Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Published by:
Public Works Department
Purta Bhaban, Segun Bagicha
Dhaka-1000.
Fifteenth Edition
01 May 2018
Written suggestions on Analysis of PWD Schedule of Rates 2018 for Civil Works
may please be addressed to
Chief Engineer
Public Works Department
Purta Bhaban, Segun Bagicha
Dhaka- 1000
Fax: +88-02-9562913
Email: ce@pwd.gov.bd
AUTHENTICATION
The Fifteenth Edition of the Analysis of PWD Schedule of Rates 2018 for Civil Works that has been recommended by the
committee formed vide memo. no. 5 sh-12/14-1551, dated 14-09-2017 is hereby authenticated and endorsed by the
undersigned for official use in Public Works Department (PWD), Bangladesh with effect from 01 May 2018.
Public Works Department (PWD) under Ministry of Housing and Public Works is pleased to publish the Analysis of PWD Schedule of
Rates 2018 for Civil Works. It is a comprehensive and useful document based on scientific assessment of inputs such as material,
labour, machinery and other ancillary factors for various item of work. With the advent of modern construction technologies and
emergence of new construction materials, the diversity and complexity of construction of buildings have increased manifold. Bangladesh
is holding the status of developing country. Timely completion of construction projects is utmost important to hold that milestone and to
accelerate achieving further goal, hope and aspiration of the nation. Unlike past, construction of high-rise buildings has become a
necessity for optimum use of scarce land in a very populous country like Bangladesh. Building services and environmental issues are
getting importance along the passage of time. As per the direction of the government, projects are now being planned keeping
provisions for onsite waste management system. Use of environment friendly building materials are also being encouraged by the
government. These have made a paradigm shift in the nature of construction of building in the public sector. Moreover, price of existing
building materials also changed over time. These called for a revision of the existing Analysis of PWD Schedule of Rates.
The current edition has been substantially enhanced to keep abreast of the modern construction practices and current market price of
construction materials. Besides increased cost, there has been a spurt of new construction materials and introduction of mechanized
construction techniques for rapid construction. Several new analysis pertaining to new materials and technologies in the construction
sector have been included in this edition. Efforts have been made to incorporate as many items as possible which are being used in the
construction sector of the country. However, due to high diversity in type and class of construction materials available in the market, only
the most commonly used materials listed in BSTI approved brands have been incorporated with their average market rates.
Rates of all the items of work prescribed in this PWD Schedule of Rates 2018 for Civil Works should be read and understood in
conjunction with Analysis of PWD Schedule of Rates 2018 for Civil Works. Analysis of rates are based on study of price of various input
such as material, labour, machine etc. of Dhaka, other metropolitan cities and district towns collected during the period of September
2017 to April 2018.
Preparation of such document within a short span of time is a challenging task. In spite of every effort to make this document flawless,
there might have inadvertent errors in various parts of the document. Notifying any such mistakes by the users would be highly
appreciated. Moreover, PWD welcomes comments, suggestions and feedback from the users to improve this document in future.
Manufacturers and dealers are also welcome to send details of materials approved by BSTI to be incorporated in the next version. The
department expresses its gratitude to all who contributed directly or indirectly in preparing and publishing this new edition.
1.0 Analysis of PWD Schedule of Rates 2018 for Civil Works is the revised edition of Anaysis of PWD Schedule of Rates 2014 for
Civil Works.
2.0 This Analysis of PWD Schedule of Rates 2018 for Civil Works incorporates most of the items with all corrections and will
replace Anaysis of PWD Schedule of Rates 2014 for Civil Works. The nomenclature of many items has been improved by
making it more generic and comprehensive. Items of Anaysis of PWD Schedule of Rates 2014 for Civil Works, which have
become obsolete over a period of time or are not in use, have been dropped.
3.0 Items of some new and imported materials are included for better quality works with the demand of time.
4.0 This Analysis of PWD Schedule of Rates 2018 for Civil Works is based on the study of current market rates of materials at
Dhaka and other metropolitan cities, district towns collected during the period of September 2017 to April 2018 and labour
rates are the current market rates.
5.0 The following are the salient features of Analysis of PWD Schedule of Rates 2018 for Civil Works.
5.1 The description of items of works of this Analysis of PWD Schedule of Rates 2018 for Civil Works bears the
adherence to PWD Book of Specification and Bangladesh National Building Code (BNBC).
5.2 Basic rates of relevant materials are provided for convenience of the user.
5.3 Generally, the basic rates of materials, incorporated in the schedule, are pertaining to materials conforming to
Bangladesh Standards (BDS) and other international standards available in the market.
6.0 A lot of effort has gone into the preparation of this Analysis of PWD Schedule of Rates 2018 for Civil Works. I convey my deep
appreciation and sincere thanks to all the members and their associates involved in producing this Analysis of PWD Schedule
of Rates 2018 for Civil Works.
