Sei sulla pagina 1di 8

THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS

90-GT-72
345 E. 47 St., New York, N.Y. 10017
The Society shall not be responsible for statements or opinions advanced in papers or in dis-
cussion at meetings of the Society or of its Divisions or Sections. or printed in its publications.
Discussion ispanted only if the paper is published in an ASME Journal. Papers are available
e^ c) from ASME for fifteen months after the meeting.
Printed in USA
Copyright © 1990 by ASME

Development of a New 25MW High Efficiency


Heavy-Duty Gas Turbine H-25
HARUO URUSHIDANI
Deputy Manager, Thermal Power Plant Design Department
TETSUO SASADA
Engineer, Gas Turbine Design Section
Hitachi Works
MASAMICHI WADA
Manager, Power Generation & Delivery Division
KAZUHIKO KAWAIKE
Senior Researcher, Mechanical Engineering Research Laboratory
Hitachi, Ltd.
Tokyo and Hitachi, Japan

ABSTRACT
INTRODUCTION
A new 25MW class gas turbine H-25 has been The H-25 gas turbine features high thermal
developed to meet both 50 Hz and 60 Hz power efficiency of over 32% (LHV), with a turbine inlet
generation needs with high reliability and efficient temperature of 1260 ° C and a pressure ratio of 14.7.
performance utilizing advanced high temperature gas Figure 1 shows performance diagrams surveyed for the
turbine technologies. Because of its superior selection of cycle conditions. Since the thermal
performance, over 32% in simple cycle efficiency, the efficiency of gas turbines is highly dependent on the
H-25 gas turbine enables significant reduction of turbine inlet temperature and the pressure ratio,, the
fuel consumption compared with previous 25MW class optimum cycle conditions were selected based on the
turbines. The H-25 also achieves higher thermal diagrams [1]. The cycle conditions of the H-25 were
efficiency in a combined cycle power plant and a selected for both high specific power and high
cogeneration plant with a waste heat recovery boiler. thermal efficiency in simple-cycle operation and also
The first unit entered commercial operation at the for high combined-cycle or cogeneration thermal
end of November 1988 after full load factory test efficiency.
instrumented with more than 800 pieces of The H-25 has the following features
instrumentation. •' Generator terminal thermal efficiency of
This paper describes the design features and the over 32% (LHV) in simple-cycle operation.
latest technological refinements in each component of • Heavy-duty design for industrial use,
the H-25 gas turbine. Also presented are the permitting long term continuous operation.
component test programs and the results of full load • Good maintainability.
factory test and field test on the first unit.

48
34 Simple cycle 47 Combined cycle
o precooled cooling system H-25 design point o precooled cooling system
> 33 _--- --^ 5 46 Pressure ratio

° 14 —__— --^ H-25 design point


4
325 ' ' 16 14 12
o
44 '
1300
30 d 1 43 1200
2. 10 -- j
29 1000 11001200
" 42 1100
1300
F 29 Turbine inlet temperature (°C) 41 Turbine inlet temperature (°C)
1000
27 40
150 200 250 300 3_ 300 350 400 450 500
Specific power kW/kg.s Specific power kW/kg.s

Fig. 1 Gas Turbine Performance


*Presented at the Gas Turbine and Aeroengine Congress and Exposition—June 11-14, 1990—Brussels, Belgium

