Sei sulla pagina 1di 12

Automation in Construction 62 (2016) 66–77

Contents lists available at ScienceDirect

Automation in Construction

journal homepage: www.elsevier.com/locate/autcon

4D CAD Based Method for Supporting Coordination of Urban Subsurface


Utility Projects
Léon L. olde Scholtenhuis ⁎, Timo Hartmann, André G. Dorée
University of Twente, Dept. of Construction Management & Engineering, Horst Building, P.O. Box 217, 7500AE Enschede, The Netherlands

a r t i c l e i n f o a b s t r a c t

Article history: Coordinators of inner city utility construction works face increasing difficulty in managing their projects due to
Received 2 June 2014 tight physical restrictions, strict deadlines and growing stakeholder fragmentation. This paper therefore presents
Received in revised form 5 October 2015 a 4D CAD based coordination method that supports project plan scoping, formalizing and synchronizing. We
Accepted 17 October 2015
developed and implemented the method by conducting ethnographic action research in four project cases. In
Available online 21 November 2015
these projects, we observed that 4D-models generated with the method allowed practitioners to identify project
Keywords:
interfaces and conflicts, to identify schedule shortcomings and to evaluate delays. By introducing the method and
Subsurface utility projects reporting on its empirical evaluation we extend 4D CAD's domain of applicability with mid and small-sized utility
Coordination projects and address a need for 4D implementation studies.
4D CAD © 2015 Elsevier B.V. All rights reserved.
Scheduling
Multi-stakeholder

1. Introduction tasks of scoping, formalizing project information and synchronizing


the master schedule.
During subsurface utility network reconstruction, service providers This paper is structured as follows: First, we elaborate on how
install new utilities while simultaneously replacing damaged and aged current physical and institutional trends complicate coordination in
infrastructure. To minimize the public impact, authorities impose tight utility projects. We then discuss how state-of-the-art 4D CAD tools
temporal and spatial constraints on these works. Within these con- can support this challenged practice. Next, we describe both our
straints, multiple service providers simultaneously try to reconstruct research approach and the four cases that we studied to develop a 4D
their networks. Often, each of them hires a distinctive contractor CAD based coordination method. In the sections that follow, we
whose plans need to be aligned with other contactors to finish projects introduce the method and explain how its iterative development and
timely and within budget. One great challenge in this tight multi-actor empirical testing allowed us to evaluate it in two complementary
context is to manually align construction schedules. To date, this task ways. The discussion and conclusion finally reflect on how our findings
is often error-prone since work planners could easily overlook schedule contribute to 4D CAD literature and existing scheduling practices in the
interfaces and details. Such practices of inaccurate scheduling are a utilities sector.
major cause of delay in the construction industry [1] and negatively
affect performance also in utility projects. 2. Coordinating intricacies in urban subsurface utility works
One technique that can be used to support this complicated coordi-
nation practice is 4D CAD. Despite its potential merit, however, only a The past decades showed a proliferation of urban utility networks
few case studies exist that report on actual 4D implementation. These both in number and geographical coverage. This resulted in veritable
studies merely focus on large-scale construction works and limitedly mazes of utilities, serving buildings in neighborhoods and parts of larger
explore 4D CAD usage in smaller infrastructure projects. To fill this grid systems [2]. Underground space gradually becomes even scarcer
gap, this study's goal is to empirically derive an approach that guides nowadays: subsoil that bears light traffic loads already hosts buried util-
development and implementation of 4D in one type of small-sized ities such as freshwater pipes, gas pipes, electricity cables and telephone
infrastructure projects: the reconstruction of subsurface utilities. To lines; while the remaining underground is often packed with existing
this end, we empirically studied four utility cases and iteratively sewer lines, water basins, waste disposal containers and abandoned
developed a 4D CAD based method that supports core coordination infrastructure. In the nearby future, this space will be even further
reduced as new systems such as smart-grids, fiber glass networks,
⁎ Corresponding author. Tel.: +31 53 489 6857; +31 6 2343 4067 (m).
subsurface waste collection and energy storage are added.
E-mail addresses: l.l.oldescholtenhuis@utwente.nl (L.L. olde Scholtenhuis), The different material properties of utility networks also cause
t.hartmann@utwente.nl (T. Hartmann), a.g.doree@utwente.nl (A.G. Dorée). coordination complexity. Since utility networks have distinctive

http://dx.doi.org/10.1016/j.autcon.2015.10.013
0926-5805/© 2015 Elsevier B.V. All rights reserved.
L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 67

