WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY

Activity ID Activity Name Original Start Finish 2019


Duration
J F M A M J J A S O N

WO 31 TRAINI
TRAINING CENTER BLDG AT MAA AND MAB REFINERY 554 23-Jul-17 A 25-Nov-19

MILESTONES 663 23-Jul-17 A 25-Nov-19

T1000 Commencement of Work Order 0 23-Jul-17 A


T4550 Completion of Cable laying at MAA & MAB (KCCEC ) 0 22-Jun-19
T2220 Completion of Construction of training building at MAA ( Tarmeem ) 0 27-Jul-19
T4580 Completion of KCCEC scope of works 0 22-Aug-19
T2340 Completion of Construction of training building at MAB ( Tarmeem ) 0 27-Aug-19
T2230 Final Electrical & HVAC Commissioning for building (MAA ) 0 24-Nov-19
T4650 Work order Handover & Close out 0 25-Nov-19

ENGINEERING
ENGINEERIN 103 29-Jan-19 A 29-May-19

BALANCE ENGINEERING
ENG 103 29-Jan-19 A 29-May-19
T2650 Fire cabinet submission ( sample ) 10 29-Jan-19 A 26-Apr-19
A1050 Fire Water Tie-in shop drawing submission 15 15-Apr-19 01-May-19
A1330 Design Electrical Drawings for electrical sub station ( low tension panel room + transforme 15 15-Apr-19 01-May-19
A1340 Drawing submission for power / light / Fire alarm /data voices/ public address / power / ea 20 15-Apr-19 07-May-19
A1840 Power factor improvement capacitor & ATS and Isolator & capacitor 20 15-Apr-19 07-May-19
A1500 Floor Drain/ Cleanout Covers submission ( sample ) 10 30-Apr-19* 11-May-19
A1730 Transformer foundation & Room design 10 19-May-19 29-May-19

