Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Review Panel
Division/Office Name
01-1022-000-SPC-FU-0007[02].docx
Table of Contents
1 Introduction .............................................................................................................. 7
1.1 General....................................................................................................... 7
1.2 Existing Facility Description ........................................................................ 7
1.3 Hierarchy of documentation ........................................................................ 8
1.4 Proprietary Items ........................................................................................ 8
1.5 Deviations and Alternatives to Specification................................................ 8
2 Preliminaries ............................................................................................................ 9
2.1 Authority Approval .................................................................................... 10
3 Applicable Standards ............................................................................................. 10
4 Inspection of the Works and Hold Points ................................................................ 11
5 Scope of Works ...................................................................................................... 12
5.1 Temporary CEPS...................................................................................... 12
5.2 Product ..................................................................................................... 13
5.3 Excluded Works ........................................................................................ 13
5.4 Interface with Other Trades ...................................................................... 13
5.5 Removal of the Temporary CEPS System ................................................ 13
6 Functional Description ............................................................................................ 14
7 Equipment Specification ......................................................................................... 15
7.1 Temporary CEPS Bulk Fuel Tank ............................................................. 15
7.2 Pumps ...................................................................................................... 15
7.3 Overflow Tank .......................................................................................... 16
7.4 Valves ....................................................................................................... 16
8 Material Specification ............................................................................................. 16
8.1 Scope ....................................................................................................... 16
8.2 Materials Use ............................................................................................ 16
8.3 Handling of Pipes & Fittings ...................................................................... 17
8.4 Carbon Steel Pipe..................................................................................... 17
8.5 Carbon Steel Pipe Fittings ........................................................................ 17
8.6 Pipe Branch Connection Sizing Table ....................................................... 17
8.7 Flanges & Flanged Joints ......................................................................... 18
8.8 Flange Guards .......................................................................................... 19
01-1022-000-SPC-FU-0007[02].docx Page 3 of 50
8.9 Underground Piping .................................................................................. 19
8.10 Trenching ................................................................................................. 19
8.11 Tie In Point ............................................................................................... 20
8.12 Penetrations ............................................................................................. 20
8.13 Pipe Welding Consumables ...................................................................... 21
8.14 Pipe Support System ................................................................................ 21
8.15 Quarantine, Storage & Segregation .......................................................... 21
9 Mechanical Installation and Piping Specification .................................................... 22
9.1 Scope ....................................................................................................... 22
9.1 Operation Procedures ............................................................................... 22
9.2 Piping Systems Performances .................................................................. 22
9.3 Design & Fabrication ................................................................................ 23
9.4 Arrangement ............................................................................................. 23
9.5 Vents and Drains ...................................................................................... 23
9.6 Identification ............................................................................................. 23
9.7 Equipment Tagging................................................................................... 24
9.8 Paint scheme ............................................................................................ 25
9.9 Pipe Spacing ............................................................................................ 25
9.10 Pipe Cleaning ........................................................................................... 26
9.11 Welding .................................................................................................... 26
9.12 Sustainability Requirements ..................................................................... 29
10 Electrical Specification............................................................................................ 29
10.1 E&IC Installation ....................................................................................... 29
10.2 Equipment Selection and Installation ........................................................ 29
10.3 Equipment Inspection and Tests ............................................................... 30
10.4 Lightning Protection System, Earthing and Bonding ................................. 30
10.5 General Construction ................................................................................ 30
10.6 Local Control Panels................................................................................. 33
10.7 Instrument Junction Box ........................................................................... 34
10.8 Automatic Tank Gauging .......................................................................... 34
10.9 Cables ...................................................................................................... 34
10.10 Conduits and Cable Ladder ...................................................................... 35
10.11 Underground Cabling ................................................................................ 35
01-1022-000-SPC-FU-0007[02].docx Page 4 of 50
11 Commissioning ....................................................................................................... 36
11.1 General..................................................................................................... 36
11.2 Scope of Commissioning .......................................................................... 36
11.3 Commissioning Plan ................................................................................. 36
11.4 Pre-Commissioning .................................................................................. 37
11.5 Testing Medium for Pipework ................................................................... 38
11.6 Pre-commissioning Tests.......................................................................... 38
11.7 Acceptance Tests ..................................................................................... 40
11.8 Handover .................................................................................................. 41
11.9 Review of documentation .......................................................................... 41
11.10 Performance ............................................................................................. 41
12 Deliverables ........................................................................................................... 42
12.1 Work Plan ................................................................................................. 42
12.2 Workshop Drawings.................................................................................. 43
12.3 Specification Details ................................................................................. 43
12.4 Commissioning Plan ................................................................................. 43
12.5 As Constructed Documentation (General) ................................................ 43
12.6 Work-as-Executed Drawings .................................................................... 44
12.7 As Constructed Drawings ......................................................................... 45
12.8 Operation and Maintenance Manuals ....................................................... 45
12.9 Manufacturer’s Data Record (MDR) .......................................................... 45
12.10 Spare Parts List ........................................................................................ 46
13 Defects Liability Period ........................................................................................... 46
13.1 Planned Maintenance ............................................................................... 46
13.2 Unplanned Maintenance ........................................................................... 46
14 Commonwealth Personnel Training ........................................................................ 48
01-1022-000-SPC-FU-0007[02].docx Page 5 of 50
Abbreviations, Acronyms and Definitions
Abbreviation Definition
AS Australian Standard
CP Cathodic Protection
FF Fuel Farm
kL Kilolitre
LL Lend Lease
01-1022-000-SPC-FU-0007[02].docx Page 6 of 50
1 Introduction
This specification describes the minimum technical requirements for supply, fabrication and testing of the fuel
system associated with the Temporary Central Emergency Power Station (CEPS) system located adjacent to
the Museum building outside Building 10 at Garden Island East.
Temporary CEPS is a standby power station that will be utilised to supply fuel to the generators in Building 10
during the decommissioning of the existing CEPS tank and construction of the new tank.
1.1 General
This Specification applies to all Works associated with the new Temporary CEPS fuel system at Garden Island
(East) NSW.
All works shall be constructed complete and serviceable, including all necessary accessories and
miscellaneous material, minor parts and other such items, whether or not indicated in the Contract drawings
or the Specification, where it is clearly the intention that they should be installed or obviously required and
necessary to complete the work.
The Temporary CEPS fuel system shall provide a safe working environment complying with legislation,
Defence regulations, relevant Codes of Practice, Australian Standards and proven Industrial Practices,
including but not limited to fuel spill prevention, environmental protection, dangerous goods storage, fire
protection; electrical safety and worksite practices.
The installation shall deliver high quality fuel, deliver fuel efficiently in service and be easy to operate.
The Temporary CEPS system is expected to operate for at least two years, during which the new CEPS 10
system will be constructed.
1.1.1 Definitions
Managing Contractor: Lendlease
Consultant: ACOR Consultants
Contractor: A person or organisation undertaking the construction phase
Sub-Contractor: Person or organisation as engaged by the contractor
Specification: This document
Suppliers: Individual or organisation supplying any equipment as part of this specification
01-1022-000-SPC-FU-0007[02].docx Page 7 of 50
During the decommissioning of the existing CEPS fuel system and the construction of the new tank, the
Temporary CEPS system will supply fuel to the existing generators in Building 10.
01-1022-000-SPC-FU-0007[02].docx Page 8 of 50
Product Data sheets and Brochures, in English;
Examples of past applications / installation / performance;
Reasons for the proposed substitutions;
Installation Details and requirements;
Maintenance Details and Requirements;
Statement of the extent of revisions to the contract documents;
Statement to the extent of revisions to the construction program;
Statement of cost implications including costs outside the contract;
Statement of consequent alterations to other parts of the works;
Verification statement that proposed alternative has been reviewed and deemed same or better than
that specified;
Statement that the proposed alternative will not necessitate alteration to other parts of the
works. Note which other part of the works had been considered in the assessment; and
Advice to be provided at what cost benefit proposed changes or substitution would be to the client.
If the identified proprietary item is unavailable, the Contractor shall submit evidence to the fact. If the
substitution covers unavailability or is for any other reason, the Contractor shall submit evidence that the
substitution:
Is of net enhanced value to the proprietor; and
Is consistent with the contract documents and is as effectual as the identified proprietary item.
Equivalency must be demonstrated by the Contractor where any such equipment is proposed for use.
2 Preliminaries
This Specification shall be read in conjunction with the drawings, general and special conditions of the contract
and all other parts of the document. Unless varied or modified by this specification, the general and specific
conditions shall apply in full.
The Contractor is responsible for all construction related facilities and site offices and is to allow for the
following items as deemed necessary for the completion of specified work scope:
Site Inductions and access approvals (e.g. confined space, working around wharves etc);
Obtain security clearance and Base access passes for all required personnel;
Provision of all plans, checklists, clearances, certificates and approvals necessary to carry out the
work (such as but not limited to Quality Plans, Method of Works Plan, ITPs, Safe Work Method
Statements, personnel background checks and qualifications);
Mobilisation and site establishment including the provision of all site labour, supervision, tools,
equipment, power, temporary buildings and facilities necessary for performance of the work on site;
Provision of lighting, telephone, water, sewer and other services to site offices as required by this
specification and/or by building and regulatory authorities;
Provision and installation of erosion and pollution control, etc. as required by the statutory
authorities, and/or the Commonwealth;
01-1022-000-SPC-FU-0007[02].docx Page 9 of 50
Removal of erosion and pollution control, etc. as required by the statutory authorities, and/or the
Commonwealth upon completion of the Works;
Provision of Toilet facilities for personnel;
Provision of safety shower facilities for personnel;
Provision of PPE as required for works and required inspections;
Provision of Container or workshop facilities as required;
Security of Contractors facilities;
Maintenance of all working areas in a clean and tidy state;
Undertake an extensive clean-up of the Site upon completion and make good any damage to the
existing facilities which has occurred as a consequence of the construction;
Maintenance of all areas in a safe working condition;
Minimise disruption to the base; and
Minimise disruption and ensure coordination with other projects on base.
