CASE

N-432
CASES OF ASME BOILER AND PRESSURE VESSEL CODE

Approval Date: February 20, 1986


See Numeric Index for expiration
and any reaffirmation dates.

Case N-432 IX and additional requirements of Section III, as modi-


Repair Welding Using Automatic or Machine Gas fied by para. 2.1, para. 2.2, and para. 3.0(c) and (d).
Tungsten-Arc Welding (GTAW) Temper Bead
Technique
Section XI, Division 1
2.1 Procedure Qualifications
Inquiry: May the automatic or machine GTAW pro- (a) The test assembly materials for the welding proce-
cess be used as an alternative to the SMAW process dure qualification shall be of the same specification
for performing the temper bead technique on Class 1 type, grade, and class as the materials being repaired.
components? The test assembly shall receive a postweld heat treatment
that is at least equivalent to the time and temperature
Reply: It is the opinion of the Committee that repair applied to the materials being repaired. The procedure
to P-Nos. 1, 3, 12A, 12B, and 12C1 base material and performance qualification tests may be combined,
and associated welds may be made by the automatic provided Section IX requirements are met. The test
or machine GTAW temper bead technique without assembly dimensions, including joint details, shall be
the specified postweld heat treatment requirements of documented on the PQR.
Section III, provided the requirements of para. 1.0 (b) The test assembly thickness shall be at least five
through para. 5.0 below are met. The depth of repair times the depth of repair, but need not exceed the
is not limited provided the test assembly meets the thickness of the material to be repaired provided the
requirements of para. 2.1. required test specimens can be removed. When the
thickness of the base metal to be repaired is greater
than 2 in., the depth of the cavity in the test assembly
shall be the greater of 1 in. or the depth of the cavity
1.0 GENERAL REQUIREMENTS
to be repaired. However, in no case shall the procedure
(a) The requirements of IWA-4000, as applicable, qualification test assembly be less than 2 in. thick, nor
shall be met. shall the depth of the cavity in the test assembly be
(b) Only the automatic or machine GTAW process less than 1 in.
using cold wire feed shall be used. No arc oscillation (c) The test assembly dimensions surrounding the
shall be used. cavity shall be at least the thickness of the component
(c) Welding materials shall be controlled during re- at the location of the repair or 6 in., whichever is
pair so that they are identified as acceptable material greater. If the repair weld is to be performed remotely,
until consumed. the procedure qualification test assembly shall be com-
(d) The neutron fluence in the repair areas shall be pleted with the same or duplicate sensing and control
taken into account when establishing the weld metal equipment to be used for the repair. The test assembly
composition limits. shall simulate the position and obstructions of the actual
(e) Peening shall not be permitted. repair.
(d) The root width and the included angle of the
cavity in test assembly shall be no greater than the
minimum specified to be used in the repair.
2.0 WELDING QUALIFICATIONS
(e) This test assembly may be used to qualify proce-
The Welding Procedure Specification and the welding dures for weld buildup of pressure retaining materials.
operators shall be qualified in accordance with Section For this application, the depth of the cavity shall not
be less than the thickness of the weld buildup or 1
1 in., whichever is greater. In addition, the area of the
P-Nos. 12A, 12B, and 12C designations refer to specific material
classifications originally identified in Section III, and subsequently cavity shall not be less than the area of the weld
reclassified in a later edition of Section IX. buildup to be applied or 54 sq. in., whichever is less.

551

See Numerical Index for expiration


This is Electrontic File Page # 551

Asme Nuclear Code Cases 1998 Edition NCASE4N432 06-20-98 15:20:43


CASE (continued)

