Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
90-GT-72
345 E. 47 St., New York, N.Y. 10017
The Society shall not be responsible for statements or opinions advanced in papers or in dis-
cussion at meetings of the Society or of its Divisions or Sections. or printed in its publications.
Discussion ispanted only if the paper is published in an ASME Journal. Papers are available
e^ c) from ASME for fifteen months after the meeting.
Printed in USA
Copyright © 1990 by ASME
ABSTRACT
INTRODUCTION
A new 25MW class gas turbine H-25 has been The H-25 gas turbine features high thermal
developed to meet both 50 Hz and 60 Hz power efficiency of over 32% (LHV), with a turbine inlet
generation needs with high reliability and efficient temperature of 1260 ° C and a pressure ratio of 14.7.
performance utilizing advanced high temperature gas Figure 1 shows performance diagrams surveyed for the
turbine technologies. Because of its superior selection of cycle conditions. Since the thermal
performance, over 32% in simple cycle efficiency, the efficiency of gas turbines is highly dependent on the
H-25 gas turbine enables significant reduction of turbine inlet temperature and the pressure ratio,, the
fuel consumption compared with previous 25MW class optimum cycle conditions were selected based on the
turbines. The H-25 also achieves higher thermal diagrams [1]. The cycle conditions of the H-25 were
efficiency in a combined cycle power plant and a selected for both high specific power and high
cogeneration plant with a waste heat recovery boiler. thermal efficiency in simple-cycle operation and also
The first unit entered commercial operation at the for high combined-cycle or cogeneration thermal
end of November 1988 after full load factory test efficiency.
instrumented with more than 800 pieces of The H-25 has the following features
instrumentation. •' Generator terminal thermal efficiency of
This paper describes the design features and the over 32% (LHV) in simple-cycle operation.
latest technological refinements in each component of • Heavy-duty design for industrial use,
the H-25 gas turbine. Also presented are the permitting long term continuous operation.
component test programs and the results of full load • Good maintainability.
factory test and field test on the first unit.
48
34 Simple cycle 47 Combined cycle
o precooled cooling system H-25 design point o precooled cooling system
> 33 _--- --^ 5 46 Pressure ratio
OVERALL DESIGN
• Fuel flexibility from light distillate oil Figure 2 shows a cross section of the H-25 gas
and crude oil to natural gas. turbine. It is a single-shaft type heavy-duty gas
• Modular design requiring minimum field turbine, exclusively for power generation. The
installation. rotational speed is of 7280 RPM and the use of
• High cogeneration efficiency when combined reduction gearing enables it to drive both 50 Hz and
with a heat-recovery steam generator. 60 Hz generators. The rotor is a fully stacked
• Performance enhancement for existing MS5001 construction supported by two tilting-pad-type
gas turbine plants, through replacement with bearings. The thrust bearing is located on the
H-25 turbines. compressor end with eight shoes on both sides of the
The Table I shows principal specifications of bearing runner.
the H-25 gas turbine. Using natural gas as fuel, The compressor is a 17-stage axial type with
output at the generator terminals is 23,500 kW, with high pressure ratio, and the combustion system
a thermal efficiency of 32.3% (LHV). The H-25 is consists of 10 combustors with effective cooling
also available with an optional pre-cooling system construction for high firing-temperature operation.
which reduces cooling air temperature for the turbine The turbine has three stages designed with advanced
nozzle and bucket via an inter-cooler. With this cooling technologies [2].
system, output can be increased approximately 15%. A portion of the compressor discharge air is
used to cool the first and second-stage buckets and
first-stage nozzle. When the optional inter-cooler
is used, this air is extracted from the compressor
TABLE I Specifications of H-25 Gas Turbine discharge and cooled by the external air cooler, then
led into the turbine to cool the blades. The second-
stage nozzle and wheel space are cooled by the 11th
Type Standard type compressor extraction air, and third-stage nozzle and
With inter-
Specifi- (Without inter- wheel space are cooled by the 6th compressor
cooler
cation cooler) extraction air. Figure 3 shows the cooling circuit.
The horizontally split casings are adopted to
Fuel Natural gas Natural gas
facilitate field maintenance.
Output (kW) 23,500 26,770
Heat rate 2661 2637
(kcal/kW-h) (LHV)
Air flow (kg/s) 88 88
Exhaust 530 550
temperature (°C)
Rotating speed 7280
(r/mir.)
Compressor Axial type, 17 stages
Turbine Axial type, 3 stages
Combustor Reverse flow, 10 cans
Compressor
800
N
600
3R
VR
0
v
1R
400
^ 6
200
0
0
20 40 60 so 100 120 140
Cooling air
Multi-path serpentine
cooling passage
1
Cooling
air
Film cooling
; Cooling air
Fig. 8 Turbine First Stage Nozzle Fig. 9 Turbine First Stage Bucket
The H-25 rotor is a fully stacked disk assembly The first machine, connected with water-
with 17 compressor bladed disks, 3 turbine bladed dynamometer as a loading device, was tested under
disks and 2 spacer disks. The first-stage through various operating conditions.