PROCUREMENT (TARMEEM)
PROCUREME 266 02-Jan-19 A 24-Nov-19

Submittals 46 15-Apr-19 06-Jun-19


Electrical 46 15-Apr-19 06-Jun-19
A1200 Switch Gear Submission (Schematic / SLD / Drawings) 10 15-Apr-19 25-Apr-19
A1260 Light Fittings & lighting works ( Internal external ) 15 15-Apr-19 01-May-19
A1400 Transformer 4 02-May-19 06-May-19
A1410 ETap Calculations 31 02-May-19 06-Jun-19
A1180 UPS submission 15 02-May-19 19-May-19
A1130 Lighting protection 14 08-May-19 23-May-19
A1280 IT Passive works 10 08-May-19 19-May-19
A1300 Switch fuse and isolator & capacitor and ATS 10 08-May-19 19-May-19
Mechanical 15 15-Apr-19 01-May-19
A1390 Submission for Car shade design 15 15-Apr-19 01-May-19
T4730 Submission for Sign board design 15 15-Apr-19 01-May-19
A1430 Submit Central water filters & Unit water heaters 15 15-Apr-19 01-May-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
A1490 Submission for Fire cabinets 5 27-Apr-19 01-May-19
Approval 59 15-Apr-19 22-Jun-19
Electrical 49 27-Apr-19 22-Jun-19
A1210 Approval Switch Gear modification & PO Placement 14 27-Apr-19 12-May-19
A1270 Light Fittings 10 02-May-19 13-May-19
A1060 Transformer 10 07-May-19 18-May-19
A1170 UPS Approval 15 20-May-19 05-Jun-19
A1290 IT Passive works 10 20-May-19 30-May-19
A1310 Switch fuse and isolator.& Capacitor & Isolator 15 20-May-19 05-Jun-19
A1140 Lighting protection 14 25-May-19 09-Jun-19
A1080 ETap Calculations 13 08-Jun-19 22-Jun-19
Mechanical 29 15-Apr-19 18-May-19
T4840 Fire Pump Approval 14 15-Apr-19 30-Apr-19
T4850 Water Pump Approval 14 15-Apr-19 30-Apr-19
A1380 Car shade design 7 02-May-19 09-May-19
A1120 Approval of sign board 10 02-May-19 13-May-19
A1420 Fire cabinet 5 02-May-19 07-May-19
A1440 Central water filters & Unit water heaters 14 02-May-19 18-May-19
A1520 Floor Drain/ Cleanout Covers ( sample ) 5 12-May-19 16-May-19
Delivery on Site
Sit 266 02-Jan-19 A 24-Nov-19
Civil and Arch.
Arch Material 65 15-Apr-19 29-Jun-19
T3460 Wooden Doors / Hardware Delivery on Site 5 15-Apr-19 20-Apr-19
A1000 Carpet Tiles / Granite/ skirting material/ Self levelling carpet 40 15-Apr-19 30-May-19
A1010 False Ceiling material & Acoustic tile 40 15-Apr-19 30-May-19
A1370 Alocobond Material (External Cladding ) 23 15-Apr-19 11-May-19
T3390 Work cubicle stations 12 15-Apr-19 28-Apr-19
A1810 UDS finishes & fence materials ( sample submission & delivery ) 40 15-Apr-19 30-May-19
T3400 Foldable partions 5 29-Apr-19 04-May-19
T4780 Aluminium Doors and Windows Delivery on Site 15 02-May-19 19-May-19
T3410 Metal shutter door 5 05-May-19 09-May-19
T3380 Car Park Shade & wheel Stopper 30 13-May-19 16-Jun-19
A1110 Building & traffic Sign boards 40 14-May-19 29-Jun-19
A1530 Floor Drain/ Cleanout Covers ( sample ) 5 18-May-19 22-May-19
Electrical 266 02-Jan-19 A 24-Nov-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
T3280 Cables /Wires /conduits Delivery on Site [Inside Building] 12 02-Jan-19 A 05-May-19
T3290 MSB+DB+SMSB 18 15-Apr-19 05-May-19
T3300 Fire alarm Cabling ( Honey well ) 53 06-May-19 06-Jul-19
T3350 Wiring acessories 33 06-May-19 12-Jun-19
A1220 (Switch Gear Modification works + Testing & commissioning MAA) ABB 168 13-May-19 24-Nov-19
T3360 Light fittings 20 14-May-19 05-Jun-19
A1160 Transformer 90 19-May-19 11-Aug-19
A1360 Switch fuse and isolator & capacitor & ATS banks 30 20-May-19 23-Jun-19
T3310 CCTV+IP Telephony +Data+Access control ( Cat 6 ) 30 01-Jun-19 04-Jul-19
T3340 Public Address Bosch ( Conduits & cables ) 13 01-Jun-19 15-Jun-19
A1190 UPS 20 06-Jun-19 29-Jun-19
A1320 Switch fuse and isolator. 5 06-Jun-19 11-Jun-19
A1150 Ligting protection 15 10-Jun-19 26-Jun-19
T3305 Fire alarm System ( Honey well ) 25 27-Jun-19 25-Jul-19
T3345 Public Address Bosch ( Active components ) 10 27-Jun-19 08-Jul-19
Mechanical 54 15-Apr-19 16-Jun-19
T4930 GRP Tanks Delivery on Site 20 15-Apr-19 07-May-19
T4870 Fire Pump Delivery on Site 10 01-May-19 12-May-19
T4880 Water Pump Delivery on Site 10 01-May-19 12-May-19
A1510 Fire cabinets 5 08-May-19 13-May-19
A1450 Central water filters & Unit water heaters 15 30-May-19 16-Jun-19