1. Md. Aminul Islam Khan Additional Chief Engineer (P&SP), PWD, Dhaka Convenor
2. Md. Shahadat Hossain Additional Chief Engineer (Establishment & Co-ord.), PWD, Dhaka Member
3 Md. Abdul Hye Additional Chief Engineer, Dhaka Zone, PWD, Dhaka Member
4. Md. Salim Khan Additional Chief Engineer (Health Wing), PWD, Dhaka Member
5. Mohammad Abdul Majid Additional Chief Engineer, E/M Zone, PWD, Dhaka Member
6. Shahadat Hossain Deputy Chief Architect (Co-ord), Department of Architecture, Dhaka Member
8. Md. Nurul Islam Superintending Engineer, E/M P&D Circle, PWD, Dhaka Member
9. Md. Nazibar Rahman Superintending Engineer, Savar Circle, PWD, Dhaka Member
11. Md. Sohel Rahman Superintending Engineer, Design Circle-1, PWD, Dhaka Member
12. Md. Rafiqul Islam Superintending Engineer, Project Circle-2, PWD, Dhaka Member
13. Md. Jamilur Rahman Superintending Engineer, Project Circle-1, PWD, Dhaka Member
14. Kazi Md. Firoze Hassan Superintending Engineer, PECU Circle, PWD, Dhaka Member
15. Md. Syied Mahbub Morshed Superintending Engineer, Monitoring & Audit Circle, PWD, Dhaka Member
16. Abdur Razzaque Khan Executive Engineer, E/M P&D Division-2, PWD, Dhaka Member
17. Md. Shakhawat Hossain Executive Engineer, Design Division-5, PWD, Dhaka Member
18. SK. Md. Kudrot-E-Khuda Chief Arboriculturist, Arboriculture PWD Division, Dhaka Member
19. Rafia Begum Executive Engineer, E/M P&D Division-1, PWD, Dhaka Member
20. Md. Shamsul Islam Executive Engineer, Design Division-1, PWD, Dhaka Member
23. Md. Maminul Haque Bhuiyan Chief Accounts Officer, PWD, Dhaka Member
24. Md. Emdadul Huq Executive Engineer, Design Division-2, PWD, Dhaka Member Secretary
Associates
Mohammad Ferdous-Uz-Zaman, Sub-Divisional Engineer, Design Division-2, PWD, Dhaka
Md. Raquibul Hasan, Sub-Divisional Engineer, Design Division-2, PWD, Dhaka
Md. Fateh Azam Khan, Assistant Engineer, Design Division-4, PWD, Dhaka
Rajib Kanti Biswas, Assistant Engineer, Design Division-2, PWD, Dhaka
Tariq Mahmud, Assistant Engineer, Design Division-1, PWD, Dhaka
SPECIAL NOTE
Utmost care has been taken to overcome mistakes and confusion etc. in description of items, units, rates although there may always be
chances of unwilling printing mistakes. However, if confusion arises in the interpretation in any item/items, unit, rates etc. and if situation
so demands, then the procuring entity must clarify and resolve the issue and approval is to be obtained in this regard from the
competent authority (HOPE or his authorized representative). Hence the decision given by the competent authority will be treated as
final.
TABLE OF CONTENTS
Sl. No Contents Page
1 Rates of man, materials and mark-ups 1-67
2 Secondary input for R. C. C. works 68-84
3 Division 1: General and site facilities 85-91
4 Division 2: Excavation, filling & site development and palisading 92-106
5 Division 3: Brick soling, CC, DPC etc. 107-111
6 Division 4: Brick works, patent stone in floor and fancy screen block works 112-132
7 Division 5: Mosaic works 133-146
8 Division 6: Tiles, marble stone and granite stone works 147-169
9 Division 7: Reinforced cement concrete (RCC) works 170-183
10 Division 8: M. S. fabrication and construction joint in RCC works 184-186
11 Division 9: Pile works and pile test 187-217
12 Division 10: Structural steel works, sheet roofing and safety canopy 218-226
13 Division 11: Wood works in door and window frame, roof truss and railings 227-234
14 Division 12: Door-window shutter & fly proof wire-net shutter 235-270
15 Division 13: Window grill, verandah grill & netting 271-280
16 Division 14: Aluminium door, window frame and glass works 281-349
17 Division 15: Cement plaster, fair-face plaster and pointing works 350-358
18 Division 16: Painting and polishing 359-365
19 Division 17: Lime terracing, roof top water proofing for garden and swimming pool 366-368
20 Division 18: False ceiling wall paneling 369-375
21 Division 19: Collapsible gate, M.S. gate, rolling shutter etc. 376-388
22 Division 20: Stair & verandah railing and stair nosing 389-401
23 Division 21: Grill fencing and barbed wire fencing 402-407
24 Division 22: Miscellaneous items 408-423
25 Division 23: Ferrocement works 424-428
26 Division 24: Road and pavement works 429-441
27 Division 25: Arboriculture works 442-448
28 Division 26: Sanitary & water supply works 449-565
29 Division 27: Deep tube-well 566-623
30 Division 28: Gas connection works 624-634
31 Division 29: Termite treatment works 635-637
32 Division 30: Concrete hollow block, facings and paving stone, non fire block 638-655
33 Division 31: Sub-soil investigation works 656-661
34 Division 32: Repair works 662-726
Analysis of PWD SoR 2018 for Civil Works 1
1 MARK-UPS
3 VAT 6.00%
5 Field Engineer (minimum BSc in Eng. with 3yrs exp or Diploma in Eng. with 8yrs exp) Tk. 1,800.00 per day
22 Helper to diesel hammer mounted rig operator Tk. 390.00 per day
