Sei sulla pagina 1di 41

MANPOWER QUANTITY

PROJECT IN-
1
CHARGE PREVIOUS TOTAL NO. OF
SITE ENGINEER 1
WORKERS:

16
FOREMAN 2

DOCS. CON. 1

PLUMBER 7 (+6)
ADDITIONAL MANPOWER FOR THIS
CAD OPERATOR 1 WEEK

+11
PIPE FITTER 2

WELDER 3

HELPER 10 (+2)
ASST. PLUMBER 3 (+3)
TOTAL 31
NO. OF WORKERS 26
Previous This Period To Date
REASON OF DELAY
Planned 19.026% 3.012% 13.484% • Lack of Manpower

Actual 2.009% 0.422% 2.014% REMEDY


• Provide Manpower
Variance -17.017% -2.59% -11.469% -Additional Plumbers

No. of Days 26.00 17.548


Delayed
• Fabrication of pipe chase brackets for (DS, VS, WS, FWR, PWR, PWDF & FWDF)
(18-Sep-19).
• Continuation on roughing ins. @ground floor common toilet. (Sep. 18-19, 2019)
• Excavation @ground floor for C.I pipe collector. (Sep. 18, 2019)
• Provision of sanitary pipe stub-outs @19th floor, zone 3 (19-Sep-19).
• Continuation on installation of soil pipe collector @7th floor, zone 3. (Sep. 19-21)
• Layouting and coring of pantry toilet @7th floor, G.L D/3. (Sep. 24, 2019)
• Layouting of male common toilet @7th & 8th floor, zone 2. (Sep. 24)
• Continuation on installation of pipe vent loop along acacia st. 7th floor, zone 1.
(Sep. 21, 23 & 24)
• Provision of sanitary pipe stub-outs @22nd floor, zone 1 (Sep. 23-24, 2019).
1st Week (September 25 – October 1, 2019)
• Provision of Sanitary pipe stub outs @ 21st Floor (Zone 2) & 20th Floor (Zone 3).
• Installation of Vent stack Ø150mm @ 7th Floor (Common Toilet).
• Installation of Soil Pipe Collector Ø100mm @ Ground Floor, (Along Borces St.)
• Continuation of Coring on Pantry toilet @8th Floor, Zone 2.
• Roughing Ins. of Pantry Toilets @7th & 8th Floor.
• Continuation on Installation of waterline loop @7th Floor GL(B-C/5-6).

2nd Week (October 2 – 8, 2019)


• Provision of Sanitary pipe stub outs @ 21st Floor (Zone 3) & 22nd Floor (Zone 2).
• Installation of Vent stack Ø150mm @8th & 9th Floor (Common Toilet).
• Installation of Waterline Riser Ø100mm @ 8th & 9th Floor, Near Fire Exit 1.
• Installation of Downspout @ 7th Floor (Zone 1).
• Excavation for Drain Pipe Installation @ Ground Floor.
• Continuation on Installation of waterline loop @7th Floor GL (B-C/1-2.).
TECSUB.:

DATE
ITEM NO. REFERENCE NUMBER TECSUB TYPE ITEM(S)FOR APPROVAL DATE NEEDED STATUS
SUBMITTED

1 01601-TEC-TritechPS-001 SHOP DRAWING PROPOSED PIPING LAYOUT OF GROUNDFLOOR TOILET 31-Jul-19 14-Aug-19 RESPONDED

2 01601-TEC-TritechPS-002 MATERIAL SUBMITTAL SOLVENT CEMENT -ATLANTA BRAND 05-Aug-19 19-Aug-19 RESPONDED

PPR PIPES-DONSEN BRAND (FOR ROUGHING-INS OF


3 01601-TEC-TritechPS-003 MATERIAL SUBMITTAL 05-Aug-19 20-Aug-19 RESPONDED
TOILET)

4 01601-TEC-TritechPS-004 SHOP DRAWING PROPOSED WATER METER LOCATION 08-Aug-19 22-Aug-19 RESPONDED

5 01601-TEC-TritechPS-005 MATERIAL SUBMITTAL GRP Water tank (Potaglas Brand) 28-Aug-19 12-Sep-19 RESPONDED

METHODOLOGY FOR INSTALLATION OF WATERLINE


6 01601-TEC-TritechPS-006 METHODOLOGY 04-Sep-19 18-Sep-19 RESPONDED
PIPES (GI & PPR)