lifecycles, ranging from ten to thirty years, each network requires main- construction process as it would be actually built” [4]. By visualizing
tenance on different moments in time. Consequently, maintenance the actual transformation of a space over time during construction [5],
work of various utility owners should be streamlined to prevent unde- 4D helps practitioners to understand a construction plan more
sirable situations where intersections and roads are being broken up realistically [6]. Further, 4D-model elements such as symbols and
frequently. icons can visually convey a large range of additional contextual project
Furthermore, institutional-level developments such as liberalization information [7].
and privatization have increased fragmentation in the utilities sector. Literature shows that 4D tools can support multiple construction
Previously, utility networks in most democratic countries were owned project management tasks. 4D tools help, for example, to: develop an
and maintained by governments. Nowadays, however, many authori- intuitive understanding of a project [8]; to better communicate and
ties only own sewer systems while private service providers take care review designs [9,10]; as well as to detect conflicts and review project
of gas, water and electricity networks. On their turn, these providers progress [10]. The tools also potentially support cost estimating and
hire dedicated contractors to schedule and execute reconstruction in-depth analysis of construction operations [11]. Further, an explorato-
work. As a consequence, information about subsurface assets is now ry study shows that construction stage 4D BIM models can reduce re-
distributed over myriads of public and private stakeholders. quests for information, rework and change orders; and improve
The institutional developments have also altered project-level schedule compliance [12]. Additionally, 4D has been applied to guide
coordination. Due to fragmentation, utility reconstruction works nowa- construction planning, resource management, and site space utilization
days rarely have a single main project owner. Instead, these projects are [6] as well as for linear task scheduling and workflow scheduling [13,
comprised of a network of multiple contractors who are hired by 14]. More recently, 4D applications were also used for safety and risk
distinctive service providers. So, unlike many other infrastructure management [7,15–17], and quality inspections [18].
projects, utility owners and contractors are not integrated within a Besides exploring these potential purposes, 4D research also focuses
single overarching project hierarchy. Consequently, stakeholders can on other themes. One recent theme directs at technical extensions of 4D
hardly enforce plans and stay individually responsible for managing CAD. Studies focus on developing methods and algorithms that inte-
their interfaces with construction plans of others. grate 4D CAD scheduling with remote sensing [19] and image process-
Project-level schedule alignment commonly takes place as contrac- ing [20,21] technologies. Experiments showed that such automatic
tors and clients manually extract and mentally process scheduling infor- updating of 4D-models meets or exceeds manual progress tracking
mation from one another's project documentation. During coordination and monitoring [22]. Additionally, latest research has developed
meetings; they use sketches, drawings and draft schedules; verbally dis- methods to connect 4D CAD with cost estimation, and simulations of
cuss dependencies between these plans; and, try to integrate them in a schedules and workspaces. Object sequencing matrices and genetic al-
master schedule. The following example illustrates how physical and gorithms were, for example, used to enrich 3D models with scheduling
institutional trends have complicated coordination: To reconstruct an knowledge to automatically develop cost-time schedules [23]. Similarly,
inner city road intersection and sewer network, gas pipes and electricity Wang, et al. [24] showed how to use BIM quantity take-offs to feed
lines often need to be re-aligned as well. In this case the municipality operations simulation packages and create 4D construction schedules.
and her contractor schedule and execute both road and sewer construc- Further, 3D models have been expanded with automatic workspace
tion activities. Within the same time frame, two service providers and generation and schedule simulation systems to support workspace
their specialized contractors occupy the construction site to reconstruct optimized re-scheduling [25].
gas and electricity networks. In absence of any hierarchical coordina- Although recent studies have added relevant features to 4D systems,
tion, the three clients and three contractors rely on each other's partic- literature provides less attention to implementation issues of existing
ipation when aligning their construction schedules. To date, this 4D tools. Applied studies are therefore necessary to develop knowledge
alignment takes place manually, which is often a difficult and cumber- about intricate field operations of trade specialties. Without such under-
some practice. Time pressures may further complicate the illustrated standing, modelers might not know which objects to include in their
situation. These pressures are often a cause for the development of too 4D-model or how to depict these properly [12]. Boton et al. [26] partly
tight and inaccurate schedules [3]. Such schedules necessitate addressed this by developing a generic business view method that
re-planning and increase project duration. Alternatively, if tasks are translates information needs of trade disciplines into coordinated 4D-
scheduled too loosely, cycle times increase, project expenditures rise model views.
and the burden on the public grows. To effectively deal with this Further, a few studies exist that elaborate on how 4D models can be
trade-off, we assume that three main conditions need to be achieved used to support coordination in real-life projects. These studies report
during construction coordination: on an intuitive implementation of 4D in larger infrastructure and
high-rise construction [10], large scale highway projects [27] and
• Clients and contractors scope their project parts by identifying metro projects [17]. However, little is known about 4D CAD implemen-
relevant constraints and construction tasks; tation in smaller infrastructure projects such as, for example, utility re-
• They formalize this information into project artifacts such as designs construction. To address this shortcoming, this research aims to
and schedules; and empirically develop and evaluate a 4D-method that supports coordina-
• Synchronize the master schedule by evaluating interdependencies and tion of subsurface utility reconstruction works.
interfaces between scheduled construction tasks. This paper will proceed as follows: the next section describes this
study's ethnographic action research approach. These efforts culminat-
ed in the 4D based method that supports coordination tasks of scoping,
State-of-the-art 4D CAD technologies offer a way to support scoping, formalizing and synchronizing (Section 5). Section 6 evaluates this
formalizing and synchronizing. The remainder of this paper outlines method by elaborating on the design iterations made while developing
features and research directions in the domain of 3D–4D construction the method, and by presenting observed 4D benefits.
visualizations, and introduces a 4D based method that supports these
tasks in practice. 4. Research approach

3. State-of-the-art and current advancements in 4D CAD research We used ethnographic action research [28] to iteratively develop a
coordination method for utility projects. This research methodology in-
A 4D CAD tool links “three dimensional graphic images to the fourth tegrates ethnography and action research techniques. In ethnography,
dimension of time […] Such a model allows planners to visualize the researchers physically join a cultural domain, such as a construction
68 L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77