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


Fia. 2 H-25 Gas Turbine Cross Section

OVERALL DESIGN

• Fuel flexibility from light distillate oil Figure 2 shows a cross section of the H-25 gas
and crude oil to natural gas. turbine. It is a single-shaft type heavy-duty gas
• Modular design requiring minimum field turbine, exclusively for power generation. The
installation. rotational speed is of 7280 RPM and the use of
• High cogeneration efficiency when combined reduction gearing enables it to drive both 50 Hz and
with a heat-recovery steam generator. 60 Hz generators. The rotor is a fully stacked
• Performance enhancement for existing MS5001 construction supported by two tilting-pad-type
gas turbine plants, through replacement with bearings. The thrust bearing is located on the
H-25 turbines. compressor end with eight shoes on both sides of the
The Table I shows principal specifications of bearing runner.
the H-25 gas turbine. Using natural gas as fuel, The compressor is a 17-stage axial type with
output at the generator terminals is 23,500 kW, with high pressure ratio, and the combustion system
a thermal efficiency of 32.3% (LHV). The H-25 is consists of 10 combustors with effective cooling
also available with an optional pre-cooling system construction for high firing-temperature operation.
which reduces cooling air temperature for the turbine The turbine has three stages designed with advanced
nozzle and bucket via an inter-cooler. With this cooling technologies [2].
system, output can be increased approximately 15%. A portion of the compressor discharge air is
used to cool the first and second-stage buckets and
first-stage nozzle. When the optional inter-cooler
is used, this air is extracted from the compressor
TABLE I Specifications of H-25 Gas Turbine discharge and cooled by the external air cooler, then
led into the turbine to cool the blades. The second-
stage nozzle and wheel space are cooled by the 11th
Type Standard type compressor extraction air, and third-stage nozzle and
With inter-
Specifi- (Without inter- wheel space are cooled by the 6th compressor
cooler
cation cooler) extraction air. Figure 3 shows the cooling circuit.
The horizontally split casings are adopted to
Fuel Natural gas Natural gas
facilitate field maintenance.
Output (kW) 23,500 26,770
Heat rate 2661 2637
(kcal/kW-h) (LHV)
Air flow (kg/s) 88 88
Exhaust 530 550
temperature (°C)
Rotating speed 7280
(r/mir.)
Compressor Axial type, 17 stages
Turbine Axial type, 3 stages
Combustor Reverse flow, 10 cans

Note: Performance is net value at the generator


terminals and includes 3.5" H2O inlet and 11th stage Compressor discharge
2.5" H2O exhaust pressure drops at ISO
standard ambient condition. Fig. 3 Cooling Circuit

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


7^
COMMENT TECHNOLOGY

Compressor

The H-25 compressor is a 17-stage axial


compressor, which achieves a pressure ratio of 14.7
by applying a high rotational speed design approach.
Figure 4 shows a photograph of the compressor. A
variable inlet guide vane (VIGV) and selective bleeds
at the 6th and 11th stages provide an adequate surge
control during start-up. The corrected speed control
of the VIGV and bleed valves accomplishes an optimum
start-up sequence according to ambient temperature
variances. The extraction air flows at 6th and 11th
are supplied to the 2nd and 3rd turbine stages for
the nozzle and wheel space cooling.

Fig. 4 Compressor and Turbine
The H-25 compressor aerodynamic and mechanical
design is basically a scale-up design of a 17-stage
model compressor [3]. This model compressor was made Combustor
prior to the development of the H-25 and installed at
Hitachi's Gas Turbine Development (GTD) center, as an A dual-fuel system for gas and oil fuel is
air source for combustion test facilities. The available for the H-25 combustor, to meet the
aerodynamic performance and the dynamic behavior of
, customers' needs.
the compressor, such as surge margin, rotating stall To permit operation at a high firing
and blade dynamic stress, were confirmed through the temperature, effective cooling constructions have
test of this model compressor. The reliability was been adopted for each part of the combustor. Figure
also confirmed through five-year operation in GTD 6 shows a sectional view of the combustor.
center. Compressor discharge air then flows into the space
Careful attention was paid to dynamic between the flow sleeve and the transition piece,
characteristics of the H-25's first three rotor cooling the surface of the transition piece.
blades, and a full-scale wheel-box test was Additional film cooling is provided especially for
performed. Figure 5 shows a full-scale wheel-box hot sections of the transition piece. For the
test facility and Campbell diagram of the first three combustion liner, slot cooling ( a kind of film
rotor blades acquired using telemetry systems. It is cooling) is used in combination with convection
clear that none of the blades have resonances in cooling enforced by the external flow sleeve.
operating speed. Figure 7 shows a photograph of the combustion
For the materials of the H-25 compressor blades, liner. This compact combustion liner has about a 30
12Cr-Nb stainless steel has been applied to the VIGV percent volume in comparison with conventional liners
and the 1st through 5th stage rotor blades. The 12Cr which operate at a firing temperature of under
stainless steel was applied for all stator blades and 1000°C. The aim is to reduce the cooled surface area
the 7th through 17th rotor blades. The 1st through and the cooling flow rate, while maintaining
8th stage rotor and stator blades are coated with combustion heat loads at the same level as
NiCd to enhance corrosion resistance. conventional combustion liners.