During construction works, temporary fencing and barricading will be required to prevent unauthorised access
to certain areas. This fencing/barricading shall be provided by the Contractor.
As a minimum fencing/barricading shall include: all excavations, areas where welding and hot-works are
underway, confined space entry and other areas as required.
3 Applicable Standards
The Contractor shall adopt the following list of standards, regulations and guidelines as a minimum, where
each standard, regulation and guideline is the most recent edition. All equipment shall be designed,
constructed and tested to the following standards. Where a conflict occurs between this document and an
Australian Standard or other referenced document, then the ‘higher’ requirement or standard shall prevail
(advice shall be sought from the Lendlease).
AS 1940-2017: The storage and handling of flammable and combustible liquids;
Department of Defence: DFI-Design Practices Manual (DFI-DPM);
Department of Defence: Manual of Infrastructure Engineering – Electrical (MIEE);
Department of Defence: DFI Hazardous Area Guide;
AS 1692: Steel Tanks for Flammable and Combustible Liquids;
AS 4041: Pressure Piping;
AS 4977-2008: Petroleum Products – Pipeline, road tanker compartment and underground tank
identification;
01-1022-000-SPC-FU-0007[02].docx Page 10 of 50
API 2000: Venting Atmospheric and Low-pressure Storage Tanks;
API RP 2350: Overfill Protection for Storage Tanks in Petroleum Facilities;
AS/NZS 3000 Electrical Installations (Known as the Australian/New Zealand Wiring Rules);
ASME B31.3 Process Piping;
API Spec 6D Pipeline Valves (Gate, Plug, Ball, and Check Valves);
API Spec 6FA Fire Test for Valves;
API Std 607 Fire Test for Soft-Seated Quarter-turn Valves;
API Std 608 Metal Ball Valves – Flanged, Threaded and Butt-welding Ends;
ASME B16.10-2009 Face-to-face and End-to-end Dimensions Of Valves; and
ASME B16.34-2013 Valves - Flanged, Threaded, And Welding End.
01-1022-000-SPC-FU-0007[02].docx Page 11 of 50
Other specific Witness points as identified in this document.
Note that a minimum notification period of five (5) working days shall be provided prior to any hold point.
All supporting Inspection Test Records and associated documentation references included in the ITP shall be
listed in a register and provided to Lendlease.
ITP progression shall be documented and incorporated in the Contractor’s Quality Control Plan. The
completed form shall be handed over to Lendlease on completion of project.
5 Scope of Works
The Works included in this Contract shall comprise of the provision for all materials, plant, labour, and the
performance of all operations for the complete and proper construction of the Works specified.
All Works will be in accordance with this scope of work and the Tender specification, which shall form the
basis of the minimum installation practices to be carried out at the site, with the drawings and shall be to the
entire satisfaction of Lendlease.
This Specification also forms part of the mechanical, hydraulic and electrical works as applicable and is to be
read in conjunction with the Mechanical, Hydraulic and Electrical drawings.
The Contractor shall be responsible for the following:
01-1022-000-SPC-FU-0007[02].docx Page 12 of 50
Security fencing - 2.4 m chainmesh fence with 600 mm barbed wire (Class 2 fence);
Spill kit and temporary bunding (around the fuel tanker and adjacent drains);
2 x powder-type fire extinguishers within 10 m from the fuel tank;
Commissioning of the system;
Documentation (such as but not limited to O&M manuals, MDR, inspection and test certificates);
Any other items identified in this document and necessary to make the system function as intended;
and
Removal of the temporary CEPS fuel system at the completion of construction works.
5.2 Product
The proposed fuel system is based on following product which will be received and dispensed at the site:
Diesel: has a flash point greater than 61.5oC and therefore, based on AS 1940, is classified as
combustible liquid.
01-1022-000-SPC-FU-0007[02].docx Page 13 of 50
Electrical services serving the temporary CEPS area;
Hydraulic services serving the temporary CEPS area;
Safety shower;
Fencing;
Lighting;
Fire extinguishers;
Spill kit;
Any ancillary items as deemed not required by Lendlease.
The area shall be made good with any excavations, holes or openings appropriately filled and sealed.
6 Functional Description
The Temporary CEPS fuel system is comprised of 1 x 30 kL double walled above ground tank. The tank will
provide fuel to the generators in Building 10 via two (2) 1000 L day tanks during decommissioning of the
existing CEPS tank and construction of the new one. The day tank controls and instrumentation are connected
to both the existing generator control panel and to the future generator control system. These connections will
be undertaken by the Electrical trade. The Temporary CEPS system shall be located adjacent to the Museum
building outside Building 10. The tank will be filled by road tankers utilising the tanker’s on-board pump.
The Temporary CEPS tank shall include a submersible dispensing pump, local control panels, instrument
junction box and emergency stops.
The system shall have the following functionality:
Allow for tanker to offload into the bulk tank using its own onboard pump;
Display tank level readouts via the Automatic Tank Gauge (ATG) system;
Provide an audible alarm when high level in the bulk tank has been reached via the overfill alarm;
Allow an operator the ability to energise the fuel system to prepare it for automatic control;
Automatically dispense fuel to either of the two day tanks when either tank has reached low level;
Automatically stop dispensing fuel when both day tanks have reached high level;
Have a switch to allow electrical power for the system to be selected from either the local generator
or Building 10 mains power;
Allow an operator to de-energise the system.
As part of operating the system, the operator shall check all valves within the system and ensure that they are
in the correct position. The operator shall then begin operations using the local control panel located within
the fenced area adjacent to the 30,000L bulk tank. Once operations have begun, fuel dispensing and control
shall be automatically and be regulated via the day tank levels. The control system shall be relay based.
01-1022-000-SPC-FU-0007[02].docx Page 14 of 50
7 Equipment Specification
7.1 Temporary CEPS Bulk Fuel Tank
The Temporary CEPS storage tank system shall be capable of storing 30 kL of diesel fuel and be completed
with the following:
1 x 30 kL double walled above ground storage tank (FES Grande or equivalent)
The tank shall be designed and tested in accordance with the latest revision of AS 1692 and AS
1940 and shall meet all the requirements of these standards. This shall include:
- Production testing
- Factory acceptance testing
- Inspection and certification
- Quality records
- Installation requirements
- Plinth and footings
- Certified lifting points
- Labelling
- Protective coatings
Tank inlet nozzle
Outlet Nozzle
Dip point with lockable seal cap
Free vent
Manway
Automatic tank gauge
Overfill alarm
Tanks shall have supports as supplied by the manufacturer and shall be compliant with AS 1692.
Tanks shall have earthing boss fitted.
Tanks shall be off the shelf FES Grande 30,000 double walled tanks or equivalent.
7.2 Pumps
An overflow collection tank shall be provided which collects fuel overflow from the day tanks. The tank shall
be a 1,200 L doubled walled carbon steel tank compliant to AS1692 and shall be located in Building 10. Fuel
shall be gravity drained from the day tanks to the overflow tank.
Level gauge shall be provided to monitor the level in the overflow tank. A hard wire high level switch shall also
be provided to isolate the pump power supply. ANSI 150 flanges and fittings shall be provided in accordance
with the P&ID.
The tank shall be painted with the same colour scheme as the CEPS10 bulk tanks.
The tank is to be emptied via a waste removal vehicle for disposal off site.
01-1022-000-SPC-FU-0007[02].docx Page 15 of 50
7.3 Overflow Tank
An overflow collection tank shall be provided which collects fuel overflow from the day tanks. The tank shall
be a 1,200 L doubled walled carbon steel tank compliant to AS1692 and shall be located in Building 10. Fuel
shall be gravity drained from the day tanks to the overflow tank.
Level gauge shall be provided to monitor the level in the overflow tank. A hard wire high level switch shall also
be provided to isolate the pump power supply.
The tank is to be emptied via a waste removal vehicle for disposal off site.
7.4 Valves
All valve body material of construction shall be carbon steel.
All valves to be fire safe according to API 607 and API 598
8 Material Specification
8.1 Scope
This specification details the technical and material requirements for pipe, piping components and associated
performance criteria for the Temporary CEPS system at Garden Island (East) NSW. The Contractor shall
ensure that that all materials and piping materials used for the proposed project are consistent, are fit for
purpose, perform as designed, provide a safe working environment and meet all regulatory standards and
requirements
01-1022-000-SPC-FU-0007[02].docx Page 16 of 50
8.3 Handling of Pipes & Fittings
Pipes & fittings shall be handled at all times with equipment designed to prevent damage. Pinch bars, chains
or cable slings or other pipe handling equipment that may be injurious to the pipe or coatings shall not be
used. Suitable padding (submitted for review or rejection in advance by the Contractor) shall be used between
the pipe and the skid to prevent damage during laying operations. Any loss or damage to piping and other
materials, as a result of their movement at the work site, shall be made good by the Contractor, at his/her
expense.