N-432
CASES OF ASME BOILER AND PRESSURE VESSEL CODE

(f) For all applications, the test assembly and cavity performance qualification tests may be combined, pro-
shall be of sufficient size to obtain the required test vided Section IX requirements are met.
specimens.
(g) Welding material shall meet the requirements of
3.0 REPAIR WELDING
Sections IX, and III, and the Edition and Addenda
shall be stated in the repair program. The appropriate Welding of the cavity or area being repaired shall
toughness testing requirements of NB-2000 shall be be in accordance with the following.
completed for the weld materials used. (a) The cavity or area to be repaired by welding
(h) Welding procedure qualification destructive tests and a band around the cavity or area shall be preheated
shall be performed in accordance with Sections IX and to 300°F minimum. This temperature shall be main-
III for groove welds, and the Edition and Addenda tained for at least 30 min before welding is started,
shall be stated in the repair program. Dropweight tests, during welding, and until starting the postweld heat
impact tests, side bend tests, and all weld metal tension treatment of 450°F to 550°F described in (e) below.
tests of the weld deposit are required. A reference The width of the band shall be at least three times,
nilductility transition temperature (RTNDT ) of the weld the thickness (3T ) of the component to be welded, but
metal and base metal shall be established in accordance not need 10 in. The component thickness (T ) shall be
with NB-2000. If RTNDT is less than or equal to 60°F, determined for the area to be welded prior to formation
the qualification test shall be considered acceptable. If of the cavity. The interpass temperature shall not exceed
RTNDT is greater than 60°F, the qualification test shall 450°F.
be rejected and a requalification of the procedure shall (b) Thermocouples and recording instruments shall
be performed. Test specimens shall be obtained from be used to monitor the preheat, interpass, and postweld
the completed test assembly at the maximum practical heat treatment temperatures. Thermocouples shall be
depth of repair. attached by welding or mechanical methods.
(i) Impact testing of the procedure qualification test (c) The first six layers of the cavity shall be buttered
assembly HAZ shall be conducted as follows. as shown in Fig. 1, Steps 1 through 3.
The TNDT of the unaffected base material shall be (d) The essential welding variables shall be controlled
determined by dropweight test to establish the test as follows.
temperature for the Cv tests. The Cv specimens represent- (1) The weld heat input for each of the first six
ing the HAZ material and the unaffected base material layers shall be controlled to within 610% of that used
shall be tested at the (TNDT + 60°F) temperature of in the procedure qualification test.
the unaffected base material. The HAZ Cv absorbed (2) The remainder of the weld deposit shall be
energy and lateral expansion shall be equal to or greater completed (see Fig. 1, Step 4) with the heat input
than the unaffected base material at the (TNDT + 60°F) equal to or less than that used for layers beyond the
temperature of the base material. sixth in the procedure qualification.
(3) The finished surface of the repair shall be
substantially flush with the surface of the component
2.2 Performance Qualification
surrounding the repair.
The welding operator shall be qualified in accordance (4) The technique described in this paragraph shall
with Section IX and the following additional require- be performed in the procedure qualification test.
ments. If the repair weld is to be performed where (e) At the completion of welding, the 3T band as
physical obstructions impair the welding operator’s defined in (a) above shall be maintained in the range
ability to perform, the welding operator shall also of 450°F to 550°F for at least 2 hr.
demonstrate the ability to deposit sound weld metal in
the positions required, using the same parameters and
4.0 EXAMINATION
simulated physical obstructions that are involved in the
repair. Also, if the repair weld is to be performed (a) The repair area and the 3T band as defined
remotely, the performance qualification test shall be in 3(a) shall be nondestructively examined after the
completed with the same or duplicate sensing and completed weld has been at ambient temperature for
control equipment to be used for the repair. For these at least 48 hr. The nondestructive examination of the
applications, only nondestructive examination of the repair welded region shall include radiography (if practi-
weld is required. The procedure and welding operator cal), ultrasonic examination, and surface examination.

552

This is Electrontic File Page # 552

Asme Nuclear Code Cases 1998 Edition NCASE4N432 06-20-98 15:20:43


CASE (continued)

N-432
CASES OF ASME BOILER AND PRESSURE VESSEL CODE

FIG. 1 AUTOMATIC OR MACHINE (GTAW) TEMPER BEAD TECHNIQUE

553

See Numerical Index for expiration


This is Electrontic File Page # 553

Asme Nuclear Code Cases 1998 Edition NCASE4N432 06-20-98 15:20:43


CASE (continued)

N-432
CASES OF ASME BOILER AND PRESSURE VESSEL CODE

(b) Areas from which weld-attached thermocouples


have been removed shall be ground and examined using
a surface examination method.

5.0 DOCUMENTATION
The use of this Code Case shall be recorded on
Form NIS-2 or other applicable documents.