PROCUREMENT (KCCEC)
PROCUREME 82 01-Jan-19 A 19-Jun-19

APPROVAL OF MATERIAL & PLACEMENT OF PO'S ( KCCEC) 35 08-Feb-19 A 25-May-19


MECHANICAL ITEMS 12 15-Apr-19 27-Apr-19
T4610 Approval of Material for Cement Fire Water line 7 15-Apr-19 22-Apr-19
T4620 Placement of PO for Cement Fire Water line 5 22-Apr-19 27-Apr-19
ELECTRICAL ITEMS & INSTRUMENTATION 35 08-Feb-19 A 25-May-19
T2190 Placement of PO for Pig Tails & Connectors ( 400 No) 14 08-Feb-19 A 05-May-19
T1580 Submission of Material Approval Request for Network Cabinet & Patch Panel 5 15-Apr-19 20-Apr-19
T1560 Submission of Material Approval for panels & control Stations 5 15-Apr-19 20-Apr-19
A1040 Submission for MEW Approvals (MAB) ( Data sheet for Transformer ) 20 15-Apr-19 07-May-19
A1045 Submission for ETAP Calculations 20 15-Apr-19 07-May-19
T1720 Approval of material request for Network Cabinet & Patch Panel 15 20-Apr-19 05-May-19
T2010 Placement of PO for Panels & Control Station 6 20-Apr-19 26-Apr-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
A1070 MEW Approval for Power 15 08-May-19 25-May-19
A1075 Approval for ETAP Calculations ( MAA) 7 08-May-19 15-May-19
CIVIL ITEMS 0
MFG, INSPECTION
INSPECT & DELIVERY AT SITE 82 01-Jan-19 A 19-Jun-19
MECHANICAL ITEMS 57 15-Apr-19 19-Jun-19
T1820 GRE fresh water line 10 15-Apr-19 25-Apr-19
T1830 Cement Lined Pipes & Fittings 47 27-Apr-19 19-Jun-19
CIVIL ITEMS 20 01-Jan-19 A 25-Apr-19
T1780 General Construction Material ( Interlock tiles, kebstone, steel, concrete etc ) 20 01-Jan-19 A 25-Apr-19
ELECTRICAL ITEMS 0
INSTRUMENTATION ITEMS
INSTRUMENT 15 05-May-19 20-May-19
T2280 Network Cabinet ( 2 No) & Patch Panel ( 4 no) 10 05-May-19 15-May-19
T2300 Pig Tails & Connectors ( 400 No) 15 05-May-19 20-May-19

CONSTRUCTION
CONSTRUCT 253 03-Feb-19 A 24-Nov-19

TRAINING BUILDINGS
BUIL ( TARMEEM ) 0
CONSTRUCTION
CONSTRUCTIO 176 03-Feb-19 A 27-Aug-19
MAB BUILDING
BUILDIN 140 10-Mar-19 A 27-Aug-19
Civil/Structural, Architectural
Civil/Struc 127 10-Mar-19 A 27-Aug-19
Finishing Works
Finishin 127 10-Mar-19 A 27-Aug-19
Ground Level
Grou 118 10-Mar-19 A 15-Aug-19
T52Install high level partition [MAB] 12 10-Mar-19 A 26-May-19

T5 External Cladding (Alcapound) [MAB] 13 27-May-19 10-Jun-19


T5 Install Toilets and kitchen Accessories [MAB] 5 18-Jun-19 23-Jun-19
T5 Internal Painting [MAB] 25 25-Jun-19 23-Jul-19
T5 Install Cubicle work stations (package including foldable partitions )[MAB] 10 23-Jul-19 03-Aug-19
T5 Install Aluminium Doors Metal & shutter Doors and Windows [MAB] 20 24-Jul-19 15-Aug-19
T5 Install Wooden Doors [MAB] 5 31-Jul-19 05-Aug-19
Roof level 30 01-Jun-19 04-Jul-19
T5 Install Suspended Ceiling [MAB] 15 01-Jun-19 17-Jun-19
T5 Install False Ceiling [MAB] 15 18-Jun-19 04-Jul-19
T5 Install False Ceiling for Toilet area [MAB] 5 18-Jun-19 23-Jun-19
Spec Flooring works
Special 20 01-Jun-19 23-Jun-19
A Granite steps & landing for entrances.[MAB] 10 01-Jun-19 11-Jun-19
A Raised flooring & vinyl skirting (IT room). [MAB] 10 01-Jun-19 11-Jun-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 4 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
A Self-leveling under carpet 5 01-Jun-19 05-Jun-19
A Fixing Carpet Tiles[MAB] 5 06-Jun-19 11-Jun-19
A Epoxy flooring at work shop (with Terrazzo skirting).[MAB] 10 12-Jun-19 23-Jun-19
A17ramp concrete & Acess steps 5 18-Jun-19 23-Jun-19

