Date

Project
Location
Owner
Subject

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Percentage


Ref Description Duration
of Work
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
100%
1.0 Preliminaries 98.63% 10.00%

i Mobilization 6 days
ii Setting Out Works 4 days 20.00%
iii On Site Security 44 days 90%

2.0 Architectural Works 85.84%

i Partitions
Gypsum Drywall 26 days 80%
ii Floor Finishes
Floor Preparation 9 days
Carpet Tiles 22 days
Ceramic Tiles 14 days
Vinyl Tiles 6 days 20.00% 70%
69.63%
iii Wall Finishes
Paint Finish 35 days
Skirting 21 days
iv Ceiling Works
Gypsum Ceiling 10 days 60%
v Doors and Hardware
Laminated Doors 37 days
vii Window Furnishings 52.05%
Roller Shades 8 days
vii Other Items 50%
Backdrop and Signage 12 days 50.00%

3.0 Furniture Works

i Tables and Cabinetry 42 days 40%


ii Modular Partitions 42 days

4.0 Engineering Works 34.70%

i Electrical Works 30 days 30%


ii Mechanical Works 25 days
iii Fire Protection and Detection Works 15 days
iv Plumbing and Coring Works 10 days
20.32%
5.0 Auxillary Works 20%

i Structured Cabling System 23 days

6.0 Finishings 10.05%


10%
i Clearing, Cleaning and Hauling of Debris 6 days
ii Retouches 3 days

7.0 Project Turn Over


0%

Prepared by: Noted by : Conforme: Legend:


Construction on Site
External Tasks
Construction Progress
Collection Billing
Associate Architect President and CEO Owners Representative