23 Rig operator including site allowances for soil exploration Tk. 600.00 per day
25 Laboratory technician (Diploma in engg in relevant field having minimum 3yrs exp) Tk. 1,400.00 per day
26 Laboratory engineer (minimum BSc in relevant field with minimum 3yrs exp) Tk. 1,800.00 per day
31 Surveyor (10yrs Exp / diploma Engineer trained in survey) Tk. 1,400.00 per day
34 Carrying charge of earth by 5-ton capacity truck in Dhaka city Tk. 1,700.00 per trip
35 Carrying charge of earth by 5-ton capacity truck in Narayanganj / Chittagong / Sylhet city Tk. 1,200.00 per trip
Carrying charge of earth by 5-ton capacity truck in Rajshahi / Barisal / Khulna metropolitan
36 Tk. 950.00 per trip
area
Carrying charge of earth by 5-ton capacity truck in all district except Dhaka/ Chittagong/
37 Tk. 800.00 per trip
Rajshahi / Barisal / Khulna and Narayangonj city
38 Carriage of earth by any means for site development in Dhaka city Tk. 7.50 cft
Carriage of earth by any means for site development in Narayanganj / Chittagong / Sylhet
39 Tk. 6.00 cft
city
40 Carriage of earth by any means for site development in Rajshahi / Barisal / Khulna city Tk. 5.50 cft
Carriage of earth by any means for site development in in all district except Dhaka,
41 Tk. 4.50 cft
Chittagong, and Narayangonj city
42 5-ton capacity truck-fare in Dhaka city including loading & unloading Tk. 1,700.00 per trip
45 Hire charge of water pump for concreting or similar purposes Tk. 500.00 per day
46 Hire charge of diesel operated 1/4 cusec capacity water pump Tk. 600.00 per day
Analysis of PWD SoR 2018 for Civil Works 3
47 Hire charge of electricity operated 1 cusec capacity water pump Tk. 800.00 per day
48 Hire charge of 1 cusec capacity diesel operated water pump Tk. 1,200.00 per day
49 Fuel & lubricant for mixer machine, vibrator, pump etc. Tk. 1,200.00 per day
51 Hire charge of marble cutting and shaping machine including cutting disc. Tk. 400.00 per day
52 Hire charge of marble polishing machine including polishing stone Tk. 550.00 per day
55 Hire charge of cast in situ pile boring complete rig set including operational expenses Tk. 6,000.00 per day
56 Hire charge of pre-cast pile driving complete rig set including operational expenses Tk. 5,500.00 per day
57 Hire charge of pre-cast micro pile driving complete rig set including operational expenses Tk. 4,000.00 per day
58 Hire charge of load testing devices including hydraulic fluid: up to 200 ton capacity Tk. 6,000.00 per test
59 Hire charge of pile load testing devices including hydraulic fluid: up to 400 ton capacity Tk. 8,000.00 per test
60 Hire charge of diesel hammer mounted completed rig set. Tk. 24,000.00 per day
61 Hire charge of auger boring complete rig set including operational expenses Tk. 75,000.00 per day
62 Hire charge of crane for auger boring Tk. 50,000.00 per day
63 Hire charge of air compressor for auger boring Tk. 5,000.00 per day
64 Hire charge of concreting equipment for auger boring Tk. 5,000.00 per day
65 Hire charge of generator for auger boring Tk. 5,000.00 per day
66 Hire charge of excavator for auger boring Tk. 10,000.00 per day
67 Hire charge of desander for auger boring Tk. 6,000.00 per day
68 Hire charge of mud silo for auger boring Tk. 1,000.00 per day
69 Hire charge of water bowser for auger boring Tk. 5,000.00 per day
70 Hire charge of hydraulic static pile driver complete rig set Tk. 75,000.00 per day
71 Generator, fuel, lubricant for hydraulic static pile driver Tk. 20,000.00 per day
73 Hire charge of MS steel tank (6'-6" x 10'-0" x 4'-0") Tk. 350.00 per trip
74 Truck fare for carrying diesel hammer mounted rig Tk. 15,000.00 per trip
Analysis of PWD SoR 2018 for Civil Works 4
76 Hire charge of vibratory (ride on) roller with 2 steel drum compactor (3-5 tons) Tk. 5,000.00 per day
77 Hire charge of pneumatic multiple tired roller (7 tires, 8-10 tons) Tk. 5,000.00 per day
80 Hire charge of dump truck/ tripping trucks Tk. 5,000.00 per day
82 Hire charge of water tanker (truck mounted) Tk. 3,000.00 per day
84 Fuel & lubricants, spares, maintenance, driver etc. for 8-12 ton road roller. Tk. 1,300.00 per day
86 Hire charge of machine for cutting terrazzo tiles Tk. 500.00 per % sft
87 Chisel for heavy duty power hammer (100 sft capacity) Tk. 1,700.00 each
88 Hire charge of heavy duty chisel machine Tk. 650.00 per day
89 Shuttering including prop for partial dismantling of R.C.C. Tk. 27.00 per sft
91 Hire charge of survey instrument (Level / Theodolite etc.) Tk. 950.00 per day
97 Placing and removing of shutter for formwork Tk. 15.00 per sft
99 Making steel door-window frame and shutter Tk. 65.00 per sft
100 Making fixed steel glazed frame Tk. 55.00 per sft
102 Filling and stitching gunny bags Tk. 10.00 per bag
103 Load testing result sheet preparation Tk. 6,000.00 per test
106 Carrying cost of steel door and window Tk. 70.00 each
107 Fabrication and erection of mild steel truss Tk. 2,100.00 per 50 kg