organization, to experience and identify its intricate routines and prac- project. We refined the concept method during the three subsequent
tices. In action research, researchers and practitioners collaboratively projects by continually analyzing practitioners' discussions and com-
implement and reflect on an intervention that addresses a real life ments about the content of the projects' 4D-models. Some discussions
organizational problem. In system development both approaches are indicated that we correctly modeled project details, while others
complementary to each other: ethnography allows researchers to showed that vital project elements were not represented adequately
develop a detailed understanding of a domain, while action researcher in our 4D models. Based on these discussions, we could either evaluate
subsequently allows to customize solutions (methods and systems) to the appropriateness of the steps in our method, or amend the method in
the needs of the domain (c.f. [29]). such a way that its next version included the missing elements. Updated
We used ethnographic techniques such as participant observation versions of the method were subsequently tested in successive projects.
[30,31] to first explore current practices of scoping, formalizing and syn- We repeated these iterative cycles until only a few changes to the meth-
chronizing project schedules. To this end, we observed coordination od were needed.
meetings and identified how practitioners manually align construction
plans. During subsequent action research [29] efforts, we worked 5. Resulting 4D based coordination method for subsurface utility
together with work planners and utility project designers to develop projects
tailored 4D-models. The models were implemented during multi-
stakeholder coordination meetings. Here, we kept track of discussions Before showing in Section 6 how our method evolved during the
about possible uses of 4D for coordination, and also observed interac- course of the four utility projects, this section first describes the final
tions with the developed 4D-models. Additionally, reflection sessions version of the coordination method. As shown in Fig. 1, the method
were organized to obtain more feedback on the content and value of comprises three main phases: project scope analysis, scope formaliza-
each projects' 4D-models. tion and synchronization of tasks in the master schedule.
Data was collected in various ways: we kept track of modeling
efforts in a written 4D-log; created a field diary to register important ob- 5.1. Scope analysis
servations; and, both tape and video recorded practitioners' interactions
with, and discussions about, 4D models. We analyzed obtained data The first phase of the coordination method involves grasping the
with the qualitative data analysis software ATLAS.ti [32]. As outlined content and boundaries of all the reconstruction activities that are
in Section 4.2, our analysis focused on identification of 4D-model planned by the multiple stakeholders. As described in construction
elements that practitioners considered to be necessary or redundant management literature [33], such understanding can be acquired by
for utility coordination. Furthermore, we identified which of the used identifying the project's scope. Our method distinguishes three scope
4D visualization techniques supported specific coordination purposes. identification steps: analysis of main reconstruction tasks; determining
the level of detail; and, identifying environmental and utility network
4.1. Description of studied utility projects constraints.
As a first step, the method proposes identifying and analyzing the
The first project involved the reconstruction of an inner city road in- main construction tasks. To this end, one retrieves scheduling informa-
tersection and construction of sewer lines and utilities in an adjacent tion, phasing drawings and meeting minutes from service providers and
street. At the execution phase of this project we joined the municipality, contractors. Service providers can also be consulted to obtain knowl-
civil works contractor, and utilities contractor during their site visits and edge about task sequencing and scheduling [9] if these documents are
coordination meetings. After observing five coordination meetings we not available. Based on the information delivered by the various stake-
developed a 4D-model and implemented it in two coordination meet- holders, we then suggest identifying projects context and, for each sep-
ings to observe how stakeholders interacted with it. arate discipline, establishing a first overview of the main reconstruction
The second project involved the reconstruction of utilities at an inner activities, cycle times, sequential relations, resources and workspace
city road intersection. In this project, utilities had to be relocated to fa- requirements. At the end of this step, the output should be a list with
cilitate the construction of a tunnel. We joined the project stakeholders construction activities and stakeholder dependencies. It is proposed to
– i.e. service providers, the municipality, civil works contractor and util- formalize this information in a multi-stakeholder master schedule in
ity contractor – during planning stage coordination meetings. Further, the method's successive phase.
we arranged five scheduling sessions with utility companies and one Furthermore, utility projects involve distinctive disciplines that
with a utility contractor. Additionally, we organized two separate ses- work with objects of different sizes. The next scoping step hence
sions to reflect on the project's 4D CAD models. suggests stakeholders to collectively define a level of detail for the
Our third project involved the reconstruction of 450 m sewer line schedules and visualizations that they plan to develop. Since 4D visual-
and several intersecting utility pipes in a residential area. The team izations do not require every single project component to be included,
consisted of representatives from the municipality and civil works we suggest selecting only the objects that are necessary to represent
contractor. We developed a 4D CAD model at the start of the project's the identified construction tasks. Generally, the level of detail of
execution phase, and introduced it during three coordination meetings 4D-models should also depend on the moment in the project's life
and a separate reflection session. cycle: while initial schedules mostly contain abstract task descriptions,
On the fourth project, we were involved during the planning and ex- construction stage schedules usually also incorporate detailed tasks.
ecution phases of the construction of 900 m sewer line and street inte- For example, one can identify detailed existing objects such as land
rior. The project team consisted of the municipality, an engineering boundaries, cables, pipes and tree roots at an early project stage. At
consulting firm and a civil works contractor. We created a 4D-model that moment, the model also includes larger-scaled object sets such as
prior to the construction activities, presented it in three coordination sewer pipes strings and large pavement sections. As the project pro-
meetings, and reflected on it during a separate session. Table 1 describes gresses, more detailed objects need to be added. These are, for example,
the projects and our research efforts in greater detail. ditches, curbstones and utility housing connections. The method
proposes to segment sewerage in tubes, manholes and joints at even
4.2. Using qualitative analysis to develop the coordination method later project stages.
The final scope analysis step identifies utility networks and project
We designed a concept of the 4D based coordination method in our environment constraints from involved service providers and authori-
first step toward its synthesis. As a starting point for this method we ties. Utility network constraints stem from network reliability require-
used the practical modeling experience that we gained during the first ments. For example, service providers only allow contractors to plan
L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 69

Table 1
description of case projects, their stakeholders and the collected project artifacts.

Project 1 Project 2 Project 3 Project 4

Project Inner city intersection reconstruction Sewer and utilities Sewer replacement and street level reconstruction Sewer replacement and street
description involving minor sewerage and utilities replacement on inner (450 m) in residential area, reconstruction of level reconstruction (900 m) in
reconstruction tasks city road intersection intersecting gas and water pipes residential area.
Project team Municipality: Municipality: Municipality: Municipality:
members Project manager, Project manager, Project manager, Project manager,
Supervisor Supervisor Supervisor Supervisor
Civil works contractor: Civil works contractor: Civil works contractor: Civil works contractor:
Project manager, Project manager Project manager, Project manager,
Work planner Service provider: Site manager Work planner
Site manager 5 Work planners Site manager
Utilities contractor: Utilities contractor: Engineering consultancy:
Site manager Work planner Consultant
Fieldwork 3 Site visits, 6 Work planning 3 Coordination meetings 3 Coordination meetings,
events 5 Coordination meetings sessions, 1 Work planner interview
8 Coordination meetings
Reflection Meeting with contractor foreman, Meeting with 4 Meeting with municipality's technical designer Meeting with civil contractor's
sessions and Meeting with municipality's technical engineers from energy work planner
participants designer provider,
Meeting with utilities
contractor's work
planner
Collected 5 Meeting minutes, 7 Meeting minutes, 1 Meeting minute, 4 Meeting minutes,
artifacts 2 2D-CAD maps of current project 6 2D-CAD maps of 3 Progress reports, 2 Master schedules,
conditions, current project 1 Master schedule, 2 Phasing drawings,
1 Phasing sketch, conditions, 1 2D-CAD map of current project conditions, 2 2D-CAD maps of current
3 2D-CAD designs, 2 Phasing drawings, 1 2D-CAD sewer and surface level design project conditions,
1 Master schedule 1 Surface level design 2 2D-CAD sewer and surface
sketch, level design
2 Design sketch utilities,
1 2D-CAD of surface level
design

