PROJECT EXECUTION PLAN

NITROGEN GENERATOR SYSTEM

GAS DEVELOPMENT PROJECT


FOR THE UNITIZATION OF
THE JAMBARAN-TIUNG BIRU FIELD

Comments are in red letter with


light yellow background.
CONTENT

1. PROJECT DATA
2. SCOPE OF WORKS
Show P&ID and GA (Datasheet)
3. SCOPE OF SUPPLY
4. PROJECT MANAGEMENT TEAM Show Org Chart
Show Schedule and also correlation Engineering,
5. ENGINEERING EXECUTION PLAN Fabrication, SubVendor, Assembly, QC.

6. MATERIAL PROCUREMENT PLAN Show target placing order & delivery

7. FABRICTION (SHOP WORK) PLAN Show Workshop Facility

8. INSPECTION & TEST PLAN Show ITP


PROJECT DATA

1. PROJECT NAME : NITROGEN GENERATOR SYSTEM


2. CONTRACTOR : REKAYASA INDUSTRI
3. OWNER : PERTAMINA EP CEPU
4. PROJECT LOCATION : CEPU, WEST JAVA
5. VENDOR : PARKER
6. WORKSHOP : MULTIFAB
SCOPE OF WORKS

1. ENIGNEERING
2. MATERIAL PROCUREMENT
3. FABRICATION
4. INSPECTION
5. HYDROTEST
6. FAT
7. ASME STAMP
8. MIGAS CERTIFICATION
9. PAINTING
10. MDR
SCOPE OF SUPPLY

1. WATER SEPARATOR For better overview, please show


P&ID and GA to show also other
• TAG NO. : 440-WS9400A-01/02 scope such as Instrument, Control
• DESIGN CODE : ASME SEC VIII DIV.1 Panel and JB, Piping, Skid.
• DIA X S/S : TBA
• DESIGN PRESS/TEMP. : 170 PSIG/175 DEG.F
• WEIGHT : TBA
• MATERIAL : SS 316

2. PRE-FILTER
• TAG NO. : 440-PF9400A-01/02
• DESIGN CODE : ASME SEC VIII DIV.1
• DIA X S/S : TBA
• DESIGN PRESS/TEMP. : 170 PSIG/175 DEG.F
• WEIGHT : TBA
• MATERIAL : SS 316
SCOPE OF SUPPLY

3. NITROGEN GENERATOR
• TAG NO. : 440-AT9400A-01/02
• DESIGN CODE : ASME SEC VIII DIV.1
• DIA X S/S : TBA
• DESIGN PRESS/TEMP. : 170 PSIG/175 DEG.F
• WEIGHT : TBA
• MATERIAL : CARBON STEEL

4. NITROGEN MIXING VESSEL


• TAG NO. : 440-NT9400A-01
• DESIGN CODE : ASME SEC VIII DIV.1
• DIA X S/S : TBA
• DESIGN PRESS/TEMP. : 170 PSIG/175 DEG.F
• WEIGHT : TBA
• MATERIAL : CARBON STEE
SCOPE OF SUPPLY

5. AFTER FILTER
• TAG NO. : 440-AF9400A-01/02
• DESIGN CODE : ASME SEC VIII DIV.1
• DIA X S/S : TBA
• DESIGN PRESS/TEMP. : 170 PSIG/175 DEG.F
• WEIGHT : TBA
• MATERIAL : SS 316
PROJECT MANAGEMENT TEAM

Provide better
visual picture.

Provide
contact info
ENGINEERING EXECUTION PLAN

1. Design
• Strength Calculation : Software Compress and others
• Shop Fabrication Drawing : CAD
• Document Output :
- Strength Calculation - GA Drawing
- Shop Fabrication Drawing - P&ID
- Material BOQ - PFD (Material Balance)
- Loading Data
- Cutting plan - Control related document
2. Fabrication Document
• Welding Document
• Fabrication Procedure
• PWHT Procedure
• Hydrostatic Test Procedure
• Painting Procedure
• Others as required
ENGINEERING EXECUTION PLAN

PARKER KOREA PARKER INDONESIA


PARKER KOREA
DOCUMENT DOCUMENT
ENGINEER CONTROL CONTROL

REKAYASA PARKER PARKER INDONESIA


DOCUMENT DOCUMENT
CONTROL CONTROL CHECK/REVEW

Above is more about document flow.

Execution plan should show allocation of manpower for each


category (Engineering, Fabrication, SubVendor, Assembly,
QC.).

It is also important to show schedule and its critical path along


with preventive/corrective action to meet project schedule.
ENGINEERING EXECUTION PLAN

REKAYASA PARKER INDONESIA


PARKER INDONESIA
DOCUMENT DOCUMENT
CONTROL CHECK / REVIEW
CONTROL

PARKER PARKER INDONESIA


PARKER KOREA
DOCUMENT DOCUMENT
ENGINEERING CONTROL CONTROL
ENGINEERING EXECUTION PLAN
PROCUREMENT EXECUTION PLAN

1. Purchase Material
• Plate (as per AML/PML) - Control Panel
• Piping Material (as per AML/PML - Junction Box
- Structure Material
• Instrument Material (as per AML/PML)
• Electrical Material (as per AML/PML)

2. Expediting
• Monitoring circulation document approval
• Monitoring arrival raw material
• Monitoring fabrication and assembly
• Keep and monitoring over all project schedule

Based on schedule we can


reckon which purchase material
target date is in the critical path.

It should be higlighted
PROCUREMENT EXECUTION PLAN

REVIEW / CHECK
ENGINEERING
RFQ TO VENDOR MATERIAL
APPROVED
QUOTATION

APPROVED
DELIVERY PO ISSUED MATERIAL
QUOTATION
FABRICATION EXECUTION PLAN

ENGINEERING RAW MATERIAL CUTTING &


APPROVED MATERIAL PO INSPECTION WELDING

FUNCTION
ASSEMBLY PAINTING HYDROTEST
TEST

DIASSEMBLY PACKAGING

Fabrication Plan and ITP are not


shown yet. Please show in this pre-
sentation also.