15 SWT
20 SRT SWT
25 SRT SRT SWT
H 40 SRT SRT SRT SWT
E 50 SOL SOL SOL SOL BWT
A 80 SOL SOL SOL SOL BRT BWT
D 100 SOL SOL SOL SOL BRT BRT BWT
01-1022-000-SPC-FU-0007[02].docx Page 17 of 50
E 150 SOL SOL SOL SOL URB BRT BRT BWT
R 200 SOL SOL SOL SOL URB URB BRT BRT BWT
250 SOL SOL SOL SOL URB URB URB BRT BRT BWT
D 300 SOL SOL SOL SOL URB URB URB URB BRT BRT BWT
N 350 SOL SOL SOL SOL URB URB URB URB URB BRT BRT BWT
400 SOL SOL SOL SOL URB URB URB URB URB URB BRT BRT BWT
450 SOL SOL SOL SOL RB RB RB RB RB RB RB BRT BRT BWT
15 20 25 40 50 80 100 150 200 250 300 350 400 450
B R A N C H D N
LEGEND
SWT Socket Weld Tee
SRT Socket Weld Reducing Tee
SOL Socket Weld O-let Fitting
BWT Butt-weld Tee
BRT Butt-weld Reducing Tee
URB Un-reinforced Branch
RB Reinforced Branch
All joints should be either full-penetration butt-welded or flanged. Any joint not flanged shall need to be
approved by Lendlease prior to work taking place.
The pipe shall be gradually graded towards low points. Low points shall have DN 25 low point drain valves to
prevent free water and contaminants stagnating in the pipeline.
01-1022-000-SPC-FU-0007[02].docx Page 18 of 50
accordance with ASME B16.5 (BS1560) for use with raised face flanges size DN15-DN600. Material
Certification is required for use of all stud bolts used throughout construction.
All flange joints shall use spiral wound gaskets (unless stated otherwise) and will be defined to the following
specification:
4.5mm nominal thickness;
Graphite filled material, outer stainless steel for C1;
PTFE filler low stress seating, inner/outer ring stainless steel 316 LL for S1; and
Designed to ASME B16.20
Material and construction certificates are required for use of all spiral (or otherwise) gaskets used throughout
construction.
Refer to Appendix B for Project piping specification.
8.10 Trenching
The trenching methodology applies to all services trenching (internal and external of the building footprint)
and includes mechanical and electrical services. This following applies for the trenching requirements for
temporary CEPS enabling works.
The Fuel contractor is to excavate all fuel trenches in accordance with the drawings and
specifications whilst at all times coordinating the works with other Contractors.
The Fuel contractor must place excavated trench material adjacent to the trench or in a location
agreed with Lendlease and the Environmental consultant to allow testing and classification of the
excavated material by the Environmental Consultant. Excavated material may be reused for
backfilling of trenches if an acceptable classification for the material is determined by the
Environmental consultant and the material complies with the requirements of the Civil Specification
for services trenches backfill as determined by the Civil consultant. The Fuel contractor is
responsible for all costs associated with the testing and certification to confirm compliance with the
civil specification of reused backfill material. Any excavated trench material tested and classified as
contaminated is to be stockpiled in a location agreed with the Contractor. The Fuel contractor is
responsible for all costs associated with the disposal of any unused trench material including
material deemed contaminated.
The services contractors will verify the trench depth and/or grades & provide acceptance prior to
installing their bedding layer, the service(s) and subsequent initial backfilling around the service(s).
Initial backfilling shall extend a minimum of 100mm above the top of the service(s). Initial backfilling
01-1022-000-SPC-FU-0007[02].docx Page 19 of 50
material must be in accordance with the civil specification i.e. cement stabilized natural sand under
building pads and pavements and select fill in landscape and other areas (or equivalent) and
compacted to the requirements of the specifications and standards. The services contractors are to
submit bedding material sample for approval prior to ordering and placing. If services are required
to be concrete encased, the supply, placement and compaction of the concrete will the responsibility
of the services contractor.
The services contractor must supply and place tracer strips or identification tape/barrier for every
service installed. Buried marker tape shall comply with the following as a minimum:
- Tape shall be located a minimum of 300mm above the pipeline;
- Tape shall be permanently coloured with a high visibility colour;
- Tape shall identify the nature of the buried pipeline;
- Tape shall have a sufficient strength, ductility and slack to prevent it breaking before
it becomes visible; and
- Tape shall have a lifespan not less than the design life.
The Fuel contractor must supply, place and compact suitable backfill material to haunch (side
support zone) to at least 300mm above service and to the top of the trench in accordance with the
drawings and specification or as instructed by Lendlease.
The Fuel contractor must undertake compaction testing and certify compliance in accordance with
the specification.
All compaction test result must be approved by the relevant services trade and also submitted to
Lendlease.
If redundant services are encountered during the services trenching works the Fuel contractor must
remove the redundant service affecting the installation of new works.
All excavation activities shall be undertaken in accordance with the Lendlease permit to work
system. An approved excavation permit is required prior to commencement of excavation and all
required control measures are to be implemented prior to commencement of excavation.
8.12 Penetrations
All penetrations in the tunnel are to be fire rated and water tight with adequate flexibility.
Penetrations through all structures shall be sealed and water tight. Additionally, penetrations through fire rated
walls shall be sealed with a suitable sealant around the pipe such as 3M Fire Barrier Sealant FD 150+ TDS
or HB Fuller to provide enough flexibility and movement for the pipe. This shall be followed by adding in
additional sealing such as Promastop Cement or equivalent where required in order to maintain the fire rating
01-1022-000-SPC-FU-0007[02].docx Page 20 of 50
of the wall. Cement shall carry a fire rating equal or better than that of the wall being sealed. Contractor shall
provide fire test certificates and reports for sealant product.
All penetrations shall comply with BCA Part C3.15 and fire rated penetrations shall comply with AS
4072.1:2005.
Span (m) 1.5 2.0 3.0 4.0 4.8 5.4 6.4 6 8.0 8.6
All supports shall be hot dipped galvanised and as per the details in the design drawings.
Separate considerations relating to material compatibility of piping (i.e. carbon steel and galvanised supports)
and their exposure to fuel should be paramount. Additionally, these products will be exposed to weather and
the grade of material shall not degrade or deform under the design temperatures and parameters indicated in
the piping construction standards and scope of works. In accordance with DFI-DPM Section 6.11, where all
pipelines are mounted on supports other than that of the pipeline material, polymeric insulators shall be
installed to isolate the sections.
Pipe supports shall be laid based on the weight and forces imposed by the fuel pipeline as detailed in drawings
to protect equipment, such as pumps, tanks and valves from excess mechanical loading.
Anchor structures and pipe supports shall be constructed to prevent wear and corrosion of the piping and
should allow for adjustment of the support.
01-1022-000-SPC-FU-0007[02].docx Page 21 of 50
8.15.2 Storage of Materials
Where all materials, goods and equipment for use in construction are stored on site, the type of storage
facilities and location of these facilities shall be agreed to by the Contractor as to their suitability before any
construction begins.
The Contractor is to provide details of their intentions regarding this clause in the tender proposal.
Any materials that become contaminated, may at the discretion of Lendlease, be removed, repaired and/or
replaced. The costs of such replacement or repair shall be at the Contractor’s expense.
01-1022-000-SPC-FU-0007[02].docx Page 22 of 50
Facility Product Requirements
9.4 Arrangement
Pipe work shall be arranged as simply as possible with a minimal number of runs.
Where required, pipes shall be arranged to provide for expansion and contraction caused by changes in
ambient temperature.
9.6 Identification
The Temporary CEPS tank and corresponding piping shall be identified as per AS 1940 and AS 1345 to
ensure markers, colour codes, etc are consistent.
Tagging for all instrumentation and valving shall be a carbon steel/stainless steel label engraved with the tag
number of the instrument or valve and back painted with a black or white UV stable epoxy paint. The tag shall
be approximately 50mm x 12mm x 1.2 thicknesses (min). Lettering shall be approximately 10mm high. The
tag shall be connected to the instrument or valve be means of a carbon steel/stainless steel wire cable and
crimped permanently to avoid unnecessary or inadvertent removal.
01-1022-000-SPC-FU-0007[02].docx Page 23 of 50
Contractor shall consult the Dangerous Goods Report (00-1022-000-REP-DG-0001) for detail on
signage;
Markings shall be displayed on the outside wall of the tanks and shall be not less than 150 mm in
height.
All markings shall be of a colour contrasting with that of the tank.
All recommendations as outlined in AS 1940 shall be followed.
All tanks shall be marked with appropriate warning placard as required by WHS or relevant
regulation.
01-1022-000-SPC-FU-0007[02].docx Page 24 of 50
Figure 1: Valve Tags
01-1022-000-SPC-FU-0007[02].docx Page 25 of 50
Sufficient clearance shall be accommodated for servicing and maintenance purposes, specifically around
flanges in pits.
9.11 Welding
9.11.1 Qualification
Welded joints done offsite (i.e. in the workshop) and onsite shall comply with AS 4041 Pressure Piping.
Qualification of alternative weld procedures may be considered and shall be provided for review or rejection
of Lendlease.
As a minimum, the following shall be submitted prior to any production welding being reviewed or rejected:
Weld Procedure Specification
Weld Procedure Qualification Record (with welder details)
Welder Qualifications
Weld Inspection & Testing Quality Procedures
Inspection & Test Plan (Procedures)
Detailed inspection and test plans outlining construction procedures for fabrication and production welds shall
also be submitted for review or rejection. The Contractor shall submit welding procedures for review or
rejection and these procedures must be qualified. The qualifying of the procedures and the welders shall be
at the cost of the Contractor.
01-1022-000-SPC-FU-0007[02].docx Page 26 of 50
Weld radiography, examination, acceptance and repair of defective welds shall be in accordance with AS
4041.