A UDS finishes materials & fence 5 18-Jun-19 23-Jun-19


Furn
Furniture works 10 15-Aug-19 27-Aug-19
A Reception counter. [MAB] 10 15-Aug-19 27-Aug-19
A Installation of pantry wooden cabinets [MAB] 5 21-Aug-19 27-Aug-19
A Instllation of window blinds & curtains [MAB] 5 21-Aug-19 27-Aug-19
Externa Works
External 85 04-May-19 11-Aug-19
T530 Septic Tank [MAB] 6 04-May-19 09-May-19
T531 Connection between WC & Septic Tank (plumbing )[MAB] 2 11-May-19 12-May-19
T633 GRP TANK [MAB] 7 13-May-19 20-May-19
T571 Car Parking foundation [MAB] 10 28-May-19 08-Jun-19
A171 Transformer Foundation & Room works 45 30-May-19 21-Jul-19
T588 Car Parking Shade [MAB] & Wheel Stopper [MAB] 14 23-Jun-19 08-Jul-19
A154 Installation of Metal handrails for entrances & ramps. 5 05-Aug-19 11-Aug-19
MEP Work
Works 135 17-Mar-19 A 20-Aug-19
Electrical Works
Electric 47 27-Jun-19 20-Aug-19
T511 Install Lightning Protection [MAB] 35 27-Jun-19 06-Aug-19
A146 Central water filters & Unit water heaters [MAB] 10 04-Jul-19 15-Jul-19
A175 Digital Signage, Audiovisual, Security ( Passive works ) 10 06-Jul-19 16-Jul-19
T507 Installation of Electrical [Data and Telephone] Conduit. [MAB] 12 09-Jul-19 22-Jul-19
T509 Install Final Fix Items (Lighting,Telephone,Date Output] [MAB] 9 24-Jul-19 03-Aug-19
T513 Install of Fire Alarm System [MAB] 8 27-Jul-19 04-Aug-19
T508 Wiring and Cabling Electrical and Telephone. [MAB] 10 04-Aug-19 14-Aug-19
T510 Install Electrical Panels [MAB] 1 04-Aug-19 04-Aug-19
T632 Install Earthing system 5 05-Aug-19 10-Aug-19
T512 Install of Public adress System [MAB] 5 15-Aug-19 20-Aug-19
Mechan
Mechanical Works 97 17-Mar-19 A 07-Jul-19
Fire Fitting System 97 17-Mar-19 A 07-Jul-19
T5 Fire Hose Cabinet [MAB] 16 17-Mar-19 A 20-May-19
A Instllation of fire Extinguisher 10 02-Jun-19 12-Jun-19
T5 Fire line installations & Tie in [MAB] 10 26-Jun-19 07-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 5 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
HVAC & DX Units 25 21-May-19 18-Jun-19
T5 Exhaust Fans [MAB] 6 21-May-19 27-May-19
A HVAC Duct Unit ( MAB ) 5 28-May-19 02-Jun-19
T5 Install DX unit [MAB] 4 03-Jun-19 06-Jun-19
T6 Installation of grills and diffusers , duct heaters [MAA] 5 08-Jun-19 12-Jun-19
T6 Installation of Electrcial Components wiring and controls 5 13-Jun-19 18-Jun-19
MAA BUILDING
BUILDIN 145 03-Feb-19 A 21-Jul-19
Civil/Structural, Architectural
Civil/Struc 145 03-Feb-19 A 21-Jul-19
Finishing Works
Finishin 133 03-Feb-19 A 09-Jul-19
Special Flooring works
Spec 15 01-Jun-19 17-Jun-19