network disruptions within specific time frames since they require min- The next formalization steps include modeling the construction ob-
imized network downtime. In specific, telecom providers will not allow jects in 3D. Various object types can be modeled for utility projects.
construction activities to take place during large-scale sports events, Based on their meaning, geospatial and temporal characteristics the
Christmas, or national holidays. Further, water suppliers oftentimes method distinguishes the following categories: (1) transient accessibility
try to avoid large-scaled network reconstructions during summer and workspace objects; (2) aged utilities, road assets to be removed and
days, while energy suppliers avoid reconstructions during winter. other obstructing subsurface objects; (3) designed utility networks and
Authorities also often define project environment constraints. Such road infrastructure and (4) non-transient contextual spatial orientation
constraints can be, for example, construction deadlines and restrictions objects.
related to the accessibility of public space. The method suggests identi- First, the method proposes to model transient accessibility and
fying constraints that are temporal and spatial, since both aspects limit workspace objects. The name of this object group is derived from the
the degrees of freedom while drafting reconstruction schedules. Tem- ‘transient objects’ in the framework of Hartmann and Vossebeld [7].
poral constraints influence possible start dates of construction tasks or Such objects represent conditions that temporarily limit construction
limit task durations, while spatial constraints physically restrain avail- space. They do not necessarily exist physically. The method suggests
able onsite workspace. two complementary ways to identify these: First, one can use environ-
mental constraint analysis outcomes to find objects that limit the avail-
able construction space. Such objects are, for example, active traffic
5.2. Formalizing scope information flows, bus routes and occupied public space. Second, the list of identified
construction activities can help identifying objects that temporarily re-
In the second phase of the coordination method, we propose to duce construction site space. Examples are workspaces like excavation
model the scope information by formalizing project objects into 3D- trenches, soil deposits, logistical routes, drilling areas and dewatering
models and integrating these with a master schedule. One precondition zones.
for this step is that stakeholders agree on the meaning of the objects and A next formalization step concerns modeling the aged utilities, road
processes they intend to formalize. This shared ontological understand- assets to be removed and other obstructing subsurface objects. This
ing is essential since stakeholders in multidisciplinary domains, such as category consists of objects that will be demolished, moved, replaced
utilities, may use identical labels to point at distinctive phenomena. For or renovated. Available maps of existing subsurface utilities provided
example, a label such as ‘excavating’ seems to unambiguously refer to by the land registry office can be used to identify infrastructure that
one set of objects or processes, while stakeholders can actually use needs to be demolished. Examples of this are pathways, asphalt, cables,
this label differently to point at distinctive excavation areas, depths, pipes, tubes, road sections, foundations and sewerage networks.
equipment, methods or sub-process. Shared understanding of used Descriptions of such objects can also be found in object libraries such
terms is therefore required to formalize a 4D model that represents as CityGML Utility ADE [34] and in the urban civil infrastructure
stakeholders' intended plans. taxonomy [35].
A first formalizing step in the coordination method proposes setting During the next formalization step within in the coordination
up a provisional master schedule based on the identified reconstruction method, designed utility networks and road infrastructure are modeled.
tasks and their sequential dependencies. In this schedule, temporal and These are the objects that will be built during the construction project.
spatial constraints can be implemented as a deadline, milestone or task. They can be extracted from clients' designs, sketches and CAD-drawings.
70 L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77

Fig. 1. 4D based coordination method for urban subsurface utility construction projects; iteratively developed based on four utility projects.

Finally, the method proposes to model non-transient contextual take place. They remain unchanged while construction progresses.
spatial orientation objects. The name of this category stems from the Examples are: buildings, street names and private property plots. The
‘non-transient’ object types that existing literature defines [7]. These ob- objects can be identified from project environment maps provided by
jects represent the environment in which the construction activities land registry offices and local authorities.
L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 71

Table 2 Third, the coordination method proposes using key-date


Object categories for modeling urban utility construction projects: types, meaning, and snapshotting. With this technique, one uses the 4D model to extract
examples.
visualizations of the project on anticipated key-dates such as milestones
Object type Semiotic meaning Example and deadlines. By comparing the actual project status with these im-
Transient accessibility Represents temporal Temporary traffic routes, ages, project managers can monitor and discuss progress, assess extents
and workspace objects that constrain road signs, available of delays and develop delay mitigation plans.
objects construction space. Objects construction site spaces
in this category are not excavation trenches,
6. Evaluation of the 4D based coordination method
necessarily a physical object drilling spaces,
dewatering zones
Aged utilities, road Represents existing objects Cables, pipes, roads, Evaluation was executed in two complementary ways: First,
assets to be removed, that will be removed, foundations, sewerage iterative development and testing ensured that the coordination
obstructing replaced or transformed network, tree roots method supports actual work practices [27]. Second, practitioners' use
subsurface objects
Designed utility Represents objects in future
of 4D-models during coordination meetings allowed us to observe
networks and road situations benefits of 4D. We elaborate below that the successful outcomes of
infrastructure this empirical evaluation shows that the method supports the develop-
Non-transient Refers to project Building, street names, ment of practically applicable 4D-models.
contextual spatial environments and provide buildings, trees, private
orientation objects visual cues for virtual property plots
navigation through the 6.1. Iterative development of the coordination method
project
In ethnographic action research, tools are continually evaluated
during their development and implementation. We illustrate this by
Table 2 summarizes the four object categories. The first and second showing how feedback provided on the 4D models helped to incremen-
columns describe objects types and their meaning. Column three tally improve the coordination method.
provides examples of related object instances. Our efforts in the first project focused on the identification and
modeling of designed utility and road infrastructure objects. Based on
5.3. Synchronization of design plans and master schedule components the project scope, we formalized the objects representing designed
road infrastructure (Fig. 2a) and utilities (as in Fig. 3a). We implement-
The coordination method's third phase involves the synchronization ed the model and used process animation videos to support discussions
of the tasks in the master schedule. At this stage, contractors and service during a stakeholder meeting. While reflecting on the 4D-model, prac-
providers can use 4D as a platform to visually explain and discuss titioners argued that it adequately visualized the current and future pro-
relations between reconstruction tasks of service providers. Below, we ject conditions. However, they also stated that it lacked information
first outline the grouping and integration of 3D-objects with scheduled about surrounding streets and land plots. Practitioners further found
tasks. Subsequently, we propose three ways to implement 4D to sup- that visual cues had to be added to enhance understanding of the dead-
port synchronization, these are: timeline snapshotting; process anima- lines and milestones in the construction progress. The feedback provid-
tions and key-date snapshotting. ed in project one eventually resulted in the amendment of the method
The first synchronization step proposes creating object sets that with the steps ‘model non-transient contextual spatial orientation
convey information about each task in the master schedule. The level objects’ and ‘modeling temporal project constraints’.
of detail in the master schedule can be used as a guide to create these In the second project we modeled designed infrastructure objects
sets. Essentially, we suggest that when the schedule breaks down one (Fig. 2b), subsurface utilities (Fig. 3b) and non-transient contextual spa-
large task into multiple smaller tasks, corresponding 3D-objects should tial orientation objects (Fig. 5a). Further, we analyzed the additional
be divided or sectioned accordingly. In reverse, to represent one task in modeling activities that we conducted during this project. These extra
the master schedule, multiple 3D-objects should be combined into one tasks expanded the method in three ways: First, we had to create
single object group. Resulting object sets are, for example, “demolished draft schedule from scratch when we became involved in the project.
pavement Section 1.2”, “new sewer pipes 1–4” and “new utility We added this to the method by formulating the step ‘assess task
connection-2”. An alternative way to cluster objects is based on ob- dependencies and convert into master schedule’. Second, the project's
ject–contractor relations. This approach is helpful to visualize the activ- reflection discussions revealed that one needs to determine the level
ities of the multiple contractors. Examples of such object sets are: of detail for the 4D-model in such a way that it captures the relevant
“pavement contractor A” and “gas pipe 2.4 contractor B”. Next, sets tasks and objects of all project stakeholders. To incorporate this, we
should be appended to the corresponding tasks in the master schedule. amended the coordination method with the step ‘level of detail-
Once this has been done, objects' visual appearance and colors settings analysis.’ Third, we also modeled new types of transient objects. These
[36,37] need to be configured to clearly represent tasks in the planned were, for example, utility installation trenches, joint-welding
construction process. workspaces (Fig. 4a) signs, and temporary road blocks (Fig. 4b). To in-
The resulting 4D-model can be used during utility project coordina- corporate these in the method, we redefined the step ‘model temporal
tion meetings. For one, the method proposes timeline snapshots to sup- project constraints’ into ‘model transient accessibility and workspace
port communication of project plans and evaluation of sequencing objects’.
alternatives. To this end, one extracts images from the 4D-model to vi- In the third project we also identified the project scope and modeled
sualize the planned status of reconstruction works on start and finish street level infrastructure (Fig. 2d), subsurface utilities (Fig. 3c), tran-
dates of tasks. By sequencing these images, one obtains a step-by-step sient accessibility and workspace objects (e.g. temporary dewatering
slideshow of the as-planned reconstruction activities. and sewer line bypasses, Fig. 4c) and non-transient contextual spatial
Second, the method proposes using process animation videos to orientation objects (e.g. street names and land contours, Fig. 5b). One
generate a detailed overview of the scheduled construction processes. example of how project three expanded our method was the addition
This allows third parties and subcontractors to quickly grasp the nature of ‘timeline snapshotting’. We added this step after we used it to better
of all planned reconstruction work. Additionally, process animation understand sequencing of a facility contractor's and civil contractor's
supports a visual rehearsal of the project and allows service providers construction tasks.
and utility contractors to analyze project interfaces and to identify Also during our fourth project, we identified the project scope and
physical jobsite conflicts. formalized the objects to be removed, designed street level objects
72 L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77