111 Bitumenous coating (for damp proof course (D.P.C)) Tk. 800.00 per % sft
113 Glass pan fitting including putty Tk. 16.00 per sft
114 Jute hessian (for making formwork water-tight) Tk. 2.50 per sft
115 1st class/Picked jhama standard bricks Tk. 8,700.00 per % 0 nos
116 Automatic machine made 1st class standard bricks Tk. 9,000.00 per % 0 nos
1st class 10 holes machine made 9.5" x 4.5" x 2.75" / 237.5 mm x 112.5 mm x 68.75 mm
117 Tk. 18,900.00 per % 0 nos
size ceramic bricks
9.5" x 4.5" x 2.75"/ 237.5 mm x 112.5 mm x 68.75 mm size machine made solid klinker
118 Tk. 13,500.00 per % 0 nos
facing bricks
9.5" x 4.5" x 2.75" / 237.5 mm x 112.5 mm x 68.75 mm size 10 hole machine made rock-
119 Tk. 13,500.00 per % 0 nos
face/textured klinker facing bricks
9.5" x 4.5" x 2.75"/ 237.5 mm x 112.5 mm x 68.75 mm size 3 hole machine made
120 Tk. 21,500.00 per % 0 nos
reinforcing facing bricks
121 8" x 4" x 2"/ 200 x 100 x 50 mm machine made hard pressed klinker facing bricks Tk. 19,000.00 per % 0 nos
122 8" x 2" x 2"/ 200 x 50 x 50 mm machine made klinker facing red or maroon strips Tk. 16,000.00 per % 0 nos
123 200 mm x 62 mm x 16.51 mm machine made clay wall tile red strips Tk. 18,500.00 per % 0 nos
124 200 mm x 62 mm x 12.7 mm machine made clay wall tile beige strips Tk. 21,000.00 per % 0 nos
125 200 mm x 62 mm x 8.9 mm machine made clay wall tile red strips Tk. 16,400.00 per % 0 nos
Analysis of PWD SoR 2018 for Civil Works 6
126 241 mm x 70 mm x 12.7 mm machine made clay wall tile red strips Tk. 28,000.00 per % 0 nos
127 242 mm x 70 mm x 12.7 mm machine made clay wall tile matt glazed textured strips Tk. 34,000.00 per % 0 nos
128 4.5'' x 4.5'' x 4.5''/ 112.5 mm x 112.5 mm x 112.5 mm fancy screen block Tk. 28,000.00 per % 0 nos
129 5.5'' x 5.5'' x 4'' / 137.5 mm x 137.5 mm x 100 mm fancy screen block Tk. 34,000.00 per % 0 nos
130 6" x 6" x 4" / 150 mm x 150 mm x 100 mm fancy screen block Tk. 37,000.00 per % 0 nos
131 8'' x 8'' x 4.25''/ 200 mm x 200 mm x 106.25 mm fancy screen block Tk. 47,000.00 per % 0 nos
132 8'' x 4.75'' x 4''/ 200 mm x 118.75 mm x 100 mm fancy screen block Tk. 47,000.00 per % 0 nos
133 6" x 6" x 6" / 150 mm x 150 mm x 150 mm fancy screen block Tk. 37,000.00 per % 0 nos
134 9.5'' x 4.5'' x 2.75''/ 237.5 mm x 112.5 mm x 68.75 mm fancy screen block Tk. 37,000.00 per % 0 nos
C6 CEMENT
Ordinary Portland Cement, BDS-EN - 197-1-CEM-I ,52.5N (52.5MPa) / ASTM C-150 Type-
136 Tk. 415.00 per bag
I, 50 kg bag
140 19 mm (3/4") down grade crushed stone chips Tk. 19,500.00 per % cft
141 12 mm (1/2") down grade stone chips Tk. 16,500.00 per % cft
142 6 mm (1/4") down grade stone chips Tk. 14,000.00 per % cft
144 Stone dust (2.38 mm down grade) Tk. 4,248.00 per % cft
147 Surki from 1st class brick Tk. 70.00 per cft
150 Pumice stone for finishing mosaic work Tk. 175.00 each
Analysis of PWD SoR 2018 for Civil Works 7
151 Minar stone for finishing mosaic work Tk. 420.00 each
154 60/70 grade bitumen for road work Tk. 52,000.00 per M. ton
156 Primer for laying PVC membrane on wall Tk. 600.00 per litre
157 Water reducing admixture in concrete: Type - A Tk. 150.00 per litre
160 Water reducing and retarding admixture in concrete: Type - D Tk. 220.00 per litre
161 Water reducing and accelerating admixture in concrete: Type - E Tk. 170.00 per litre
162 Water reducing high range admixture in concrete: Type - F Tk. 230.00 per litre
163 Water reducing high range retarding admixture in concrete: Type - G Tk. 160.00 per litre
165 Shutter releasing agent / form oil Tk. 150.00 per litre
C8 EARTH/SAND
185 Shal ballah (avg. dia 6") for driving Tk. 70.00 per foot
186 Burma teak veneered flush door shutter Tk. 335.00 per sft
187 Champ veneered flush door shutter Tk. 240.00 per sft
188 Chapalish veneered flush door shutter Tk. 240.00 per sft
189 Garjan veneered flush door shutter Tk. 250.00 per sft
190 12 mm thick Plain Particle board : 550kg/m3 Tk. 38.00 per sft
191 Melamine board (12 mm thick): 8' -0" x 4'-0" size, 700kg/m3 Tk. 2,150.00 per pc
194 12 mm thick laminated vinyl board : 550 kg/m3 Tk. 65.00 per sft
195 12 mm thick Burma Teak veneered board : 550kg/m3 Tk. 86.00 per sft
C10 STEEL
202 M.S. angle, T and Z-section, Channel etc. Tk. 55,000.00 per M. ton
Analysis of PWD SoR 2018 for Civil Works 9
203 M.S. plain bar and F.I. bar (non-structural use) Tk. 55,000.00 per M. ton
206 0.45 mm thick coloured C.I. sheet: Tk. 81,000.00 per M. ton
208 0.27 mm thick 6'-0" x 18" coloured ridging: Tk. 400.00 per pc
213 Hot rolled W, I, S, T shape sections of grade 275 MPa Tk. 80,000.00 per M.Ton
Fabrication charge for column, beam, rafter using MS plates including the cost of
215 Tk. 20,000.00 per M.Ton
electricity, LP gas, machinares etc.
Fabrication charge for column, beam, rafter using Hot Rolled sections including the cost of
216 Tk. 12,000.00 per M.Ton
electricity, LP gas, machinares etc.
