mine, Australia

Integrated mine closure: good practice guide 79


TOOL 3: OBJECTIVE SETTING

The following worksheet tool can be used to identify aspects of the


mine that may need associated objectives.
Site-specific objectives will be set for compliance conditions, risk components of the site. The provided
mining installations such as assessments and technical designs. worksheet is also intended to prompt
pits, infrastructure and mine waste identification of potentially appropriate
deposits and may be derived from Site-specific objectives can also be objectives. Not all aspects will be
the mine’s licence to operate, set for a variety of physical and social applicable at all sites.

Aspect What must be protected? What can be enhanced? Objectives

Geology and soils

Land use

Surface-water hydrology

Groundwater/
hydrogeology

Biodiversity

Air quality

Settlement status

Transport networks

Population and
demographics

Household composition,
density and distribution

Languages

Culture and heritage

Community groups and


organisations

Indigenous Peoples

Livelihood and income


streams

Surrounding land uses

80 Integrated mine closure: good practice guide


Aspect What must be protected? What can be enhanced? Objectives

Per capita income

Economic context

Artisanal mining

Educational facilities and


levels

Health facilities and


statistics

Community
infrastructure

Government planning
schemes

Examples of objectives that might result from this exercise are:

Examples of general closure objectives Examples of specific closure objectives with


measurable success criteria

Land suitable for grazing Land able to sustain grazing for nine months of the year
(non-winter) for up to 100 head of cattle

Two small and medium-sized enterprises Two small and medium-sized enterprises with total
employment of 100 full-time equivalent local staff

Permanent healthcare facilities in village 30-bed (1% of population) permanent healthcare facilities
with outpatient facility and maternity unit

Water supply to village Reticulated potable water to a minimum of six


standpipes in the village, with sustainable supply at 45
litres per person per day for the population of the village

Improvement in primary education Achievement of greater than 70% attendance to Grade 4,


with equivalent demographic representation of boys and
girls

Integrated mine closure: good practice guide 81


Where possible, the partial a progressive means of assessing of milestones on the pathway to
achievement of objectives should be whether the operation is ‘on track’ to completion of the objective:
set as milestones, as the following meet the defined closure objectives.
examples illustrate, so that there is The following table provides examples

Closure activity Milestone – 0% Milestone – Milestone – Milestone – Closure objective


25% 50% 75%

Rehabilitation Final land use 100 hectares 200 hectares 300 hectares 400 hectares
plan formulated graded, topsoil graded, topsoil graded, topsoil graded, topsoil
applied and applied and applied and applied and
seeded seeded seeded seeded

Capacity Determine Vocational Transfer of Self-funded, Future skill base


building current and training vocational self- achieved
future skill programmes training administered
base in village, in place and administration vocational
including full enrolment to government- training
gender equality achieved owned institution
corporation running at full
enrolment

Tailings dam Tailings Capping options Capping Capping Capping


closure impoundment determined, option chosen instituted on completed,
location and and testing and material 50% of the monitoring in
dimensions programmes selection (completed) place
scoped commenced confirmed cells in the
tailings facility
and under
validation
testing

Objectives will be developed and some words to act as prompts (the In both cases the list is not exhaustive,
refined over time. Brainstorming right-hand column) that can be used and elements should be added or
sessions may be appropriate for to formulate specific and quantifiable deleted to suit the local conditions of
identifying objectives or testing the objectives to assist in closure the operation being considered.
completeness of existing lists of planning.
objectives. This format of the tables lends itself
The first table is to support setting to facilitated workshops in multi-
The following tables provide some objectives for social transition, and the stakeholder forums and helps identify
suggested categories for objective second for objectives oriented towards social risks and opportunities in
setting (the left-hand column) and environmental protection. closure planning.

Objective setting for social transition

Closure category Typical open question Prompts

Poverty What social and socioeconomic values or gains can be Quantity, quality, availability,
achieved in poverty reduction? potential yield, productivity,
historical, modern, cultural,
Hunger What social and socioeconomic values or gains can be recreational, tourism,
achieved in hunger reduction? amenity, subsistence,

82 Integrated mine closure: good practice guide


Objective setting for social transition

Closure category Typical open question Prompts

Education What social and socioeconomic values or gains can be agriculture, cash crop,
achieved in education? stability, shelter, longevity,
drought, flood, famine,
Gender equality What social and socioeconomic values or gains can be health, contamination,
achieved in gender equality? positive legacy, negative
legacy, utility, proximity,
Child mortality What social and socioeconomic values or gains can be adaptability, stability,
achieved in child mortality? resource value appreciation,
resource value depreciation,
Maternal health What social and socioeconomic values or gains can be safety, character, unique,
achieved in maternal health? benchmark, respiratory,
carcinogenic, replenishment,
HIV/AIDS, malaria and What social and socioeconomic values or gains can be depletion, insufficient,
other diseases achieved in the management of HIV/AIDS, malaria and excess, low, high, minimum,
other diseases? maximum, educational,
future value, future cost, past
Healthcare What social and socioeconomic values or gains can be value, past cost, improve,
achieved in healthcare management? worsen, develop, destroy,
add, remove, increase,
Water supply What social and socioeconomic values or gains can be reduce, popular, unpopular,
achieved in water supply? repute, disrepute, ethical,
unethical, government, NGO,
Employment What social and socioeconomic values or gains can be policy, standard, guideline,
achieved in the employment market? practice, throttle, block,
bottleneck, controlled,
Youth employment What social and socioeconomic values or gains can be uncontrolled, stability,
achieved in youth employment? variability, instability, success,
failure, catastrophic,
Employability What social and socioeconomic values or gains can chronic, modulated, peaky,
be achieved in the employability of people in the predictable, unpredictable,
community? proactive, reactive,
indigenous, wealth, poverty,
Technology What social and socioeconomic values or gains can be education, illiteracy, health,
achieved in the application of technology? disease, trauma, capital,
revenue, funding, operating
Recreation What social and socioeconomic values or gains can be capital, wages, salaries,
achieved in recreation? income, GDP, GNP, markets,
distribution channel,
Infrastructure What social and socioeconomic values or gains can be subsidy, partnerships,
achieved through the adaptation of infrastructure? equity, investment, finance,
lending, interest, collateral,
Indigenous What social and socioeconomic values, gains or losses profit, loss, asset, liability,
are inherent to indigenous affairs? enterprise, business, service,
supply, goods, labour,
Cultural What social and socioeconomic values, gains or losses exchange, trading, economy,
are inherent to the cultural heritage of the community? rights, expectations,
responsibility, accountability,
Enterprise What social and socioeconomic values or gains can be governance, life expectancy,
achieved through the generation of enterprise? quality of life, leisure,
demography

Integrated mine closure: good practice guide 83


Objective setting for environmental protection

Closure category Typical open question Prompts

Land resources What environmental values, gains or losses are Quantity, quality, availability,
inherent to land resources? potential yield, productivity,
scarification, sterilisation, species,
Water resources What environmental values, gains or losses are biodiversity, habitat, historical,
inherent to water resources? modern, cultural, recreational,
tourism, amenity, grazing,
Terrestrial flora What environmental values, gains or losses are subsistence, agriculture, cash
inherent to terrestrial flora? crop, stability, shelter, longevity,
drought, flood, famine, health,
Terrestrial fauna What environmental values, gains or losses are contamination, positive legacy,
inherent to terrestrial fauna? negative legacy, utility, proximity,
adaptability, stability, resource
Aquatic flora What environmental values, gains or losses are value appreciation, resource value
inherent to aquatic flora? depreciation, safety, character,
unique, benchmark, pH, metals,
Aquatic fauna What environmental values, gains or losses are toxic, hazardous, respiratory,
inherent to aquatic fauna? carcinogenic, velocity, volume, rate
of flow, density, concentration,
Acid rock drainage What environmental values, gains or losses are diffusion, dispersion,
inherent to acid rock drainage? replenishment, depletion,
insufficient, excess, low, high,
Air What environmental values, gains or losses are minimum, maximum, educational,
inherent to air? future value, future cost, past
value, past cost, improve, worsen,
Noise What environmental values, gains or losses are develop, destroy, add, remove,
inherent to noise? increase, reduce, popular,
unpopular, repute, disrepute,
Waste What environmental values, gains or losses are ethical, unethical, government,
inherent to waste? NGO, policy, standard,
guideline, practice, throttle,
Tailings dam What environmental values, gains or losses are block, bottleneck, controlled,
inherent to the tailings dams? uncontrolled, stability, variability,
instability, success, failure,
Overburden dump What environmental values, gains or losses are catastrophic, chronic, modulated,
inherent to the overburden dumps? peaky, predictable, unpredictable,
proactive, reactive, repopulation,
Final pit void What environmental values, gains or losses are extinction, indigenous, dominant,
inherent to the final pit voids? passive, feral

Underground workings What environmental values, gains or losses are


inherent to the underground workings?

Heap leach pad What environmental values, gains or losses are


inherent to the heap leach pad?

Bore field What environmental values, gains or losses are


inherent to the bore field?

84 Integrated mine closure: good practice guide


Objective setting for environmental protection

Closure category Typical open question Prompts

River diversion What environmental values, gains or losses are


inherent to the river diversion?

Sewage treatment What environmental values, gains or losses are


plant inherent to the sewage treatment plant?

Water treatment plant What environmental values, gains or losses are


inherent to the water treatment plant?

Contractor What environmental values, gains or losses


accommodation are inherent to the contractor accommodation
complex?

Mine buildings and What environmental values, gains or losses are


village inherent to the mine buildings and village?

©Goldcorp

Integrated mine closure: good practice guide 85


TOOL 4: SCREENING ALTERNATIVES
FOR REPURPOSING

This tool provides a set of proposed steps towards identifying possible


alternatives for repurposing sites.
At some closed sites, repurposing facilitates the relinquishment of the that typically constrain or facilitate
of the site is possible post-closure. former mine site. repurposing
Repurposing typically involves finding • identify potentially feasible options.
a new use for the site, either in whole Evaluating repurposing alternatives
or in part, that takes advantage of requires thinking broadly about Not all closed sites will be amenable
the site characteristics to provide a possible options. This tool provides to repurposing. In some instances,
productive economic activity post- ideas to help identify and evaluate only certain domains may be available
closure, or other beneficial post- alternatives that may be feasible for for repurposing. If the screening
closure land use. repurposing. identifies an alternative land use
and a positive business case can be
There is a growing body of successful The evaluation process outlined in this developed, this approach may be
repurposing case histories in the tool is to: incorporated into the mine closure
mining industry, with examples plan. Prior to incorporation in the plan,
of post-closure uses that range • ensure that the required the repurposing must be the subject
from power generation to tourist information to start evaluating of engagement with stakeholders to
attractions. With a productive use options is available ensure the option aligns with what the
of the land secured, repurposing • look at the site characteristics community and government desires.

Step 1. Information collection

Prior to screening alternatives for repurposing, the following basic information should be
available from closure planning and post-closure land use option analysis:
• population density – proximity to potential users • status of decommissioning and infrastructure removal
• socioeconomic context • buildings available for reuse
• identification of indigenous communities • ancillary properties/buildings/infrastructure
• characterisation of environmental impacts • local business partnering opportunities
• legal considerations/problems (landownership) • water rights
• maturity/capability of future operator • neighbouring site issues
• status of landscape rehabilitation, including stability of • ‘sacrifice zones’ – areas that cannot be used
slopes • regional and local plans
• soil, surface water and groundwater contamination • potential offset requirements.

