PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT PILING WORKS : 150mm x 150mm Pre-Cast R.C. Piles Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

PILING WORKS (All Provisional)

PILING PLANT AND EQUIPMENT

1.00 Allow for the provision of all necessary piling Item 1.00 15,000.00 15,000.00
equipment, plant, tools and ancillary Fair Rate
equipment and for their transportation to
site, handling, assembling, erecting,
dismantling and removal on completion

1.00 Allow for moving, handling and maintaining Item 1.00 5,000.00 5,000.00
piling equipment, plant tools and ancillary Fair Rate
equipment about the site as often and
whenever necessary for the execution of the
whole piling operation including any
excavation and filling required for moving the
plant, tools and ancillary equipment from
differing levels of the site, erection of any
staging required, installing piles on
embankments or slopes and dismantling and
removal on completion and all idling time.

1.00 Allow for the submission of records of all piles Item 1.00 200.00 200.00
in five (5) copies duly signed by the Fair Rate
Contractor and the Consultant's
Representative and delivered to the
Superintending Officer as the work proceeds.

PRE-CAST REINFORCED CONCRETE PILES

Supply, deliver and unload on site 150mm x no. 8.00 186.00 1,488.00
150mm x 6.0m long Preliminary Pre-cast R.C. SOR 2015
Piles as specified complete with head and
shoe all as per Engineer's drawings.

4
2.00 Type P2
8.00 - 2 points per pile cap

Extension pile = 6.0m

Extension pile = 6.0m

Initial pile with shoe = 6.0m

1 point
Total Carried To Summary 21,688.00
PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT PILING WORKS : 150mm x 150mm Pre-Cast R.C. Piles Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

PILING WORKS (All Provisional) (Cont'd)

PRE-CAST REINFORCED CONCRETE PILES

Supply, deliver and unload on site 150mm x m 96.00 31.00 2,976.00


150mm x 6.0m long Extension Pre-cast R.C. SOR 2015
Piles exceeding 3.00m as specified all as per
Engineer's drawing.
4
2
12.00 Type P2 Length (m)
96.00 - 2 nos per point 2/ 6.00
12.00

Drive only vertical 150mm x 150mm Pre-cast m 144.00 13.30 1,915.20


4 R.C. Piles SOR 2015
2
18.00 Type P2 Length (m)
144.00 - 3 nos per point 3/ 6.00
18.00

4 Pile extension joints no. 16.00 24.20 387.20


2 SOR 2015
2.00 Type P2
16.00 - 2 joints per point

Cutting off top of pile to required level no. 8.00 62.80 502.40
including prepare concrete pile head and SOR 2015
reinforcement for capping

4
2.00 Type P2
8.00 - 2 points per pile cap

PILE TESTING

Pile Driving Analyser (PDA)

1.00 Providing all necessary plant, equipment, Item 1.00 6,000.00 6,000.00
labour, etc. and carry out one (1) no. of Pile Fair Rate
Driving Analyser (PDA) in compliance to
specification on working pile including
standing time, supervision and submission of
analysis and test report all to satisfaction of
the Engineer as specified in Engineer's
drawing.

END OF PILING WORKS

Total Carried To Summary 11,780.80


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT PILE CAP : 1060mm (L) x 460mm (W) x 600mm (D) Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional)

Excavation pit for pile cap not exceeding m³ 2.24 18.10 40.54
2.00m deep, commencing from formation SOR 2015
level, get out, part return, fill in and ram and
remove surplus excavated materials off the
site to Contractor's own dump site :

4 Type P2 Length (m)


1.06 1060.00
0.46
1.15 Width (m)
2.24 460.00

Depth (m)
Add : 600.00
Column Stump 500.00
50mm thk. Lean Conc. 50.00
1150.00

50mm thk plain in-situ concrete; BS 5328 m² 1.95 11.60 22.62


Grade 15 as described in blinding to receive SOR 2015
pile cap
(Pro-rata Rate)

4 Type P2 Length (m)


1.06 1060.00
0.46
1.95 Width (m)
460.00

Reinforced concrete; BS5328 designed mix m³ 1.17 303.40 354.98


Grade 25 (1:1½:3 - 20mm aggregate) as SOR 2015
specified in pile cap.