800

N
600
3R
VR
0
v
1R
400

^ 6

200

0
0
20 40 60 so 100 120 140

Rotor Speed (rps)



(a) Full-scale test rotor (b) Campbell diagram

Fig. 5 Compressor Rotor Wheel Box Test

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


The first-stage nozzle is single-vane design
Combustion liner Transition piece with minimized thermal stresses, and second and
Slot cooling &
third-stage nozzles are two-vane segment design.
convection( Convection cooling
The first stage buckets and nozzles, which
cooling & film cooling
(
operate in especially high gas temperature
conditions, are provided with advanced cooling
a\ Flow sleeve technologies (21.
Figure 8 shows an external view of the first
stage turbine nozzle and its internal cooling
configuration as well. The cooling system combines
impingement cooling, film cooling, and pin-fin
cooling. The interior is divided into two chambers
containing perforated inserts. Cooling air flows
into the inserts from the exterior, and jets out
through the small holes onto the nozzle's inner
surface, thereby achieving effective impingement
cooling. After cooling the inner surface, part of
the air blows out to the gas passage through film
Compressor discharge air cooling holes in the nozzle, forming a cooling air
film on the exterior surface. The remaining cooling
Fig. 6 Sectional View Fig. 7
air blows out to the gas passage through a pin-fin
of Combustor Combustion Liner cooling channel at the trailing edge.
Figure 9 shows an exterior view of the first
stage turbine bucket and its internal cooling
configuration. The cooling air comes in at the
The material of the combustion liner and bottom of the bucket and branches into front and rear
transition piece is Ni-base superalloy, and the inner flow paths. It flows outward in both paths, then
surface of the transition piece is coated with a inward after turning 180° at the blade tip. The
ceramic thermal barrier coating. For NOx control, paths both turn again at the root of the blade, and
steam is injected through a nozzle attached at the then the front path leads out into the gas passage
combustion case cover. from the tip of the blade, while the rear flow enters
During the component development stage, the the gas passage via the trailing edge of the blade.
combustor was tested under actual operating Cooling effectiveness is increased by turbulence-
conditions of flow rate, pressure, firing temperature promoter fins installed on the inner surface of the
and so on at a full-scale combustor test facility in channels.
Hitachi's GTD center. An optimization of combustion A prototype model of the first-stage turbine was
and dilution air is accomplished through this test in made and its performance was tested. Turbine blade
combination with single-type fuel nozzle. Combustion cooling efficiency and aerodynamic characteristics
characteristics, reliability such as metal were both confirmed in these tests.
temperature and dynamic behavior, and the effect of A newly developed cobalt-base (Co-base)
steam injection were also confirmed. corrosion-resistant superalloy was used for the
first-stage nozzles. This new alloy has enhanced
Turbine creep-rupture strength about 30 percent in comparison
with FSX-414 Co-base alloy. For the turbine bucket
The 525 turbine is a low-reaction three-stage materials, the Ni-base superalloy was used. In order
design which brings low heat loads to rotor buckets. to prevent hot corrosion and oxidation, the first-
The first-stage bucket is free-standing construction stage buckets are coated with improved Co, Ni, Cr,
and the second and third-stage buckets are Al, and Y metal coating using low pressure plasma
continuously connected with Z tip shrouds. spray technique.

Cooling air
Multi-path serpentine
cooling passage

1
Cooling
air
Film cooling

; Cooling air

Forward cooling Afterw^


passage cooling
Pin-fin cooling passage
Impingement
cooling
Film cooling
Cooling air

Fig. 8 Turbine First Stage Nozzle Fig. 9 Turbine First Stage Bucket

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


Rotor Factory Test Results

The H-25 rotor is a fully stacked disk assembly The first machine, connected with water-
with 17 compressor bladed disks, 3 turbine bladed dynamometer as a loading device, was tested under
disks and 2 spacer disks. The first-stage through various operating conditions.
16th-stage disks are of NiCrMoV or NiCrMo steel and A total of 812 instrumentation sensors were
stage 17th disk is of CrMoV steel. For the turbine installed on the first machine, 29 of these sensors
disks and spacers, newly developed 12CrNiM0VNb steel were instrumented for rotating components as shown in
was used. This new disk material has improved Table II. Rotating components instrumentation,
creep rupture strength and embrittlement toughness at thermocouples and strain gauges, were brought out
temperatures over 400 ° C. using the high-speed 100-channel slip ring at the
The rotor cooling air flows into 12 drilled- front end of the shaft.
holes and radial slots of the distance piece between Five desktop computers, composing a local area
compressor and turbine rotors. The air then flows network, were used to acquire, process, display and
into a chamber between first-stage and second-stage print the data to monitor the condition of each
disks through the rotor bore, and is supplied to component and part. Tests were performed using No.2
first-stage and second-stage buckets while it cools Distillate Fuel under the conditions below :
turbine disks during base load operation and warms up • Loading test, from no load to full load.
I Inlet guide vane modulation test for heat
during start-up. The air also cools a third-stage
disk and flows out to wheel space. A full-scale recovery cycle.
model rotor was made and tested to confirm the Steam injection for NOx control
characteristics of disk-cooling and warming and its During the tests, this machine experienced 146
capability of supplying cooling air (Figure 10). start/stop cycles and fired runs totaling 150 hours,
Pressure drops of the cooling air in the rotor and the measurements were performed so well that the
internal circuits and the flow stability was broken sensors numbered less than 1 percent.
confirmed in this test.
(1) Gas Turbine Performance
The power output and thermal efficiency of the
first H25 gas turbine achieved the design goal, and
the rating at the generator terminals, including
inlet/exhaust pressure losses, was committed as shown
in Table I .

