Sei sulla pagina 1di 5

CRONOGRAMA VALORIZADO DEL PROYECTO

PROYECTO : CONSTRUCCION DE LOSA MULTIDEPORTIVA CON TRIBUNAS DE LA UNIVERSIDAD NACIONAL DE


TRUJILLO - TRUJILLO PROPIETARIO : UNIVERSIDAD NACIONAL DE TRUJILLO
UBICACION : DPTO:LA LIBERTAD PROV:TRUJILLO
DIST:TRUJILLO FECHA PROYECTO : 26/11/2018
Mes 1 Mes 2
Item Descripción Unid. Cantidad Precio Parcial Del Del
3/12/2018 3/01/2019
Al Al
2/01/2019 2/02/2019
1 CONSTRUCCION LOSA TRUJILLO 280,232.91 127,954.50 152,278.41
1.1 OBRAS GENERALES 47,658.13 47,658.13
1.1.1 TRABAJOS PRELIMINARES 7,722.26 7,722.26
MOVILIZACION Y DESMOVILIZACION DE
1.1.1.1 GLB 1.00 3,787.20 3,787.20 3,787.20
EQUIPOS Y MAQUINARIA
1.1.1.2 LIMPIEZA DE TERRENO MANUAL m² 1,030.12 0.65 669.58 669.58
1.1.1.3 TRAZO Y REPLANTEO PRELIMINAR m² 1,030.12 3.17 3,265.48 3,265.48
1.1.2 OBRAS PROVISIONALES 5,010.48 5,010.48
CARTEL DE IDENTIFICACION DE LA
1.1.2.1 und 1.00 822.00 822.00 822.00
OBRA DE 3.60X2.40M
1.1.2.2 ALMACEN Y CASETA DE GUARDIANIA m² 48.00 87.26 4,188.48 4,188.48
1.1.3 MOVIMIENTO DE TIERRAS 34,925.39 34,925.39
1.1.3.1 EXCAVACION MASIVA CON MAQUINARIA m³ 232.36 17.03 3,957.09 3,957.09
1.1.3.2 EXCAVACION MANUAL m³ 31.32 13.04 408.41 408.41
1.1.3.3 RELLENO CON MATERIAL SELECCIONADO m³ 117.04 52.38 6,130.56 6,130.56
RELLENO CON PIEDRA DE RIO TM = 2-4''
1.1.3.4 m³ 208.28 29.25 6,092.19 6,092.19
(02 CAPAS DE 02)
1.1.3.5 REFINE Y NIVELACION EN TERRENO m² 1,030.12 2.61 2,688.61 2,688.61
NORMAL
1.1.3.6 MEJORAMIENTO CON AFIRMADO m³ 150.92 59.27 8,945.03 8,945.03
ELIMINACION MATERIAL EXCEDENTE
1.1.3.7 m³ 267.39 6.52 1,743.38 1,743.38
HASTA 50.00 MT
ELIMINACION DE MATERIAL
1.1.3.8 und 334.24 14.84 4,960.12 4,960.12
EXCEDENTE CON MAQUINARIA
1.2 LOSA DEPORTIVA 79,750.92 61,379.96 18,370.96
1.2.1 OBRAS DE CONCRETO SIMPLE 53,758.11 53,758.11
ENCOFRADO Y DESENCOFRADO
1.2.1.1 m² 56.50 43.74 2,471.31 2,471.31
DE LOSA DEPORTIVA
CONCRETO FC=175 KG/CM2-LOSA
1.2.1.2 m³ 126.80 404.47 51,286.80 51,286.80
DEPORTIVA SEMI FROTACHADO
1.2.2 JUNTAS 15,243.70 7,621.85 7,621.85
1.2.2.1 JUNTAS DE CONSTRUCCION E=3/4'' m 240.00 38.01 9,122.40 4,561.20 4,561.20
1.2.2.2 JUNTAS DE DILATACION E=5 mm" m 410.00 14.93 6,121.30 3,060.65 3,060.65
1.2.3 PINTURA 2,249.11 2,249.11
1.2.3.1 PINTURA DE CAMPO DEPORTIVO m 412.68 5.45 2,249.11 2,249.11
1.2.4 CARPINTERIA METALICA 8,500.00 8,500.00
1.2.4.1 SISTEMA DE ARCOS Y NET 8,500.00 8,500.00
Mes 1 Mes 2
Item Descripción Unid. Cantidad Precio Parcial Del Del
3/12/2018 3/01/2019
Al Al
2/01/2019 2/02/2019
1.2.4.1.1 SISTEMA DE ARCOS CON TABLERO DE GLB 1.00 7,000.00 7,000.00 7,000.00
MADERA
1.2.4.1.2 SISTEMA DE NED PARA VOLEY GLB 1.00 1,500.00 1,500.00 1,500.00
1.3 TRIBUNAS 74,831.08 18,916.41 55,914.67
1.3.1 OBRAS DE CONCRETO ARMADO 51,768.61 18,916.41 32,852.20
1.3.1.1 ENCOFRADO Y DESENCOFRADO DE m² 814.40 24.02 19,561.89 11,737.13 7,824.76
TRIBUNA
1.3.1.2 CONCRETO FC=175 KG/CM2 EN TRIBUNAS m³ 76.45 327.37 25,027.44 25,027.44
1.3.1.3 ACERO FY= 4200 KG/CM2 kg 2,136.69 3.36 7,179.28 7,179.28