16th-stage disks are of NiCrMoV or NiCrMo steel and A total of 812 instrumentation sensors were
stage 17th disk is of CrMoV steel. For the turbine installed on the first machine, 29 of these sensors
disks and spacers, newly developed 12CrNiM0VNb steel were instrumented for rotating components as shown in
was used. This new disk material has improved Table II. Rotating components instrumentation,
creep rupture strength and embrittlement toughness at thermocouples and strain gauges, were brought out
temperatures over 400 ° C. using the high-speed 100-channel slip ring at the
The rotor cooling air flows into 12 drilled- front end of the shaft.
holes and radial slots of the distance piece between Five desktop computers, composing a local area
compressor and turbine rotors. The air then flows network, were used to acquire, process, display and
into a chamber between first-stage and second-stage print the data to monitor the condition of each
disks through the rotor bore, and is supplied to component and part. Tests were performed using No.2
first-stage and second-stage buckets while it cools Distillate Fuel under the conditions below :
turbine disks during base load operation and warms up • Loading test, from no load to full load.
I Inlet guide vane modulation test for heat
during start-up. The air also cools a third-stage
disk and flows out to wheel space. A full-scale recovery cycle.
model rotor was made and tested to confirm the Steam injection for NOx control
characteristics of disk-cooling and warming and its During the tests, this machine experienced 146
capability of supplying cooling air (Figure 10). start/stop cycles and fired runs totaling 150 hours,
Pressure drops of the cooling air in the rotor and the measurements were performed so well that the
internal circuits and the flow stability was broken sensors numbered less than 1 percent.
confirmed in this test.
(1) Gas Turbine Performance
The power output and thermal efficiency of the
first H25 gas turbine achieved the design goal, and
the rating at the generator terminals, including
inlet/exhaust pressure losses, was committed as shown
in Table I .
Lens
Cooling and
— purge air ° Actuator
Mirror
Leading-edge side
1
Trailing-edge side (a) Spark probe setup
a 1.5f k
c : Cold clearance
a I-
C 1.0j /Turbine 1st stage blade
w 1 Revolution c u Compressor 2nd s`_age blade
a
C
a C
EMS
U 0.5
E aCU
m
0-
0 0 1 2 3
0.00
Time --^
l0.00. Time after Start (hour)
After the first H-25 gas turbine was completed (1) Physical Arrangement
and delivered to the site at the Tokuyama Refinery of Figure 17 shows the typical setup of an H-25 gas
Idemitsu Kosan Co., Ltd. in Japan, it was installed turbine. The H-25 is a modular design consisting of
in place of the MS5001 gas turbine which had been four packages : control compartment, gas turbine
operated for more than 100,000 hours over 13 years package, generator package, and generator auxiliary
[4). The existing cogeneration plant equipment, compartment. These packages are transported
except gas turbine, was re-utilized. Figure 16 shows separately and assembled at the installation site.
this H-25 cogeneration installation. Field tests It typically takes about 3.5 months for erection and
were carried out, and the results were quite testing.
successful under actual site conditions. Performance
and other gas turbine characteristics were as (2) Cogeneration
expected. This first unit started commercial Figure 18 shows the typical system arrangement
operation at the end of November 1988. This machine and layout of a cogeneration plant. The total
had successfully accomplished the first one-year base thermal efficiency of the H-25 cogeneration plant is
load operation. Four combustion inspections and higher than a conventional gas turbine cogeneration
bore-scope inspections were carried out periodically plant because of its higher exhaust temperature.
to confirm the condition of this first unit.
The inspection results were good with the (3) Replacement of MS5001 Gas Turbine
exception of small cracks on the fuel-nozzle swirler The H-25 gas turbine can be used not only for
tips. To correct this problem, the cooling of the new power plants, but also for replacement of
swirler tip was improved to prevent cracking. existing MS5001 gas turbines. In this case, fuel
The second machine was also installed at a consumption can be reduced by approximately 20%, and
refinery plant in Japan and started successful many existing components such as the generator, inlet
commercial operation as a new cogeneration plant in and exhaust facilities, and a variety of accessory
August 1989. The third unit will start the operation equipment can be re-used.
for cogeneration service in August 1990.
Process steam
DeNOx
Desuper heater
Fuel Exhaus t
Inlet air
Waste heat boiler
Fecd water
-
--- Generator
{ - - Electrical
room
_ 36 .5 _ Waste heat boiler
Stack
I i
Inlet filter
x Inlet duct
Exhaust duct
Inlet filter
GL
Exhaust
Package Weight (ton)
l) Control compartment to
0
2 Gas turbine package 87
0
3 Generator package 82 q ^ s ium
Generator auxiliary
13
(b) Layout
REFERENCES