86 Integrated mine closure: good practice guide


Step 2. Constraining and facilitating characteristics

External infrastructure aspects to consider as part of the screening process could include:
• industrial context • access to airports
• rail access to site • tourism potential
• availability of high-pressure natural gas • renewable energy potential
• access to electric transmission lines • deep-water port/dock facilities
• available power options, including alternative/ • proximity to other ‘compatible’ industries
renewable energy supplies • proximity to communities
• availability of city/town sewer and water • land zoning/tenure.
• access to major roadways

Internal infrastructure, permit and utility considerations could include:


• location and availability of reclaimed land and domains • existing water abstraction and discharge permits
• existing water storage (storm, industrial, effluent)
• available buildings for reuse, sale, lease; condition of • existing air quality permits
buildings and maintenance needs • existing waste treatment or waste disposal permits
• site utilities (power, water wells) • land contamination and feasible remediation levels (eg
• site transport (roads, rail) – extent, coverage, condition industrial, agricultural or residential levels).
• remaining mineral resources for industrial purposes
(eg rock, stone, sand, gravel)

Step 3. Potential options to consider

Residential and industrial options and considerations could include:


• regional planning, such as future residential growth • other infrastructure or buildings, and available
area subsidies for economic development
• mixed use and industrial land use plans – light or heavy • water and wastewater supply and treatment for
industry growth area community or municipality.
• Tourism potential and studies available

Some of the non-industrial, non-residential options for repurposing to evaluate include:


• forestry, agriculture, rangeland • mining or metallurgy research and development
• solid (and hazardous) waste management (storage, • water supply for agricultural and/or farming purposes
transport, disposal) (eg fish farming, livestock watering, crop irrigation)
• low-level radiological waste storage • credit trading and offsets (compensation for
• communications infrastructure rehabilitated site producing rich biodiversity)
• deep-water port • carbon sequestration.

Power generation options should be evaluated, especially where the site is already connected to the regional
power grid. State/federal/provincial incentives for renewable energy sources may apply and provide additional
business-case enablers. Some of the options available include:
• solar farm projects (now successfully implemented • small-scale hydroelectric systems
at many sites) (in-line elevation drop)
• wind farms (also common) • waste to energy, biofuels and other renewables.

Integrated mine closure: good practice guide 87


TOOL 5: KEY MESSAGES FOR
SOCIAL TRANSITION

This tool provides a collection of example key messages that are appropriate
for each stage of the mining life cycle leading up to the implementation of
final closure.
Communication and engagement social transition through the closure with internal stakeholders and
with stakeholders will be an important process. The example messages are external stakeholders.
part of planning for the successful provided both for communications

Phase: Design and permitting

Internal External
• We are launching a process called ‘social transition – messages included during environmental and social
for mine closure’ that will help us make strategic impact assessment (ESIA) consultation, as required
decisions during the mine planning and operations according to local jurisdiction and company policy
phases to support the well-being of local community’s
post-closure. • Every mining project has a finite lifespan and every
mining project will eventually come to an end. To be
• The process is being launched now to ensure decisions
communicated to internal and external stakeholders
made early will support the objectives of the social
at all stages of LoM.
transition; the process will continue until the post-
closure phase of the mining life cycle. • Mine closure is an inevitable part of the mining life
cycle, but it does not need to be the end of the social
• This process will be led by our [social team] and will
and economic growth of the local community. To be
include cross-functional internal input and external
communicated to internal and external stakeholders
stakeholder input.
at all stages of LoM.
• We are currently looking at what decisions we can
make and what programmes we can support that will
help the community when this mine transitions from
operations to closure.
• We are interested in the thoughts and ideas you have
about the future land use of this site.

Phase: Construction

Internal External
• We are working with relevant business units to develop • We are seeking your input as we develop ideas
strategies for social investment, local employment, to optimise opportunities for local employment,
workforce training and local procurement that align workforce training and local procurement to support
with the social transition objectives. the community’s long-term sustainability.
• We are engaging regularly with external stakeholders • We are working with [local communities] to help them
to ensure the social transition process reflects their [articulate/update] their vision for the community
own vision and priorities for a post-mining community. post-mining; this will help to ensure we are all working
towards the same objectives during operations.
• We [are/will be] seeking input from you to develop
a social investment strategy that will ensure the
programmes we support help build skills and capacity
in the local community and enable continued economic
growth post-closure.

88 Integrated mine closure: good practice guide


Phase: Operations

Internal External
• Progressive rehabilitation. • We are currently monitoring our social investment,
• We are currently working to ensure our social local employment, workforce training and local
investment, local employment, workforce training and procurement programmes to ensure they are
local procurement programmes are contributing to the effectively contributing to community outcomes.
future social transition at closure. • We are in the process of developing agreements for the
• Our shared social transition vision is [xx] and agreed transfer of buildings and infrastructure post-closure so
objectives are [xx]. they will be available for public use.
• We are working with community leaders to develop • We are developing a monitoring plan that will support
agreements for the transfer of buildings and you in tracking social and economic changes following
infrastructure post-closure so they will be available for mine closure.
public use. • We are seeking your involvement in a multi-
• We are developing a social transition monitoring plan stakeholder community development group to lead this
that will continue to track the changes and growth of effort.
the local community post-closure. • The LoM could potentially change due to a number
of factors – that is, commodity price, identification of
resources, etc.

Phase: Pre-closure and closure

Internal External
• As we prepare for mine closure, we are monitoring • Thank you for all your work in helping design a social
the implementation of our exit strategies related transition plan for this community.
to local employment, workforce training and local • As we prepare for mine closure, we are monitoring the
procurement; the transfer of sites and infrastructure implementation of all the commitments we have made
to the local community/government as per our signed to date, including:
agreements; and the transfer of ownership over
– completion of training programmes for workers not
all our social investment programmes to the local
required during the closure phase
community/government.
– support for small business still actively contributing
• We will be working with [local/regional] government
to our local supply chain
to ensure the effective launch of the social transition
monitoring programme, which they will lead to track – the transfer of sites and infrastructure to the
social and economic changes in the community post- local community/government as per our signed
closure. agreements
– the transfer of ownership over all our social
investment programmes to the local community/
government.
• We will soon be launching the social transition
monitoring programme with the [local/regional]
government, which will help the local community track
social and economic changes following mine closure.

Integrated mine closure: good practice guide 89


TOOL 6: SOCIAL TRANSITION
ACTIVITIES CHECKLIST

This tool provides a checklist of activities that will assist planning for social
transition from the early stages of design and permitting through to closure.
Planning for social transition should activities have been presented to greenfield projects, existing active
take place from the early stages according to development phase, the operations and those that have been
of the mining life cycle. Although checklist is intended to be applicable reopened/reactivated.

Activity Resources Stakeholders Check

Phase: Design and permitting

Conduct a desktop review of Documents related to closure, Environment team, mine


internal plans, policies and mine planning and design, planning and design team,
commitments related to the social stakeholder engagement, social operations management,
transition for mine closure investment, local employment, social team, human
workforce training, local resources team, procurement
procurement, socioeconomic team, legal team
baseline data

Conduct a desktop review of Regulatory requirements for Regulator, government,


external plans, processes or studies mine closure, government NGOs, academia
relevant to the social transition for plans/policies for local/regional
mine closure economic growth, development,
land use

Assess suitability of socioeconomic ESIA Environment team, social


baseline data from ESIA for social team
transition planning purposes;
plan to include social transition
indicators in the next iteration of
socioeconomic baseline update

Assess suitability of social impact ESIA Environment team, social


assessment from ESIA for social team
transition planning purposes and
plan for update during construction

Conduct a stakeholder mapping ICMM’s Community Social team, human


process to identify relevant internal Development Toolkit resources team, community,
and external stakeholders government, NGOs

Engage relevant internal Social team, environment


stakeholders on social transition for team, human resources
mine closure; set internal objectives team, mine planning and
and procedure for internal design team, operations
collaboration going forward management

90 Integrated mine closure: good practice guide


Activity Resources Stakeholders Check

Engage relevant internal Mine design plan, mine business Mine planning and design
stakeholders on mine planning and plan, risk assessments team, environment team,
design to encourage alignment with social team
social transition objectives

Engage relevant internal Human resources team,


stakeholders on local employment, procurement team, social
workforce training and local team, legal team
procurement to encourage
alignment of construction phase
strategy with social transition
objectives

Where appropriate, engage with Mine design plan, mine business Mine planning and design
external stakeholders on future plan, closure plan, regulatory team, environment team,
land use and success criteria requirements for mine closure, social team
relevant to social transition government plans/policies for
local/regional economic growth,
development, land use

Phase: Construction

Consider setting up social transition Mine design plan, mine closure Social team, mine planning
team to foster cross-functional plan and design team
collaboration on items that affect
social transition for mine closure

Transition team to track social Social team


transition plan objectives into
development/update of mine
closure plan; update social
transition objectives and costs as
closure constraints become more
apparent

Support the development of local Human resources team,


employment, workforce training and procurement team, social
local procurement strategies team

Support engagement with external ICMM’s Tool 11: Social Community, government,
stakeholders and commence investment for closure NGOs, academia, social
discussions on leveraging team, industry peers, other
socioeconomic benefits and private sector actors
current/future land use discussions
and business development; develop
plan for longer-term facilitation of
closure discussions

Integrated mine closure: good practice guide 91


TOOL 6: SOCIAL TRANSITION
ACTIVITIES CHECKLIST

Activity Resources Stakeholders Check

Engage internal and external ICMM’s Tool 11: Social Social team, community,
stakeholders to develop a high-level investment for closure government, NGOs
social investment strategy that
aligns with the local community’s
baseline socioeconomic
context; incorporate handover of
programmes/infrastructure to local
community/government post-
closure into closure plan

External stakeholder engagement ICMM’s Tool 11: Social Social team, community,
and implementation of social investment for closure government, NGOs
investment strategy

Review socioeconomic baseline Mine design plan, mine closure Social team
and impact assessment in line plan
with current external and internal ESIA and permits
context

Phase: Operations

Hold regular meetings of cross- Social team


functional group to foster cross-
functional input on issues that
affect the social transition for mine
closure

Ensure cross-functional input is Mine design plan, mine closure Social team
incorporated into update of mine plan
closure plan

Launch and monitor ICMM’s Tool 11: Social Social team, community,
implementation of social investment investment for closure government, NGOs
strategy

Monitor alignment of local Social team, human


employment, workforce training resources team, procurement
and local procurement strategy with team, government,
social transition objectives; support community
development of exit strategy for pre-
closure and closure phases

Review socioeconomic baseline and ICMM’s Tool 11: Social Social team
social impact assessment; update investment for closure
based on current external (and Mine closure plan
internal) context; review against
management measures and social
investment programme

92 Integrated mine closure: good practice guide


Activity Resources Stakeholders Check

Draft and sign agreements Social team, government,


for transfer of buildings and community, legal team
infrastructure to local community/
government/landholders post-
closure

Provide training and capacity Social team, government,


building to assist with sustainable community
community operation of transferred
infrastructure

Incorporate social transition Social team, government,


monitoring into post-closure community
monitoring plan for the mine, or
develop a standalone plan for
monitoring social transition post-
closure

Phase: Pre-closure and closure

Monitor implementation of exit Social team, human


strategy for local employment, resources team, government,
workforce training and local community
procurement

Initiate transfer of buildings and Mine closure team,


infrastructure to local community/ social team, government,
government community

Initiate handover of social Social team, government,


investment programmes to local community, NGOs
community/government

Set up key performance indicators Mine closure team,


and independent monitoring social team, government,
programme, grievance mechanism community, NGOs
and communications method for
implementation

Integrated mine closure: good practice guide 93


TOOL 7: CLIMATE CHANGE AND
MINE CLOSURE CONCERNS

This tool provides a list of concerns that should be considered as part of the
closure planning process, suggested management approaches to address
these and suggested resources/tools to use in consideration of climate change
in the closure planning process.
Mine voids and mine waste on observations of a previous period Increases in the active layer of
deposits are generally permanent may suggest a certain magnitude permafrost may negatively impact
modifications of the land, and their of event corresponds to a 1-in-100- stability.
closure requires design horizons that year probability of occurrence, the
extend for many hundreds of years. future probability may be much Management approaches
Closure planning should consider higher once recent observed
Some mining companies address
the impacts of a changing climate changes to the historical record
climate change through a risk
on closure design. Climate is an and projected changes have been
framework and conceptual modelling
important input to closure design, and considered. This can result in much
(eg groundwater, solute transport,
significant changes in global climate more robust designs being needed
etc). Probabilities of climate change
are predicted based on current for hydraulic structures and for
and their effects are assessed
climate models made. erosion control.
together with other risk factors, and
• Water balance changes: Drier appropriate mitigations are adopted
Climate change is also a subject or wetter conditions can affect based on risk level.
of regulatory and public concern. the water balance, affecting
Questions around the impact of the designs of closure activities In more general terms, management
climate change on the closure plan such as covers and revegetation. approaches can be divided into
and how it is being addressed should Wetter conditions may overwhelm adapting or reacting to climate
be expected in any review process. the storage capacity of store- change.
Several jurisdictions now have explicit and-release covers, resulting in
regulatory requirements to address greater infiltration. Alternatively, Adapting to climate change: In this
climate change in closure plans. drier conditions may make it approach, the outputs from numerical
difficult to maintain water covers models are used to project future
Concerns or saturated soil covers or reduce climate at the site under a variety of
Climate change can affect many water availability for plants. Drier scenarios. These projections are used
aspects of closure design. Conditions conditions could also result in to inform design. This may be in the
may become wetter than historically benefits, with reduced volumes of form of modified design approaches
observed or subject to more extreme water for treatment. or changes in risk profiles. The
storm events. Higher temperatures • Baseflow conditions: Drier numerical techniques used, referred
and drier conditions can also affect conditions may result in reduced to as general circulation models or
the water balance or ice conditions. baseflow in streams or other GCMs, are based on future scenarios
receiving waters, resulting in less outlined in the Fifth Assessment
A few of the more common concerns assimilative capacity. Report (AR5) produced by the
that are regularly discussed are listed • Fires: Increased frequency or Intergovernmental Panel on Climate
below: severity of forest or grassland fires Change (IPCC).3 The AR5 outlines four
may negatively impact rehabilitation possible climate change futures that
• Design storm changes: Recent efforts or result in disruptions to represent different levels of future
experience suggests that changes site access/power. greenhouse gas emissions. Using the
to rainfall intensity and frequency outputs from the available models
will affect statistically predicted • Permafrost changes: Many
to design for future conditions may
design storm events. Whereas northern sites rely on permafrost
reduce the probability of a significant
published historical records based conditions either to provide physical
failure in the design. However, the
stability or to isolate wastes.