7 01601-TEC-TritechPS-007 MATERIAL SUBMITTAL DECK DRAIN (JAMAN PRODUCTS INC. BRAND) 10-Sep-19 24-Sep-19 RESPONDED

8 01601-TEC-TritechPS-008 MATERIAL SUBMITTAL FLOOR DRAIN (JAMAN PRODUCTS INC. BRAND) 10-Sep-19 24-Sep-19 RESPONDED

9 01601-TEC-TritechPS-009 MATERIAL SUBMITTAL MANHOLE COVER (JAMAN PRODUCTS INC. BRAND) 10-Sep-19 24-Sep-19 RESPONDED

10 01601-TEC-TritechPS-010 MATERIAL SUBMITTAL CLEANOUT (JAMAN PRODUCTS INC. BRAND) 10-Sep-19 24-Sep-19 RESPONDED

PROPOSED WATER METER CLEARANCE @GROUND


11 01601-TEC-TritechPS-011 SHOP DRAWING 18-Sep-19 2-Oct-19 WAITING
FLOOR
RFI:

ITEM REFERENCE DATE DATE


SUBJECT STATUS
NO. NUMBER SUBMITTED NEEDED

1 01601-RFI-TritechPS-001 PROPOSED CORING ON TIE BEAM 01-AUG-19 21-Aug-19 RESPONDED

2 01601-RFI-TritechPS-002 URINAL AND WATER CLOSET SENSOR HEIGHT 04-SEP-19 24-SEP-19 RESPONDED

3 01601-RFI-TritechPS-003 SUB WATER METER HEIGHT 04-SEP-19 24-SEP-19 RESPONDED

4 01601-RFI-TritechPS-004 SHOWER HEIGHT 04-SEP-19 24-SEP-19 RESPONDED


TECSUB
- GROUND FLOOR PLUMBING LAYOUT, RELOCATION AND ITS DETAILS
- 7TH FLOOR PLUMBING LAYOUT AND TOILET BLOW UP
- LOWER GROUND FLOOR PIPING LAYOUT AND PAD LOCATION
- 2ND - 6TH FLOOR TOILET BLOW UP
- 8TH- ROOF DECK PIPING LAYOUT
FABRICATION OF GI PIPE AND BRACKETS FOR WATER LINE PIPE LOOP

7th FLOOR (ZONE 2)


INSTALLATION OF SANITARY SOIL PIPE LOOP

7th FLOOR (ZONE 2)


INSTALLATION OF PIPE STUBOUTS

18th FLOOR (ZONE 3)


CORING AND INSTALLATION OF ROUGHING INS FOR LAVATORY @ COMMON TOILET

7th FLOOR (ZONE 2)


FABRICATION AND INSTALLATION OF GI PIPE AND BRACKETS FOR WATER LINE PIPE LOOP

7th FLOOR (ZONE 2)


FABRICATION AND INSTALLATION OF GI PIPE AND BRACKETS FOR WATER LINE PIPE LOOP

7th FLOOR (ZONE 1 & 2)


INSTALLATION OF PIPE STUBOUTS

21st FLOOR (ZONE 1)


CORRING OF ROUGHING INS FOR WATER CLOSET @ COMMON TOILET

7th FLOOR (ZONE 2)


FABRICATION OF GI PIPE AND BRACKETS FOR WATER LINE PIPE LOOP
Along Acacia St.
INSTALLATION OF SANITARY SOIL PIPE LOOP

Along Acacia St.


INSTALLATION OF PIPE STUBOUTS
20th FLOOR (ZONE 2)
CORRING OF ROUGHING INS FOR WATER CLOSET @ COMMON TOILET

7th FLOOR (ZONE 3)


ROUGHING INS OF SANITARY PIPES COMMON TOILET
GROUND FLOOR (Along Borces St.)
ROUGHING INS @ PWD COMFORT ROOM, COMMON TOILET

7th FLOOR (ZONE 2)


INSTALLATION OF SOIL PIPE COLLECTOR

7th FLOOR (Along Acacia St.)


INSTALLATION OF PIPE STUBOUTS

22nd FLOOR (ZONE 1)


CORRING AND INSTALLATION ROUGHING INS @ PANTRY TOILET

7th FLOOR (G.L D/3)


CONT. ON ROUGHING INS OF SANITARY PIPES, COMMON TOILET

GROUND FLOOR (Along Borces St.)


CONT. ON INSTALLATION OF SOIL PIPE COLLECTOR

7th FLOOR (ZONE 1)


CONT. ON INSTALLATION OF VENT LOOP

7th FLOOR (ZONE 3)


FABRICATION OF GI PIPE BRACKETS FOR WATER LINE PIPE LOOP & PIPE RISERS
Along Acacia St.