4.5.3 Procedure for Incident OHS/P12
t no.
Investigation, Non-conformance, Rev no. 02
Corrective & Preventive action Date 20/06/2015
Page 1 of 8
PURPOSE:
To establish and maintain procedures for defining responsibilities &
authorities for:-
Handling & investigation of incident & non conformance.
Taking Corrective & Preventive Action.
To define the method of reporting Incidents occurring in the organization
and to prevent recurrence by improving working condition actions and
supervision as a part of Safety Management systems
SCOPE:
This document is valid for the scope mentioned in the Apex Manual.
RESPONSIBILITIES:
Safety Officer & MA, Dept. Head
PROCEDURE:
Incident Investigation: -
This procedure describes how to record, investigate and analyze the
incident in order to
1. Determine underlying OH&S deficiencies and other factors that
might be causing or contributing to the occurrence of incidents;
2. Identify the need for corrective action;
3. Identify opportunities for preventive action;
4. Identify opportunities for continual improvement;
5. Communicate the results of such investigations.
Prepared by Approved by
Signature
1
Thermax Engineering Construction Co. Ltd
Documen
4.5.3 Procedure for Incident OHS/P12
t no.
Investigation, Non-conformance, Rev no. 02
Corrective & Preventive action Date 20/06/2015
Page 2 of 8
Major Incident:
Near Miss:
Any occurrence which could have resulted in an Incident but was
prevented.
1. At site
2
Thermax Engineering Construction Co. Ltd
4.5.3 Procedure for Incident Documen
OHS/P12
Investigation,
2.0Scope 3.0Why isNon-conformance,
it required? t no.
Rev no. 02
Corrective & Preventive action
Date 20/06/2015
Page 3 of 8
Definition of an Incident:-
1.0 Summary
This procedure is applicable for all accidents, incidents and near misses
that involve THERMAX employees, and non-THERMAX employees
present on, or affected by THERMAX operations, namely, contractors,
visitors and members of the public. It describes the reporting and
investigation process to be followed, identifies the persons responsible
for its implementation, and the timescales for completion.
3
Thermax Engineering Construction Co. Ltd
4.5.3 Procedure for Incident Documen
OHS/P12
Investigation,
4.0What needs to beNon-conformance,
done ? t no.
Rev no. 02
Corrective & Preventive action
Date 20/06/2015
Page 4 of 8
4
Thermax Engineering Construction Co. Ltd
Documen
4.5.3 Procedure for Incident OHS/P12
t no.
Investigation, Non-conformance, Rev no. 02
Corrective & Preventive action Date 20/06/2015
Page 5 of 8
4.3 Investigation
The relevant Site in-charge/ Section Head/Dept. Head must initiate the
site investigation and will decide whether any additional internal or
external support is required. The HO Team shall visit the site and then
5
Thermax Engineering Construction Co. Ltd
4.5.3 Procedure for Incident Documen
OHS/P12
Investigation,
5.0 Who should do it? Non-conformance, t no.
Rev no. 02
Corrective & Preventive action
Date 20/06/2015
Page 6 of 8
6
Thermax Engineering Construction Co. Ltd
Documen
4.5.3 Procedure for Incident OHS/P12
t no.
Investigation, Non-conformance, Rev no. 02
Corrective & Preventive action Date 20/06/2015
Page 7 of 8
7
Thermax Engineering Construction Co. Ltd
Documen
4.5.3 Procedure for Incident OHS/P12
t no.
Investigation, Non-conformance, Rev no. 02
Corrective & Preventive action Date 20/06/2015
Page 8 of 8
Preventive action:
1. Analyze all processes to eliminate potential causes of non-Conformances.
2. Initiate Preventive Actions.
3. Ensure that the Preventive Actions are effective.
4. The findings of Internal OH & S Audit also forms input for taking necessary
Corrective / Preventive Actions.
DOCUMENT GENERATED:-
1. Incident recording document Doc. No. OHS/D24
2. Incident investigation report Doc. No. OHS/D25