Fig. 2. Modeled designed road infrastructure objects in projects 1, 2, 3, and 4 (resp. a, b, c, d).

Fig. 3. Modeled designed subsurface infrastructure in projects 1, 2, 3, and 4 (resp. a, b, c, d).


L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 73

Fig. 4. Modeled transient accessibility and workspace objects: (a) cable trenches and (b) traffic rerouting flows in project 2, (c) dewatering zones in project 3 and (d) sewerage trench in
project 4.

Fig. 5. Modeled non-transient contextual spatial orientation objects: (a) trees and surroundings in project 2, and street names and trees in (b) project 3, and (c) project 4.
74 L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77

(Fig. 2d), designed utility infrastructure (Fig. 3d) workspaces (Fig. 4d) when the 4D-model showed him that a telecom line was being buried
and contextual objects (e.g. trees, Fig. 5d). We made only a minor while gas pipes had not been installed yet. He argued:
change to the method by relating ‘identified tasks and LOD overview’
“This situation is not possible, since a telecom line installation never
to the step ‘create objects sets and attach to schedule’. We did this
precedes gas installation activities.”
since we experienced during fieldwork that we often consulted
the level of detail in the master schedule to develop useful 3D Another engineer realized by using the 4D-model that electricity
object sets. Finally, we moved toward saturation since analysis of lines and gas pipes were not well aligned in the design. He argued
fieldwork and reflection sessions did not require other changes to the that the 4D-model did not integrate both utility lines in a single trench,
method. although that would have been the most cost-efficient design solution.
Further, 4D CAD appeared to be beneficial when discussing project
delay. In the third project, for example, practitioners used the timeline
6.2. Observed benefits of 4D CAD
snapshots we created to identify extents and causes of delay at the
time of a project coordination meeting. Similarly, in the fourth project
Additional evaluation took place by observing how project
they compared the as-planned situation with the actual situation onsite.
stakeholders experienced benefits from the 4D-models that were
The work planner then argued:
generated with the method. This section provides examples of such
benefits and discusses how 4D supported tasks such as: detecting “This is right … excavations already took place, or not? Look, we are
potential design conflicts (formalizing), elaborating schedule omissions, already excavating and preparing [pavement] foundations right
understanding project interfaces and conducting delay analysis there, but our sewer has only been constructed until here.”
(synchronizing).
We observed benefits of 4D CAD when practitioners used 3D visual- Typically, the above quotations exemplify the benefits of 4D based
izations to identify conflicts between the infrastructure designs of the coordination. It is shown how 3D models help to gain insight in design
different clients. In this study 2D-CAD drawings were first converted conflicts and enhance understanding of project interfaces, while inte-
into 3D-models before they were implemented in 4D process visualiza- gration of these models with schedules structures process thinking. In
tions. Since this enabled 3D inspections of the designs, 3D conflict detec- sum, this section showed how evaluation of the coordination method
tion can be seen as a feature of the 4D based coordination practice. took place while we (1) iteratively developed and implemented it,
During the second project, for example, spatial conflicts were detected and (2) observed its benefits in practice. These findings are summarized
once an engineer noticed that a piece of underground foundation of in Table 3.
an adjacent building constrained the design space for his utilities. He
zoomed in on it and argued (all verbatim quotes are translated from 7. Discussion
Dutch):
“That's right. On that side we also have the entrance of the hospital This study's ethnographic action research approach enabled us to
building […] with several foundation columns. As you can see, we empirically develop and evaluate a 4D-method that supports schedul-
[cannot install our pipes] right underneath that place.” ing practices in the subsurface utility domain. Findings provide evidence
that, if used, the 4D method could successfully support alignment of the
The visualized situation was in conflict with the company's design service providers and contractors involved in utility projects. The
protocol because the building and gas network were not located at suf- proposed method is therefore a meaningful way by which 4D based
ficient distance. This triggered the engineer to investigate the issue in coordination and decision making can be implemented in practice.
detail. In another example, 4D supported the utility contractor's project This section elaborates on these contributions and provides suggestions
planner when he studied interfaces and conducted a conflict analysis. for future research.
He zoomed in on various places where gas pipes and tree roots Besides the method as its main contribution, this study extends liter-
intersected and argued as follows: ature in two ways. First, we bring 4D research and application beyond
existing large-scale construction projects [10,17,27]. Although one can
“Watch over there at the location of these two trees. We are also
connecting gas pipes right there, so this situation will not be possi-
ble”. Table 3
Summary of the coordination method's iterative improvement (column 1) and observed
After this observation, the planner wrote down a description of this benefits of its use (column 2).
conflict and addressed it during the next project meeting. Iterative improvements of the method Observed benefits of 4D based
Additionally, we observed how the 4D-model generated with our (examples) coordination (examples)
method helped practitioners to identify shortcomings and omissions Project 1: Practitioners used 4D based
in the master schedule. In the fourth project, for example, the work Created steps: model aged utilities, coordination to:
planner explained his construction schedule by making use of 4D visu- road assets to be removed, obstructing Detect potential conflicts between
alizations. While doing this, he noticed that his schedule contained an subsurface objects model utility and foundation and utilities as well as
road infrastructure design objects between gas pipes and tree roots.
error. He then asked:
Added step: model non-transient Elaborate omitted holiday week in
contextual spatial orientation objects schedule.
Project 2: Discuss scheduled interfaces between
“Can you navigate to next week? Pavement activities are probably Added step: assess task dependencies telecom cable and gas pipe installation.
completed in the visualization by then, right? [In reality, this is not and convert into master schedule, level Conduct analysis about root and cause
correct] because I forgot to incorporate a week of summer holiday of detail-analysis of excavation delay.
Redefined step: ‘model temporal
in this [visualized] schedule.”
project constraints’ as ‘model transient
accessibility and workspace objects’
We also observed that 4D CAD allowed practitioners to integrate Project 3:
drawings and schedules to better understand the interfaces and se- Added step: timeline snapshotting
quential relations between construction activities. This understanding Project 4:
occurred, for example, when an engineer watched the second project's Added link: Create objects sets and
attach to schedule
animation. He questioned whether the task sequencing was correct
L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 75