217 MS sheet for purlin of any thickness Tk. 75,000.00 per M.Ton
218 GP sheet for purlin of any thickness Tk. 98,000.00 per M.Ton
219 0.70 mm thick GP decking sheet of Grade 345 Mpa Tk.125,000.00 per M.Ton
223 Galvanized nut bolt of varying dia ASTM 325 Tk. 250.00 per Kg
224 Galvanized nut bolt of varying dia ASTM 307 Tk. 205.00 per Kg
225 Fabrication charge for roof / wall sheet Tk. 7,500.00 per M.Ton
227 Fabrication charge for decking panel Tk. 9,000.00 per M.Ton
229 Erection charge for built-up or hot rolled sections Tk. 8,000.00 per M.Ton
Analysis of PWD SoR 2018 for Civil Works 10
232 Erection charge for roof/wall sheet including flashing and trims Tk. 10.00 per Kg
233 Fitting and fxing of dubble bubble insulation on roof and wall Tk. 50.00 sqm
235 Anti corrosive red oxide paint Tk. 180.00 per litre
236 Thinner for anti corrosive red oxide paint Tk. 120.00 per litre
237 Labour charge for redoxide painting Tk. 600.00 per M.Ton
238 Labour charge for enamel painting Tk. 3,500.00 per M.Ton
239 Labour charge for application of non-shrink grout including the cost of making shutter Tk. 50.00 per cft
241 16 mm I bolt with heal side washer and clamp Tk. 175.00 per set
242 12 mm I bolt with heal side washer and clamp Tk. 150.00 per set
243 Shear stud of variable dia of grade 275 Mpa Tk. 120.00 per Kg
245 Nut with washer for 12 mm dia sag rod Tk. 150.00 per Kg
246 cost of non-shrink grout per bag (25 kg ) Tk. 1,500.00 per bag
247 Labour charge for wire bracing Tk. 10.00 per foot
18 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or
249 Tk. 450.00 per sft
equivalent)
16 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or
250 Tk. 400.00 per sft
equivalent)
12 mm thick marble stone, Indian standard quality (Bansowara/ Indian grey/ Indian pink or
251 Tk. 370.00 per sft
equivalent)
252 12 mm thick marble stone, Indian superior quality Tk. 400.00 per sft
253 18 mm thick marble stone, Indian superior quality Tk. 500.00 per sft
254 16 mm thick marble stone, Indian superior quality Tk. 420.00 per sft
Analysis of PWD SoR 2018 for Civil Works 11
255 18 mm thick marble stone, Italian or equivalent Tk. 650.00 per sft
256 12 mm thick marble stone, Italian or equivalent Tk. 600.00 per sft
257 Country made wall tiles less than , equal or equivalent to 250mmx330mm in sizes Tk. 40.00 per sft
Country made wall tiles more than 250 mm x 330 mm & less than 310 mm x 510 mm in
258 Tk. 62.00 per sft
sizes or equaivalent
259 Country made wall tiles more than 310 mm X 510 mm in sizes or equivalent Tk. 80.00 per sft
262 Country made rustic wall tiles less than or equal to 300 mm x 600 mm Tk. 90.00 per sft
263 GP (glazed/unglazed homogeneous) 300 mm x 300 mm floor tiles country made Tk. 60.00 per sft
264 GP (glazed/unglazed Homogeneous) 400 mm x 400 mm floor tiles country made Tk. 70.00 per sft
265 GP (mirror polished) 300 mm x 300 mm floor tiles country made Tk. 65.00 per sft
266 GP (mirror polished) 400 mm x 400 mm floor tiles country made Tk. 80.00 per sft
267 GP (mirror polished) 600 mm x 600 mm floor tiles country made Tk. 100.00 per sft
268 GP (mirror polished) 500 mm x 500 mm floor tiles country made Tk. 90.00 per sft
269 GP (mirror polished) 800 mm x 800 mm floor tiles country made Tk. 110.00 per sft
270 GP (mirror polished) 600 mm x 900 mm country made Tk. 132.00 per sft
271 GP (mirror polished) 600 mm x 1200 mm country made Tk. 165.00 per sft
272 Matt or rustic floor tiles of size 400 mm x 400 mm and min. thick 8.4 mm (country made) Tk. 87.00 per sft
273 Matt or rustic floor tiles of size 600 mm x 600 mm and min. thick 9.8 mm (country made ) Tk. 103.00 per sft
274 GP 300 mm x 300 mm stair tiles (country made) Tk. 62.00 per sft
275 GP 300 mm x 600 mm stair tiles (country made ) Tk. 95.00 per sft
276 Stair tiles size 300 mm x 600 mm foreign (China/equivalent) made Tk. 100.00 per sft
277 Rustic stair tiles country made Tk. 90.00 per sft
278 Rustic stair tiles foreign (China/equivalent) made Tk. 95.00 per sft
279 Mirror polish 600 mm x 600 mm floor tiles foreign(China/equivalent) made Tk. 125.00 per sft