A Granite steps & landing for entrances. 10 01-Jun-19 11-Jun-19
A Raised flooring & vinyl skirting (IT room). 10 01-Jun-19 11-Jun-19
A Epoxy flooring at work shop (with Terrazzo skirting). 10 01-Jun-19 11-Jun-19
A Self-leveling under carpet 5 01-Jun-19 05-Jun-19
A Fixing Carpet Tiles 5 06-Jun-19 11-Jun-19
A ramp concrete & Acess steps 5 06-Jun-19 11-Jun-19
A UDS finishes materials & fence 5 12-Jun-19 17-Jun-19
Grou Level
Ground 116 03-Feb-19 A 17-Jun-19
T5 Internal Painting [MAA] 8 03-Feb-19 A 25-May-19
T3 Wall Ceramic Tiles [MAA] 5 10-Mar-19 A 15-Apr-19
T4 External Cladding (Alcapound) [MAA] 21 01-Apr-19 A 23-May-19
T3 Install Cubicle work stations (package including foldable partitons )[MAA] 13 24-Apr-19 09-May-19
T4 Install Wooden Doors [MAA] 6 16-May-19 21-May-19
T3 Install Aluminium , Metal & shutter Doors and Windows [MAA] 8 20-May-19 28-May-19
A Fixing Carpet Tiles [MAA] 10 06-Jun-19 17-Jun-19
T4 Install Toilets and kitchen Accessories [MAA] 5 08-Jun-19 12-Jun-19
Roof level 31 17-Feb-19 A 09-Jul-19
T3 Install False Ceiling [MAA] 20 17-Feb-19 A 09-Jul-19
T3 Install False Ceiling for Toilet area [MAA] 6 17-Feb-19 A 09-Jul-19
T3 Install Suspended Ceiling [MAA] 10 17-Feb-19 A 09-Jul-19
Furn
Furniture works 10 26-Jun-19 08-Jul-19
A Reception counter. 10 26-Jun-19 08-Jul-19
A Installation of pantry wooden cabinets 5 02-Jul-19 08-Jul-19
A Instllation of window blinds & curtains 5 02-Jul-19 08-Jul-19
External Works
Externa 80 20-Apr-19 21-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 6 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
T431 Septic Tank [MAA] 12 20-Apr-19 04-May-19
T452 Connection between WC & Septic Tank (plumbing )[MAA] & Testing 10 04-May-19 14-May-19
T454 Car Parking foundation [MAA] 10 11-May-19 21-May-19
T492 GRP TANK [MAA] 7 13-May-19 20-May-19
A155 Installation of Metal handrails for entrances & ramps. [MAA] 5 29-May-19 03-Jun-19
A172 Transformer Foundation works & Room works [MAA] 45 30-May-19 21-Jul-19
T457 Car Parking Shade [MAA] & Wheel Stopper [MAA] 14 17-Jun-19 02-Jul-19
MEP Work
Works 130 14-Feb-19 A 18-Jul-19
Electrical Works
Electric 30 13-Jun-19 18-Jul-19
T413 Wiring and Cabling Electrical and Telephone. [MAA] 13 13-Jun-19 27-Jun-19
T441 Install Lightning Protection [MAA] 3 27-Jun-19 01-Jul-19
T440 Install Electrical Panels [MAA] 3 29-Jun-19 02-Jul-19
T443 Install of Fire Alarm Cabling [MAA] 7 29-Jun-19 07-Jul-19
T442 Install Earthing system [MAA] 5 02-Jul-19 08-Jul-19
A1760 Central water filters & Unit water heaters [MAA] 10 04-Jul-19 15-Jul-19