If radiographic testing is not possible and suitable reasoning and qualification is submitted to and approved
by Lendlease, dye-penetrant testing in accordance with AS 2062 and AS 4041 can be conducted.
At least one weld must be radiographed for each welder. NATA registered personnel shall carry out
radiographic inspections. Weld repairs and repeat NDT shall be at the cost of the Contractor. Re-testing shall
only be done once and if the additional test specimen fails, the welding procedure shall be deemed non-
compliant to the standard.
The Contractor shall nominate the personnel, methods (i.e. radiographic) and equipment for inspection of
welds during the tender submission. The Contractor is also to prepare a Weld Testing Plan for submission
and approval by Lendlease.
A clearance of 450 mm minimum, or greater if required by an inspecting radiographer, shall be provided at all
points around joints to permit ease of radiographing of the welded joint. A similar clearance shall be provided
around closing welds in the trench.
The Contractor, at their own expense, shall repair all defective welds.
100% visual inspections shall be undertaken for all welds by a qualified Welding Inspector.
The nominated NDT level will be 10% (radiographic inspection weld tests) for butt welded pipe joints.
01-1022-000-SPC-FU-0007[02].docx Page 27 of 50
No fabrication shall occur until all fabrication procedures have been reviewed or rejected by
Lendlease;
Identification of all materials shall remain throughout the fabrication process;
Spool fabrication numbers shall be assigned by the fabricator and should be in accordance with the
pipe drawings schedule. These numbers shall be marked on the pipework using an approved marker
pen during construction and on the spool fabrication (workshop) drawings;
Only consumable items designated for use with carbon steel may be used (silicon carbide, iron free
cutting and grinding discs, wire brushes etc.);
Covering of open ended piping spools, piping construction materials and equipment shall occur at
the completion of daily work procedures or when the constructed item is not being worked on to
ensure that no contamination occurs;
All seam welded piping shall be staggered longitudinally;
Unless otherwise stated, flange boltholes shall straddle the natural vertical and horizontal centrelines
of pipework;
All machined faces of piping flanges and proprietary items (valves) shall be checked for damage
before installation. If any item is damaged it will be removed and replaced at the Contractor’s
expense;
Internal butt-weld surfaces of orifice flanges and other flow equipment are to be ground flush;
All butt-weld connections shall be bevel-cut using machining or grinding processes. All preparations
should reflect the procedure outlined in the weld procedure specification. It is recommended that all
field weld preparations in areas classified as hazardous areas (especially for tie-in welds) be
performed by cold cutting machines, as these devices provide quality in position preparation;
On socket weld piping a gap of 1.5 mm should be left between the bottom of the pipe and the fitting
to ensure that “Bottoming” of the joint does not occur;
Welders making branch connections, socket weld or weldolet connections shall be qualified
accordingly and a procedure for the connections provided. Weldolet connections shall be performed
as per manufacturers recommendations;
The minimum distance between full penetration butt welds shall be minimum 100 mm or 6 times the
pipe wall thickness (whichever is the greater). Any weld that contradicts this clause will be brought
to the attention of Lendlease for assessment;
Line heating for correction to distortion or for correction of flange position is not permitted;
Cold springing or forcing of pipework for alignment or making a joint is not permitted;
All pipe fabrication shall be performed using the appropriate use of pipe supports during the tacking
phase and the practices of dogging into alignment the pipe or fitting is not permitted. If pipe clamps
are used they must be stainless steel or be appropriately insulated for use with stainless alloys;
The alignment of flanges across the perpendicular plane shall be plus or minus 5mm/m (1/4 Degree)
of the theoretical centreline of the joint;
Deviation of bolt hole alignment shall be +/- 1.5mm; and
Alignment of Bore:
- Piping above 6.0 mm wall thickness +/- 1.5mm.
- Piping below 6.0 mm wall thickness +/- 25% wall thickness.
Installation of UPP piping shall be in accordance with the manufacturer’s instructions.
01-1022-000-SPC-FU-0007[02].docx Page 28 of 50
9.11.9 Weld Repairs
All weld repairs should be performed in accordance to a weld repair procedure, and the weld procedure
specification for the repair must be qualified and approved by Lendlease before use. The Contractor shall
inform Lendlease of all weld failures as part of their ITP quality assurance plan.
10 Electrical Specification
10.1 E&IC Installation
All E&IC installations shall conform to the wiring rules (AS/NZS 3000) and to requirements in the Defence
MIEE.
01-1022-000-SPC-FU-0007[02].docx Page 29 of 50
The ambient temperature range for all electrical/instrumentation equipment associated with the installation is:
-10°C to +50°C.
All electrical equipment shall meet or exceed this ambient temperature range.
The Contractor shall ensure that all field electrical/ instrumentation equipment to be installed in an area not
protected by a dedicated structure against the effects of solar radiation is installed with a suitable protective
cover suited to the equipment.
The equipment shall be installed so that there is ease of access for future inspection and maintenance
activities.
All power and controls wiring to the fuel installation shall be protected from overcurrent, short circuit and earth
fault conditions. To comply with this the Contractor shall test all power circuits in accordance with the
mandatory tests stipulated in Clause 8.3.2 of AS/NZS3000.
The Contractor shall arrange to have all necessary testing completed prior to the completion of the
construction period.
All electrical equipment and related fittings (e.g. cable glands, bushings, plugs, etc.) shall be certified to comply
with the requirements of the equipment protection technique.
The Contractor shall ensure that all conduits shall have a suitable seal to stop the accumulation of dust, insect
nests, debris etc.
01-1022-000-SPC-FU-0007[02].docx Page 30 of 50
Switchboard shall be designed as per site conditions and applicable Australian/ Defence standards for
electrical installations.
Switchboards shall be rated for the wind loading for the appropriate region and terrain category as per AS
1170.2.
An adequate number of suitably sized eye bolts shall be provided to facilitate handling. Eye bolts shall be
located so that no distortion or fatigue will result from lifting. It should be possible to remove all lifting
accessories without needing access to any internal section of the enclosure.
Rivets in the assembly of all enclosures shall not be used. All metallic non-current-carrying parts of the
switchboard shall be electrically bonded to the main earth bar.
All electrically conductive doors shall have a flexible 6 mm2 earth connection to the enclosure frame.
Hinged internal panels are preferred over removable panels.
Water shedding feature on doors, door restraints with auto latch/unlatch feature shall be provided.
10.5.4 Doors
Door openings shall be of sufficient size as to permit the easy removal of equipment mounting panels and
components without interference to the construction and service entries.
Hinged doors should be mounted on heavy duty hinges and shall be capable of swinging through an angle of
not less than 120° from the closed position.
Lift-off hinges shall have unequal length pins to enable the door to be refitted with ease.
For outdoor switchboard, all hinges, handles and locks shall be stainless steel. Switchboards with a door
greater than 1000 mm high shall have a door stay fitted to the bottom of the door. Door stays and struts shall
be selected as heavy duty and suitable for high winds.
All doors shall be earthed.
All doors shall be fitted with pinchweld or neoprene rubber seals.
All doors shall have a Perspex holder for an A3 drawing or circuit schedule, mounted on the inside.
01-1022-000-SPC-FU-0007[02].docx Page 31 of 50
All doors should be padlockable.
10.5.5 Roof
All outdoor enclosures shall have a sloping rain / sun hood (at least 10° from the front to rear) and guttering
directing water away from doors. The enclosure roof shall be fitted with water shedding lip or gutter at the front
to prevent water running back under the roof.
10.5.7 Ventilation
Enclosures shall generally be non-ventilated except where resistors, electronic power devices or transformers
are enclosed. However, where heating from control devices results in a temperature rise detrimental to the
enclosed equipment or its operation, natural or forced ventilation shall be used. Any ventilating opening shall
be so designed as to minimise the entry of dust/ moisture.
10.5.10 Finish
Grade 316 stainless steel or aluminium enclosures shall be unpainted, matte finish, orbital sanded or similar.
Powder coating or painting may also be considered and approval shall be sought from Lendlease prior to
manufacturing.
10.5.11 Wiring
All control wiring within electrical equipment enclosures shall be installed in horizontal or vertical duct
(enclosed wiring/cable run) system. Wiring diagonally is not acceptable.
Where PVC insulated conductors are laid or secured to steel supports, they shall be covered over their entire
length with an insulating material (e.g. split PVC spiral sleeving or similar). Where wiring is to pass through
cut-outs in panelling, the hole shall be bushed with a PVC grommet or similar. All cabling shall comply with
AS/NZS 3000 and AS/NZS 3191, as applicable.
01-1022-000-SPC-FU-0007[02].docx Page 32 of 50
Where colours are used for identification purposes they shall comply with AS/NZS 2700 or Defence electrical
standard.
Low voltage and extra low voltage wiring within control panels should be kept separate.
AC and DC wiring within control panels shall be clearly labelled as such.
All low level signal wiring shall use screened pairs. A minimum of two pair of Dekoron type cabling shall be
used with a minimum cross-sectional area of 1.5mm².
Profibus, Ethernet, and Modbus wiring should be carefully routed away from mains and 24V DC cables.
AC wiring and DC wiring within Switchboard, where practicable, be kept separate. All equipment shall remain
fully accessible with labels and ferrules visible, after wiring and cabling has been completed.
Every wire shall be identified at both ends with an approved wire labelling system. Wire markers shall be
installed such that they may be read from the left to the right for horizontal runs when facing them and from
the bottom up for vertical markings. All markers shall be fully visible without removing equipment or ducting
covers.