3. IPCC (2014). Climate change 2014: synthesis report. Contribution of working groups I, II and III to the
Fifth Assessment Report of the Intergovernmental Panel on Climate Change [core writing team, RK
Pachauri and LA Meyer (eds)]. Geneva, Switzerland: IPCC. 151 pp.

94 Integrated mine closure: good practice guide


outputs from the available models practice. It is also the only approach for anywhere in the world. Accessing
may not be of sufficient detail or may that could be considered compatible such data is an important first step
have uncertainty that does not cover with closure scenarios without in developing and implementing
all the issues that may need to be ongoing management of the site plans that respond to material
considered, and there are limitations (relinquishment or ‘walk away’). climate risks that could impact
in the confidence in the predictions. closure design. The tool can be
There is also not a clearly accepted Resources accessed here: https://icmm-mica-
standard of practice for selecting live.azurewebsites.net
There are several resources available
which climate change scenario should • More detailed downscaled climate
to help with consideration of climate
be used in closure design; therefore, projections may be available for
change. As mentioned, climate
this work may have to be repeated at the region or location of interest
change can be addressed as a risk
some time in the future. than available in the ICMM tool
and managed within the context of a
risk-assessment framework (see Tool through climate data portals and
Reacting to climate change: In a watershed analyses from national,
8: Risk/opportunity assessment and
reactive approach, closure activities subnational and research agencies.
management).
are designed based on our current The detailed downscaled climate
knowledge. For example, water projections could be compared to
• ICMM’s 2013 report Adapting to a
management structures could be the output from the screening tool
changing climate: implications for
designed to accommodate a 1-in- to better understand the differences
the mining and metals industry
1,000-year flood or a probable between the current and projected
provides an overview on addressing
maximum precipitation event, climate data sets and understand
climate change across the mining
estimated based on data collected to the uncertainties that can influence
industry, with a focus on measures to
date. If significant changes in climate design.
enhance resilience and address the
occur in the future that invalidate
implications of a changing climate. • The Mine Environment Neutral
or modify design assumptions,
• In 2016, ICMM launched an Drainage 2011 report Climate
designs may be updated or the risk
interactive/online Mining Climate change and acid rock drainage –
of not updating them evaluated. If
Assessment tool that has since been risks for the Canadian mining sector
climate change results in damage
updated to enable ICMM members
4
provides information specific to the
to structures, these will be repaired
to easily access relevant, comparable impact of climate change on mine
as part of ongoing maintenance. The
future climate projection data sets closure activities.
reactive approach requires that there
are resources available to assess,
repair and modify closure structures
as required. The reactive approach
will tend to be more inexpensive in
the short run as it will generally result
in postponing capital expenditures
and will reduce the risk of overdesign
based on uncertain predictions. It
may, however, be significantly more
expensive in the long run if the
future changes result in a failure of
the design and significant repair/
rework. This approach will also result
in greater future risks, including
reputational risks.

While both approaches are seen


in practice, incorporating adaption
©Teck

to climate change in design and


risk evaluations is now standard

4. Source: http://mend-nedem.org/wp-content/uploads/2013/01/1.61.7.pdf

Integrated mine closure: good practice guide 95


TOOL 8: RISK/OPPORTUNITY
ASSESSMENT AND MANAGEMENT

Risk management standard, Council of Standards Australia and Council


of Standards New Zealand, 2018 (AS ISO 31000:2018)
AS ISO 31000:2018 Risk management The risk management standard This tool can be used for the
– guidelines provides detailed is a comprehensive document following:
instructions on how to set out and with considerably more contextual
implement a risk management information and should be referred to • to evaluate issue-specific (eg
process. The following information in association with this tool. This tool biodiversity, community health)
shows how the standard can be details an application of the standard risks or opportunities, and the
applied to planning and operating to closure. This approach can be used impact of its management, or
for integrated closure, with a by companies that do not have their • to evaluate, based on specific
particular emphasis on how social own standards for risk assessment closure objective, the risk that the
opportunities may be captured using and guidance on acceptable levels of objective will not be met, and the
the same framework that is typically risk. impact of subsequent management
used to manage hazards or threats. on that risk.

Terms used in risk assessment

Term Definition

Risk Effect of uncertainty on objectives. Risk is usually expressed in terms of risk sources,
potential events, their consequences and their likelihood

Residual risk The remaining risk after management actions have been implemented to reduce the
initial risk

Latent risk Those risks that are unknown or that are not imminent

Likelihood The chance of something happening. In risk management it may be measured or


determined objectively or subjectively, qualitatively or quantitatively, and described in
general terms or mathematically

Consequence The outcome of an event affecting objectives

Event The occurrence or change of a particular set of circumstances

Control Measure that maintains and/or modifies risk

It is important that these risks are workshopped by a multidisciplinary team with the appropriate
range of technical expertise so that an agreed rating can be determined.

96 Integrated mine closure: good practice guide


Likelihood and consequence scales for risk and opportunity
In calculating the pre-mitigation rating of each impact, presuming a worst-case
scenario, the likelihood for each risk event occurring for each impact needs to
be agreed upon. The table below provides a description of the likelihood ratings.

Likelihood rating of the risk occurring

Likelihood

Almost certain (5) Greater than 90% likelihood of occurring


>90% Has happened, will probably happen during the mine life and there is no reason to suspect it
won’t happen

Likely (4) Likelihood of occurring is equal to or more than 30% and less than 90%
30%–90% This consequence is not uncommon in the mining and metals industry/area

Possible (3) Likelihood of occurring is equal to or more than 10% and less than 30%
10%–30% There is a possibility of this risk occurring as it has occurred before (albeit infrequently) in
the mining and metals industry/area

Unlikely (2) Likelihood of occurring is more than or equal to 3% and less than 10%
3%–10% There are no specific circumstances to suggest this could happen

Improbable (1) Likelihood of occurring is less than 3%


<3% It would require a substantial change in circumstances to create an environment for this to
occur, and even then, this is a rare occurrence

The consequence of the risk event also needs to determine the severity factor
for each impact type, including:

• schedule
• financial
• safety
• environment
• legal and regulatory
• social/communities
• reputation.

Integrated mine closure: good practice guide 97


TOOL 8: RISK/OPPORTUNITY
ASSESSMENT AND MANAGEMENT

The table below shows an example of the consequence ratings should various
types of risks occur. Note that for this table and the previous one, examples
are shown, but the content of these tables can be redefined to suit the
circumstances and risk sensitivity of any organisation.

Consequence rating of the risk occurring

Consequence rating

Consequence Insignificant Minor Moderate High Major


type (1) (2) (3) (4) (5)

Schedule Less than 1% May result in May result in May result in May result in
impact on overall project overall project overall project overall project
overall project timeline overrun timeline overrun timeline overrun timeline overrun
timeline of equal to or of equal to or of equal to or of 30% or more
more than 1% more than 3% more than 10%
and less than and less than and less than
3% 10% 30%

Financial Less than 1% May result in May result in May result in May result in
impact on the overall project overall project overall project overall project
overall budget budget overrun budget overrun budget overrun budget overrun
of the project of equal to or of equal to or of equal to or of 30% or more
more than 1% more than 3% more than 10%
and less than and less than and less than
3% 10% 30%

Safety First-aid case Medical- Lost-time injury Permanent Numerous


treatment case disability or permanent
single fatality disabilities
or multiple
fatalities

Environment Lasting days or Lasting weeks; Lasting months; Lasting years; Permanent
less; affecting affecting limited affecting affecting area impact; affecting
small area area (hundreds extended area on sub-basin area on a whole
(metres); of metres); (kilometres); scale; receiving basin or regional
receiving receiving receiving environment scale; receiving
environment environment environment classified as environment
altered with altered with comprising having sensitive classified as
no sensitive little natural largely natural natural habitat highly sensitive
habitats and habitat and habitat and with high natural habitat
no biodiversity low biodiversity moderate biodiversity with very high
value (eg urban/ value biodiversity value biodiversity value
industrial areas) value

98 Integrated mine closure: good practice guide


Consequence rating

Consequence Insignificant Minor Moderate High Major


type (1) (2) (3) (4) (5)

Legal and Technical non- Breach of Minor breach of Breach of Significant


regulatory compliance. regulatory the law; report/ the law. May breach of the
No warning requirements; investigation attract criminal law. Individual
received; no report/ by authority. prosecution, or company
regulatory involvement of Attracts penalties/ lawsuits; permit
reporting authority. compensation/ enforcement to operate
required Attracts penalties/ action; substantially
administrative enforcement individual modified or
fine action licence withdrawn
temporarily
revoked

Social/ Minor Some impacts Ongoing social Significant Major


communities disturbance of on local issues. Isolated social impacts. widespread
culture/social population, complaints from Organised social impacts.
structures mostly community community Community
repairable. members/ protests reaction
Single stakeholders threatening affecting
stakeholder continuity of business
complaint in operations continuity.
reporting period Licence to
operate in
jeopardy

Reputation Minor impact; Limited impact; Local impact; Suspected Noticeable


awareness/ concern/ public concern/ reputational reputational
concern complaints from adverse publicity damage; local/ damage;
from specific certain groups/ localised within regional public national/
individuals organisations neighbouring concern and international
(eg NGOs) communities reactions public
attention and
repercussions

The risk level is identified based on the likelihood that an event occurs, and
its consequence. Using the previous two tables for input as the number of
likelihood and consequence categories, the following risk-level matrix can be
developed. The decision as to how to categorise the various levels of risk shown
in the matrix also depends on the circumstances and risk sensitivity of any
organisation.

Integrated mine closure: good practice guide 99


TOOL 8: RISK/OPPORTUNITY
ASSESSMENT AND MANAGEMENT

Risk-level matrix

Likelihood Consequence scale

Insignificant Minor Moderate High Major

Almost certain 11 16 20 23 25
>90% (Medium) (Significant) (Significant) (High) (High)

Likely 7 12 17 21 24
30%–90% (Medium) (Medium) (Significant) (High) (High)

Possible 4 8 13 18 22
10%–30% (Low) (Medium) (Significant) (Significant) (High)

Unlikely 2 5 9 14 19
3%–10% (Low) (Low) (Medium) (Significant) (Significant)

Improbable 1 3 6 10 15
<3% (Low) (Low) (Medium) (Medium) (Significant)

©Anglo American

Sishen mine open pit look out, South Africa

100 Integrated mine closure: good practice guide


©Newmont

Integrated mine closure: good practice guide 101


TOOL 9: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR TRANSVERSAL ISSUES

This tool provides basic background for consideration in developing closure


activities for transversal issues, as well as some suggestions on where to find
additional support.
There are aspects of closure planning understanding of water movement geographically linked ecosystems
that cover all components of the over the whole of the site and off-site (although it can also be developed by
site. Social transition activities are is necessary. domain).
undertaken to facilitate or ease the
social transition from the operational Ecosystem establishment of the Social transition activities
to post-closure phase, and inherently site through techniques such as
Social transition management and
apply to the whole mining operation. revegetation is also addressed as
mitigation designed for the active
a transversal issue. While there
operation phase can continue being
Water management also needs will likely be differences in how and
applied into the closure transition
to be addressed on a site-wide why ecosystems are established
process and post-closure. Examples
basis and may also have off-site in individual components of the
of management activities that may
implications. While aspects of water site, programmes for ecosystem
be implemented during the life cycle
management will be tied to individual establishment are usually developed
and mechanisms to achieve those are
site domains, an integrated approach on a site-wide basis, informed by
presented in the table below.
to water management based on an a common ecosystem or set of

Considerations in developing social transition activities

Activity Example mechanisms

Closure communications • Develop a communications plan that outlines key messages about the project closure
management process, proposed consultation timing and location, and grievance redress mechanisms.
• Include closure in messaging for the start of a project, including clear indication of the
finite nature of the mine life, and the variety of factors that can affect its duration.