T414 Install Final Fix Items (Lighting,Telephone,Date Output] [MAA] 7 06-Jul-19 14-Jul-19
A174 Digital Signage, Audiovisual, Security ( Passive works ) 10 06-Jul-19 16-Jul-19
T436 Install of Public adress System [MAA] 8 09-Jul-19 18-Jul-19
T444 Install of Fire Alarm System [MAA] 7 09-Jul-19 16-Jul-19
Mechan
Mechanical Works 121 14-Feb-19 A 07-Jul-19
Fire Fitting System 97 17-Mar-19 A 07-Jul-19
T4 Fire Hose Cabinet [MAA] 11 17-Mar-19 A 21-May-19
A Installation of fire exinguisher & hose reel 10 09-Jun-19 19-Jun-19
T6 Fire line installations & Tie in [MAA] 10 26-Jun-19 07-Jul-19
HVAC & DX Units 78 14-Feb-19 A 18-May-19
T3 HVAC duct [MAA] 9 14-Feb-19 A 25-Apr-19
T3 Exhaust Fans [MAA] 5 28-Mar-19 A 01-May-19
T4 Install DX unit [MAA] 7 27-Apr-19 04-May-19
T4 Installation of grills and diffusers , duct heaters [MAA] 5 05-May-19 09-May-19
T4 Installation of Electrcial Components wiring and controls [MAA] 7 11-May-19 18-May-19
HANDING OVER
OVE AND CLOSE OUT (TARMEEM) 136 19-Jun-19 24-Nov-19
AS BUILT SUBMISSIONS
SUB 33 17-Jul-19 25-Aug-19
T4530 As Built Drawing for MAA 8 17-Jul-19 27-Jul-19
T4470 As Built Drawing for MAB 8 17-Aug-19 25-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 7 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
TESTING & C
COMMISSIONING 136 19-Jun-19 24-Nov-19
T4200 HVAC Testing and Commissioning 10 19-Jun-19 30-Jun-19
T6260 Testing & Commissioning of Fire water line 5 08-Jul-19 13-Jul-19
T4300 Fire Alarm and figting System Testing and Commissioning 7 05-Aug-19 12-Aug-19
T4190 Public Adress System Testing and Commissioning 3 21-Aug-19 24-Aug-19
T4940 Electrical Testing and Commissioning ( After feeder & Transformer Instllation ) 5 19-Nov-19 24-Nov-19
Site Cleaning 34 18-Jul-19 27-Aug-19
T5020 Site Cleaning [MAA] 2 18-Jul-19 21-Jul-19
T5030 Site Cleaning [MAB] 2 25-Aug-19 27-Aug-19
BUILDING EXTERNAL
EXT WORKS (KCCEC) 84 08-Apr-19 A 25-Jul-19
MAB REFINERY
REFINE 45 04-Jun-19 25-Jul-19
ROAD WORKS
WO 45 04-Jun-19 25-Jul-19
T6110 Earth Works ( Excavation & Compaction of gatch) [MAB] 15 04-Jun-19 20-Jun-19
T6120 Installation of Curbstone [MAB] 15 04-Jun-19 20-Jun-19
T2680 Road Works & walkways [MAB] 20 22-Jun-19 14-Jul-19
T6290 Installation of Interlock tiles 10 22-Jun-19 02-Jul-19
T6130 Installation of Road Marks [MAB] & Traffic signs 10 15-Jul-19 25-Jul-19
LANDSCAP
LANDSCAPPING ( KCCEC ) 31 20-Jun-19 25-Jul-19
A1025 Cement line pipe Installation [MAB] 5 20-Jun-19 25-Jun-19
T6140 Earth works [MAB] 15 20-Jun-19 05-Jul-19
A1020 GRE fresh line installation ( Excavation & pipe installation) [MAB] 15 06-Jul-19 22-Jul-19
T6160 Installation of Irrigation system [MAB] 15 09-Jul-19 25-Jul-19
MAA REFINERY
REFINE 71 08-Apr-19 A 10-Jul-19
ROAD WORKS
WO 71 08-Apr-19 A 10-Jul-19
T6190 Installation of Curbstone [MAA] 15 08-Apr-19 A 23-May-19
T6170 Earth Works ( Excavation & Compaction of gatch) [MAA] 10 25-May-19 04-Jun-19
T6180 Road Works & walkways [MAA] 25 05-Jun-19 03-Jul-19
T6280 Installation of Interlock tiles [MAA] 10 05-Jun-19 16-Jun-19
T6200 Installation of Road Marks & Traffic signs [MAA] 10 30-Jun-19 10-Jul-19
LANDSCAP
LANDSCAPPING 36 29-May-19 10-Jul-19