10.5.13 Labels
Each switchboard shall have a nameplate in accordance with the requirements of AS/NZS 3439.1. In addition,
the nameplate shall indicate the switchboard internal arcing-fault tested value and time according to AS/NZS
3439.1 ZD.
Switchboard shall have a main label bearing the name or number of the switchboard in letters at least 25mm
high fixed to the door and the number and location of the source it is fed from.
Main labels for outdoor switchboards shall be stainless steel or anodised aluminium, engraved letters.
All equipment and devices inside switchboards should be identified with engraved traffolyte labels with black
letters and white surfaces.
Nameplates and labels shall be fixed by screws in slotted holes. Adhesive labels shall not be used.
Screws shall be stainless steel for all external labels on external switchboards and nickel plated for all other
labels. Labels larger than 100mm x 40mm shall have four fixing points.
All components shall be labelled in accordance with the related design drawings, indicating where necessary
their functions and ‘ON’ and ‘OFF’ positions. Labels shall not be fixed to removable equipment such as duct
covers and switchgear. External and internal labels shall be provided to identify equipment that is accessible
externally and internally, e.g. switches. Danger and warning signs shall have white letters on a red
background.
01-1022-000-SPC-FU-0007[02].docx Page 33 of 50
The Contractor shall supply, install and commission three Local Control Panels (LCP). One of the LCPs shall
contain relays to control the temporary CEPS fuel system. The LCP shall be mounted on a suitable pedestal
within the Temporary CEPS fenced area. Specific reference shall be made to Section 10.8.
Two local control panels (LCP022 and LCP023) shall be provided within Building 10 for use in the final CEPS
fuel system.
For local control panel details refer to drawing 01-1022-010-DRG-FU-6078.
10.9 Cables
The Contractor shall supply, install and commission all the electrical and control including communications
cables (if required) as per the design documentation. All cable installations shall comply with the requirements
of AS/NZS 3000.
The Contractor shall supply, install and terminate all electrical and instrument cabling, glands and associated
labels (contractor to prepare the electrical termination drawings and compile a final cable schedule).
All cable ties exposed to direct sunlight are to be stainless steel type. Nylon type is acceptable within cable
tray.
Analogue signal cables shall be segregated from power cables to avoid interference.
Intrinsically safe (I.S.) circuits and non-intrinsically (I.S.) safe circuits shall not be mixed within multi-core
cables and shall also be physically segregated from power cables.
Cables shall be terminated at each device or junction box using cable glands.
All external glands exposed to weather shall have PVC shrouds fitted.
All cables shall be in a continuous run unless the Managing Contractor approves otherwise in writing. Prior to
commencing the pulling or laying of cables the actual route length shall be checked by the Contractor to
ensure sufficient cable is available to meet the run without having to join the cable. The Contractor shall be
responsible for cutting cable to the correct length.
The outer sheaths of cables shall be coloured as follows:
Power Cables Orange or Black,
Control Cables Orange or Black, and
Intrinsically Safe Circuit Cables Blue.
01-1022-000-SPC-FU-0007[02].docx Page 34 of 50
All cables shall be identified at each end with stainless steel cable markers and carrier straps (or approved
equal).
01-1022-000-SPC-FU-0007[02].docx Page 35 of 50
Seal the buried entries to ducts and conduits with a pliable non-setting waterproof compound. Seal spare
ducts or conduits immediately after installation, and seal the others after the cable installation. Once cables
are installed, install warning tape as per AS/NZS 3000.
All pits installed in trafficable areas (including for maintenance purposes) shall be appropriately load rated and
approved before installation. Electrical pits shall be Class D, precast type and shall be lockable with a common
key.
11 Commissioning
11.1 General
Commissioning refers to operation of all the constituent functions of the completed works using fuels and all
other working media, as far as possible, under actual working conditions.
The Contractor shall ensure all the relevant pre-commissioning activities are undertaken, including completion
of FSB Commissioning Check Forms and the Pre-Start Up Safety Review (PSSR) and/or any Thales forms
(if applicable).
The Contractor shall take all steps necessary during commissioning to avoid accidental loss of fuel or other
oils to a minimum and contain any such leakage. The Contractor shall be responsible for any spills of fuel or
oil that shall be cleaned up immediately they occur and any remediation of the ground that may be required.
The Contractor shall be responsible for the disposal of spilled or leaked fuel after commissioning in
accordance with legislation and the Contractor’s CEMP.
During commissioning, the Contractor shall ensure that:
The operation of all the constituent functions of the completed works are satisfactory;
The integrity of the completed works is satisfactory; and
The fuel to be dispensed from the completed works must be of a very high standard of cleanliness.
01-1022-000-SPC-FU-0007[02].docx Page 36 of 50
The Contractor shall prepare a Commissioning Plan for Submission to Lendlease, a minimum of sixty [60]
days prior to any commissioning activities taking place. The Contractor shall update this document with
comments issued by Lendlease following review or rejection of the commissioning plan.
The Contractor shall also include in the commissioning plan details on the following:
A schedule of service shutdowns (if required);
Duration of shutdown periods; and
Contingency in the event of shutdown period overrun (at the expense of the Contractor).
The Contractor shall liaise with Lendlease and the Base to ensure that shutdown periods do not occur during
high activity periods.
11.4 Pre-Commissioning
Reference shall also be given to Installation Qualification Training detailed below.
The Contractor shall complete all works covered by the project and any other associated works that can be
completed prior to the introduction of fuel into the system.
The Contractor shall prepare commissioning plans detailing the tests to be carried out and the program and
procedures. Reference must be made to the Commonwealth of Australia’s legislation. This must incorporate
procedures for the works and the proposed emergency procedures that will be undertaken in the event of a
site spillage. The commissioning plans shall be submitted to Lendlease for review or rejection before
commissioning is due to commence.
Lendlease shall be notified in writing of the proposed fuel supplies for commissioning or hydrostatic testing a
minimum of thirty [30] days before they are required. The final requirement for fuel supplies shall be confirmed
to the Commonwealth before the fuel is required at the site.
The Commonwealth will be responsible for the supply of fuel in limited quantities for testing and
commissioning. The Contractor should calculate this quantity of fuel and have it agreed with by the
Commonwealth. Any excessive quantity of fuel will be supplied by the Commonwealth and shall be paid by
the Contractor. This requirement ensures that a high level of quality control in works will be maintained to
minimise fuel leakage and area contamination in testing and commissioning. The Contractor shall be
responsible for the provision of facilities and personnel to supply fuel and for the disposal of contaminated
fuel, under the supervision of the Commonwealth.
Lendlease shall advise and provide direction should the Commonwealth elect to not provide fuel for testing.
Fuel shall not be introduced into the equipment, pipelines, work or installation until the following have been
completed satisfactorily:
All essential checks and tests have been undertaken;
The installation is in a suitable, safe condition to accept fuel;
All emergency and safety procedures are in place;
The testing of all electrical installations and bonding, earthing and lightning protective systems;
The issue to the Commonwealth, test certificates with respect to the testing referred to in the
foregoing item above;
The execution of alignment checks on all major items of plant and equipment such as the pipeline,
and valves, and availability of certificates relating to performance and pressure test;
The pressure testing of all piping; with certification;
All identification markings, danger/warning notices positioned; and
01-1022-000-SPC-FU-0007[02].docx Page 37 of 50
Test position indicators on valves.
Completion of Fuel Services Branch’s Pre-Startup Safety Review forms and/or any Thales forms (if
applicable).
The Contractor shall provide Lendlease written confirmation that the above checks have been undertaken and
that the installation is in a suitable, safe condition to accept fuel. Prior to fuel being introduced to the
installation, the prior approval must be sought from Defence, Thales, Operating Authority of the fuel facility
via Lendlease. This shall be a Hold point in the ITP.
01-1022-000-SPC-FU-0007[02].docx Page 38 of 50
11.6.1 Pipework
The Contractor will ensure that the following is conducted with regard to Pipework:
Tested to AS 4041;
Welding tests - visual inspection, non-destructive testings and other necessary surveys;
Pressure tests of leak and strength; and
Dry film thickness and 100% holiday inspection tests for paint.
All new pipelines shall be blanked off and subjected to hydrostatic test using treated potable water or
demineralised water. Hydrostatic tests shall be performed in accordance to AS 4041 Section 6.7.
The testing shall be conducted and certified by an accredited NATA registered agency.
In the eventuality that a hydrostatic test does not pass the criteria of AS 4041 as noted, the Contractor shall
be responsible for rectification and any retesting.
The procedure shall also include full details of the proposed test report, which shall include, but not limited to:
Date of test;
Pipeline identification;
Test fluid;
Duration of test;
Test equipment; and
Test certification by examiner
At least twenty one [21] days’ notice shall be given prior to hydrotesting regarding attendance at the time of
testing. Testing shall only proceed on receipt of written approval by the Contractor. All items in the pipeline
such as isolating valves, strainers etc. shall be tested for correct operation prior to the test. Test gauges in
kPa accurate to 1% test pressure range shall be used.
By calibrated transducer and chart recording giving a paper copy print out of test incorporating pressure
of pipe system, ambient temperature, product temperature or surface temperature; and
Subject to total duration time of the test the Contractor should allow to conduct these tests in out–of-
hours periods.
Discharge of test water shall follow local authority requirements. Lendlease’ approval must be sought prior
to discharge.
01-1022-000-SPC-FU-0007[02].docx Page 39 of 50
HB 13, AS/NZS 1020, AS 1076 Series, AS/NZS 1768, AS 2381 Series, AS/NZS 3000, AS/NZS 3100
and AS/NZS 3017;
All Fuel tanks, pipework and equipment shall be bonded by the fuel contractor.
