Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Total 7 processes in this knowledge area. First 6 processes are belongs to Planning Process Group and
last process belongs to Controlling & Monitoring Process Group
This is a methodology or a guide line which help teams members to perform time management on
project.
In this process we prepare the Schedule Management Plan, policies, procedures and documentations.
INPUT
(iii) EEF
(iv) OPA
(iii) Meetings
OUTPUT
It contains details like; Project Schedule Model Development, Level of Accuracy, Units of Measures,
Organizational Procedures Links, Project Schedule Model Maintenance, Control Threshold, Rule of
Performance Measurement.
INPUTS
(i) Schedule Management Plan
(iii) EEF
(iv) OPA
(i) Decomposition
Iterative planning technique in which work in near time will be decomposed in detail and the work in
future will be decomposed in later time. In a contractually bound environment regarding time, this
option is not very applicable.
OUTPUTS
It is a document which shows activity description, scope of work, activity identifier etc...
Supporting document which contain more details about activity like; sequential logic, activity code,
duration, resource requirements, resource constraints etc.....
Mile stone have zero duration and does not have any resource requirement.
INPUTS
(vi) EEF
(v) OPA
In this method activities are shown by nodes and graphically linked by logical relationship (FS, FF, SS, SF)
c) External Dependencies
d) Internal Dependencies
Application of lead & lags majorly depends on nature of work & activities relationship.
Lead: It is the amount of time where successor activity can be advance with respect to a predecessor
activity. (e.g. FS + 2 weeks lead; meaning successor activity will be start prior 2 weeks finishing the
predecessor activity)
Lag: It is the amount of time where successor activity can be delayed with respect to the predecessor
activity (e.g. SS + 15 days lag; meaning successor activity will be start after 15 days of starting
predecessor activity.)
In Lead we count time from the end of predecessor activity while in Lag we count time from the start of
predecessor activity.
OUTPUTS
(i) PROJECT SCEDULE NETWORK DIAGRAM
Majorly we do estimation for three attributes i.e. Resource, Duration & Cost.
It is advisable that estimation should be done who is going to perform the work.
Never pad an estimate (add days or cost just for the sake of "just in case")
It is a process of estimating the type & quantity of resources to perform each activity.
The benefit of this process is that it identifies he type, quantities and characteristics of resources which
will help in more accurate cost & duration estimates.
INPUTS
A calendar that identifies the working days & shifts of specific resource availability.
A document in which the results of risk analysis & risk response planning are recorded.
There is always a connection between resource & cost estimation. Later we have a chapter for this.
(vi) EEF
(v) OPA
It is a data based different organizations published for the production rates & unit costs of resources
according to particular location/city/country.
A technique in which we decompose the work packages in to activity level and estimate resources,
duration, cost of those activities and summing up those estimate for work packages and above level/s.
OUTPUT
To complete particular activity what resources we required (labor, material, machinery etc...)
INPUTS
(x) OPA
This is not a good estimating technique, can be used for preliminary estimation purpose just to know
quickly what will be the estimate.
Normal Distribution: 68% (with one standard deviation), 95% (with two standard deviation), 99.7% (with
three standard deviation)
Statistically we cannot sum the standard deviation, in this case we have find out the Variance of each
activity. Variance = SD2; then Sum of variance and then square root of variance will give us total SD.
OUTPUT
INPUTS
It is basically human resource assignment on each activity and it will help in Resource Levelling.
(xii) EEF
(xiii) OPA
It uses various techniques such as CPM, CCM, What-if Analysis, Resource Optimization etc.
Critical path is a longest path through a project, which determines the shortest possible duration.
Forward Pass
Backward Pass
Activity Duration
Total Float = LF -EF (TF is an amount of time we can delay an activity without delaying project end date)
Free Float: The amount of time we can delay the activity without delaying the successor activity.
It is a method which accounts resource limitations & project constraint as well, while in CPM we assume
that resources are unlimited and we concentrate only on time but in reality it is not a case.
Two Types:
a) Resource Leveling: Level resources according to availability, duplicate resources should be level.
Resource leveling will result into increased project duration. CPM might change because of resource
leveling.
b) Resource Smoothing: In this technique we use floats for utilizing resources. CPM will not be change in
this because we are utilizing floats to adjust resources.
SIMULATION: By using computer model, probability curves, statistics we can generate simulated models.
MONTE CARLO ANALYSIS: It is a simulation technique which uses Range Estimation (minimum,
maximum values)
Always perform Schedule Compression techniques on Critical Path to impact the Project Duration.
It is a technique to shorten the project duration without reducing the project scope.
a) Crashing: Adding more resources with least incremental cost. Side effect of crashing is Increased Cost.
b) Fast Tracking: Activities done in parallel manner to fast track the project based on dependency type
(mandatory or discretionary). Side effect of fast tracking is Increased Risk.
OUTPUT
It is a latest approved version of project time schedule. It can only be change through Formal Change
Control Procedure.
Actual representation of Project Schedule Model (Bar chart, milestone, network diagram etc...)
(vi) OPA
OUTPUTS
End of Chapter