logically expect that large and smaller projects face comparable coordi- further by also collecting data on coordination costs to evaluate the
nation problems – yet on a different scale – 4D usage in mainstream cost-effectiveness of 4D implementation.
infrastructure projects has been limited to date. By developing a method Next, one may reasonably assume that the coordination method's
that supports coordination of urban utility reconstruction works, we scoping, formalization and synchronization phases apply to construc-
provide first evidence that more regular construction projects can tion and civil engineering projects in general (such as in [10,27]). How-
benefit from 4D as well. ever, since we developed and evaluated the method only for utility
Second, most existing 4D literature focuses on system prototype de- projects, we suggest conducting next research steps to explore whether
velopment (c.f. [14,38–40]) and integration of 4D with technologies these phases are applicable to a broader domain. This suggested re-
such as remote sensing and simulation. These studies are relevant for search could also explore how to extend the coordination method
development of state-of-the-art 4D-tools but often exclude technology with state-of-the-art 4D features such as automated progress monitor-
implementation aspects. Consequently, less attention is given to the ar- ing [19–22,41], schedule simulation [23] and automated quality inspec-
gument that understanding of real-life organizational practices is neces- tion [18].
sary to design information systems that effectively support practice [12, Another limitation is that practitioners in this study lacked the skills
26]. Implementation studies are needed to gain such understanding. In and facilities to develop and implement 4D-models themselves. The au-
this respect, our method contributes implementation knowledge and thors therefore had to take on these tasks. Such active involvement is
supports integration of current manual coordination practices with 4D common in engaged research approaches [42], but inevitably influences
coordination techniques. practitioners' uptake and use of 4D CAD. To reduce this effect, re-
The remainder of this section addresses suggestions for future re- searchers could take a more distanced role in future when studying
search. First, we reflect on the potential value of 4D for coordination practitioners' abilities to implement the proposed 4D coordination
purposes that were not observed in the coordination meetings. Practi- method.
tioners suggested such ‘anticipated 4D benefits’ after they had watched Furthermore, scholars assume that 4D adoption requires new com-
the 4D-models that we developed during the four cases. They expected petences [43] and tasks. Although such tasks can be fulfilled by 4D spe-
4D-models to, for example: cialists or information model managers [44,45], it can be argued that
4D-coordination functions should be integrated within existing organi-
zational roles. Consecutive studies should therefore investigate how
• Help managers communicating construction plans to colleagues, tasks in our proposed 4D based coordination method can be allocated
suppliers or third parties. The foreman in the first project, for example, to actors in organizations.
argued that 4D visualizations potentially support him when commu- Additionally, we propose future research to develop color schemes
nicating the sequence of planned construction works to clients. for 4D visualizations in multi-stakeholder meetings. In our research,
Engineers added that the models also help informing external different sets of colors were tried and tested. From the iterations it
stakeholders about project plans. emerged that identifying understandable color sets becomes more
• Support the development of site logistics plans. The municipal design- difficult as the number of stakeholders involved increases. Unfortunate-
er in the third project, for example, indicated that sewer pipes and soil ly, existing color schemes are developed for single-contractor projects
oftentimes need to be deposited on a small construction site. He found (e.g. [36,37]). As modelers in multi-stakeholder projects should be
it helpful to use a 4D CAD model in early stages to find suitable storage cautious in accepting these schemes, future research could devote
places for these materials. attention to develop color schemes for multidisciplinary construction
• Support identification of conflicts between the planned construction projects.
work and its surrounding environment. The work planner on the Another point for further research relates to notion of 4D as a BIM
fourth project saw potential in using 4D when assessing the conse- tool. Ideally, BIM systems support “parametric modeling and allow
quences of delay on availability of public spaces. Similarly, the new levels of spatial visualization, simulation of the behavior of the
municipality's designer in this project argued that the 4D-model building, as well as more efficient project management” [46]. Building
could be used to check whether a construction plan fits earlier project information models contain geometric as well as non-geometric design
phasing plans, if it properly reroutes traffic and whether it achieves and construction information [47]. In our study, however, 4D-models
deadlines. were not parametric in nature, neither were they attributed with
• Perform a feasibility check for developed schedules. The work planner meta-data. Instead, we developed 4D visualizations by only converting
in project four, for example, argued that it occurs frequently that he 2D polylines into surfaces and extruded 3D objects, and by linking
reconsiders initial plans after realizing that they appear not to be fea- these objects to manually created schedule tasks. This approach easily
sible. He thought that 4D-models could help avoiding this at early integrates with existing 2D-based manual work styles, but delivers
stages when project leaders, foremen and work planners use it to ver- 4D-models that are less useful during later stages in the project life
ify the feasibility of a project's initial schedule. cycle. Therefore we suggest conducting more research on developing
implementation methods for 4D BIM in utility projects. In turn, this
work will contribute to the growing amount of BIM studies that concep-
We suggest additional empirical studies to analyze how the pro- tually describe models to, for example: integrate building information
posed 4D method needs to be adapted to achieve these anticipated models with project management data systems during project delivery
benefits. [48], enable BIM usage in shop drawing creation [47] or use BIM to
Besides studying anticipated benefits, we also suggest future re- obtain a competitive edge [49].
search steps to addresses the limitations of this study. We elaborate Finally, one stream of literature focuses on project specific arrange-
these points below. For one, this study's ethnographic approach enabled ments for BIM. This BIM Execution plan literature proposes templates
us to tailor the 4D based method to its community of practice, and to for defining roles and responsibilities of stakeholders, BIM goals and
empirically observe how the 4D-models supported real life coordina- uses and required technical infrastructure [50,51]. Although existing
tion. From a research methodological perspective, it would however BIM Execution plans may be applicable to infrastructure projects as
be stronger to test the proposed 4D based coordination method by in- well, they predominantly focus on facility construction. In addition,
vestigating whether similar benefits also have been observed without they limitedly elaborate on how a BIM practice should integrate with
the use of the method. We therefore suggest future research to compare existing manual project management styles. Taking our study as a
coordination in a case in which the proposed method is applied, with a point of departure, future research could address these shortcomings
similar case in which it is not. This comparison could be extended even by identifying requirements for Infrastructure BIM Execution plans.
76 L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77