Factory Acceptance Testing of electrical equipment and switchboards;
Tested to any requirements defined in the Defence Infrastructure Manual, including but not limited
to:
- Visual inspection of installation
- Full functional tests
- Insulation and continuity testing for HV and LV requirements
- Correction operation of protection relays and other protective devices
- Instrument configuration and calibration
Copies of the test records shall be incorporated in the Operations and Maintenance Manual.
The Contractor shall provide Lendlease a copy of “Notification of Electrical Works” or equivalent,
together with all test results, particularly, the earth test results;
All ‘Point to Point’ checks for instrumentation and equipment; and
The Contractor shall provide logbooks with the original test results as required for equipment and
earthing systems.
01-1022-000-SPC-FU-0007[02].docx Page 40 of 50
Specifically, The Commonwealth will supply the initial batch of fuel for soak testing. The Contractor, prior to
any project fuel use, shall confirm this amount with Lendlease.
The fuel shall be able to be recovered for full testing and re-certification. It is not expected that any form of
contamination to be present in the system, other than particulates and small amounts of water, and therefore
it is reasonable to expect that the fuel can be recertified for use.
The supply of fuel by the Commonwealth is at their discretion. Lendlease shall advise and provide direction
should the Commonwealth elect to not provide fuel for testing.
The following costs are to be borne by the Contractor:
Cost of fuel lost through spillages; and
Cost of fuel that is rendered unserviceable due to contamination by the system.
11.8 Handover
The Contractor must give Lendlease all test certificates including, but not limited to, work test certificates of
all electrical services, pressure vessels and valves, radiography records, painting tests and inspections,
pressure tests, completed commissioning plans and records and any other documents requested before
handover.
The full set of “as installed” drawings, in the required format with the correct number of copies, must be
submitted, together with operation and maintenance manuals, prior to handover. Refer to Section 12 for
deliverable requirements.
11.10 Performance
The Contractor is required to demonstrate the capability of the delivered product to perform to the parameters
of the design. Where there is no standard or test method published, it shall be demonstrated to Lendlease
that the delivered product performs to the design specification.
The demonstrated operation of all new or modified components, in accordance with the documented
procedures using various scenarios, including 100% design capacity and maximum effort (i.e. surge capacity)
is required by the Contractor.
01-1022-000-SPC-FU-0007[02].docx Page 41 of 50
Note that not less than twenty one [21] days’ notice shall be provided to Lendlease of intent to undertake
functional testing.
12 Deliverables
The Contractor shall not rely solely on dimensions provided, but shall check all dimensions on site prior to
construction. The Contractor shall report any discrepancies, inconsistencies, errors and contradictions on
drawings and documentation immediately and seek Lendlease’s direction.
All equipment & fittings proposed for procurement shall be submitted to Lendlease with verification indicating
compliance with design intent and technical specification. Submissions shall be in the form of technical data
sheets and samples where relevant.
01-1022-000-SPC-FU-0007[02].docx Page 42 of 50
Construction of services conduits where specified;
Geotechnical testing, inspections and supervision as specified, with all costs associated with the
provision of Geotechnical activities borne by the Contractor;
Inspection Test and Hold Point Plan. Refer to Section 4 for a list of minimum hold point items
Works as executed drawings;
Ancillary and maintenance works related to WH&S and environmental protection during the course
of this contract; and
A consolidated register of all Works Plans (WPs), Installation and Test Records, Field Installation
Checklists, etc to be utilised by the Contractor shall be provided and included in the Quality Plan.
01-1022-000-SPC-FU-0007[02].docx Page 43 of 50
Schedules Microsoft Excel
Specifications and Sundry Text Microsoft Word
Data Projector Presentations Microsoft PowerPoint
Program Microsoft Project
3D Model Navis Works
Documentation shall be compiled and submitted in accordance with the Defence Estate Maintenance
procedures.
01-1022-000-SPC-FU-0007[02].docx Page 44 of 50
The Contractor shall sign the work as executed drawings on completion of the works verifying that all proposed
works have been constructed as specified.
01-1022-000-SPC-FU-0007[02].docx Page 45 of 50
FAT and SAT records;
File notes, records or approvals detailing any departures from the design;
Construction and Installation certificates certifying that the installation complies with the relevant
Australian Standards, Defence policies and Acts and Regulations; and
Any other information deemed important to the construction and commissioning of the system.
01-1022-000-SPC-FU-0007[02].docx Page 46 of 50
The Contractor shall address unplanned maintenance requirements to ensure that in an emergency
the site is made safe and secure. The response criteria shall be agreed between Lendlease and the
Contractor.
01-1022-000-SPC-FU-0007[02].docx Page 47 of 50
14 Commonwealth Personnel Training
Specific training for nominated Commonwealth Personnel is to be provided. As a minimum this shall include
training for all new and modified equipment and systems supplied under the Contract.
The Contractor shall provide training to ensure the Commonwealth operators and maintenance staff are
capable of operating and maintaining the CEPS facility correctly, safely and efficiently. The Contractor shall
allow training for an agreed number of operating and maintenance personnel prior to the handover of the
commissioned facility. The operating and maintenance personnel will have had previous general CEPS facility
operational and/or maintenance training and fuel product knowledge. The content of the training shall be
tailored to the level of the participants, with greater depth provided where appropriate.
The training should concentrate on the operational and maintenance requirements of the CEPS facility. The
content of the training sessions will utilise content from the O&M manuals and where applicable, will also
include an orientation tour of the facility to reinforce the locations of key plant and equipment, isolation
valves/switches etc. Training shall be coordinated with the other trade Contractors to ensure that all aspects
of the facility are covered.
Prior to training, the agreed operating and maintenance manual and a full listing of vendor equipment
information should be available. It is expected the training will be conducted by an agreed number of
specialists from the Contractor. At least, one specialist should have a full understanding of operating the CEPS
facility. Each participant should have a set of trainer notes and handouts. All presentation slides and any other
training aids (such as O&M manual) used during presentations should be handed-over to The Commonwealth.
Signed documentation by Contractor Trainers – Defence personnel who undertook the training and Lendlease
confirming all training modules have been undertaken and completed to the satisfaction of Lendlease will be
required at Commissioning/Hand-over.
Completed documentation in draft format shall be submitted to Lendlease for review or rejection prior to
commencing training. Any changes, alteration or further explanations advised by Lendlease shall be
incorporated prior to modification from ‘draft’ to ‘final release’ format of the training documentation.
01-1022-000-SPC-FU-0007[02].docx Page 48 of 50
Appendix A - Reference Safety Data Sheet (SDS)
01-1022-000-SPC-FU-0007[02].docx Page 49 of 50
SAFETY DATA SHEET
Automotive Diesel Fuel
Section 1. Identification
GHS product identifier Automotive Diesel Fuel
Other means of G10, BP 10 ppm diesel fuel,Ultra Low Sulphur diesel Fuel, Automotive Diesel Fuel
identification AD 20 , AD40, ALPINE DIESEL, Biodiesel B5
Product code 0000002718
SDS no. 0000002718
Historic SDS no. AD0K1
Relevant identified uses of the substance or mixture and uses advised against
Use of the substance/ Fuel for compression ignition diesel engines.
mixture
Manufacturer
Supplier BP Australia Pty Ltd
Level 17, 717 Bourke Street
Docklands, Victoria 3008
ABN 53 004 085 616
www.bp.com.au
Product name Automotive Diesel Fuel Product code 0000002718 Page: 1/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 2. Hazard(s) identification
Prevention P201 - Obtain special instructions before use.
P260 - Do not breathe vapour.
P280 - Wear protective gloves. Wear eye or face protection. Wear protective
clothing.
P210 - Keep away from heat, hot surfaces, sparks, open flames and other ignition
sources. No smoking.
P241 - Use explosion-proof electrical, ventilating, lighting and all material-handling
equipment.
P273 -Avoid release to the environment.
Response P314 - Get medical attention if you feel unwell.
P308 + P313 - IF exposed or concerned: Get medical attention.
P304 + P340 + P312 - IF INHALED: Remove victim to fresh air and keep at rest in a
position comfortable for breathing. Call a POISON CENTER or physician if you feel
unwell.
P301 + P310 + P331 - IF SWALLOWED: Immediately call a POISON CENTER or
physician. Do NOT induce vomiting.
P302 + P352 + P362-2 + P363 - IF ON SKIN: Wash with plenty of soap and water.
Take off contaminated clothing. Wash contaminated clothing before reuse.
P332 + P313 - If skin irritation occurs: Get medical attention.
Storage P405 - Store locked up.
P403 - Store in a well-ventilated place.
P235 - Keep cool.
Disposal P501 - Dispose of contents and container in accordance with all local, regional,
national and international regulations.
Supplemental label Not applicable.
elements
Other hazards which do not This material may contain significant quantities of polycyclic aromatic hydrocarbons,
result in classification some of which have been shown by experimental studies to induce skin cancer.
Note: High Pressure Applications
Injections through the skin resulting from contact with the product at high pressure
constitute a major medical emergency.
See 'Notes to physician' under First-Aid Measures, Section 4 of this Safety Data
Sheet.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 2/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 4. First aid measures
Skin contact In case of contact, immediately flush skin with plenty of water for at least 15 minutes
while removing contaminated clothing and shoes. Clean shoes thoroughly before
reuse. Drench contaminated clothing with water before removing. This is necessary
to avoid the risk of sparks from static electricity that could ignite contaminated
clothing. Contaminated clothing is a fire hazard. Contaminated leather, particularly
footwear, must be discarded. Get medical attention.
Ingestion Do not induce vomiting. Never give anything by mouth to an unconscious person. If
unconscious, place in recovery position and get medical attention immediately.