4 Type P2 Length (m)


1.06 1060.00
0.46
0.60 Width (m)
1.17 460.00

Depth (m)
600.00

Total Carried To Summary 418.14


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT PILE CAP : 1060mm (L) x 460mm (W) x 600mm (D) Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

12mm Ø high tensile bar reinforcement to kg 68.13 3.60 245.27


BS4449 as described in pile cap. SOR 2015

4
5 Type P2 : 5T12 Length (m)
2.03 2/ 600.00
40.60 1060.00
kg/m 0.888 2260.00
36.05 Ddt :
50mm top conc. cover 2/ 50.00
25mm bottom conc. cover 2/ 25.00
75mm pile head 2/ 75.00
25mm conc. cover b/side 2/ 25.00
1910.00
Add :
Bend 5D = 5(12) 2/ 120.00
2030.00

4
7 Type P2 : 7T12 Length (m)
0.41 460.00
11.48 Ddt : 25mm conc. cover 2/ 25.00
kg/m 0.888 410.00
10.19

Total Carried To Summary 245.27


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT PILE CAP : 1060mm (L) x 460mm (W) x 600mm (D) Page : 3

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

12mm Ø high tensile bar reinforcement to


BS4449 as described in pile cap.
4
2 Type P2 : 2T12 Loops Length (m)
3.08 2/ 1060.00
24.64 2/ 460.00
kg/m 0.888 3040.00
21.88 Ddt : 25mm conc. cover 8/ 25.00
2840.00
Add :
Bend 5D = 5(12) 4/ 240.00
3080.00

Total (kg)
a) Type P2 : 5T12 36.05
b) Type P2 : 7T12 10.19
c) Type P2 : 2T12 Loops 21.88
68.13

Sawn formwork to sides of pile cap m² 7.30 25.70 187.61


SOR 2015
4 Type P2 Girth (m)
3.04 2/ 1060.00
0.60 2/ 460.00
7.30 3040.00

Height (m)
600.00

END OF PILE CAP WORKS

Total Carried To Summary 187.61


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN STUMP : 300mm (L) x 150mm (W) Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional)

Reinforced concrete; BS5328 designed mix m³ 0.09 303.40 27.31


Grade 25 (1:1½:3 - 20mm aggregate) as SOR 2015
specified in column stump.

4 Type P2 Length (m)


0.30 300.00
0.15
0.50 Width (m)
0.09 150.00

Depth (m)
900.00
Ddt : Grd. Beam 400.00
500.00

12mm Ø high tensile bar reinforcement to kg 53.28 3.60 191.81


BS4449 as described in column stump. SOR 2015
4
6 Type P2 : 6T12
2.50 Length (m)
60.00 Lapping in column 36D = 36(12) 432.00
kg/m 0.888 Grd beam 400.00
53.28 Stump 500.00
Pile cap (vertical) 600.00
Pile cap (horizontal) 150.00
2082.00
Ddt :
75mm pile head 75.00
25mm bottom conc. cover 25.00
12mm rebar 2/ 12.00
1958.00
Add :
Bend 5D = 5(12) 60.00
Lapping 40D = 40(12) 480.00
2498.00

Total Carried To Summary 219.11


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN STUMP : 300mm (L) x 150mm (W) Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

6mm Ø mild steel bar reinforcement to kg 11.99 3.50 41.97


BS4449 as link as described in column stump. SOR 2015
4
16 Type P2 : R6 - 125 c/c
0.84 Girth (m)
54.02 2/ 300.00
kg/m 0.222 2/ 150.00
11.99 900.00
Ddt : 25mm conc. cover 8/ 25.00
700.00
Add : Binder 24D = 24(6) 144.00
844.00

Height (m)
Lapping in column 36D = 36(12) 432.00
Grd beam 400.00
Stump 500.00
Pile cap (vertical) 600.00
1932.00
Ddt :
75mm pile head 75.00
25mm bottom conc. cover 25.00
12mm rebar 2/ 12.00
1808.00
Bil. of link
= 1808mm ÷ 125mm c/c +1
= 15.46
≈ 16 nos