8. Conclusions less likely. This eventually contributes to overall reliability of utility


reconstruction works.
Subsurface utility projects are, by and large, coordinated manually.
Utility project clients and contractors often align their construction Acknowledgments
plans through paper-based discussions in construction meetings. Now-
adays, these practices are time consuming and become more error- We gratefully thank the anonymous reviewers for their constructive
prone since public pressures are exerted to minimize project cycle feedback and suggestions to improve this paper. We also express grati-
times. More complexity is added by the fragmentation of ownership tude to the Dutch Pioneering Foundation for subsidizing this research.
and control over utilities. As a result, reconstruction schedules are
often sub-optimally aligned, causing delays and cost overruns. We em- References
pirically developed and evaluated a 4D based coordination method to
support this challenged practice. [1] A.S. Faridi, S.M. El-Sayegh, Significant factors causing delay in the UAE construction
industry, Constr. Manag. Econ. 24 (11) (2006) 1167–1176.
We used ethnographic action research in four urban utility recon-
[2] P.J. Lancaster, E.S. Plotkin, J.N. Lerner, Construction in Cities: Social, Environmental,
struction projects to develop the method. We identified current coordi- Political, and Economic Concerns, CRC Press, Boca Raton, 2001.
nation practices; iteratively developed 4D-models for four projects; and, [3] I.W. Koster, Hardlopen, doodlopen?, Verkenning van urgentie en procesoplossingen
evaluated how these models were used in coordination meetings and voor tijdsdruk in de infrastructurele bouw, CROW, 2012.
[4] B. Koo, M. Fischer, Feasibility study of 4D CAD in commercial construction, J. Constr.
reflection sessions. This paper presents the method that resulted after Eng. Manag. 126 (4) (2000) 251–260.
cycles of iterative 4D-model development, implementation and evalua- [5] R.M. Webb, J. Smallwood, T.C. Haupt, The potential of 4D CAD as a tool for construc-
tion. Essentially, the method describes: tion management, J. Constr. Res. 5 (1) (2004) 43–60.
[6] H. Wang, J. Zhang, K. Chau, M. Anson, 4D dynamic management for construction
planning and resource utilization, Autom. Constr. 13 (5) (2004) 575–589.
• Main coordination stakeholders who provide information sources and [7] T. Hartmann, N. Vossebeld, A semiotic framework to understand how signs in con-
constraints for utility reconstruction (e.g. service providers, authori- struction process simulations convey information, Adv. Eng. Inform. 27 (3) (2013)
378–385.
ties and registry offices). These are needed to scope and explicate con-
[8] D. Heesom, L. Mahdjoubi, Trends of 4D CAD applications for construction planning,
struction plans; Constr. Manag. Econ. 22 (2) (2004) 171–182.
• Most relevant utility reconstruction objects that need to be formalized [9] T. Hartmann, M. Fischer, Supporting the constructability review with 3D/4D models,
Build. Res. Inform. 35 (1) (2007) 70–80.
in a project's 4D-model (e.g. accessibility objects and workspace, road
[10] A. Mahalingam, R. Kashyap, C. Mahajan, An evaluation of the applicability of 4D CAD
assets to be removed, subsurface objects, designed utility networks on construction projects, Autom. Constr. 19 (2) (2010) 148–159.
and road infrastructure and non-transient contextual spatial orienta- [11] T. Hartmann, J. Gao, M. Fischer, Areas of application for 3D and 4D models on
tion objects) and; construction projects, J. Constr. Eng. Manag. 134 (10) (2008) 776–785.
[12] S.-L. Fan, M.J. Skibniewski, T.W. Hung, Effects of building information modeling
• Visualization steps (i.e. timeline snapshotting, key date snapshotting during construction, J. Appl. Sci. Eng. 17 (2) (2014) 157–166.
and process animations) that use 4D-models to synchronize the mas- [13] R. Jongeling, T. Olofsson, A method for planning of work-flow by combined use of
ter schedule. location-based scheduling and 4D CAD, Autom. Constr. 16 (2) (2007) 189–198.
[14] A. Russell, S. Staub-French, N. Tran, W. Wong, Visualizing high-rise building con-
struction strategies using linear scheduling and 4D CAD, Autom. Constr. 18 (2)
(2009) 219–236.
We evaluated the method in an iterative way by testing whether 4D- [15] Z. Hu, J. Zhang, BIM-and 4D-based integrated solution of analysis and management
for conflicts and structural safety problems during construction: 2. Development
models – that were created by following the method – matched practi- and site trials, Autom. Constr. 20 (2) (2011) 167–180.
tioners' needs. In addition, we observed that the developed 4D-models [16] L.S. Kang, S.-K. Kim, H.S. Moon, H.S. Kim, Development of a 4D object-based system
supported coordination tasks such as detection of potential design for visualizing the risk information of construction projects, Autom. Constr. 31
(2013) 186–203.
conflicts (formalizing), analysis of schedule omissions and project inter- [17] Y. Zhou, L. Ding, L. Chen, Application of 4D visualization technology for safety
faces, and investigations of delays (synchronizing). management in metro construction, Autom. Constr. 34 (2013) 25–36.
Besides contributing the method, this study extends literature on 4D [18] L. Chen, H. Luo, A BIM-based construction quality management model and its
applications, Autom. Constr. 46 (2014) 64–73.
CAD in two ways: First, the empirically observed benefits provide evi- [19] C. Kim, H. Son, C. Kim, Automated construction progress measurement using a 4D
dence of how 4D CAD can be used in a range of utility project coordina- building information model and 3D data, Autom. Constr. 31 (2013) 75–82.
tion tasks. This use in more mainstream projects extends 4D CAD's [20] C. Kim, B. Kim, H. Kim, 4D CAD model updating using image processing-based
construction progress monitoring, Autom. Constr. 35 (2013) 44–52.
application domain and complements to existing research on 4D in
[21] M. Golparvar-Fard, F. Peña-Mora, S. Savarese, Integrated sequential as-built and
major infrastructure and high-rise projects. Second, our empirical ex- as-planned representation with D 4 AR tools in support of decision-making tasks
amples of 4D implementation enrich recent 4D literature that focuses in the AEC/FM industry, J. Constr. Eng. Manag. 137 (12) (2011) 1099–1116.
mostly on technical extensions of 4D systems. [22] Y. Turkan, F. Bosche, C.T. Haas, R. Haas, Automated progress tracking using 4D
schedule and 3D sensing technologies, Autom. Constr. 22 (2012) 414–421.
Practitioners' reflections on the use of 4D-models resulted in a [23] C.-W. Feng, Y.-J. Chen, J.-R. Huang, Using the MD CAD model to develop the
shortlist of anticipated benefits of 4D. They, for example, indicated time–cost integrated schedule for construction projects, Autom. Constr. 19 (3)
that 4D is likely to support coordination tasks such as: communicating (2010) 347–356.
[24] W.-C. Wang, S.-W. Weng, S.-H. Wang, C.-Y. Chen, Integrating building information
construction plans (scoping); developing site logistics plans (formaliz- models with construction process simulations for project scheduling support,
ing); evaluating the relation between construction plans and processes Autom. Constr. 37 (2014) 68–80.
in the project's surrounding; and, verifying schedules (synchroniza- [25] H. Moon, N. Dawood, L. Kang, Development of workspace conflict visualization
system using 4D object of work schedule, Adv. Eng. Inform. 28 (1) (2014) 50–65.
tion). We suggest future research to explore how the proposed method [26] C. Boton, S. Kubicki, G. Halin, Designing adapted visualization for collaborative 4D
should be tailored to support these benefits. We also recommend applications, Autom. Constr. 36 (2013) 152–167.
conducting additional research to: compare a case in which the 4D [27] P. Zanen, T. Hartmann, S. Al-Jibouri, H. Heijmans, Using 4D CAD to visualize the im-
pacts of highway construction on the public, Autom. Constr. 32 (2013) 136–144.
method is used with a case of manual coordination; investigate applica- [28] T. Hartmann, M. Fischer, J. Haymaker, Implementing information systems with
tion of the method to the broader civil engineering domain; study how project teams using ethnographic-action research, Adv. Eng. Inform. 23 (1) (2009)
utility project professionals can gain skills to implement 4D CAD in their 57–67.
[29] R.L. Baskerville, Investigating information systems with action research, Commun.
organization; develop multi-stakeholder color schemes for 4D visuali-
AIS 2 (3es) (1999) 2–31.
zations; and finally, integrate the proposed 4D-method with BIM ap- [30] M.H. Agar, The Professional Stranger: an Informal Introduction to Ethnography,
proaches and execution plans. Academic Press, San Diego, 1996.
As a summarizing reflection, we argue that 4D based coordination [31] D.L. Jorgensen, Participant Observation: a Methodology for Human Studies, Sage
Publications, Inc., 1989
helps utility project managers to reduce uncertainties and to synchro- [32] ATLAS.ti, ATLAS.ti Scientific Software Development GmbH, Berlin, 2010.
nize reconstruction schedules. Consequently, errors and delays become [33] G.M. Winch, Managing Construction Projects, Blackwell Publishing Company, 2002.
L.L. olde Scholtenhuis et al. / Automation in Construction 62 (2016) 66–77 77