(2) Turbine Blade Metal Temperatures


Three pyrometers were used to measure the
turbine blade metal temperatures of the first and the
second stage blades, together with thermocouples
through slip ring. For the first-stage blades with
serpentine cooling passages, the metal temperature
was detected both from leading-edge and trailing-edge
sides using sighting tube with Pt-Ro mirror. Cooling
air was supplied to cool and purge the lens and
mirror (Figure 11).
Figure 12 shows the results of pyrometric
measurement and reveals that the metal temperatures
were well within the allowable temperature, while the
maximum temperature spread between individual blades
was 25 ° C.
(a) Full-scale test rotor
Table II Summary of Factory Test
Instrumentation

Thermocouples 425 points


Pressure taps to measure 231
static/dynamic pressure
Pyrometer to detect blade 3
temperatures
Strain gauges to measure 41
dynamic stresses
Acceleration probes 2
• Tip clearance probes 4
Shaft vibration and 58
displacement probes
Load cell to measure 2
thrust loads
(b) Cross section of test rotor
• Acoustic emission probes 2
to detect rubbing
Fig. 10 Testing Apparatus of Cooling Air
• Miscellaneous 44
Supply System ( Total instrumentation 812

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


Figure 13 shows the comparison between
prediction of metal temperatures and those by
thermocouples. The comparison shows good agreements
between the predictions and the measured results, Measurement
excepting the pressure-side point. O
The cause of the discrepancy on the pressure-
side point is estimated to be due to flow disturbance
w
when the blades cut the upstream nozzle wake, which
40 O
greatly affects the heat transfer rate of pressure
side of the downstream blades.
a
m
a Prediction
(3) Combustor Metal Temperatures e
w
E
Figure 14 shows the outer metal temperature
distribution of the combustor liner and transition Suction side Pressure side
piece. The data shows that the metal temperatures
were well below the design goal.
Trailing Edge Leading Edge T.E.
(4) Tip Clearance Measurement Blade surface position
Tip clearances of both compressor and turbine
blades were measured by the use of four spark type
tip clearance probes. Fig. 13 1st Stage Blade Metal Temperature
Figure 15 shows the variation of tip clearances of
second-stage compressor bladesand first-stage turbine
buckets, from start to full load.
The pinch point was found at transient and steady Allowable temp.
condition, which was strongly dependent on the U 110 I Measured region
a Q
thermal response of the rotor-casing interaction. U 0 9
After the scheduled tests were completed, the J

first machine was disassembled and carefully MS -IW

inspected. The machine and each component were in a


very good condition without the necessity of ^m o
modification. MS
a)
0 2W iW (44) MW I,WII

Distance from combustor front end

Fig. 14 Metal Temperature of Combustor


Pyrometer 1 2 3

Lens
Cooling and
— purge air ° Actuator

Mirror

(a) Installation of pyrometer (b) Sighting tube


Fig. 11 Pyrometric Measurements of Blade Temperature Purge N 2 gas

Leading-edge side

1
Trailing-edge side (a) Spark probe setup

a 1.5f k
c : Cold clearance
a I-
C 1.0j /Turbine 1st stage blade
w 1 Revolution c u Compressor 2nd s`_age blade
a
C
a C
EMS
U 0.5
E aCU
m
0-

0 0 1 2 3
0.00
Time --^
l0.00. Time after Start (hour)