Sawn formwork to sides of column stump m² 1.80 25.70 46.26


SOR 2015
4 Type P2 Girth (m)
0.90 2/ 300.00
0.50 2/ 150.00
1.80 900.00

Height (m)
500.00

END OF COLUMN STUMP WORKS

Total Carried To Summary 88.23


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional)

Excavation trench for ground beam not m³ 1.24 12.60 15.62


exceeding 1.00m deep, commencing from SOR 2015
formation level, get out, part return, fill in and
ram and remove surplus excavated materials
off the site to Contractor's own dump site :

2 Length (m)
5.15 GB1 & GB3 3000.00
0.15 2000.00
0.40 Add: 2/ 75.00
0.62 5150.00

Width (m)
150.00

Depth (m)
400.00

1.85 GB2 Length (m)


0.15 2000.00
0.40 Ddt : 2/ 75.00
0.11 1850.00

Width (m)
150.00

Depth (m)
400.00

Total Carried To Summary 15.62


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

Excavation trench for ground beam not


exceeding 1.00m deep, commencing from
formation level, get out, part return, fill in and
ram and remove surplus excavated materials
off the site to Contractor's own dump site :

3 Length (m)
2.85 GB4, GB5 & GB6 1800.00
0.15 1200.00
0.40 Ddt : 2/ 75.00
0.51 2850.00

Width (m)
150.00

Depth (m)
400.00

Total (m³)
a) GB1 & GB3 0.62
b) GB2 0.11
c) GB4, GB5 & GB6 0.51
1.24

Reinforced concrete; BS5328 designed mix m³ 1.24 303.40 376.22


Grade 25 (1:1½:3 - 20mm aggregate) as SOR 2015
specified in ground beam.

2 Length (m)
5.15 GB1 & GB3 3000.00
0.15 2000.00
0.40 Add : 2/ 75.00
0.62 5150.00

Width (m)
150.00

Depth (m)
400.00

Total Carried To Summary 376.22


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 3

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

Reinforced concrete; BS5328 designed mix


Grade 25 (1:1½:3 - 20mm aggregate) as
specified in ground beam.

1.85 GB2 Length (m)


0.15 2000.00
0.40 Ddt : 2/ 75.00
0.11 1850.00

Width (m)
150.00

Depth (m)
400.00

3 Length (m)
2.85 GB4, GB5 & GB6 1800.00
0.15 1200.00
0.40 Ddt : 2/ 75.00
0.51 2850.00

Width (m)
150.00

Depth (m)
400.00

Total (m³)
a) GB1 & GB3 0.62
b) GB2 0.11
c) GB4, GB5 & GB6 0.51
1.24

Total Carried To Summary -


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 4

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

12mm Ø high tensile bar reinforcement to kg 20.85 3.60 75.06


BS4449 as described in ground beam. SOR 2015

2 GB1 & GB3 - 2T12


2 (Top Rebar) Length (m)
5.87 3000.00
23.48 2000.00
kg/m 0.888 Column Stump 2/ 75.00
20.85 Rebar (vertical) 2/ 325.00
≈ ( 400-(2x25)-25 = 325 ) 5800.00
Ddt :
25mm conc. cover b/side 2/ 25.00
5750.00
Add :
Bend 5D = 5(12) 2/ 60.00
5870.00

16mm Ø high tensile bar reinforcement to kg 37.30 3.40 126.82


BS4449 as described in ground beam. SOR 2015

2 GB1 & GB3 - 2T16


2 (Bottom Rebar) Length (m)
5.91 3000.00
23.64 2000.00
kg/m 1.578 Column Stump 2/ 75.00
37.30 Rebar (vertical) 2/ 325.00
≈ ( 400-(2x25)-25 = 325 ) 5800.00
Ddt :
25mm conc. cover b/side 2/ 25.00
5750.00
Add :
Bend 5D = 5(16) 2/ 80.00
5910.00

Total Carried To Summary 201.88


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 5

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

10mm Ø mild steel bar reinforcement to kg 26.73 3.40 90.88


BS4449 as stirrups as described in ground SOR 2015
beam.