[34] T. Becker, C. Nagel, T.H. Kolbe, CityGML UtilityNetworkADE, Open Geospatial [44] M.B. Barison, E.T. Santos, An overview of BIM specialists, in: W. Tizani (Ed.),
Consortium, Berlin, 2012. Proceedings of the International Conference on Computing in Civil and Building
[35] T. El-Diraby, H. Osman, A domain ontology for construction concepts in urban Engineering, Nottingham University Press, Nottingham, UK 2010, pp. 141–147.
infrastructure products, Autom. Constr. 20 (8) (2011) 1120–1132. [45] N. Gu, K. London, Understanding and facilitating BIM adoption in the AEC industry,
[36] H.-S. Chang, S.-C. Kang, P.-H. Chen, Systematic procedure of determining an ideal Autom. Constr. 19 (8) (2010) 988–999.
color scheme on 4D models, Adv. Eng. Inform. 23 (4) (2009) 463–473. [46] R. Miettinen, S. Paavola, Beyond the BIM utopia: approaches to the development
[37] C. Ya-Hsin, T. Meng-Han, K. Shih-Chung, L. Chin-Wei, Selection and evaluation of and implementation of building information modeling, Autom. Constr. 43 (2014)
color scheme for 4D construction models, 18 (2013) 1–19. 84–91.
[38] V. Bansal, M. Pal, Construction schedule review in GIS with a navigable 3D [47] T. Nath, M. Attarzadeh, R.L. Tiong, C. Chidambaram, Z. Yu, Productivity improvement
animation of project activities, Int. J. Proj. Manag. 27 (5) (2009) 532–542. of precast shop drawings generation through BIM-based process re-engineering,
[39] N. Dawood, E. Sriprasert, Z. Mallasi, B. Hobbs, Development of an integrated Autom. Constr. 54 (2015) 54–68.
information resource base for 4D/VR construction processes simulation, Autom. [48] A. Monteiro, P. Mêda, J.P. Martins, Framework for the coordinated application of two
Constr. 12 (2) (2003) 123–131. different integrated project delivery platforms, Autom. Constr. 38 (2014) 87–99.
[40] M. Mawlana, A. Hammad, A. Doriani, S. Setayeshgar, Discrete event simulation and [49] P.E. Love, J. Matthews, I. Simpson, A. Hill, O.A. Olatunji, A benefits realization
4D modelling for elevated highway reconstruction projects, in: V. Telichenko, A. management building information modeling framework for asset owners, Autom.
Volkov, I. Bilchuk (Eds.),International Conference on Computing in Civil and Constr. 37 (2014) 1–10.
Building Engineering Moscow, 2012. [50] Centre for Construction IT, BIM Essential Guide for BIM Execution Plan, Building
[41] H. Kim, K. Anderson, S. Lee, J. Hildreth, Generating construction schedules through Construction Authority, Singapore, 2013.
automatic data extraction using open BIM (building information modeling) technol- [51] Computer Integrated Construction Research Program, BIM Project Execution
ogy, Autom. Constr. 35 (2013) 285–295. Planning Guide — Version 2.0, The Pennsylvania State University, University Park,
[42] A.H. Van de Ven, Engaged Scholarship: a Guide for Organizational and Social PA, USA, 2010.
Research, Oxford University Press, Oxford, 2007.
[43] B. Succar, W. Sher, A. Williams, An integrated approach to BIM competency
assessment, acquisition and application, Autom. Constr. 35 (2013) 174–189.

Potrebbero piacerti anche