Social investment/ • Support livelihood diversification programmes (eg agricultural diversification,


community development aquaculture improvement).
strategy • Improve food security (if a local issue) by prioritising final land use planning and
rehabilitation that support food security (eg arable land and improvements in irrigation
productivity).
• Provide local business development and entrepreneurial support beyond procurement
of goods and services to the mine (eg establish supply chains for locally produced goods
and services independent of the mine acting as a primary customer/consumer).
• Support programmes that provide access to financial services through community-
based banks or microfinance (eg provide technical support and opportunities for
training, find suitable NGOs for implementation).
• Develop and/or support programmes aimed at assisting vulnerable groups in preparing
for and transitioning through closure.
• Implement a programme of support to local suppliers and/or further develop existing
initiatives to ease the transition to closure.
• Use the knowledge base/studies/monitoring and data to improve agricultural capacity of
communities. Water in particular is a critical issue. Concerns about lack of water may in
some cases be addressed through better management of resources.

102 Integrated mine closure: good practice guide


Activity Example mechanisms

Local government • Support local government development initiatives.


development • Support training centre(s) and/or programmes.

Employment and skills • Provide training and skills transfer.


development • Develop specific training programmes towards the end of operations aimed at
improving skills specifically related to other opportunities/businesses in the region
(personal finance, entrepreneurship, small-scale business, etc) as a way to prepare
employees for change.
• Support education opportunities through scholarships, site-based placements, etc.
• Develop and implement preferential local recruitment policies for operations and
closure to maximise employment opportunities for local communities.
• Develop a retrenchment plan, which could include staggering the workforce reduction
over time to minimise impact on local community socioeconomic conditions (eg
demographics, economy) and employees.

For any of the example activities been working on strategies to of climate change. The design and
and mechanisms presented above, reduce the impact of water-related selection of closure activities for water
it is important to understand the risks (availability, consumption, management needs to provide an
demographic profile of affected dependency). ICMM has established integrated approach for addressing
stakeholders and their existing a water stewardship position site-wide issues, balanced with
livelihood strategies to identify statement that all members must solutions that are specific to individual
opportunities specific to different commit to and has issued supporting installations.
categories of stakeholders. tools such as Water stewardship
framework and A practical guide to Details on typical water management
Water management catchment-based water management closure activities are provided in the
By the time a mine reaches the end for the mining and metals industry. following subsections.
of its productive life, the pre-mining The management of water has
baseline context is likely to have transitioned from an internally Assessment and management
been significantly altered through focused operational consideration to a of a site-wide water balance
physical changes made during more holistic approach that considers
the broader needs of the surrounding A site-wide water balance is typically
operations. These alterations can
catchment/watershed, its ecosystem, developed during mine design to
include activities such as diversion
dependent communities and other provide an overall understanding of
of watercourses, water removal,
users. As such, these issues should water movement at the site during
discharges, or groundwater pumping
form an integral part of stakeholder operations. This water balance is a
for process use and/or dewatering
communication and planning for fundamental tool for closure design.
of mining areas. Mine voids (such as
closure activities. A site-wide water balance is often used
pits) and mine waste facilities (such
to evaluate the impacts of different
as tailings facilities) can significantly
Implementing activities to address closure options. It is typically developed
impact both the pattern of surface
water management needs can be as a numerical model. Site-wide water
and groundwater flow and its quality,
a significant closure cost, a major balance models often include linkages
both on-site and off-site. Ongoing
source of technical uncertainty, with more detailed water management
documentation of the knowledge base
an area for the most stringent models, such as hydrogeological,
should serve as a reference point for
regulatory requirements and one seepage and watershed flow routing
understanding alterations during the
of the most contentious issues for models. Geochemical models are also
mine life, and for the design of closure
surrounding communities. It is also often linked to water balance models
activities.
one of the areas where it is usually to add a water quality component
necessary to consider the impacts to the water balance. These models
Many mining companies have

Integrated mine closure: good practice guide 103


TOOL 9: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR TRANSVERSAL ISSUES

typically use many assumptions, and it features that control erosion through the effects of those impacts.
is good practice to consider outputs in forms that are analogous
terms of ranges or conduct sensitivity to natural drainage features (using The ‘source–pathway–receptor’
analysis, rather than consider results the principles of geomorphic design) model can be used to help identify
as deterministic outputs. • restoration of pre-mining drainage potential impacts to water quality. If
features, such as streams and water quality impacts appear to be
Water management will normally creeks removal of temporary water unacceptable, the model can then be
have a physical component for the control structures (culverts, roadside used to help identify management
management of water movement, ditches, and sediment or diversion approaches for breaking the pathway
as well as an interrelated chemical dams), to restore pre-mining water (divert, treat). The source–pathway–
component for the management of flow patterns receptor model is shown and described
water quality. in more detail in the figure below.
• potential community interactions
such as transferring the ownership
Implementation of physical The source–pathway–
of potable water wellfields or
activities assessing the impacts of the end receptor model
Closure water management activities of dewatering on water supplies With a clear understanding of
that relate directly to the physical • changes to downstream the pathways, mitigations can be
movement of water include: infrastructure since mining considered, for example:
commenced and how that relates to
• constructing engineered structures dischargeable volume at closure. • Take steps to isolate the
to direct water flow over or divert contaminant and to prevent or
water around the site, including Addressing impacts or potential minimise the amount of contact
spillways, swales, ditches and other impacts on water quality water (surface water diversions,
structures covers, footprint minimisation,
• upgrading operational structures in Mine waste facilities or other waste segregation).
consideration of long-term success impacted lands can affect the quality • If there is a pathway, evaluate
criteria (eg water diversions built of downgradient surface water and approaches to address contaminant
considering a 1-in-50-year storm groundwater. Not all impacts are movement (barrier walls, grout
event may need to be upgraded necessarily unacceptable, and part of curtains, pumping wells).
to accommodate a 1-in-200-year the evaluation of applicable closure
activities should include both prediction • Evaluate methods to change
event if that is the success criteria) contaminant concentrations in
of potential impacts and evaluation of
• development of surface drainage the pathways (active treatment,

The source–pathway–receptor model


SOURCE PATHWAY RECEPTOR

• Identify potential sources of • Identify pathways between the • Identify potential receptors:
contaminants to water, including: source and potential receptors. This - human
- acidic mine waste may be surface water, groundwater - environmental
- metal-impacted soils or combinations of both • Evaluate potential impacts of
- fuel spills predicted concentrations on the
- process chemicals receptors
• Characterise/predict the effect of
contact with mine waste on water
quantity

104 Integrated mine closure: good practice guide


development, but once started,
the reactions do not necessarily
require exposure to oxygen in the
air to continue. Acid production can
continue for millennia until either the
acid-generating mineralogies are
exhausted or some form of source/
pathway control is enacted.

All mine waste materials should


be geochemically characterised

©Anglo American
to predict if ARD/ML will be
generated. The Global Acid Rock
Drainage (GARD) Guide5 provides
a comprehensive and authoritative
resource in making such predictions.
River diversion at Isibonelo Colliery, South Africa
The preferred strategies (in order of
passive treatment, reactive water may need to be managed, typical preference) to prevent ARD/ML
permeable walls, etc). both during operations and during issues are:
• Evaluate water use changes or closure.
1. Limit the exposure of unoxidised
restrictions to eliminate receptors. • Hydrocarbons: Mine activities
potentially acid-forming material
can result in areas of hydrocarbon
to oxygen to limit the rate of acid
There are many potential contamination, with the risk to
generation. This can be done by
contaminants that may need to affect water quality.
immersion in water (subaqueous
be evaluated on a site-specific
disposal) or by placing a cover that
basis. Some of the more commonly Strategies to prevent acid rock restricts the flow of oxygen and limits
encountered issues are: drainage/metal leaching issues the migration of water through the
• ARD/ML: This is discussed in more ARD/ML on an industry-wide basis is system.
detail in the subsection below. a widely recognised risk and potential
source of ongoing residual risk and 2. Prevent ARD/ML generation by
• Nutrients: Use of standard avoiding contact between reactive
financial liabilities post-closure. At
explosives can leave waste rock materials and water.
sites where this is a risk, operational
with nitrogen residues that may
and closure activities must be
impact surface water quality. These 3. Prevent transport from the ARD/
developed to prevent or mitigate
can be difficult to quantify without ML source to sensitive receptors.
ARD/ML.
site-specific data.
• Non-metal leaching: There are ARD/ML results from water 4. Neutralise ARD/ML with neutral or
a variety of non-metals that can contacting geochemically reactive alkaline materials.
negatively impact water quality. materials such as certain types of
Selenium, cyanide and sulphates waste rock, tailings and pit walls. 5. Treat ARD/ML-impacted water.
are all examples of non-metals Acid drainage is a common issue Typically, the number of alternative
that can be encountered in mining of concern, but neutral (or even closure activities available is greatest
wastes and may need to be alkaline) drainage with elevated early in the asset life- cycle stages,
addressed in water management. metals concentration, or neutral with less flexibility if operations are
• Salts: Increased concentrations but impacted with salts, can be of significantly under way or solutions
of salts in water, with saltwater equal concern. need to be designed nearer the date
contamination of freshwater, can of closure. Water treatment is listed
be a significant water management Acidic drainage often contains last in the order of preference as it
issue. Some deep mining significantly elevated metals and typically results in a long-term liability
operations can bring saltier deep metalloid concentrations. Oxygen is and may impede relinquishment of
groundwater to the surface, and this important in initiating acidic drainage the site.

5. Source: http://www.gardguide.com/index.php?title=Main_Page

Integrated mine closure: good practice guide 105


TOOL 9: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR TRANSVERSAL ISSUES

Assessment and treatment needs and costs • Active treatment: Active treatment
implementation of water • future changes in effluent systems include mechanised
treatment systems regulations that could increase systems and a variety of processes
treatment complexity and costs for the treatment of mine water,
At some sites, long-term water including aeration, neutralisation,
treatment may be required as part • risks and impacts if treatment
metal content precipitation, metals
of the closure plan when water underperforms or treatment
removal, chemical precipitation,
quality would otherwise fail to meet funding is discontinued
membrane processes, ion exchange
success criteria. Even when long- • the common view that long-term and biological sulphate removal.
term water treatment appears to water treatment is incompatible They typically require ongoing inputs
be a cost-effective solution to water with relinquishment of the mine, of energy, supplies and staff for
quality concerns (when evaluated on unless innovative arrangements can daily operation and maintenance,
an NPV basis), there are a number of be found including management of sludges
reasons why mining companies (and • the need to maintain financial or brines.
regulators) prefer to avoid it: assurance with the regulator that • Passive treatment: Passive
is sufficient to cover the cost of systems include different treatment
• the typically very long-term ongoing treatment systems that use natural processes
nature of treatment requirements,
• long-term generation and disposal for the removal of contaminants of
generating residual risk
of water treatment by-products/ concern and operate without power
• the difficulty in accurately predicting brines. or chemical supplies (although they
the true duration needed for may need periodic replenishment of
treatment At some sites there may not be an spent media). Anaerobic reducing
• conflict with finite funding and alternative. The most commonly used cells, wetlands and reactive
management resources that may approaches for water treatment are channels are all passive treatment
be available following closure active and passive treatment, with systems.
• the risk of underestimating the true numerous possible hybrids of the two:

©Teck

Water treatment plant at closed Sullivan mine, Canada

106 Integrated mine closure: good practice guide


Active, passive and hybrid systems Ecosystem establishment it would be difficult to prevent
should be designed and evaluated vegetation from encroaching on
Revegetation is a closure activity
by specialists. The evaluation disturbed lands after closure.
that is applicable site-wide and
process typically includes technology Between those two extremes, there
is commonly used as the basis to
screening, laboratory scale studies are many sites where revegetation
achieve a variety of closure objectives
and pilot plants prior to full-scale requires careful management and
such as:
implementation. The identification of planning to meet closure objectives
the preferred system will depend on and success criteria.
• erosion control
site-specific conditions such as flow • Direct revegetation: There may be
rates, flow variability, contaminants • ecosystem establishment
an opportunity to revegetate directly
of concern, climate, receiving • evapotranspiration/infiltration on mine wastes or disturbed areas.
environment characteristics and objectives Success has been demonstrated
land availability. Passive systems • preparation of land for with direct revegetation of both
typically offer lower ongoing operating post-closure use waste rock and tailings, although
and maintenance requirements, these successes are dependent
• meeting biodiversity goals
but with greater land requirements, on site-specific conditions. The
(flora and fauna)
less process control, more climate possibility of this should be
sensitivity and less flexibility in the • aesthetics.
evaluated, especially where there
contaminants that can be treated. are limitations on the available soil
Passive treatment systems are not Different methods of revegetation may
substrates to support revegetation.
‘walk away’ solutions and will require be applied at different areas within
the site to achieve different objectives. • Soil salvage: It is now standard
periodic renovation and maintenance.
While it is not always technically practice to recognise organic soils
and economically feasible to actively as a valuable and scarce resource,
The GARD Guide provides additional
revegetate closed sites, it is commonly one that should be secured from
discussion of common treatment
either strongly advocated for by the site prior to mining or the
technologies for mine water.
stakeholders or legally mandated. construction of mine waste facilities
If ongoing water treatment is required, and safeguarded for rehabilitation.
there may be benefits. These can Revegetation activities can be classed • Soil stockpiling: Stockpiles are
include: as either active, where seeds or plants used to store salvaged soil until it
are placed on the target surfaces, or is needed to support revegetation.
• continued employment passive, where some degree of ground Soil characteristics will change
opportunities and contribution to preparation may be undertaken over time in a stockpile, tending to
the local economy but the vegetation is expected to become less viable as an organic
propagate over the disturbed areas substrate. Soil stockpiles should be
• promotion of continual site
naturally. designed and managed to minimise
presence, which promotes adequate
capacity for ongoing site inspection, the loss of soil viability over time.
In designing revegetation This typically includes activities
maintenance and management
programmes, the following site- such as minimising the height of
capability for the closed site
specific factors typically need to be the piles and ensuring that they are
• reasonable closure outcomes considered: stabilised with vegetation until they
for installations that may not be
can be used.
practicably closed otherwise • Climate evaluation: The
• Direct soil placement: It may be
• possible benefits of combining the possibilities and limits for
possible to avoid soil stockpiles
treatment of mine water with other revegetation are controlled in large
– and the associated loss of soil
treatment requirements of the local part by the climate. There are
viability over time – through direct
community on an ongoing basis sites where revegetation of lands
placement of salvaged soil on
• residual value of treated water or disturbed by mining activity is not
another part of the site in support of
by-products generated from the practicable or in keeping with the
revegetation. This also provides the
water treatment process. surrounding ecological conditions
benefits of progressive closure, and
(eg at sites in the High Arctic or
an economic benefit by reducing
extreme desert environments). At
double handling of the soil. Direct
other sites, such as in the tropics,
soil placement requires confidence

Integrated mine closure: good practice guide 107


TOOL 9: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR TRANSVERSAL ISSUES

that the placed soil will not be undertake preparation of the seed
disturbed again in the future. banks needed for closure.
• Substrate deficiency: If insufficient • Engagement: The design and
stockpiled soil is available to testing of revegetation approaches
address revegetation needs, there for the site provide engagement
are several approaches available opportunities. These can
to provide suitable substrates include engagement related to
for revegetation purposes. Mine the definition of desired plant
wastes, such as inert tailings or species for final land use, and
inorganic mineral soils, may be an opportunity to demonstrate
combined with other materials visible progress towards closure.
to provide a substrate. Organic Where indigenous communities
matter (eg water treatment by- are present, they can also present
products, peat, manure, agricultural an opportunity to inform the
waste, mulch) can be combined development of revegetation
to generate substrates that will programmes with traditional
support revegetation efforts. knowledge.
Fertilisers, chemical amendments • Ongoing management: The
and soil conditioners can all play establishment of self-sustaining
roles in developing functioning vegetation can take years to
substrates. Species selection can accomplish, and natural succession
also be used to help condition the of species on revegetated terrain
substrate and prepare it for further may result in a process that takes
use (ie nitrogen-fixing plant species decades (progressive closure
can be used to condition soil). activities can provide early
• Species selection: The plant demonstration of this trajectory).
species to be used in revegetation In typical practice, ongoing
efforts should be selected based on management is needed to ensure
site-specific analysis by qualified that revegetation efforts are well
specialists. In the early stages established and sustainable. This
of revegetation, the terrain to be may include activities such as
revegetated is likely to be distinct reseeding, weed control, erosion
from the surrounding ecosystems, repair, and short-term nutrient
and species should be selected addition or irrigation. Monitoring
to put the terrain on a trajectory may be significantly limited or
towards the desired final land use. completed once it has been
• Research: The development of demonstrated that the revegetated
revegetation programmes benefits system is on a stable and desired
greatly from research work and trajectory. This type of control may
collection of data, typically through generate a long-term management
progressive closure. There should need.
ideally be years of experience Care and attention should be given to
leading up to closure to test effective revegetation and to tracking
alternative approaches; evaluate and documenting the results of work
seed mixes, seeding methods carried out.
and seedbed preparation; and

108 Integrated mine closure: good practice guide


©Anglo American

Integrated mine closure: good practice guide 109


Biodiversity monitoring at Barro Alto, Brazil

©Anglo American

110 Integrated mine closure: good practice guide


TOOL 10: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR DOMAIN-SPECIFIC ISSUES

This tool provides basic background for consideration in understanding some


of the most common closure activities for each of these three domains, as well
as some suggestions on where to find additional support.
At the most basic level, the physical shafts. Subsidence areas generated • Salvageable material removal:
components of a mining operation as a surface expression from the Remove materials that can be
to be addressed in a closure plan are: collapse of underground openings are safely and economically salvaged
another type of mine void. These can from the underground. Once
• Mine voids: the openings generated be generated both intentionally and hazardous material is removed, the
by the mining of material, which unintentionally. decision to remove other material
include pits, subsidence areas, from the underground should be an
shaft openings and adits, and While there are considerable economic one, driven by the balance
underground workings. differences in the closure activities between the cost of removal and
• Mine waste: waste material applicable to the different types of the economic benefit of its reuse or
generated after the extraction of mine voids, they all share concerns scrap value.
the ore, including processing by- over risks to humans and wildlife • Backfilling: While not a standard
products (such as tailings, spent associated with falling into the approach, consideration may be
heap leach material) and waste opening or otherwise becoming given to backfilling some or all of
rock. trapped in it. As the potential the underground voids with tailings,
consequences of such an incident paste tailings (including cemented
• Mine infrastructure: structures
are high, closure activities to control paste) or similar materials. This
and facilities constructed to
access are a common requirement for may be undertaken to provide
support mining activities, including
mine voids. additional support to the voids
elements such as processing
facilities, offices, roads, pipelines, where there is a risk of subsidence,
Details on typical closure activities for especially where subsidence is
power supplies, culverts and
both underground mines and pits are not compatible with the planned
laydown areas.
provided in the following subsections. post-closure land use. This may
The closure of subsidence areas may also provide a benefit as a preferred
Together, these components make up
be analogous to pit closure, although disposal location for the tailings.
the physical site aspects subjected
backfilling approaches are more
to intervention and will need to be • Flooding: Underground mining
common for subsidence issues.
addressed in the closure plan. is often carried out below the
groundwater table, facilitated by
Note that domains should also be Underground mine workings
dewatering activities. Dewatering
evaluated together and interactions While there are many exceptions is normally terminated as part
between them considered. The best and site-specific considerations, of closure, and the underground
solution at a given site may combine the activities to close underground workings flooded or partially
domains. As an example, disposing mine workings have become more flooded as water returns to steady-
of reactive tailings below the water standardised. A typical procedure state levels.
table in an open pit (a mine void) may involves the following: • Access control: Openings to the
be the best closure solution for both
surface are typically blocked
installations. • Hazardous material removal: off by collapsing openings with
Remove all potentially hazardous explosives; placing rockfill; using
Mine voids material from the underground, combinations of expanding foams
such as hydrocarbon products, and rockfill, grout or grouted plugs,
The main types of mine voids are
chemicals and explosives. The and concrete fill or reinforced
underground mine workings and open
focus is usually to remove material concrete caps; and constructing
pits. Underground mine workings
that has the potential to significantly gates/lockable caps where post-
include openings to the surface
impact water quality when (or if) the closure access to the underground
such as vents, raises, stopes and
underground is flooded.

Integrated mine closure: good practice guide 111


TOOL 10: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR DOMAIN-SPECIFIC ISSUES

is required. Consideration should of pits with mine waste. This can • hydro energy generation
be given to the design life of the provide benefits for physical (and • recreational use and aesthetics
engineered feature, including the possibly chemical) stability of the
• aquaculture and fisheries,
future replacement cost. waste facilities. While backfilling
agriculture
• Water management: Depending of pits is often raised as a potential
closure activity, it is normally not • ecological habitat.
on the configuration of the openings
and the site hydrogeology, there cost-effective unless combined with
waste disposal from active mining When the water quality is predicted
may be either intermittent or
operations, such as may be practical to be poor, water treatment may be
ongoing water discharges from
with the sequencing of a strip-mining needed. This may be either in-pit
the underground mine openings.
programme. treatment (such as periodic dosing with
Management approaches will
lime) or water treatment systems or
depend on flow rates and the
Pit lakes may form after the end some combination of the two. In some
current and expected chemical
of operations. When dewatering cases, poor water quality is associated
composition of the discharge.
activities were needed to keep the pit with oxidation of acid- forming
dry in operation, the end of dewatering materials on pit walls. While placing
Open pits covers on pit walls is occasionally
can lead to accumulation of water in
Open pits can require implementation the open pit, effectively forming a lake. proposed as an option for addressing
of closure activities to control a variety this, the geometry of most pit walls
of physical and chemical risks. Pit lakes can create significant means that this approach is seldom,
residual risks at closure since if ever, practical in the long term. LoM
Issues around physical access they often have steep sides, great planning should seek to avoid exposing
control are commonly addressed depths and large volumes, and may these materials if possible.
with perimeter berms to discourage attract people. Depending on the
inadvertent or unauthorised access, deposit nature and management The climate and local hydrogeology
and/or with blockage of the access practices, the large volume of water have a significant influence over pit lake
roads. As pit walls are often not in the pit may also be contaminated, closure activities. In very dry climates,
developed with long-term stability in presenting additional closure the pit lake may never have any outflow,
mind, geotechnical/rock mechanics challenges. However, unlike many and the pit will remain a groundwater
studies should be undertaken of the other closure landforms, pit lakes can sink. In wetter climates, pit lakes may
final pit configuration at the time offer substantial benefits. Properly eventually overflow, either seasonally
of final closure. These studies can managed with regard to the change in or consistently. Water management
be used to identify a safe setback land type from terrestrial (pre mining) approaches will be determined based
distance for the berm so that the to aquatic (post-mining), pit lakes can on the tendency to overflow or not. The
access control is located outside of present opportunities for beneficial time taken for pits to fill can present a
the expected long-term extent of post-closure use. post-closure management challenge.
the pit. It is not uncommon for pit filling to
The selection of closure activities take 20 to 80 years or longer. This can
At some mines where there are for pit lakes typically involves the impact approaches for post-closure
multiple pits, integrated closure integration of social, environmental land use, monitoring durations and
planning may facilitate backfilling and economic viewpoints. Long-term relinquishment.
water quality is key to pit lake closure
planning, with good water quality Mine waste
generating additional options for
©Anglo American