Aspiration hazard if swallowed. Can enter lungs and cause damage. Get medical
attention immediately.
Specific hazards arising Combustible liquid. Fire water contaminated with this material must be contained
from the chemical and prevented from being discharged to any waterway, sewer or drain. In a fire or if
heated, a pressure increase will occur and the container may burst, with the risk of a
subsequent explosion. Runoff to sewer may create fire or explosion hazard.
Hazardous thermal Combustion products may include the following:
decomposition products carbon dioxide
carbon monoxide
other hazardous substances.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 3/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 5. Firefighting measures
Special protective actions Promptly isolate the scene by removing all persons from the vicinity of the incident if
for fire-fighters there is a fire. No action shall be taken involving any personal risk or without
suitable training. Move containers from fire area if this can be done without risk.
Use water spray to keep fire-exposed containers cool.
Special protective Fire-fighters should wear positive pressure self-contained breathing apparatus
equipment for fire-fighters (SCBA) and full turnout gear.
Hazchem code 3z
Environmental precautions Avoid dispersal of spilt material and runoff and contact with soil, waterways, drains
and sewers. Inform the relevant authorities if the product has caused environmental
pollution (sewers, waterways, soil or air). Water polluting material. May be harmful
to the environment if released in large quantities.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 4/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 7. Handling and storage
obtain special instructions before use. Do not handle until all safety precautions
have been read and understood. Do not swallow. Aspiration hazard if swallowed.
Can enter lungs and cause damage. Never siphon by mouth.
Advice on general Eating, drinking and smoking should be prohibited in areas where this material is
occupational hygiene handled, stored and processed. Wash thoroughly after handling. Remove
contaminated clothing and protective equipment before entering eating areas. See
also Section 8 for additional information on hygiene measures.
Conditions for safe storage, Store in accordance with local regulations. Store in a segregated and approved
including any area. Store in original container protected from direct sunlight in a dry, cool and well-
incompatibilities ventilated area, away from incompatible materials (see Section 10) and food and
drink. Store locked up. Eliminate all ignition sources. Separate from oxidising
materials. Keep container tightly closed and sealed until ready for use. Store and
use only in equipment/containers designed for use with this product. Containers
that have been opened must be carefully resealed and kept upright to prevent
leakage. Do not store in unlabelled containers. Use appropriate containment to
avoid environmental contamination.
Appropriate engineering All activities involving chemicals should be assessed for their risks to health, to
controls ensure exposures are adequately controlled. Personal protective equipment should
only be considered after other forms of control measures (e.g. engineering controls)
have been suitably evaluated. Personal protective equipment should conform to
appropriate standards, be suitable for use, be kept in good condition and properly
maintained.
Your supplier of personal protective equipment should be consulted for advice on
selection and appropriate standards. For further information contact your national
organisation for standards.
Provide exhaust ventilation or other engineering controls to keep the relevant
airborne concentrations below their respective occupational exposure limits.
The final choice of protective equipment will depend upon a risk assessment. It is
Product name Automotive Diesel Fuel Product code 0000002718 Page: 5/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 8. Exposure controls and personal protection
important to ensure that all items of personal protective equipment are compatible.
Environmental exposure Emissions from ventilation or work process equipment should be checked to ensure
controls they comply with the requirements of environmental protection legislation. In some
cases, fume scrubbers, filters or engineering modifications to the process
equipment will be necessary to reduce emissions to acceptable levels.
Protective gloves must give suitable protection against mechanical risks (i.e.
abrasion, blade cut and puncture). Protective gloves will deteriorate over time due
to physical and chemical damage. Inspect and replace gloves on a regular basis.
The frequency of replacement will depend upon the circumstances of use.
Recommended: Nitrile gloves.
Skin protection Use of protective clothing is good industrial practice.
Cotton or polyester/cotton overalls will only provide protection against light
superficial contamination that will not soak through to the skin. Overalls should be
laundered on a regular basis. When the risk of skin exposure is high (e.g. when
cleaning up spillages or if there is a risk of splashing) then chemical resistant aprons
and/or impervious chemical suits and boots will be required.
Wear suitable protective clothing.
Footwear highly resistant to chemicals.
When there is a risk of ignition from static electricity, wear anti-static protective
clothing. For greatest effectiveness against static electricity, overalls, boots and
gloves should all be anti-static.
When there is a risk of ignition wear inherently fire resistant protective clothes and
gloves.
Work clothing / overalls should be laundered on a regular basis. Laundering of
contaminated work clothing should only be done by professional cleaners who have
been told about the hazards of the contamination. Always keep contaminated work
clothing away from uncontaminated work clothing and uncontaminated personal
clothes.
When the risk of skin exposure is high (from experience this could apply to the
following tasks: cleaning work, maintenance and service, filling and transfer, taking
samples and cleaning up spillages) then a chemical protective suit and boots will be
required.
Personal protective equipment for the body should be selected based on the task
being performed and the risks involved and should be approved by a specialist
before handling this product.
Recommended: overall
Other skin protection Appropriate footwear and any additional skin protection measures should be
selected based on the task being performed and the risks involved and should be
approved by a specialist before handling this product.
Respiratory protection Use with adequate ventilation.
In case of insufficient ventilation, wear suitable respiratory equipment.
If there is a requirement for the use of a respiratory protective device, but the use of
breathing apparatus (independent of ambient atmosphere) is not required, then a
suitable filtering device must be worn.
The filter class must be suitable for the maximum contaminant concentration (gas/
vapour/aerosol/particulates) that may arise when handling the product.
The correct choice of respiratory protection depends upon the chemicals being
handled, the conditions of work and use, and the condition of the respiratory
Product name Automotive Diesel Fuel Product code 0000002718 Page: 6/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 8. Exposure controls and personal protection
equipment. Safety procedures should be developed for each intended application.
Respiratory protection equipment should therefore be chosen in consultation with
the supplier/manufacturer and with a full assessment of the working conditions.
Recommended: If ventilation is inadequate, use respirator that will protect against
organic vapour and dust/mist.
Refer to standards: Respiratory protection:AS/NZS 1715 and AS/NZS 1716
Gloves:AS/NZS 2161.1
Eye protection:AS/NZS 1336 and AS/NZS 1337
Product name Automotive Diesel Fuel Product code 0000002718 Page: 7/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 11. Toxicological information
Information on toxicological effects
Acute toxicity
Product/ingredient name Result Species Dose Exposure
Fuels, diesel LC50 Inhalation Dusts and mists Rat 4.1 mg/l 4 hours
LD50 Dermal Rabbit >4300 mg/kg -
LD50 Dermal Rabbit >4300 mg/kg -
LD50 Oral Rat 17900 mg/kg -
LD50 Oral Rat 7600 mg/kg -
Irritation/Corrosion
Product/ingredient name Result Species Score Exposure Observation
Fuels, diesel Skin - Irritation Rabbit - - -
Skin - Irritation Rabbit - - -
Eyes - Non-irritating to the Rabbit - - -
eyes.
Eyes - Non-irritating to the Rabbit - - -
eyes.
Skin Causes skin irritation.
Sensitisation
Product/ingredient name Route of Species Result
exposure
Fuels, diesel skin Guinea pig Not sensitising
skin Guinea pig Not sensitising
Mutagenicity
Product/ingredient name Test Experiment Result
Fuels, diesel OECD 471 Experiment: In vitro Positive
Subject: Non-mammalian species
Equivalent to OECD Experiment: In vitro Negative
476
Subject: Mammalian-Animal
Cell: Germ
not guideline Experiment: In vivo Negative
Subject: Unspecified
Cell: Somatic
Conclusion/Summary Not classified. Based on available data, the classification criteria are not met.
Carcinogenicity
Product/ingredient name Result Species Dose Exposure
Fuels, diesel Positive - Dermal - Mouse - 2 years
Unspecified
Conclusion/Summary Suspected of causing cancer.
Reproductive toxicity
Product/ingredient name Maternal Fertility Developmental Species Dose Exposure
toxicity toxin
Fuels, diesel - - Negative Rat Dermal 20 days
- - Negative Rat Dermal 10 days
- - Negative Rat Dermal 10 days
Conclusion/Summary Development: Not classified. Based on available data, the classification criteria are
not met.
Fertility: Not classified. Based on available data, the classification criteria are not
met.
Effects on or via lactation: Not classified. Based on available data, the classification
criteria are not met.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 8/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 11. Toxicological information
Specific target organ toxicity (repeated exposure)
Name Category Route of Target organs
exposure
Fuels, diesel Category 2 Not determined bone marrow, liver
and thymus
Aspiration hazard
Name Result
Fuels, diesel ASPIRATION HAZARD - Category 1
Alkanes, C10-20-branched and linear ASPIRATION HAZARD - Category 1
Delayed and immediate effects as well as chronic effects from short and long-term exposure
Eye contact Vapour, mist or fume may cause eye irritation. Exposure to vapour, mist or fume
may cause stinging, redness and watering of the eyes.
Inhalation Vapour, mists or fumes may contain polycyclic aromatic hydrocarbons some of
which are known to produce skin cancer. Vapour, mists or fumes may contain
polycyclic aromatic hydrocarbons some of which are known to produce skin cancer.
Vapour, mist or fume may irritate the nose, mouth and respiratory tract.
Skin contact As with all such products containing potentially harmful levels of polycyclic aromatic
hydrocarbons, prolonged or repeated skin contact may eventually result in dermatitis
or more serious irreversible skin disorders including cancer.
Ingestion If swallowed, may irritate the mouth, throat and digestive system. If swallowed, may
cause abdominal pain, stomach cramps, nausea, vomiting, diarrhoea, dizziness and
drowsiness.