280 Mirror polish 800 mm x 800 mm floor tiles foreign(China/equivalent) made Tk. 150.00 per sft
281 Mirror polish 600 mm x 1200 mm floor tiles foreign(China/equivalent) made Tk. 300.00 per sft
282 Mirror polish 1000 mm x1000 mm floor tiles foreign(China/equivalent) made Tk. 400.00 per sft
Analysis of PWD SoR 2018 for Civil Works 12
283 Mirror polish 1200 mm x 1200 mm floor tiles foreign (China/equivalent) made Tk. 500.00 per sft
Matt or rustic floor tiles of size 600 mm x 600 mm and minimum thickness 9.8 mm foreign
284 Tk. 170.00 per sft
(China/equivalent) made
foreign (China/ equivalent) glazed wall tiles of size 300 mm x 600 mm with mathcing floor
285 Tk. 150.00 per sft
tiles, décor and border (if any)
foreign (China/equivalent) rustic wall tiles of size 300 mm x 600 mm with mathcing floor
286 Tk. 150.00 per sft
tiles, décor and border (if any)
287 20 mm to 25 mm thick machine made cement pavement tiles (country made) Tk. 130.00 per sft
288 Roof tiles of size 100 mm x 200 mm or equivalent (Red colour) (country made) Tk. 14,000.00 per % sft
Roof tiles of size 125 mm x 170 mm to 200 mm x 200 mm or equivalent (red colour)
289 Tk. 17,575.00 per % sft
(country made)
290 Roof tiles of size 160 mm x 268 mm or equivalent (red colour) (country made) Tk. 15,600.00 per % sft
291 Roof tiles of size 225 mm x 300 mm or larger (red colour) (country made) Tk. 16,200.00 per % sft
Flower shaped roof tiles of size 175 mm x 175 mm or equivalent (red colour) (country
292 Tk. 22,420.00 per % sft
made)
293 Roof tiles of size 100 mm x 200 mm or equivalent (beige colour) (country made) Tk. 14,500.00 per % sft
Roof tiles of size 125 mm x 170 mm to 200 mm x 200 mm or equivalent (beige colour)
294 Tk. 18,500.00 per % sft
(country made)
295 Roof tiles of size 225 mm x 300 mm or larger (beige colour) Tk. 18,000.00 per % sft
Flower shaped roof tiles of size 175 mm x 175 mm or equivalent (beige colour)(country
296 Tk. 23,600.00 per % sft
made)
Flower shaped roof tiles of size 175 mm x 175 mm or equivalent (grey or black colour)
297 Tk. 26,200.00 per % sft
(country made)
315 Adjustable mechanism including top and bottom plate Tk. 600.00 per set
316 I-section joist to support inclined prop Tk. 400.00 per foot
317 4" x 2" M.S. box channel with 1/8" thick M.S. sheet Tk. 350.00 per foot
318 Steel prop with adjustable mechanism including top and bottom plate Tk. 1,650.00 per set
322 Sealer for exterior emulsion paint Tk. 174.00 per litre
326 Thinner for oil-based paint (turpentine) for general purpose Tk. 120.00 per kg
328 Synthetic polyvinyl (S.P.) distemper primer /sealer Tk. 149.00 per litre
329 Acrylic plastic emulsion paint (plastic/matt finish) Tk. 202.00 per litre
330 Acrylic plastic emulsion paint (silky finish) Tk. 391.00 per litre
331 Acrylic plastic emulsion paint (odorless) Tk. 500.00 per litre
332 Sealer for acrylic plastic emulsion paint Tk. 149.00 per litre
Analysis of PWD SoR 2018 for Civil Works 14
336 Thinner for oil-based paint (turpentine) for general purpose Tk. 120.00 per litre
340 Epoxy enamel primer including base, curing agent & thinner Tk. 500.00 per litre
341 Epoxy enamel paint including base, curing agent & thinner Tk. 523.00 per litre
342 Textured coating including sealer, texture coat & top coat Tk. 250.00 per litre
343 Wood varnishing: Yacht ( alkyd based) Tk. 250.00 per litre
344 Wood varnishing: Egg-shell ( alkyd based) Tk. 250.00 per litre
345 Wood varnishing: Matt ( alkyd based) Tk. 250.00 per litre
346 Thinner for alkyd based wood varnishing Tk. 130.00 per litre
347 Self leveling epoxy coating (4 mm thickness) Tk. 150.00 per sft
350 Design Paint including base coat , design coat & protection coat Tk. 390.00 per litre
French-Polishing
Powder
C14 ALUMINIUM : Anodized coated
coated
S.S Any
I. Aluminium Channel / Sections: Rate per foot Bronze Silver Unit
colour colour
359 101.60 mm, 44.45 mm wall frame of 1.2 mm thick Tk. 118.00 Tk.115.00 Tk.122.00 Tk.125.00 per foot
361 16.54 mm, 15.49 mm Door glass bit of 0.99 mm thick Tk. 16.00 Tk. 15.00 Tk. 16.00 Tk. 18.00 per foot
362 101.54 mm, 42.93 mm closure system of 1.8 mm thick Tk. 131.00 Tk.126.00 Tk.134.00 Tk.141.00 per foot