2
19 GB1 & GB3 : R10 - 275 c/c
1.14 Girth (m)
43.32 2/ 150.00
kg/m 0.617 2/ 400.00
26.73 1100.00
Ddt : 25mm conc. cover 8/ 25.00
900.00
Add : Binder 24D = 24(10) 240.00
1140.00

Length (m)
3000.00
2000.00
Ddt : Column Stump 2/ 75.00
4850.00
Bil. of link
= 4850mm ÷ 275mm c/c +1
= 18.64
≈ 19 nos

Total Carried To Summary 90.88


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 6

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

12mm Ø high tensile bar reinforcement to kg 10.19 3.60 36.68


BS4449 as described in ground beam. SOR 2015

GB2 - 2T12
4 (Top & Bottom Rebar) Length (m)
2.87 2000.00
11.48 Column Stump 2/ 75.00
kg/m 0.888 Rebar (vertical) 2/ 325.00
10.19 ≈ ( 400-(2x25)-25 = 325 ) 2800.00
Ddt :
25mm conc. cover b/side 2/ 25.00
2750.00
Add : Bend 5D = 5(12) 2/ 60.00
2870.00

10mm Ø mild steel bar reinforcement to kg 5.63 3.40 19.14


BS4449 as stirrups as described in ground SOR 2015
beam.

8 GB2 : R10 - 275 c/c


1.14 Girth (m)
9.12 2/ 150.00
kg/m 0.617 2/ 400.00
5.63 1100.00
Ddt : 25mm conc. cover 8/ 25.00
900.00
Add : Binder 24D = 24(10) 240.00
1140.00

Length (m)
2000.00
Ddt : Column Stump 2/ 75.00
1850.00
Bil. of link
= 1850mm ÷ 275mm c/c +1
= 7.73
≈ 8 nos

Total Carried To Summary 55.83


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 7

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

12mm Ø high tensile bar reinforcement to kg 20.62 3.60 74.23


BS4449 as described in ground beam. SOR 2015

3 GB4, GB5 & GB6 - 2T12


2 (Top Rebar) Length (m)
3.87 3000.00
23.22 Column Stump 2/ 75.00
kg/m 0.888 Rebar (vertical) 2/ 325.00
20.62 ≈ ( 400-(2x25)-25 = 325 ) 3800.00
Ddt :
25mm conc. cover b/side 2/ 25.00
3750.00
Add : Bend 5D = 5(12) 2/ 60.00
3870.00

16mm Ø high tensile bar reinforcement to kg 37.02 3.40 125.87


BS4449 as described in ground beam. SOR 2015

3 GB4, GB5 & GB6 - 2T16


2 (Bottom Rebar) Length (m)
3.91 3000.00
23.46 Column Stump 2/ 75.00
kg/m 1.578 Rebar (vertical) 2/ 325.00
37.02 ≈ ( 400-(2x25)-25 = 325 ) 3800.00
Ddt :
25mm conc. cover b/side 2/ 25.00
3750.00
Add : Bend 5D = 5(16) 2/ 80.00
3910.00

Total Carried To Summary 200.10


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND BEAM : GB1, GB2, GB3, GB4, GB5 & GB6 - 150mm x 400mm Page : 8

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

10mm Ø mild steel bar reinforcement to kg 7.74 3.40 26.32


BS4449 as stirrups as described in ground SOR 2015
beam.

11 GB4, GB5 & GB6 : R10 - 275 c/c


1.14 Girth (m)
12.54 2/ 150.00
kg/m 0.617 2/ 400.00
7.74 1100.00
Ddt : 25mm conc. cover 8/ 25.00
900.00
Add : Binder 24D = 24(10) 240.00
1140.00

Length (m)
3000.00
Ddt : Column Stump 2/ 75.00
2850.00
Bil. of link
= 2850mm ÷ 275mm c/c +1
= 11.36
≈ 11 nos

