Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A. Project Description
Height of the building Shelter column : 7.00 m, high bay column line D : 8.23 m
span of the building 2 building. 6 m and 4,6 m. The total span of the shelter is 13,25
m
Type of the structure Light steel structure : structure WF300.150, Purlin CNP15.65
2.4. Make sure the scaffolding not disturbing during process erection.
2.5. Using tag line, positioning column D1 to the top of pier D1.
2.6. Make sure center line of column symmetric to the center line of pier and base
plate holes parallel with the center line of drill holes
2.7. Put bolt fisher Ø 4/3” and installed. Don’t full tightening first. Tightening conducted
after alignment the column.
2.8. After column D1 installed, connect two rafter using bolt (Rafter D1-4) on the
ground before lifting.
2.9. Place 2 (two) personnel on the scaffolding at wall D4 and install bolt fisher before
the rafter D1-4 is lifted (method for install bolt fisher different between column
and rafter, if column after steel structure on position, but for rafter install first
before steel lifted). Prepare to lifting rafter D1-4 use webbing sling.
2.10. Place another scaffolding at the position D1, and put 2 (two) personnel on the
scaffolding for install bolt and nuts after rafter at the designated position.
2.11. Lifted Rafter to the designated position between column D1 and wall D4. After
rafter at the position, secure the position using tommy M18 and then install M20
bolt and nuts.
2.12. Don’t release webbing sling from the Rafter before alignment and tightening
completed for column D1, Wall D4, rafter D1-4.
2.13. First of all, alignment column using waterpass to check the verticality. After
verticality fulfilled, tightening After column alignment finish, continue to
alignment Rafter and tightening.
2.14. Release webbing sling. Continue install column at south side of pervious column
(column C1 and C2)
2.15. Procedure for install another column refer to step 2.3 up to step 2.7
2.16. Remove scaffolding to the west between column D1 and C1 for install beam CD-1.
2.17. Install beam CD-1 after column C1 finished install.
2.18. After beam CD-1 installed, continue to install Rafter C1-4.
2.19. Continue install another steel member following pervious method until finished
install all steel member.
2.20. after all steel member installed, continue install purlin, sagrod, and roofing.