Costs to close mine waste installations


beneficial post-closure pit lake use. can be high depending on chemical and
physical stability of the waste and how
Some common beneficial closure
large an area it occupies.
approaches for pit lakes, listed in
the order of increasingly stringent The most common types of mine
requirements for pit water quality, are: waste are:

• site-impacted water control • tailings


• water storage and flood mitigation • waste rock
Lomas Bayas copper mine, Chile

112 Integrated mine closure: good practice guide


• heap leach piles Given this, the design criteria used may be needed to stabilise the facilities
to establish the physical stability of at closure, reducing the overall cost of
• slag and process residues.
mine waste facilities are usually more closure activities.
Proper design and closure of mine stringent after closure than during
operation. Some guidance documents The following subsections provide
waste facilities requires that the
recognise this explicitly. additional detail of the closure
waste materials be characterised with
respect to their physical and chemical activities specific to different types
The use of more stringent design of mine waste facilities, with a focus
properties, based on adequate
criteria after the mine operations on the two key guiding principles
geotechnical and geochemical testing phase implies that activities to stabilise
on the waste materials. for physical and chemical stability.
mine waste facilities may need to be These are not the only concerns to
undertaken as part of implementing be addressed by closure activities.
Closed mine waste facilities will closure (eg constructing stabilisation
typically have a long or indefinite Factors that could significantly shape
berms on tailings dams, enhancing the design and closure of the facilities
design life as they will remain in place spillway capacity or flattening waste
for the foreseeable future. Closed mine include future land use, desired
dump slopes). For mines in the landform shapes, aesthetic values to
waste facilities often need to be stable planning phase, it is usually more stakeholders and interests of future
in the long term with infrequent or no sensible to adopt a ‘design for closure’
parties at relinquishment.
human intervention. Further, the long/ approach. In other words, the mine
indefinite duration of the design life waste facilities should be designed
means that it is much more likely that
Tailings facility closure
with eventual closure needs in mind,
the facility will eventually be exposed and then developed to fit the post- Attention should be given in the early
to extremely infrequent events, such closure design criteria. This approach design stages to selecting the tailings
as large earthquakes or floods. will reduce the additional effort that technology that is most appropriate for

©Glencore

Collahuasi copper mine, Chile

Integrated mine closure: good practice guide 113


TOOL 10: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR DOMAIN-SPECIFIC ISSUES

all stages of the design life including including tailings facilities with Design of closure activities for
closure, and to considering additional containment dams, dry stack physical stability of tailings storage
activities that may be needed to attain tailings and disposal in mine voids. facilities
physical and chemical stability in the The option selected will have a Closure activities for tailings storage
long term. profound influence on the post- facilities should consider and address
closure performance of the facility in the potential modes of failure
There are numerous options available terms of physical stability, chemical that could occur post-closure as
for the management of tailings, stability, public safety and land use. summarised in the table below.

Closure activities for various modes of failure for surface tailings impoundments

Possible mode of failure Disruptive agent Closure activities

Overtopping Extreme rainfall or snowmelt, Increase capacity of emergency


blocked spillway spillway if necessary; inspect and
clear spillway

Dam instability Loading from earthquake Design geotechnical stabilisation


activities such as a toe berm

Dam instability Rising phreatic surface in Monitor and clean or augment


downstream drains as necessary; reduce pond
water level

Dam instability Tailings liquefaction Design geotechnical stabilisation


activities such as a toe berm or
buttress

Wave erosion Wind storm and high pond water Lower spillway (or breach dam if
level possible); place larger riprap

Runoff erosion Runoff from rainfall Monitor, repair and enhance


vegetative cover or erosion
protection

Wind erosion Wind storms Monitor, repair and enhance


vegetative cover or erosion
protection

Tailings dam failures have resulted in guidance available on the design closure, and closure activities should
catastrophic environmental damage and operation of tailings dams, and be developed to properly address and
and loss of life, and recent history accepted industry guidelines should control the identified risks. Dams
suggests that inadequate design, be used, such as the documents that remain medium- to high-risk
construction and maintenance produced by the Canadian Dam structures (in CDA classifications)
continue to result in catastrophic Association (CDA)6 or the Australian after closure should have post-
failures (see ICMM’s 2016 Position National Committee on Large Dams. closure operation, maintenance and
statement on preventing catastrophic surveillance plans and emergency
failure of tailings storage facilities). Tailings dams typically remain as preparedness plans in place.
There is considerable technical permanent structures after mine

6. Particularly relevant is the CDA (2013) Dam safety guidelines 2007 (2013 edition) and the CDA (2014)
Technical bulletin: application of dam safety guidelines to mining dams.

114 Integrated mine closure: good practice guide


Design of closure activities for of tailings), and the evaluation of the use of a cover to minimise or
chemical stability of tailings storage closure needs to be considered in eliminate impacted contact water.
facilities the context of planning for site water There are a number of different types
Tailings are usually physically contained management. of covers, which have different modes
within a mine site. Unacceptable of operation. The selection of the type
environmental impacts from tailings During mine operations, when of cover is strongly driven by climate,
usually relate to the discharge of reactive tailings are present, water as illustrated in the figure below.
tailings contact water off-site into treatment and/or pump back
a receiving environment such as a systems are often used to mitigate Submerging tailings under water
groundwater or surface water resource, impacts from the seepage of tailings (in-pit disposal) or flooding a tailings
or wind-blown dust impacts on the contact water. The need for water area to form a water cover for closure
surrounding environment. Tailings treatment may diminish over time can both provide very effective limits
are the uneconomic end product of after closure as the tailings dry and on oxygen. When water covers are
processing ores, which by nature are the seepage rate decreases. This not viable, another potential control
enriched in mineralisation and may be may lead to an adaptive management mechanism is to construct a ‘dry’
at risk of generating ARD/ML. approach, where the water treatment cover over the tailings, which could
is continued after closure until it is comprise a layer of non-reactive
It is vital for design that the no longer required to meet success tailings, overburden or topsoil layers,
geochemistry of tailings be thoroughly criteria. or geosynthetic materials. Dry covers
characterised (refer to the GARD can also limit the rate of infiltration
Guide for appropriate protocols Another approach to controlling and thereby reduce the volume
for geochemical characterisation seepage from reactive tailings is of seepage/leachate from a mine

Cover types for different climates


0.1

50
25
0.2

5
12
5

Permafrost
0
0.5

Thermal covers
25

(freeze-thaw effects)
o
ati

Latitudinal region
nr

-8°C
An
tio

0
50

nu
ira
1

Polar
al
sp

pre
an
otr

cip

1.5°C
00
ap

ita
1,0
2
ev

tio

Subpolar
l

n(
tia

Lo ygen

mm
Wa erm arrie
ten

Ox
wp

3°C
00
ter ea rs
Po

)
2,0
cov bilit
4

Wa

Boreal
Infi r she

ers y
te
ltr dd
(su

ati ing

00

6°C
4,0
on
sta
Sto abilit
8

con cove
in
re y o

Cool temperate
tro rs
an f ve
dr

00

12°C
ele geta

8,0
16

Warm temperate
as tion
e

Subtropical
0
,00

24°C
)

Tropical
16
32

Super-arid Perarid Arid Semi-arid Subhumid Humid Perhumid Super-humid

Source: Wickland et al 20067

7. Wickland, BE, Wilson, GW, Wijewickreme, D, and Klein, B (2006). ‘Design and evaluation of mixtures of
mine waste rock and tailings’, Canadian Geotechnical Journal, 43:9, pp 928–45.

Integrated mine closure: good practice guide 115


TOOL 10: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR DOMAIN-SPECIFIC ISSUES

waste facility. Dry covers may not backs are placed between each terrain with convex and concave
completely stop either acid generation sloped area, such that the overall surfaces leading to dendritic drainage
or infiltration. Consequently, closure average slope will meet the closure swales that are designed based on
planning needs to consider the need objective. Appropriate stability criteria the characteristics of stable natural
for ongoing monitoring of seepage will need to be met for both the berms streams in the vicinity of the site.
to confirm that volumes and quality during operation and the flattened Practices around geomorphic design
meet discharge criteria. It may also closure slope. are evolving rapidly.
remain necessary to manage seepage
for some time after closure. The overall stability of a waste rock Design of closure activities for
facility is often governed by the chemical stability of waste rock
The design of covers is a highly strength of the soil foundation at facilities
technical area. Closure plans that the toe of the facility. Geotechnical Waste rock can be a source of ARD/
include the use of covers should investigation and design is required ML, and the risk of this must be
contain details of the tailings to provide an adequate factor of evaluated and addressed from the
geochemistry, cover material safety against an overall foundation earliest design stages. The GARD
properties and analytical predictions failure, and to verify that the inputs Guide addresses protocols for waste
of the cover performance. Refer to the and assumptions used in the rock characterisation.
GARD Guide for a discussion on cover calculation of the factor of safety are
selection and design. credible. Typically, events that are Water that infiltrates into the top
statistically rare (‘long return period’) and sides of a waste rock facility
Waste rock facilities closure are selected for design (ie loading may eventually appear at one or
from an earthquake). In the case of more points on the toe of the facility,
The closure of waste rock facilities
residual or reactive waste rock, the or infiltrate directly to underlying
needs to address a range of closure
effects of rock weathering should also groundwater. At some sites, it is
objectives. Closure activities for the
be considered. Waste rock facilities possible to design for collection of
objectives related to the guiding
should be designed and constructed this toe seepage for monitoring and, if
principles of both physical and
with closure in mind because it may needed, treatment.
chemical stability are discussed
be difficult or impossible to augment
below.
the stability of a waste rock facility The rate of acid generation can be
after placement. reduced by reducing the flux of oxygen
Design of closure activities
for physical stability of waste rock and/or water to problematic waste
Runoff from waste rock facilities rock. One approach is to preferentially
facilities
should be controlled to prevent place waste rock that is susceptible to
Waste rock facilities are typically possible erosion of the slopes and acid rock drainage generation into the
formed by dumping waste rock off covers. A conventional approach for middle of the facility and encapsulate
the edge of a working bench. This this is to construct erosion-protected it with inert or alkaline waste rock.
dumped material will stand at an channels (or ‘chutes’) to safely carry Another approach is to place a cover
angle that is called ‘angle of repose’. runoff down the side slopes to the over the surface of the waste rock
While this angle varies depending toe. In this approach, the top of the facility to reduce the oxygen and/or
on the characteristics of the rock, waste rock facility and any remaining water flux into the pile.
it is typically too steep to practically benches are graded to direct runoff
place and retain soil – if a soil cover is into the chutes. Care is needed in Considerations for the design of
needed either to control infiltration or developing these designs as there are covers on waste rock facilities are
promote rehabilitation and vegetation many examples where these channels similar to those previously outlined
of the site, it will be necessary to have been under-designed and failed for covers on tailings. An important
flatten the slope. A slope of 18 due to storm water flows exceeding difference is that steeper slopes are
degrees or even less is typically the design capacities, or these systems common on waste rock facilities and
limit, with 22.5 degrees considered being unable to cope with differential may require flattening to permit cover
the outer limit for effectively grading settlement of the underlying material. placement (which can be expensive),
cover materials. This flattening can Alternatively, geomorphic design or the cover options available will be
be facilitated by a process known as principles may be applied to develop severely limited to approaches that
‘benching’ during the placement of a waste rock facility structure that are feasible on steep slopes.
the waste. Several horizontal step is curvilinear and mimics natural