363 101.60 mm closure cover of 1.2 mm thick Tk. 45.00 Tk. 44.00 Tk. 47.00 Tk. 54.00 per foot
364 101.60 mm, 12.70 mm floor bottom of 4 mm thick Tk. 133.00 Tk.123.00 Tk.131.00 Tk.131.00 per foot
365 82.60 mm, 43.99 mm door shutter bottom of 1.8 mm thick Tk. 173.00 Tk.168.00 Tk.178.00 Tk.186.00 per foot
366 51 mm, 43.99 mm door shutter top of 1.8 mm thick Tk. 142.00 Tk.138.00 Tk.146.00 Tk.153.00 per foot
368 101.60 mm, 44.45 mm top & side 1.8 mm thick Tk. 176.00 Tk.171.00 Tk.182.00 Tk.187.00 per foot
369 101.35 mm, 44.45 mm bottom of 1.2 mm thick Tk. 90.00 Tk. 88.00 Tk. 93.00 Tk. 96.00 per foot
370 44.32 mm, 19.61 mm fixed bottom cover of 1.2 mm thick Tk. 52.00 Tk. 51.00 Tk. 54.00 Tk. 55.00 per foot
371 83.21mm, 16.00 mm fixed grouve cover of 1.2 mm thick Tk. 79.00 Tk. 76.00 Tk. 81.00 Tk. 83.00 per foot
372 39.09mm, 14.81mm fixed glass protector of 1.0 mm thick Tk. 25.00 Tk. 24.00 Tk. 26.00 Tk. 27.00 per foot
374 75.50 mm, 17.79 mm outer low bottom 0f 1.2 mm thick Tk. 82.00 Tk. 81.00 Tk. 85.00 Tk. 96.00 per foot
375 75.5 mm, 26.8 mm outer top of 1.2 mm thick Tk. 92.00 Tk. 89.00 Tk. 95.00 Tk.107.00 per foot
376 33 mm, 26.80 mm, 22 mm shutter top of 1.2 mm thick Tk. 62.00 Tk. 60.00 Tk. 64.00 Tk. 66.00 per foot
377 60 mm, 24 mm shutter bottom of 1.2 mm thick Tk. 87.00 Tk. 84.00 Tk. 89.00 Tk. 92.00 per foot
378 75.50 mm, 19.90 mm outer side of 1.2 mm thick Tk. 77.00 Tk. 74.00 Tk. 79.00 Tk. 81.00 per foot
379 49.20 mm, 26.20 mm shutter lock of 1.2 mm thick Tk. 80.00 Tk. 78.00 Tk. 82.00 Tk. 85.00 per foot
381 31.75 mm shutter divider of 1.2 mm thick Tk. 66.00 Tk. 64.00 Tk. 68.00 Tk. 71.00 per foot
Analysis of PWD SoR 2018 for Civil Works 16
382 31.00 mm, 26.00 mm sliding fixed side of Tk. 46.00 Tk. 44.00 Tk. 47.00 Tk. 50.00 per foot
383 7.14 mm spandrel of 1.4mm to 1.2mm thick Tk. 88.00 Tk. 85.00 Tk. 90.00 Tk. 92.00 per foot
384 75.50 mm, 32 mm outer bottom (high) of 1.2 mm thick Tk. 90.00 Tk. 88.00 Tk. 93.00 Tk. 96.00 per foot
385 75.5 mm, 26.80 mm outer top of 1.2 mm thick Tk. 92.00 Tk. 89.00 Tk. 95.00 Tk. 98.00 per foot
386 37.78 mm, 31.78 mm bottom cover of 1.2 mm thick Tk. 39.00 Tk. 38.00 Tk. 40.00 Tk. 42.00 per foot
387 76.20 mm, 38.10 mm grouve cover of 1.2 mm thick Tk. 88.00 Tk. 85.00 Tk. 90.00 Tk. 92.00 per foot
388 57.15 mm, 15.80 mm grouve cover of 1.2 mm thick Tk. 59.00 Tk. 57.00 Tk. 60.00 Tk. 62.00 per foot
76.20 mm, 38.10 mm, 57.15 mm fixed top & side of 1.2 mm
389 Tk. 115.00 Tk.112.00 Tk.118.00 Tk.123.00 per foot
thick
390 38.88 mm, 36.63 mm casement outer 1.2 mm thick Tk. 52.00 Tk. 50.00 Tk. 53.00 Tk. 56.00 per foot
393 57.15 mm, 15.80 mm grouve cover of 1.2 mm thick Tk. 59.00 Tk. 57.00 Tk. 60.00 Tk. 62.00 per foot
394 17.40 mm, 31.78 mm bottom cover of 1.2 mm thick Tk. 39.00 Tk. 38.00 Tk. 40.00 Tk. 42.00 per foot
395 76.20 mm, 38.10 mm fixed bottom cover of 1.2 mm thick Tk. 115.00 Tk.112.00 Tk.118.00 Tk.120.00 per foot
396 57.15 mm, 38.10 mm top & side of 1.2 mm thick Tk. 128.00 Tk.125.00 Tk.132.00 Tk.135.00 per foot
397 76.00 mm, 38.10 mm wall frame of 1.2 mm thick Tk. 90.00 Tk. 88.00 Tk. 93.00 Tk. 99.00 per foot
398 55.02 mm, 37.39 mm louver Z-section of 1.2 mm thick Tk. 30.00 Tk. 30.00 Tk. 31.00 Tk. 34.00 per foot
399 39.67 mm, 15.06 mm louver U-section of 1.2 mm thick Tk. 35.00 Tk. 34.00 Tk. 37.00 Tk. 40.00 per foot
400 95.00 mm, 38.00 mm outer bottom of 1.2 mm thick Tk. 113.00 Tk.110.00 Tk.117.00 Tk.124.00 per foot
401 95.00 mm, 28.50 mm outer top of 1.2 mm thick Tk. 113.00 Tk.110.00 Tk.117.00 Tk.122.00 per foot
402 95.00 mm, 19.50 mm outer side of 1.2 mm thick Tk. 90.00 Tk. 88.00 Tk. 93.00 Tk. 97.00 per foot
403 42.2 mm, 13.2 mm net section of 1.2 mm thickness Tk. 55.00 Tk. 53.00 Tk. 57.00 Tk. 59.00 per foot
404 1" x 1" square pipe Tk. 38.00 Tk. 37.00 Tk. 39.00 Tk. 41.00 per foot
405 7.14 mm span drel of 1.2 mm thick (0.70 kg/m) Tk. 90.00 Tk. 88.00 Tk. 92.00 Tk. 94.00 per foot
406 Mosquito net (fiber net) (per sft) Tk. 17.00 Tk. 15.00 Tk. 19.00 Tk. 21.00 per foot
407 T-section (main T) for false ceiling Tk. 25.00 Tk. 24.00 Tk. 26.00 Tk. 29.00 per foot