1.3.2 REVESTIMIENTOS 629.00 629.00
REVESTIMIENTO DE ESTRUCTURAS
1.3.2.1 m² 92.50 6.80 629.00 629.00
C/MORTERO 1:4X2CM+PULIDO 1.2X1CM
1.3.3 PINTURA 1,316.29 1,316.29
1.3.3.1 PINTURA EN GRADERIAS m 233.80 5.63 1,316.29 1,316.29
1.3.4 CARPINTERIA METALICA 21,117.18 21,117.18
1.3.4.1 PROTECCION DE GRADAS 21,117.18 21,117.18
1.3.4.1.1 MALLA OLIMPICA H=1.00 m 70.40 299.96 21,117.18 21,117.18
1.4 GALERIAS DE CIRCULACION 27,642.92 27,642.92
1.4.1 OBRAS DE CONCRETO SIMPLE 15,552.56 15,552.56
1.4.1.1 ENCOFRADO Y DESENCOFRADO DE m² 38.00 41.26 1,567.88 1,567.88
GALERIA
1.4.1.2 CONCRETO FC=175 KG/CM2 EN GALERIA m³ 27.39 406.03 11,121.16 11,121.16
ENCOFRADO Y DESENCOFRADO DE
1.4.1.3 m² 46.47 40.40 1,877.39 1,877.39
CANAL DE DRENAJE PLUVIAL
CONCRETO FC=175 KG/CM2 DE
1.4.1.4 m³ 3.28 300.65 986.13 986.13
CANAL DE DRENAJE PLUVIAL
1.4.2 JUNTAS 955.60 955.60
1.4.2.1 JUNTAS DE DILATACION E=3/4" m 79.90 11.96 955.60 955.60
1.4.3 CARPINTERIA METALICA 11,134.76 11,134.76
REJILLA PARA CANALETA DE
1.4.3.1 m 72.80 152.95 11,134.76 11,134.76
DRENAJE DE POLIPROPILENO
1.5 COBERTURA 36,941.35 36,941.35
1.5.1 MOVIMIENTO DE TIERRAS 119.41 119.41
1.5.1.1 EXCAVACION MANUAL m³ 4.90 18.62 91.24 91.24
1.5.1.2 MEJORAMIENTO CON AFIRMADO m² 0.49 55.20 27.05 27.05
ELIMINACION MATERIAL EXCEDENTE
1.5.1.3 m³ 0.06 18.62 1.12 1.12
HASTA 50.00 MT
1.5.2 OBRAS DE CONCRETO SIMPLE 2,488.57 2,488.57
1.5.2.1 ENCOFRADO Y DESENCOFRADO DE m² 25.20 51.62 1,300.82 1,300.82
DADOS
1.5.2.2 CONCRETO FC=175 KG/CM2- DE DADOS m³ 4.41 269.33 1,187.75 1,187.75
1.5.3 CARPINTERIA METALICA 13,865.76 13,865.76
1.5.3.1 ARMADURA TIPO 01 DE TUBO DE F°G° 2" und 16.00 369.72 5,915.52 5,915.52
ARMADURA PARA CORREAS DE
1.5.3.2 und 48.00 165.63 7,950.24 7,950.24
ACERO CORRUGADO 1/2"
1.5.4 COBERTURA 20,467.61 20,467.61
Mes 1 Mes 2
Item Descripción Unid. Cantidad Precio Parcial Del Del
3/12/2018 3/01/2019
Al Al
2/01/2019 2/02/2019
COBERTURA CON POLICARBONATO
1.5.4.1 m² 193.20 105.94 20,467.61 20,467.61
ALVEOLAR E=10MM
1.6 INSTALACIONES ELECTRICAS 13,408.51 13,408.51
1.6.1 SALIDA DE PUNTOS DE ILUMINACION 13,408.51 13,408.51
1.6.1.1 EXCAVACION DE ZANJAS PARA TUBERIAS m 86.60 5.93 513.54 513.54
1.6.1.2 CABLEADO CON CONDUCTOR NYY- pto 4.00 250.91 1,003.64 1,003.64
2X1X10MM2
1.6.1.3 POSTE CON LINTERNAS DE 400W und 4.00 1,950.25 7,801.00 7,801.00
1.6.1.4 POSTE CON LINTERNAS DE 120W und 2.00 1,610.25 3,220.50 3,220.50
TABLERO DE DISTRIBUCION 8
1.6.1.5 und 1.00 317.64 317.64 317.64
POLOS (02INT. TERMOMAGNETICOS
DE 2X25A)
1.6.1.6 POZO PUESTA A TIERRA und 1.00 552.19 552.19 552.19
Costo directo: 127,954.50 152,278.41
280,232.
91
Gastos Generales (10.00%) 28,023.29 12,795.45 15,227.84
Utilidad (5.00%) 14,011.65 6,397.73 7,613.92
Parcial 322,267.85 147,147.68 175,120.17
I.G.V.(18.00%) 58,008.21 26,486.58 31,521.63
TOTAL 380,276.06 173,634.26 206,641.80
Porcentaje de avance por Mes 45.66% 54.34%
Porcentaje de avance acumulado 45.66% 100.00%

Potrebbero piacerti anche