Sawn formwork to sides of ground beam m² 16.56 25.70 425.59


2 SOR 2015
2 GB1 & GB3 Length (m)
5.15 5150.00
0.40 Height (m)
8.24 400.00

2 GB2 Length (m)


1.85 1850.00
0.40 Height (m)
1.48 400.00

3
2 GB4, GB5 & GB6 Length (m)
2.85 2850.00
0.40 Height (m)
6.84 400.00

Total (m²)
a) GB1 & GB3 8.24
b) GB2 1.48
c) GB4, GB5 & GB6 6.84
16.56
END OF GROUND BEAM WORKS Total Carried To Summary 451.91
PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND FLOOR SLAB Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional)

Excavation oversite to reduce level average m² 13.12 2.90 38.05


150mm deep, commencing from platform SOR 2015
level (finished ground level) and get out,
deposit and spread in making up levels where
directed and remainders load and cart away
from site.

2.85 Area A Length (m)


2.85 3000.00
8.12 Ddt : 2/ 75.00
2850.00

Width (m)
1800.00
1200.00
Ddt : 2/ 75.00
2850.00

1.85 Area B Length (m)


1.05 2000.00
1.94 Ddt : 2/ 75.00
1850.00

Width (m)
1200.00
Ddt : 2/ 75.00
1050.00

Total Carried To Summary 38.05


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT GROUND FLOOR SLAB Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

WORK BELOW LOWEST FLOOR FINISHES


(All Provisional) (Cont'd)

Excavation oversite to reduce level average


150mm deep, commencing from platform
level (finished ground level) and get out,
deposit and spread in making up levels where
directed and remainders load and cart away
from site.

1.85 Area C Length (m)


1.65 2000.00
3.05 Ddt : 2/ 75.00
1850.00
Width (m)
1800.00
Ddt : 2/ 75.00
1650.00

Total (m²)
a) Area A 8.12
b) Area B 1.94
c) Area C 3.05
13.12

Bed of hardcore average 100mm thick as m² 13.12 5.55 72.82


described spread and levelled well rammed SOR 2015
and consolidated watered and blinded with
fine sand well rolled in and finished to receive (Pro-rata Rate)
ground floor slab.

- Refer taking off details as above

150mm thick reinforced concrete; BS5328 m² 13.12 46.80 614.02


designed mix Grade 25 (1:1½:3 - 20mm SOR 2015
aggregate) as specified in ground floor slab.
(Pro-rata Rate)
- Refer taking off details as above

Welded steel fabric reinforcement of 200mm m² 13.12 26.20 343.74


x 200mm mesh weighing 3.02kg/m² and SOR 2015
embedded in ground floor slab (MS-
A193/A7).

- Refer taking off details as above

Approved bituminious damp proof m² 13.12 13.70 179.74


membrance applied on concrete surfaces all SOR 2015
to the approval of the S.O. and in accordance
with the manufacturer's instruction

- Refer taking off details as above


END OF GROUND FLOOR SLAB WORKS Total Carried To Summary 1,210.32
PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN : 300mm x 150mm & STIFFENER : 150mm x 150mm Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

FRAME

Reinforced concrete; BS5328 designed mix m³ 0.65 303.40 197.21


Grade 25 (1:1½:3 - 20mm aggregate) as SOR 2015
specified in column and stiffener.

4 Column, C1 Length (m)


2.90 3300.00
0.30 Ddt : Roof Beam 400.00
0.15 2900.00
0.52
Width (m)
300.00

Depth (m)
150.00

2 Stiffener Length (m)


2.90 3300.00
0.15 Ddt : Roof Beam 400.00
0.15 2900.00
0.13
Width (m)
150.00

Depth (m)
150.00

Total (m³)
a) Column, C1 0.52
b) Stiffener 0.13
0.65

Total Carried To Summary 197.21


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN : 300mm x 150mm & STIFFENER : 150mm x 150mm Page : 2

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

FRAME (Cont'd)

12mm Ø high tensile bar reinforcement to kg 70.76 3.60 254.74


BS4449 as described in column. SOR 2015

4 C1 : 6T12 Length (m)


6 3300.00
3.32 Ddt : Roof Beam 400.00
79.68 Ddt : Kickers 75.00
kg/m 0.888 2825.00
70.76 Add :
Lapping in column 36D = 36(12) 432.00
Bend 5D = 5(12) 60.00
3317.00