116 Integrated mine closure: good practice guide


©Gold Fields

Integrated mine closure: good practice guide 117


TOOL 10: CONSIDERATIONS IN
DEVELOPING CLOSURE ACTIVITIES
FOR DOMAIN-SPECIFIC ISSUES

Heap leach facilities closure rock facilities. Slag is crystallised the sequencing, temporary camps and
material with a high content of facilities may be needed to support the
Heap leach facilities involve the
iron silicates, which is usually final period of closure activities.
irrigation of ore piles with solutions
not particularly prone to acid
(acid or cyanide solutions are For mine and processing infrastructure
generation. A closure plan should
common) to dissolve the metals and (buildings; power lines and
still, however, contain a geochemical
carry them into a leachate collection pipelines; roads, ports and railways;
characterisation of the slag
system. Closure of heap leaches concentrators, refineries and smelters),
materials.
usually starts with allowing residual the typical sequence of closure
solutions to drain from the heap and Process residues often contain activities is often as follows:
processing them for as long as is substantial quantities of chemical
economically viable. Closure plans precipitates such as gypsum that can 1. Compile an inventory: An asset
should contain predictions of the considerably alter their geotechnical register with all buildings and
drain-down time and chemistry as properties in comparison to infrastructure will be needed for
required. conventional particulate tailings. planning purposes. This list should
include risks associated with each
In some cases, it may be desirable The chemistry of process residues individual asset. A rigorous assessment
to ‘flush’ the heap leach to remove can also vary widely, and they of all hazardous substances is
solution from the heap leach in a can contain relatively unstable necessary to evaluate the need for
controlled way (typically for gold oxides. Process residues need to decontamination, and to develop
heaps). Experience shows that be subject to careful geochemical appropriate provisions. At the detailed
interactions are chemically complex, characterisation. design stage, surveys should be
and general rules such as flushing undertaken to capture all underground
with three pore volumes of water are Closure plans should include and redundant services and
inaccurate. Site-specific laboratory geotechnical properties, termination points. Design or as-built
column tests are likely to give more geochemical testing of the residue documents (eg structural drawings,
defensible estimates. In other cases, and predictions of the long-term equipment lists, material take-offs)
it may be better to not flush the heap physical and chemical stability, will assist design and planning for
leach as it uses a significant amount with risk assessments conducted if decommissioning.
of clean water and generates a appropriate.
substantial amount of impacted water 2. Explore alternative uses: Alternative
that must then be managed. Mine infrastructure uses for infrastructure should be
explored, such that it can stay in place,
Seepage collected from heap leaches Closure activities for mine
with appropriate responsibility for
may or may not require treatment infrastructure are relatively
operation and maintenance transferred
for some period of time (dependent standardised. Transitioning from an
to the regulatory authority, community
on the climate). The need for this operating site to a closed site typically
or other third party. For example, roads,
requires evaluation on a site-specific involves a decommissioning process
clinics and camps may be of interest
basis, and in consideration of the with the removal of infrastructure
for community use; wellfields may
site’s overall water management for a variety of reasons, including
be attractive for agricultural or other
approach. If treatment is needed, eliminating physical, chemical and
industrial use; and airports may be
appropriate designs will need to be electrical hazards associated with
of interest for regional use. Careful
developed. unauthorised access to buildings and
discussion and planning is required
preparing the land for transition to its
in transferring mining infrastructure
Slag and process residues post-closure use.
as the receiving owner may not be
closure in a position to safely operate the
One of the most important
Slag can be in either of two forms: infrastructure, or have the capacity
challenges for managing the closure
dumped slag, which physically (technical skills, finances) to operate
of infrastructure is ensuring that the
resembles waste rock, and granulated and maintain it safely and sustainably.
sequence of activities is correctly
slag, which is physically like coarse Transfer of legal liabilities also requires
planned. Power infrastructure,
sand tailings. The design of stable documented agreements.
camps and maintenance facilities
physical containments for slag is may all be needed for support of
similar to the design of stable waste 3. Wind-down: Inventory of assets
other closure activities. Depending on
such as mobile equipment, tools and

118 Integrated mine closure: good practice guide


consumable inventory in stores/ contaminated transformers; and hazardous landfill, either off-site or
warehouses should be managed clean-up of any other associated on-site. This may require construction
leading into closure, with inventories soil or water. This may occur before, of new licensed landfills. It is also
brought down to needed levels and during or after demolition and common practice to dispose of inert
excess material sold, recycled or deconstruction activities. construction wastes (particularly
disposed of. concrete rubble) in on-site waste
6. Demolition/deconstruction: disposal facilities. This may require
4. Isolation: The first steps of This is the process of physically specific authorisations from regulatory
decommissioning typically involve taking apart infrastructure and may authorities and planning to ensure
safely isolating utilities, including involve disassembly of some or all that suitable capping material and
connections for power, water and gas. of the structures or destruction of the like is available. Where landfilling
Prior to decontamination, fuels, oils infrastructure with heavy equipment is required, quantities to be disposed
or bulk chemicals should be removed or explosives. Modelling the cutting of should be carefully estimated to
from all storage vessels and purged sequence and induced collapse of ensure there is sufficient capacity. The
from any service lines that run within some of the more challenging and decontamination process itself will
the site, pumps, motors or the like. complex structures may also be likely generate a significant volume
undertaken to inform the safest and of liquid (wash-down water) and solid
5. Decontamination: Decontamination most effective demolition method. hazardous materials to be managed
of structures and industrial in accordance with waste handling
equipment is required where 7. Salvage: Typically, some portion and disposal requirements, such as
hazardous substances have been of the demolished infrastructure will secure on-site disposal, or to licensed
used or equipment has been have economic salvage value. This landfills for solid and/or hazardous
contaminated through the operational material is separated during the wastes. On-site water treatment may
process. This may involve cleaning demolition process and transported be necessary.
structures to remove undesirable off-site for sale or reuse.
residues; abatement of hazardous 9. Remediation: During the operational
materials such as lead paints, 8. Disposal: Inert demolition waste phase, some soil or groundwater
asbestos or polychlorinated biphenyl- is typically disposed of in a non- contamination may have occurred.
If remediation was not done during
the operational phase, it should be
completed as part of closure. This will
require assessment of the extent and
nature of contamination, and related
impacts, implementation remedial
activities (such as landfarming or
disposal of impacted soils in an
authorised facility) and verification
that remediation has been carried
out to applicable standards. It is
recommended to have a conceptual
understanding of where contamination
is likely to have occurred prior to the
removal of infrastructure.

10. Ground preparation: Depending


on the next land use, foundations may
be left in place, covered or broken
up. Compacted surface soils may
©Anglo American

be de-compacted and/or scarified.


Direct revegetation may be possible,
or soils placed in the areas of former
infrastructure and revegetated.

Dishaba mine infrastructure, South Africa

Integrated mine closure: good practice guide 119


TOOL 11: SOCIAL INVESTMENT
FOR CLOSURE

This tool is designed to foster collaboration for those involved in the


development, allocation and delivery of a mine’s social investment
programme and/or a mine closure plan, such as:
• members of the operation’s • external stakeholders (government, The table below provides a qualitative
community, corporate affairs or NGOs and communities) who self-assessment questionnaire
sustainability team in charge of understand the considerations intended to prompt discussion
developing and implementing the in devising a company’s social between social investment planners
social investment programme investment programme, and and implementers. It comprises
• procurement/supply chain, therefore can identify and prepare a series of questions that can be
government relations, human for opportunities and their considered in their entirety or partially.
resources, mine planning and participation.
operational teams

Social investment for closure self-assessment questionnaire

Significantly

Completely
Moderately
Somewhat
Not at all /
unknown

How good an understanding of social transition issues is there?

• To what extent is the currently available social baseline information


adequate for helping understand social issues and social trends?

• To what extent are the post-closure social impacts understood?

• To what extent have the business risks of social transition been


identified, including employee retention when the operation nears
closure?

• To what extent have different scenarios relating to social transition been


developed?

• To what extent can the predicted impacts and scenarios be relied upon
as being accurate?

• Have groups that may be particularly vulnerable to the impacts of


closure been identified and the potential impacts on them understood?

To what extent is there a common shared vision of a post-mining future for the area?

• To what extent is there a long-term vision and/or development plan for


the area?

• To what extent do different key stakeholders share and agree about this
long-term vision or plan?

120 Integrated mine closure: good practice guide


Significantly

Completely
Moderately
Somewhat
Not at all /
unknown
• To what extent does this vision consider the social impacts of mine
closure?

• To what extent are other big trends or changes that can be foreseen
understood and taken account of in this vision or plan?

To what extent does the current approach to mine management integrate social transition issues?

• To what extent has mine design incorporated social transition issues (eg
shared infrastructure design)?

• To what extent have social transition issues been considered and


managed through operations (eg skills development, local supplier
development, progressive land rehabilitation, etc)?

• How fully have closure plans been developed?

• To what extent does the current closure plan consider social issues?

• To what extent have success criteria for social transition been defined?

To what extent are there legal or other requirements that support social investment for closure?

• To what extent are there legal requirements that are relevant to social
investment for closure?

• To what extent are there corporate or financing requirements that are


relevant to social investment for closure?

• To what extent has the company made specific commitments relating


to social investment for closure?

• To what extent are there wider societal expectations, norms or peer


practices that may determine social investment for closure?

How strong is the need for additional social investment to build socioeconomic resilience?

• How soon is closure expected?

• To what extent are the risks that mine closure may occur earlier than
expected understood?

• To what extent are the economies and livelihoods of affected


communities dependent on the mine?

Integrated mine closure: good practice guide 121


TOOL 11: SOCIAL INVESTMENT
FOR CLOSURE

Significantly

Completely
Moderately
Somewhat
Not at all /
unknown
• To what extent are there other economic or livelihood opportunities that
could replace mining-reliant jobs?

• To what extent have post-closure impacts been designed out or


progressively managed to minimise significant shocks during and
beyond closure?

• To what extent have financial provisions been made to finance


investments to support social transition?

• How clearly has the business case for social investment for closure
been defined?

To what extent does the site’s current approach to social investment integrate social transition issues?

• To what extent have the scope and boundaries of social investment for
closure been defined?

• To what extent has the site’s social investment policy or procedure been
developed?

• To what extent has a comprehensive site social investment plan been


developed?

• To what extent do existing social investments consider long-term


sustainability in terms of capacity for ongoing management and
financing post-closure?

• To what extent is the social investment plan aligned with the site closure
plan?

• To what extent is social investment focused on supporting priority areas


to build social resilience?

• To what extent does social investment support the following areas:

– capacity building of local government for post-closure governance and


service delivery?

– capacity building of community groups and civil society organisations?

– support to long-term development planning?

– securing land and property rights?

– skills development appropriate to post-closure skills demands?

122 Integrated mine closure: good practice guide


Significantly

Completely
Moderately
Somewhat
Not at all /
unknown
– business development appropriate to post-closure economy?

– vulnerable and marginalised groups particularly at risk from post-


closure impacts?

– support to public infrastructure?

– investments in land availability and use?

• To what extent do the above areas align with anticipated social transition
priorities?

• To what extent is the social investment approach aligned with local


long-term development plans and priorities?

• To what extent is social investment for closure being progressively


implemented?

To what extent are key stakeholders engaged in the social transition planning process?

• To what extent have the different stakeholder groups related to mine


closure been identified?

• How well are the roles and responsibilities of different stakeholder


groups in the closure process understood?

• To what extent do key stakeholders understand the closure plan and


objectives?

• To what extent are communities open to discussion about social


transition issues?

• To what extent is the current relationship between the mine and


stakeholders supportive of engagement on social transition issues?

To what extent is there a coordinated and competent team responsible for managing social transition issues?

• To what extent are senior management aware of the social impacts of


closure?

• To what extent are management committed to investing in managing


social closure issues?

• To what extent is the company willing and able to make investments in


social issues for closure (eg what is the risk appetite, financial capacity,
time horizon of management, etc)?

Integrated mine closure: good practice guide 123


TOOL 11: SOCIAL INVESTMENT
FOR CLOSURE

Significantly

Completely
Moderately
Somewhat
Not at all /
unknown
• To what extent are departments other than those directly responsible
for social performance/community relations supportive of social
transition issues?

• To what extent have roles and responsibilities been defined for social
transition and social investment for closure?

• To what extent has a central point been given the authority to lead and
coordinate social investment for closure activities?

• To what extent is there a defined and working team responsible for


social investment for closure?

• To what extent are there incentives relating to performance of


management of social transition?

• To what extent is there a clear budget and staff resources for social
investment for closure?

• To what extent is the mine clear about what skills and competencies are
required to successfully manage social investment for closure?

• To what extent does the mine team have these skills and competencies?

To what extent do other stakeholders have the capacity to govern and manage social transition issues?

• To what extent are collaborative or partnership models being used in


social investment for closure?

• To what extent is there a detailed understanding of the capacity of the


different stakeholders that are responsible for governing and managing
social transition issues?

• To what extent does local government have the capacity to govern and
manage post-mining social transition issues?

• To what extent do communities and community-based organisations


have the capacity to govern and manage post-mining social transition
issues?

To what extent are there sustainable and effectively governed financial resources for social investment for closure?

• To what extent is the scale of financial provisions for social investment


in line with social impacts/risks and requirements/needs for social
investment?