T6210 Earth works [MAA] 15 29-May-19 13-Jun-19
A1030 GRE fresh line installation ( Excavation & pipe installation [MAA] 15 15-Jun-19 01-Jul-19
A1035 Cement line pipe Installation [MAA] 5 20-Jun-19 25-Jun-19
T6230 Installation of Irrigation system [MAA] 15 24-Jun-19 10-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 8 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
CABLE LAYING (KCCEC) 137 16-Mar-19 A 22-Aug-19
MAA REFINERY
REFINE 129 16-Mar-19 A 22-Aug-19
POWER CA
CABLE (3.3 KV PILOT) FRM S/S U-195 BLDG 112 15-Apr-19 22-Aug-19
T5660 Cable Trench Excavation/ Road Crossing (1 no road crossing) [MAA] 25 15-Apr-19 10-May-19
T5670 Soft Sand Bedding [MAA] 7 02-May-19 11-May-19
T5680 Laying of cable [MAA] 3 11-May-19 13-May-19
T5690 Sand Bedding & Protection tiles [MAA] 7 12-May-19 19-May-19
T5700 Caution tape, Backfilling/Asphault Works & providing cable route marker [MAA] 7 12-May-19 19-May-19
T5730 Laying of Cable trays in S/S ( if required ) & Earthig Cables [MAA] 7 20-May-19 27-May-19
T6240 Transformer Installation & commissioning [MAA] 7 11-Aug-19 19-Aug-19
T5720 Cable termination ( Tie -in )& Testing [MAA] 3 19-Aug-19 22-Aug-19
FOC CABLE
CABL 48 C SM ARMOURED CABLE FRM SHELTER 7 (SECURITY) 39 17-Mar-19 A 09-May-19
T5470 Cable Trench Excavation/Road Crossing [MAA] 25 17-Mar-19 A 20-Apr-19
T5480 Soft Sand Bedding [MAA] 7 15-Apr-19 22-Apr-19
T5490 Laying of cable [MAA] 3 25-Apr-19 28-Apr-19
T5500 Sand Bedding & Protection tiles [MAA] 7 29-Apr-19 06-May-19
T5440 Caution tape, Backfilling/Asphault Works & providing cable route marker [MAA] 7 02-May-19 09-May-19
T5450 Cable termination ( Tie -in )& Testing [MAA] 3 07-May-19 09-May-19
FOC CABLE
CABL 48 C ITU IG 652 FRM IOB ( SECURITY) (DATA VOICE) 70 16-Mar-19 A 16-Jun-19
T5520 Cable Trench Excavation/Road Crossing 35 16-Mar-19 A 25-May-19
T5530 Soft Sand Bedding 3 26-May-19 28-May-19
T5540 Laying of cable 3 30-May-19 02-Jun-19
T5550 Sand Bedding & Protection tiles 7 30-May-19 06-Jun-19
T5560 Caution tape, Backfilling/Asphault Works & providing cable route marker 5 08-Jun-19 12-Jun-19
T5570 cable termination ( Tie -in )& Testing 3 13-Jun-19 16-Jun-19
FOC CABLE
CABL 48 C ITU IG 652 FRM ADMIN BLDG (DATA VOICE) 76 16-Mar-19 A 22-Jun-19
T5590 Cable Trench Excavation/Road Crossing 25 16-Mar-19 A 30-May-19
T5600 Soft Sand Bedding 7 27-May-19 03-Jun-19
T5610 Laying of cable 3 05-Jun-19 08-Jun-19
T5620 Sand Bedding & Protection tiles 6 09-Jun-19 15-Jun-19
T5630 Caution tape, Backfilling/Asphault Works & providing cable route marker 5 16-Jun-19 20-Jun-19
T5640 cable termination ( Tie -in )& Testing 3 19-Jun-19 22-Jun-19
FOC CABLE
CABL 48 C ITU IG 652 FRM SM FRM PD1 ( FOR FIRE ALARM) 57 16-Mar-19 A 01-Jun-19
T5380 Cable Trench Excavation/Asphault Cutting/Road crossing 20 16-Mar-19 A 11-May-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 9 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
T5390 Soft Sand Bedding 5 09-May-19 14-May-19
T5400 Laying of cable 3 12-May-19 14-May-19
T5410 Sand Bedding & Protection tiles 5 15-May-19 20-May-19
T5420 Caution tape, Backfilling/Asphault Works & providing cable route marker 7 21-May-19 28-May-19
