Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Attendees:
1. Engr. Bryan M. Suliguin - Lead Project Inspection Coordinator, Civil/Structural Works Inspector, UPMO
2. Engr. Ariel R. Dela Cruz - Civil Engineer, CSIS-UPMO
3. Engr. Arnel I. Pantig - Section Chief, CSIS-UPMO
4. Engr. John Jeric F. Catabay – Electrical Engineer, CSIS-UPMO
5. Engr. John Raph Luigi S. Bautista - Mechanical Works Inspector, UPMO
6. Arch. Ronald P. Belizario – Architectural Works Inspector, CSIS-UPMO
7. Vladimir G. Amatorio - End-user, AO IV, HRDO
8. Engr. Sonny Riguer - Project Engineer, NGP Construction
9. Arch. John Arve Espinosa – Architect, NGP Construction
10. Arch. Ronald P. Belizario - Architectural Works Inspector, UPMO
Agenda:
1. Review of the minutes of the 5th Coordination Meeting
2. Approval of the minutes of the 5th Coordination Meeting
3. Matters arising from the minutes of 5th Coordination Meeting
4. Report of the Project Engineer
5. Updates/Other Matters
1
5th COORDINATION MEETING MATTERS
AGENDA UPDATES SPECIFICS/AGREEMENT IN-CHARGE TIMELINE UPDATES
A. Documents
1. Updated and
detailed PERT-
Contractor received the
CPM & S- approved PERT-CPM & S-
Curve Curve
Schedule
D. Concerns/
requests
2
Time extension:
Recommendation for
Contract Time Extension
No. 1 is for signature
Contract amount:
P2,785,386.11 CSIS to conduct evaluation
Contract Duration: 150 on Monday morning, 2 Sep
calendar days (5 April 2019 2019
F. Contract CSIS/End-
to 1 September 2019)
User/Contractor
PVO for corrections.
PVO 2 recommendation
includes lighting, repainting
of partition edging (frame)
and repainting of
ceiling/slab.
OTHER MATTERS
ITEM DETAILS REPLY/AGREEMENT IN-CHARGE UPDATES
1. Billing of the Contractor with pending progress
Contractor billing
Pictures of accomplishment to
include in the BOQ
4
REPORT OF THE PROJECT ENGINEER
PARTICULARS DETAILS UPDATE
As of 27 August 2019
Target accomplishment based on S-Curve:
97.24%
Actual accomplishment: 96.84%
Variation: -.40 slippage
Project Engineer
Project Supervisor
Safety Officer
B. Workers 1 Project Foreman
2 Electrician
5 Aircon Installer
2Carpenter
1 Helper
2 electric drills
1 circular saw
2 chipping hammers
2 electric grinder
C. Equipment and
2 welding machine
tools
1 sander
1 air compressor
1 exhaust fan
1 lot hand tools
Painting of masonry wall
Wrapping-in of electrical conduits
D. Previous Activities Installation of drywall partition
Tile works
Installation of aircon
5
Installation of new modular partitions
Painting of window frames
Installation of kitchen counter
Hydro-pressure test
Varnishing of wooden cabinets
Installation of water and sanitary lines
Installation of main feeder line
Installation of data cabinet and ptc
F. Remaining
Return of furniture, copiers and refrigerator
Activities