General May cause damage to organs through prolonged or repeated exposure. Vapour,
mists or fumes may contain polycyclic aromatic hydrocarbons some of which are
known to produce skin cancer. Vapour, mists or fumes may contain polycyclic
aromatic hydrocarbons some of which are known to produce skin cancer.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 9/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 11. Toxicological information
Carcinogenicity Suspected of causing cancer. Risk of cancer depends on duration and level of
exposure.
Mutagenicity No known significant effects or critical hazards.
Teratogenicity No known significant effects or critical hazards.
Developmental effects No known significant effects or critical hazards.
Fertility effects No known significant effects or critical hazards.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 10/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 12. Ecological information
Bioaccumulative potential
This product is not expected to bioaccumulate through food chains in the environment.
Mobility in soil
Soil/water partition Not available.
coefficient (KOC)
Mobility Spillages may penetrate the soil causing ground water contamination. This material
may accumulate in sediments.
Other ecological information Spills may form a film on water surfaces causing physical damage to organisms.
Oxygen transfer could also be impaired.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 11/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 14. Transport information
Additional Remarks This product is not regulated This product is not regulated
information Combustible liquid Class C1 as a dangerous good when as a dangerous good when
(AS 1940). transported in sizes of ≤5 L or transported in sizes of ≤5 L or
≤5 kg, provided the ≤5 kg, provided the
Hazchem code packagings meet the general packagings meet the general
3Z provisions of 4.1.1.1, 4.1.1.2 provisions of 5.0.2.4.1, 5.0.2.6.
and 4.1.1.4 to 4.1.1.8. 1.1 and 5.0.2.8.
Initial emergency response
guide Emergency schedules
47 (EmS)
F-A, S-F
Transport in bulk according Proper shipping name MARPOL Annex 1 rules apply for bulk shipments
to Annex II of Marpol and by sea.
the IBC Code Category: gas oils, including ship's bunkers
International lists
National inventory
REACH Status For the REACH status of this product please consult your company contact, as
identified in Section 1.
Australia inventory (AICS) All components are listed or exempted.
Canada inventory All components are listed or exempted.
China inventory (IECSC) Not determined.
Japan inventory (ENCS) Not determined.
Korea inventory (KECI) Not determined.
Philippines inventory Not determined.
(PICCS)
Taiwan Chemical All components are listed or exempted.
Substances Inventory
(TCSI)
United States inventory All components are listed or exempted.
(TSCA 8b)
Product name Automotive Diesel Fuel Product code 0000002718 Page: 12/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Section 16. Any other relevant information
History
Date of printing 07/04/2016
Date of issue/Date of 07/04/2016
revision
Date of previous issue 07/04/2016
Version 1
Product Stewardship
Key to abbreviations ADG = Australian Dangerous Goods
ATE = Acute Toxicity Estimate
BCF = Bioconcentration Factor
GHS = Globally Harmonized System of Classification and Labelling of Chemicals
IATA = International Air Transport Association
IBC = Intermediate Bulk Container
IMDG = International Maritime Dangerous Goods
LogPow = logarithm of the octanol/water partition coefficient
MARPOL = International Convention for the Prevention of Pollution From Ships,
1973 as modified by the Protocol of 1978. ("Marpol" = marine pollution)
NOHSC = National Occupational Health and Safety Commission
STEL = Short term exposure limit
SUSMP = Standard Uniform Schedule of Medicine and Poisons
UN = United Nations
TWA = Time weighted average
VOC = Volatile Organic Compound
SADT = Self-Accelerating Decomposition Temperature
Varies = may contain one or more of the following 101316-69-2, 101316-70-5,
101316-71-6, 101316-72-7, 64741-88-4, 64741-89-5, 64741-95-3, 64741-96-4,
64741-97-5, 64742-01-4, 64742-44-5, 64742-45-6, 64742-52-5, 64742-53-6,
64742-54-7, 64742-55-8, 64742-56-9, 64742-57-0, 64742-58-1, 64742-62-7,
64742-63-8, 64742-64-9, 64742-65-0, 64742-70-7, 72623-85-9, 72623-86-0,
72623-87-1, 74869-22-0, 90669-74-2
Procedure used to derive the classification
Classification Justification
Flam. Liq. 4, H227 On basis of test data
Acute Tox. 4, H332 Calculation method
Skin Irrit. 2, H315 Calculation method
Carc. 2, H351 Calculation method
STOT RE 2, H373 (bone marrow, liver and thymus) Calculation method
Asp. Tox. 1, H304 Calculation method
Indicates information that has changed from previously issued version.
Notice to reader
All reasonably practicable steps have been taken to ensure this data sheet and the health, safety and environmental
information contained in it is accurate as of the date specified below. No warranty or representation, express or implied
is made as to the accuracy or completeness of the data and information in this data sheet.
The data and advice given apply when the product is sold for the stated application or applications. You should not use
the product other than for the stated application or applications without seeking advice from BP Group.
It is the user’s obligation to evaluate and use this product safely and to comply with all applicable laws and regulations.
The BP Group shall not be responsible for any damage or injury resulting from use, other than the stated product use
of the material, from any failure to adhere to recommendations, or from any hazards inherent in the nature of the
material. Purchasers of the product for supply to a third party for use at work, have a duty to take all necessary steps to
ensure that any person handling or using the product is provided with the information in this sheet. Employers have a
duty to tell employees and others who may be affected of any hazards described in this sheet and of any precautions
that should be taken. You can contact the BP Group to ensure that this document is the most current available.
Alteration of this document is strictly prohibited.
Product name Automotive Diesel Fuel Product code 0000002718 Page: 13/13
Version 1 Date of issue 07/04/2016 Format Australia Language ENGLISH
(Australia) (ENGLISH)
Appendix B - Pipe Specification
01-1022-000-SPC-FU-0007[02].docx Page 50 of 50
Piping Class C1
SERVICE: Naval Fuel F-76, Diesel Fuel
Design Condition Temperature 500C
Maximum Operating 1500 kPa(g)
Pressure
Hydrotest Pressure 1960 kPa(g)
AS 4041, ANSI B36.10, ASME B16.9, ASME B16.11, ASTM A182, ASTM A234,
Applicables Codes
ASTM A105, ASTM A53
Size Range DN15 - DN450
Flange Rating Class #150
Material Carbon Steel
Corrosion Allowance 1.5 mm
MATERIAL DIMENSION
SIZE DESCRIPTION NOTES
SPECIFICATION SPECIFICATION
PIPE:
ERW OR SEAMLESS, SCH 80, ASTM A53 GR B; API 5L
DN15 - DN40 ASME B36.10
NPT THREADED GR B; ASTM A106-B
ASTM A53 GR B; API 5L
DN50 – DN450 ERW OR SEAMLESS, SCH 40, BW ASME B36.10
GR B; ASTM A106 GR B
FITTINGS:
DN15 - DN40 CLASS 3000#, NPT THREADED ASTM A105 ASME B16.11
DN50 – DN450 SCH 40, BW ASTM A234 GR WPB ASME B16.9 1,2
ELBOW RADII:
SCH 40, BW, Elbow shall be long radius,
unless otherwise specified on project design
DN50 - DN450 ASTM A234 GR WPB ASME B16.9 1,2
drawings or approved by principal.
UNIONS:
DN15 3000#, FEMALE NPT THREADED ASTM A234 GR B ASME B16.3
‘OLETS:
MSS-SP-97,
DN15 - DN40 CLASS 3000#, NPT THREDOLET ASTM A105 2
ends as per ASME B1.20.1
MSS-SP-97,
DN50 - DN80 WELDOLET, SCH 40 ASTM A105 2
ends as per B16.9 & B16.25
FLANGES:
DN50 - DN450 WELD-NECK, RF, STOCK-FINISH, ASTM A105 ASME B16.5
CLASS 150#, SCH 40
GASKETS:
DN50 - DN450 4.5mm THK, SPIRAL WOUND, STAINLESS STEEL 316 ASME B16.20
GRAPHITE FILLED, OUTER RING GRAPHITE FILLED
STAINLESS STEEL 316L
BOLTING:
BOLTS / STUDS CARBON STEEL ASTM A193 GR B7 ASME B18.2.1
NUTS CARBON STEEL ASTM A194 GR 2H ASME B18.2.2
Valves
Size Valve Specification Valve Type
DN15 - DN40 BA4 Ball Valve, Threaded, Female NPT
DN50 - DN350 BA1, BA2 Ball valve, Flanged
DN50 - DN350 NR1 Non Return Valve, Flanged
DN15 - DN80 PRV1 Pressure Relief Valve
DN15 - DN25 TRV1 Thermal Relief Valve
Notes:
1) Where butt-welding elbows are specified, long radius type shall be used, unless specified by the design engineer.
2) For permitted methods of connecting branches refer to “Branch Connection Chart”
3) Refer to valve specification and valve datasheets for full valve description
4) Flat faced equipment or pipe fitting flanges shall be provided with flat faced flanges.
5) Where pipeline standard detail drawings show Class 300 flanges, these should be to the same specification as that described for
Class 150, with the exception of Class rating. Gaskets to be installed between Class 300 flanges should conform to the same
specification as those described for Class 150, with the exception of flange rating.
6) Where possible, piping shall be arranged in parallel groups to facilitate multiple uses of supports and to minimise the walkway
requirements over the pipes.
Piping schedule requirements may be reviewed at the discretion of the Head Contractor
7) Threads shall be sealed with appropriate PTFE sealing compound (not tape)
8) Non-destructive testing as per works description and AS 4041 (most stringent requirements to take precedence)