124 Integrated mine closure: good practice guide


Significantly

Completely
Moderately
Somewhat
Not at all /
unknown
• To what extent have provisions been made to guarantee ongoing social
investment for closure independently from financial or operational
performance of the site?

• To what extent have dedicated financial mechanisms (eg trusts) been


established to ensure independent management of social investment
for closure?

• To what extent have joint institutional arrangements (eg multi-


stakeholder boards, advisory committees, forums, etc) been established
to manage and hand over responsibility for some areas?

• To what extent is there potential for other sources of complementary


funding?

• To what extent is there coordination with or leverage of other


funding sources?

To what extent is social investment for closure monitored and evaluated?

• To what extent have outcomes, objectives, targets and indicators been


set for social investment for closure?

• To what extent is the performance of social investment for closure


regularly monitored?

• To what extent are improvements identified, implemented and tracked


in response to monitoring and evaluation?

Integrated mine closure: good practice guide 125


TOOL 12: CLOSURE PLAN
DOCUMENTATION

This tool provides a set of key considerations when developing and updating a
mine closure plan specifically relating to the contents of the plan and frequency
of updates, as well as documentation for final closure.
The closure planning process must have one plan developed specifically to • Closure activities: the core of the
be documented in a formal written address regulatory needs and another plan, describing what activities will
plan accompanied by supporting more extensive plan (or version of the be carried out to attain closure.
documents. This plan will be regularly plan) developed to address internal • Post-closure: one or more
updated throughout the mining life corporate needs. sections describing what will be
cycle. Closure plans will vary in detail carried out after closure, including
depending on the mine’s evolution While the exact contents of the plan monitoring, maintenance, and plans
in the LoA, and may be classified as will vary, almost all plans include for post-closure land use and/or
conceptual, preliminary, detailed or sections to address these four relinquishment.
concepts:
final.
Closure plans establish a defined
• Context: information describing the basis for closure cost estimates, which
Contents of a closure plan mine and the environment in which are based on the costs for carrying
The contents and organisation of it is situated. out closure activities. The tables
the closure plan may be dictated • Vision: a description of what the below summarise the recommended
or suggested by regulation in the final state of the site will be at final minimum closure plan contents and
jurisdiction or by corporate standards. closure, underpinned by more recommended additional closure plan
In some cases, it may be necessary to specific closure objectives. contents for good practice.

Recommended minimum closure plan contents

Section Content

Introduction Summary of the content of the plan.

Environmental context Description of the environment, including climate, geology, land use, surface
water, groundwater, flora/fauna, air quality and archaeology. This typically
refers to the baseline study, updated with information collected during
the operational life of the mine. The description may include traditional
knowledge where applicable and appropriate.

Socioeconomic context Description of the socioeconomic environment, including populations and


settlement patterns in the areas of influence, demographic data, land claims
(including indigenous land claims and traditional land tenure), livelihoods
and economy, natural resource use and cultural heritage. This typically
refers to baseline studies, updated with information collected during the life
of the mine.

Mine context Description of the mine, in terms of current installations and the
installations included in the LoM plan. The focus of this description is on the
extent and composition of the mine installations, and not on their functional
role.

126 Integrated mine closure: good practice guide


Section Content

Closure vision, post-closure land An overview of the closure vision, guiding principles and planned post-
use and closure approach closure land use. This should also include documentation of engagement
that has been done in the development of the closure approach.

Stakeholder engagement Documentation of all engagement conducted with stakeholders on the plan.
This can include a register of the instances of engagement, as well as a
summary of how engagement results were incorporated into the plan.

Risk and opportunity assessment Results of the risk assessments, either as a chapter integrated to the
structure of the closure plan or as an appendix that provides supporting
documentation and justification for choices made in the plan.

Closure activities Documents the closure activities that will be implemented as part of
progressive or final closure, often organised by mine installation and
domain. This includes plans or designs for the closure activities and may
include explicit identification of the objectives or risks that the closure
activities have been designed to address. It may also include lessons learned
through progressive closure activities and how those have influenced the
choice of final closure activity, trade-off studies conducted to evaluate
alternative activities and indications of how climate change considerations
were incorporated into design.

Success criteria and post-closure A description of the methods and duration of monitoring and maintenance
monitoring and maintenance activities to be carried out after implementation of the closure activities.
Monitoring is typically described with reference to the applicable success
criteria.

Cost estimate An estimate of the cost of implementing closure. This may be a calculation
of the financial assurance amount for regulatory documents or an estimate
of accounting provisions or LoM estimates for internally oriented closure
plans.

Recommended additional closure plan contents for good practice

Section Content

Plain language summary A plain language summary of the closure plan is good practice. This serves
as both a non-technical executive summary and as an aid to engagement
with stakeholders on the closure plan. It is good practice to translate this
summary into local language(s) where needed to help communicate the
plan to affected communities.

Regulatory framework/ A summary of the regulatory framework and commitments related to


commitments closure is useful to include in the closure plan. This provides a single
location where the regulatory constraints acting on the closure plan can be
summarised, including legally binding closure commitments made through
the environmental impact assessment process, as well as a registry of those
commitments made to external stakeholders.

Integrated mine closure: good practice guide 127


TOOL 12: CLOSURE PLAN
DOCUMENTATION

Section Content

Post-mine land use/relinquishment When significant work has been done to define the post- mine land use
or establish a clear pathway to relinquishment, it can be useful to have a
section of the closure plan that documents this.

Data management For internal use, it is good practice to have clear data management
protocols, which include monitoring data, research studies and results, as-
built information for completed progressive closure works, and stakeholder
engagement records, and to document this in the closure plan. Closure
plans may evolve over years or decades at a given site, and robust data
management protocols are needed to minimise the loss of information
through staff changes.

References It is good practice to track all the literature cited within the plan, including
scientific literature, guidelines, engineering designs, study reports and other
supporting documentation generated for the closure plan.

©Teck

128 Integrated mine closure: good practice guide


Updating the plan conceptual, pre-feasibility, feasibility reporting to document ongoing
and detailed design) rapidly, whereas information collection such as:
As is stressed throughout this guide,
closure designs for mines with very
closure planning is an iterative • reporting of results from ongoing
long lives may remain at a conceptual
process, and these iterations will be progressive closure
level for many years.
captured in progressive updates of the
• updates on closure plan
closure plan document. Update frequency: There is no hard optimisations and research
rule for the frequency of updating • documentation of ongoing
The broad trajectory of closure plan closure plans. Some jurisdictions
evolution over the LoM is expected to stakeholder engagement.
mandate the frequency of updates,
be from conceptual to detailed as the either directly or through permit Internally focused accounting
mine progresses towards final closure conditions. Typical industry and requirements may also require more
and rehabilitation. However, the regulatory practice is to update frequent updating of accounting
details of this progression will be site plans every three to five years, with provisions for closure – typically,
specific. Where significant progressive additional updates when there are accompanied by a report documenting
closure is undertaken, the aspects of major changes in the mine plan. In what has changed from the previous
the plan related to implementation many cases, companies will have estimate of the provision.
of progressive closure will advance their own internal LoM plans that are
to detailed design earlier. For mines updated on an annual basis. The following provides a list of typical
with short lives, closure designs will questions to ask when updating the
need to progress through the typical These required updates may be closure plan or to inform whether an
engineering design stages (such as supplemented by annual external update may be required.

Key questions to ask when updating the closure plan

Has the business plan changed (eg mining process, mine plan, scale or pace, different processing method,
amended mine waste disposal strategy, LoM, mining area)?

Have new environmental risks been identified (eg ARD/other leachate or seepage, topsoil loss, cumulative
impacts from surrounding development)?

Have new socioeconomic risks been identified (eg artisanal/illegal mining, social unrest)?

Have laws and regulations changed?

Have surrounding/local land use practices changed?

Has the rate of progressive closure been slower or faster than planned?

Have learnings from progressive closure resulted in changes to the plan?

Have unit rates or inputs such as fuel price significantly changed?

Have non-compliances or design changes occurred that indicate flaws in construction or operation (eg tailings
dam leak, waste dump stability angles)?

Have climatic conditions changed beyond design predictions? For example, have storms occurred during the
operating phase that will significantly revise the estimated design storms? (see also Tool 7: Climate change
and mine closure concerns)

Integrated mine closure: good practice guide 129


TOOL 12: CLOSURE PLAN
DOCUMENTATION

Key questions to ask when updating the closure plan

Have community structures, including population and demographics, and cultural considerations changed in
terms of either current status or predictions?

Have environmental or socioeconomic impacts been greater or less than predicted during the impact
assessment?

Have operating strategies’ impact on closure design changed?

Have benchmarking studies provided new/different ideas that should be considered?

Have long-term risks been effectively mitigated by the closure options or designs?

Post-closure documentation • as-built documentation criteria, in support of release of the


• summary of maintenance and financial assurance amount and/or
The final closure plan is typically
inspections works relinquishment of the site.
generated at the end of mine
operations. Additional documentation • monitoring reports with summaries Note that final closure and/or
related to the implementation of the of comparisons of monitoring relinquishment may take place at
closure plan is usually needed during results to success criteria. different times for different parts
and following implementation of the of the site, such that multiple
final closure activities, whether they The form this documentation takes relinquishment reports may be
are completed progressively or at the will vary according to the needs of the generated as different areas are
end of the mine life. jurisdiction and the mining company. relinquished or different portions
In an ideal process, post-closure of the financial assurance are
Post-closure documentation is reports will document progress released. Closure reports may also
needed for: towards meeting success criteria, be generated even when a formal
with a final closure or relinquishment relinquishment is not possible, in
• regulatory acceptance of the report documenting the completion of support of devolution of all or part
final closure the closure to the previously agreed of the financial assurance.
©Newmont

Educational facility at Waihi gold mine, New Zealand

130 Integrated mine closure: good practice guide


Acknowledgements
The development of this publication would not have been possible without the
input and support of the individuals below. ICMM gratefully acknowledges the
following contributions:

Consulting team Claudio Andrade (Barrick)


This report was developed in two Dave Bucar (GoldCorp)
phases. ERM supported the initial Amiel Boullemant (Rio Tinto)
phase of development under the Thomas Calhoun (Freeport-McMoRan)
guidance of Kylie Ashenbrenner Chris Cormier (GoldCorp)
and Scot Foster. Golder Associates Jon Crosby (MMG)
supported the second phase Klaus Eppinger (Newmont)
in finalising the document for Kim Ferguson (AngloGold Ashanti)
publication to which ICMM is Mark Freberg (Teck Resources)
indebted to Björn Weeks. Carl Grant (Anglo American)
Joanne Heyes (BHP)
ICMM team Thiess Lindsay (Newmont)
Dawn Brock led the process to Victoire Luquet de Saint Germain (Orano)
develop this guide, with input and Donna Noonan (MMG)
support from Nicky Black, Hannah Antje Nieder (Glencore)
Clayton, Roper Cleland, Aidan Davy, Darren Sharp (Rio Tinto)
Duncan Roberts and Hafren Williams. Charlene Wrigley (Gold Fields)
Peter Waters (South32)
Alice and Will Beaven (Positive 2) and
Nic Benton (ICMM) provided creative An independent peer review team
design support. from SMI CSRM including Nick
Bainton, Dr Jo-Anne Everingham,
Special thank you Dr Sarah Holcombe, Deanna Kemp,
The ICMM Closure Working Group Anna Littleboy, Sarah Mackenzie,
were key contributors to this John Owen and Dr Vlado Vivoda.
document. The group provided
direction, input and expert review to Andrew Brown (independent
the guide. Working group members consultant) and Matthew Bliss from the
included: Intergovernmental Forum who provided
helpful feedback on an advanced draft.

Integrated mine closure: good practice guide 131


ICMM is an international organisation
dedicated to a safe, fair, and
sustainable mining and metals industry.
Bringing together 27 companies –
and over 30 regional, national, and
commodities associations – we support
mining with principles to sustainably
manage the natural resources of our
planet, and enhance the wellbeing of
local communities.

35/38 Portman Sq. ICMM is committed to the environment.


London W1H 6LR
United Kingdom
+44 (0) 20 7467 5070
info@icmm.com
www.icmm.com
Printed by seacourt – proud to be counted amonsgt the top environmental printers in the world

Follow us:
@ICMM_com Published February 2019

132 Integrated mine closure: good practice guide

Potrebbero piacerti anche