T5430 cable termination ( Tie -in )& Testing 3 29-May-19 01-Jun-19
MAB REFINERY
REFINE 131 16-Mar-19 A 15-Aug-19
POWER CA
CABLE (11 KV PILOT) FRM AMIN OIL S/S 131 17-Mar-19 A 15-Aug-19
T5910 Cable Trench Excavation/Road Crossing & duct bank [MAB] 20 17-Mar-19 A 05-May-19
T5920 Soft Sand Bedding [MAB] 7 04-May-19 11-May-19
T5930 Laying of cable [MAB] 3 09-May-19 12-May-19
T5940 Sand Bedding & Protection tiles [MAB] 7 11-May-19 18-May-19
T5950 Caution tape, Backfilling/Asphault Works & providing cable route marker [MAB] 7 19-May-19 26-May-19
T5890 Laying of Cable trays in S/S ( if required ) & Earthig Cables [MAB] 7 20-May-19 27-May-19
T5885 Transformer Installation & commissioning [MAB] 2 11-Aug-19 13-Aug-19
T5960 cable termination ( Tie -in )& Testing [MAB] 2 13-Aug-19 15-Aug-19
FOC CABLE
CABL 48 C ITU IG 652 FRM CCB( SECURITY) (DATA VOICE) 52 16-Mar-19 A 26-May-19
T6050 Cable Trench Excavation/Road Crossing & duct bank 30 16-Mar-19 A 30-Apr-19
T6060 Soft Sand Bedding 7 30-Apr-19 07-May-19
T6070 Laying of cable 3 07-May-19 10-May-19
T6080 Sand Bedding & Protection tiles 7 10-May-19 17-May-19
T6090 Caution tape, Backfilling/Asphault Works & providing cable route marker 5 18-May-19 22-May-19
T6100 Cable termination ( Tie -in )& Testing 3 23-May-19 26-May-19
FOC CABLE
CABL 48 C SM ARMOURED CABLE FRM SHELTER 1 ( SECURITY) ( ON HOLD ) 42 15-Apr-19 02-Jun-19
T5740 Route Survey & permit Authorization ( On hold ) 1 15-Apr-19 15-Apr-19
T5750 Cable Trench Excavation/Road Crossing 25 15-Apr-19 10-May-19
T5760 Soft Sand Bedding 7 11-May-19 18-May-19
T5770 Laying of cable 3 20-May-19 22-May-19
T5780 Sand Bedding & Protection tiles 7 20-May-19 27-May-19
T5790 Caution tape, Backfilling/Asphault Works & providing cable route marker 7 25-May-19 01-Jun-19
T5800 Cable termination ( Tie -in )& Testing 3 30-May-19 02-Jun-19
FOC CABLE
CABL 48 C ITU IG 652 FRM SM FRM IOB ( FOR FIRE ALARM/DATA VOICE) 45 16-Mar-19 A 01-Jun-19
T5820 Cable Trench Excavation/Road Crossing (1 no ) 25 16-Mar-19 A 13-May-19
T5830 Soft Sand Bedding 7 11-May-19 18-May-19
T5840 Laying of cable 3 20-May-19 22-May-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 10 of 11
15-Apr-19 Revised schedule
Actual Work Critical Remainin...
WO 31 TRAINING CENTER BLDG AT MAA AND MAB REFINERY
Activity ID Activity Name Original Start Finish 2019
Duration
J F M A M J J A S O N
T5850 Sand Bedding & Protection tiles 7 20-May-19 27-May-19
T5860 Caution tape, Backfilling/Asphault Works & providing cable route marker 7 23-May-19 30-May-19
T5870 Cable termination ( Tie -in )& Testing 3 29-May-19 01-Jun-19
FOC CABLE
CABL 48 C ITU IG 652 FRM FRM PD1 ( FOR FIRE ALARM) 55 17-Mar-19 A 29-May-19
T5970 Cable Trench Excavation/Road Crossing 30 17-Mar-19 A 07-May-19
T5990 Soft Sand Bedding 5 05-May-19 09-May-19
T6000 Laying of cable 3 12-May-19 14-May-19
T6010 Sand Bedding & Protection tiles 7 15-May-19 22-May-19
T6020 Caution tape, Backfilling/Asphault Works & providing cable route marker 5 23-May-19 28-May-19
T6030 Cable termination ( Tie -in )& Testing 3 27-May-19 29-May-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 11 of 11
15-Apr-19 Revised schedule