Proyecto: MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DEL SECTOR 80: A. H. FORTIN CAYCHO Y A. H.

H. MORADORES DEL PASAJE VENUS, DISTRITO


Fecha : 30-11-2015
DE LOS OLIVOS - LIMA
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
Costo
Item Descripción MES 1 MES 2 MES 3 MES 4 MES 5
Directo

01 OBRAS CIVILES
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 15,492.49 15,492.49
01.02 PLANES Y MITIGACION DE IMPACTO AMBIENTAL, SEGURIDAD Y SALUD 169,583.62 33,916.72 33,916.72 33,916.72 33,916.72 33,916.72
OCUPACIONAL
01.03 DEMOLICION DE RESERVORIO EXISTENTE V=450m3 59,609.46 59,609.46
01.04 CONSTRUCCION DE RESERVORIO ELEVADO REP- 01 V =100 m3 475,538.31 190,215.32 166,438.41 118,884.58
01.05 CERCO PERIMETRICO RESERVORIO ELEVADO REP-01 108,295.18 54147.59 54147.59
01.06 MEJORAMIENTO DE LA CISTERNA CB-1 16,311.83 16,311.83
02 EQUIPAMIENTO HIDRAULICO Y ELECTRICO
EQUIPAMIENTO HIDRAULICO BYPASS PROVISIONAL - MANTENIMIENTO DEL
02.01 SERVICIO DE AGUA POTABLE 11,413.13 11,413.13
02.02 EQUIPAMIENTO HIDRAULICO REP-01 53,670.78 53,670.78
02.03 EQUIPAMIENTO ELECTRICO REP-01 190,081.69 190,081.69
02.04 MEJORAMIENTO DEL EQUIPAMIENTO HIDRAULICO CISTERNA CB-1 43,920.43 43,920.43
02.05 MEJORAMIENTO DEL EQUIPAMIENTO ELECTRICO CISTERNA CB-1 154,712.62 154,712.62
02.06 SISTEMA DE COMUNICACION LOCAL 59,790.00 59,790.00
03 LINEAS DE AGUA POTABLE
03.01 OBRAS PROVISIONALES 87,567.25 29,189.08 29,189.08 29,189.08
03.02 LINEA DE IMPULSION DE LA CISTERNA CB-1 AL REP-01 58,032.72 29,016.36 29,016.36
03.03 LINEA DE ADUCCION DEL REP-01 (EMPALME 1-2) 105,377.09 52,688.55 52,688.55
03.04 LINEA DE ADUCCION DEL REP-01 (EMPALME 3) 19,097.48 9,548.74 9,548.74
03.05 LINEA DE EMPALME DE LA RED DE AGUA POTABLE A LA CISTERNA CB-1 3,676.76 3,676.76
04 LINEAS DE ALCANTARILLADO
04.01 LINEA DE REBOSE DEL RESERVORIO REP-01 21,871.27 21,871.27
04.02 REBOSE DE CISTERNA A RED DE ALCANTARILLADO 1,187.70 1,187.70

TOTAL COSTO DIRECTO S/. 1,655,229.81 109,018.67 224,132.05 320,797.86 360,676.02 640,605.21
GASTOS GENERALES S/. 281,389.07 18,533.17 38,102.45 54,535.64 61,314.92 108,902.89
UTILIDAD S/. 132,418.38 8,721.49 17,930.56 25,663.83 28,854.08 51,248.42
SUB TOTAL INCL. GASTOS GENERALES Y UTILIDAD S/. 2,069,037.26 136,273.33 280,165.06 400,997.33 450,845.02 800,756.52

SUMINISTRO ELECTRICO S/. 641.00 641.00


MONITOREO ARQUEOLOGICO S/. 29,000.00 9,666.67 9,666.67 9,666.67

PARCIAL S/. 2,098,678.26 136,273.33 289,831.72 410,664.00 461,152.69 800,756.52


I.G.V. (18.00%) S/. 377,762.09 24,529.20 52,169.71 73,919.52 83,007.48 144,136.17

COSTO TOTAL PRESUPUESTO REFERENCIAL S/. 2,476,440.35 160,802.53 342,001.43 484,583.52 544,160.17 944,892.69
CRONOGRAMA DE DESEMBOLSOS
Presupuesto: MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DEL SECTOR 80: A. H. FORTIN CAYCHO Y A. H. MORADORES DEL PASAJE
VENUS, DISTRITO DE LOS OLIVOS - LIMA
Lugar: LIMA - LIMA - LIMA
Costo al: 11/30/2015

DESEMBOLSOS DE EJECUCION DE OBRAS MONTO EN NUEVOS SOLES


ADELANTOS Y AMORTIZACIONES VALORIZACION DESEMBOLSOS PARA OBRAS

PARCIALES DE
CALENDARIO EFECTIVO MATERIALES TOTAL LA OBRA PRESUPUESTO IGV. (18%) PRESUPUESTO
(1) (2) (1 + 2) (3) PARCIAL 3-(1+2) (INCL IGV)

0 209,867.83 209,867.83 419,735.65 #VALUE! #VALUE! #VALUE!

30 13,627.33 13,627.33 27,254.67 136,273.33 109,018.66 19,623.36 128,642.02

60 28,983.17 28,983.17 57,966.34 289,831.72 231,865.38 41,735.77 273,601.15

90 41,066.40 41,066.40 82,132.80 410,664.00 328,531.20 59,135.62 387,666.82

120 46,115.27 46,115.27 92,230.54 461,152.69 368,922.15 66,405.99 435,328.14

150 80,075.65 80,075.65 160,151.30 800,756.52 640,605.21 115,308.93 755,914.14

PARCIAL 0.00 0.00 0.00 2,098,678.26 #VALUE! #VALUE! #VALUE!

 MONTO TOTAL DEL PRESUPUESTO Incl. TRIBUTOS #VALUE!

Costos no incluyen IGV
Ejecucion de Obras = S/. 2,098,678.26
Adelanto en efectivo 10% de Obras = S/. 209,867.83
Adelanto para materiales 10% de Obras = S/. 209,867.83

(*): Las Deducciones por adelanto Directo seran considerados en las Valorizaciones del Plazo contractual de Ejecuion de
Obra y seran deducidos de acuerdo a los indices unificados del plazo contractual de obra.

(**): Las Deducciones por adelanto de Materiales; seran considerados en las Valorizaciones del Plazo contractual de Ejecuion de Obra y seran
deducidos de acuerdo a los materiales utilizados en obra y a los indices unificados del plazo contractual de obra.

(***): Los Reajustes se cosideraran en las Valorizaciones del Plazo Contractual de Ejecucion de Obra.