6mm Ø mild steel bar reinforcement to kg 60.31 3.50 211.10


BS4449 as link as described in column. SOR 2015
4
24 C1 : R6 - 125 c/c
2.83 Girth (m)
271.68 2/ 300.00
kg/m 0.222 2/ 150.00
60.31 1100.00
Ddt : 25mm conc. cover 8/ 25.00
900.00
Add : Binder 24D = 24(6) 144.00
1044.00

Length (m)
2825.00
Bil. of link
= 2825mm ÷ 125mm c/c +1
= 23.6
≈ 24 nos

Total Carried To Summary 465.83


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN : 300mm x 150mm & STIFFENER : 150mm x 150mm Page : 3

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

FRAME (Cont'd)

12mm Ø high tensile bar reinforcement to kg 23.59 3.60 84.92


BS4449 as described in stiffener. SOR 2015

2 Stiffener : 4T12 Length (m)


4 3300.00
3.32 Ddt : Roof Beam 400.00
26.56 Ddt : Kickers 75.00
kg/m 0.888 2825.00
23.59 Add :
Lapping in column 36D = 36(12) 432.00
Bend 5D = 5(12) 60.00
3317.00

6mm Ø mild steel bar reinforcement to kg 5.75 3.50 20.13


BS4449 as link as described in stiffener. SOR 2015
2
24 Stiffener : R6 - 125 c/c
0.54 Girth (m)
25.92 2/ 150.00
kg/m 0.222 2/ 150.00
5.75 600.00
Ddt : 25mm conc. cover 8/ 25.00
400.00
Add : Binder 24D = 24(6) 144.00
544.00

Length (m)
2825.00
Bil. of link
= 2825mm ÷ 125mm c/c +1
= 23.6
≈ 24 nos

Total Carried To Summary 105.05


PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT COLUMN : 300mm x 150mm & STIFFENER : 150mm x 150mm Page : 4

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

FRAME (Cont'd)

Sawn formwork to sides of column and m² 16.98 25.70 436.39


stiffener

4 Column, C1 Girth (m)


0.90 2/ 300.00
2.83 2/ 150.00
10.19 900.00

Height (m)
2825.00

4 Stiffener Girth (m)


0.60 2/ 150.00
2.83 2/ 150.00
6.79 600.00

Height (m)
2825.00

Total (m²)
a) Column, C1 10.19
b) Stiffener 6.79
16.98

END OF COLUMN & STIFFENER WORKS


Total Carried To Summary 436.39
PROJECT NAME MEMBINA DAN MENYIAPKAN STRUKTUR BANGUNAN PONDOK PENGAWAL

ELEMENT ROOM BEAM : RB1, RB2, RB3, RB4, RB5 & RB6 - 150mm x 400mm Page : 1

Dimensions Description Unit Qty Rate Amount


(RM) (RM)

FRAME

Reinforced concrete; BS5328 designed mix m³ 1.24 303.40 376.22


Grade 25 (1:1½:3 - 20mm aggregate) as SOR 2015
specified in roof beam.

Total (m³)
a) RB1 & RB3 0.62
b) RB2 0.11
c) RB4, RB5 & RB6 0.51
1.24

12mm Ø high tensile bar reinforcement to kg 51.66 3.60 185.98


BS4449 as described in roof beam. SOR 2015

Total (kg)
a) RB1 & RB3 20.85
b) RB2 10.19
c) RB4, RB5 & RB6 20.62
51.66

16mm Ø high tensile bar reinforcement to kg 74.32 3.40 252.69


BS4449 as described in roof beam. SOR 2015

Total (kg)
a) RB1 & RB3 37.30
b) RB2 0.00
c) RB4, RB5 & RB6 37.02
74.32

10mm Ø mild steel bar reinforcement to kg 40.10 3.40 136.34


BS4449 as stirrups as described in roofbeam. SOR 2015

Total (kg)
a) RB1 & RB3 26.73
b) RB2 5.63
c) RB4, RB5 & RB6 7.74
40.10

- Refer ground beam taking off details

Total Carried To Summary 951.22


-