Fig. 12 Pyrometric Temperature Measurements (b) Test results


of Turbine 1st Blade Fig. 15 Blade Tip Clearance Measurement

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


FIELD TEST AND OPERATION APPLICATION

After the first H-25 gas turbine was completed (1) Physical Arrangement
and delivered to the site at the Tokuyama Refinery of Figure 17 shows the typical setup of an H-25 gas
Idemitsu Kosan Co., Ltd. in Japan, it was installed turbine. The H-25 is a modular design consisting of
in place of the MS5001 gas turbine which had been four packages : control compartment, gas turbine
operated for more than 100,000 hours over 13 years package, generator package, and generator auxiliary
[4). The existing cogeneration plant equipment, compartment. These packages are transported
except gas turbine, was re-utilized. Figure 16 shows separately and assembled at the installation site.
this H-25 cogeneration installation. Field tests It typically takes about 3.5 months for erection and
were carried out, and the results were quite testing.
successful under actual site conditions. Performance
and other gas turbine characteristics were as (2) Cogeneration
expected. This first unit started commercial Figure 18 shows the typical system arrangement
operation at the end of November 1988. This machine and layout of a cogeneration plant. The total
had successfully accomplished the first one-year base thermal efficiency of the H-25 cogeneration plant is
load operation. Four combustion inspections and higher than a conventional gas turbine cogeneration
bore-scope inspections were carried out periodically plant because of its higher exhaust temperature.
to confirm the condition of this first unit.
The inspection results were good with the (3) Replacement of MS5001 Gas Turbine
exception of small cracks on the fuel-nozzle swirler The H-25 gas turbine can be used not only for
tips. To correct this problem, the cooling of the new power plants, but also for replacement of
swirler tip was improved to prevent cracking. existing MS5001 gas turbines. In this case, fuel
The second machine was also installed at a consumption can be reduced by approximately 20%, and
refinery plant in Japan and started successful many existing components such as the generator, inlet
commercial operation as a new cogeneration plant in and exhaust facilities, and a variety of accessory
August 1989. The third unit will start the operation equipment can be re-used.
for cogeneration service in August 1990.

Process steam

DeNOx
Desuper heater

Fuel Exhaus t

Inlet air
Waste heat boiler
Fecd water

I!-25 gas turbine Generator

(a) System arrangement

Fig.16 H-25 Cogeneration Plant,Tokuyama,Japan H-25 gas turbine


Oil tank Inlet filter

-
--- Generator

t E Fuel forwarding pump

{ - - Electrical
room
_ 36 .5 _ Waste heat boiler
Stack
I i
Inlet filter
x Inlet duct
Exhaust duct
Inlet filter

Oil tank Generator

GL

Exhaust
Package Weight (ton)
l) Control compartment to
0
2 Gas turbine package 87
0
3 Generator package 82 q ^ s ium
Generator auxiliary
13
(b) Layout

Fig. 17 Machine Arrangement Fig. 18 Typical System Arrangement and Layout

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use


CONCLUSION

A new 25MW class gas turbine H-25 was developed


and the features of this gas turbine were described.
The results of the factory test and the field
test showed that the H-25 achieved the highest level
of performance among existing 25MW class of heavy-
duty gas turbines, and design goals concerning
reliability such as hot parts metal temperatures were
well satisfied.
The first unit of H-25 started commercial
operation at the end of November 1988, and has now
operated continuously over 7,100 hours for one year.
The inspection results showed good reliability of
this machine under actual operating condition.
We intend to accumulate on-site operation
records of this gas turbine while complying with
customers' various needs.

REFERENCES

(1) K. Kawaike et al., "Effect of New Blade Cooling


System with Minimized Gas Temperature Dilution
on Gas Turbine Performance," Journal of
Engineering for Gas Turbines and Power, Trans,
ASME 106, No. pp.756-764 (Oct.1984)[84-GT-89]

(2) M. Shizuya and K. Kawaike, "Experimental


Investigation of Blade Internal Cooling Methods
Using Ribs and Fins", Proceedings of the 1987
Tokyo International Gas Turbine Congress III
pp.159-166 (Oct. 1987) [87-TOKYO-IGTCD-65].

(3) Y. Kashiwabara et al., "Development of a High-


Pressure-Ratio Axial Flow Compressor for a
Medium-size Gas Turbine" Journal of
Turbomachinery, Trans. ASME 108 pp. 233-239
(Oct. 1986)[86-GT-85]

(4) R. Furukawazono et al., "A Prototype Replacement


of a 100,000 Hours Operation, 25,000 kW Gas
Turbine at Idemitsu Kosan Co., Ltd." ASME Gas
Turbine and Aeroengine Congress and Exposition
(Jun. 1989) [89-GT-26]

Downloaded From: https://proceedings.asmedigitalcollection.asme.org on 06/22/2019 Terms of Use: http://www.asme.org/about-asme/terms-of-use

Potrebbero piacerti anche