Analysis of PWD SoR 2018 for Civil Works 17
408 T-section (cross T) for false ceiling Tk. 22.00 Tk. 21.00 Tk. 22.00 Tk. 27.00 per foot
409 L-section for wall and ceiling Tk. 21.00 Tk. 20.00 Tk. 22.00 Tk. 26.00 per foot
410 Aluminium curtain rail including hard-wares and fittings Tk. 27.00 Tk. 26.00 Tk. 28.00 Tk. 30.00 per foot
411 44 mm, 44 mm, 1.20 box Tk. 79.00 Tk. 76.00 Tk. 81.00 Tk. 84.00 per foot
412 25 mm, 25 mm, 1.20 angle Tk. 23.00 Tk. 22.00 Tk. 24.00 Tk. 25.00 per foot
413 25 mm, 25 mm, 1.20 fitting angle Tk. 48.00 Tk. 47.00 Tk. 50.00 Tk. 52.00 per foot
414 Alluminium composite Panel Tk. 250.00 Tk.248.00 Tk.252.00 Tk.255.00 per foot
415 Curtain wall sub mullium (100mm X 50 mm X 2.00 mm) Tk. 294.00 Tk.286.00 Tk.303.00 Tk.313.00 per foot
416 Curtain wall sub mullium (50mm X 50 mm X 1.50 mm) Tk. 177.00 Tk.173.00 Tk.184.00 Tk.191.00 per foot
417 Casement outer frame (29mm X 20 mm X 1.20 mm) Tk. 39.00 Tk. 38.00 Tk. 40.00 Tk. 44.00 per foot
418 Casement outer section (52mm X 22 mm X 40mm X 1.5 mm) Tk. 152.00 Tk.147.00 Tk.156.00 Tk.163.00 per foot
419 Aluminium angle (50mm X 50 mm X 6mm) Tk. 235.00 Tk.230.00 Tk.240.00 Tk.245.00 per foot
420 Aluminium cover (50mm X 6 mm X 1.5mm) Tk. 74.00 Tk. 72.00 Tk. 76.00 Tk. 78.00 per foot
421 50mm X 6 mm X 1.5mm angle for casement shutter Tk. 78.00 Tk. 75.00 Tk. 80.00 Tk. 82.00 per foot
422 38mm x 38mm Aluminium frame (Wall box) of 1.5 mm Tk. 75.00 Tk. 72.00 Tk. 77.00 Tk. 80.00 per foot
424 20 mm Aluminium pipe Tk. 93.00 Tk. 91.00 Tk. 95.00 Tk. 98.00 per foot
Analysis of PWD SoR 2018 for Civil Works 18
465 6 mm thick PVC board of size 600x600 mm Tk. 40.00 per sft
466 0.6 mm thick plain aluminium board of size 600x600 mm Tk. 95.00 per sft
467 0.6 mm thick perforated aluminium board of size 600x600 mm Tk. 75.00 per sft
474 Rod tilt / Hexagon Aluminium Rod Tk. 8.50 per foot
475 End cap set / End closure set Tk. 75.00 per set
485 Glass fiber Fabrics (special quality, foreign made) Tk. 100.00 per sft
490 Aluminium Strips (special quality, foreign made) Tk. 80.00 per foot
494 Rod till / hexagon aluminium Rod Tk. 7.00 per foot
503 Bottom cap / end cap for head rail Tk. 10.00 each
509 Head control tube, 38mm aluminium tube with wall thickness 1mm Tk. 20.00 per foot
511 End cap set/end closure set Tk. 50.00 Per set
521 PVC/ vinyl laminated fiberglass fabrics Tk. 90.00 per sft
527 38mm thick rope chain bead clutch Tk. 70.00 per set
529 25mm thick bottom aluminum tube with 1mm wall thickness Tk. 15.00 per foot
532 mounting profile for outside mount of roller tube Tk. 30.00 per foot
Analysis of PWD SoR 2018 for Civil Works 22
C15 PVC
536 Wall grade 3/4" / 19 mm dia pipe, 1.2 mm thick Tk. 5.00 per foot
537 Wall grade 1"/ 25 mm dia pipe, 1.2 mm thick Tk. 7.00 per foot
538 Roof grade 3/4"/19 mm dia pipe, 1.5 mm thick Tk. 5.50 per foot
539 Roof grade 1"/ 25 mm dia pipe, 1.5 mm thick Tk. 8.50 per foot
540 Roof grade 1.25"/ 32 mm dia pipe, 1.5 mm thick Tk. 11.00 per foot
552 PVC door frame thickness min 2.5 mm Tk. 107.00 per meter
553 G.I inner joint (76.2 mm x 38.1 mm) clamp Tk. 12.00 each
554 G.I inner joint (72.2 mm x 76.2 mm) clamp Tk. 13.00 each
559 uPVC hollow section wall thickness 2.5 mm Tk. 880.00 per meter
580 10mm glass for partition wall Tk. 300.00 per sqm
614 Rowl plug (10 Nos. per pack) Tk. 20.00 per pack
II. Consumable
645 5/8" x 3" long nut bolt including washer Tk. 74.18 each
646 Valve Pit (Titas Gas T&D Co. Ltd. design & plan.) (for 2" dia above) Tk. 18,342.50 each
647 M.S. sheet cover supplied by Titas Gas T & D Co. Ltd.(for 2" dia above) Tk. 15,516.23 each
649 50 mm ND dia ball valve class 150 R.F. Tk. 7,318.60 each
650 25 mm ND dia plug valve class 150 R.F. Tk. 5,221.92 each
656 3/4" / 19 mm dia G.I. pipe (NTL or eqv.) Tk. 41.70 per foot
657 1/2" / 12 mm dia G.I. pipe (NTL or eqv.) Tk. 32.00 per foot
663 70 mm non load bearing concrete hollow block Tk. 24.00 each
666 90 mm non load bearing concrete hollow block Tk. 36.00 each
668 140 mm non load bearing concrete hollow block Tk. 53.00 each
670 140 mm load bearing concrete hollow block Tk. 56.06 each
671 190 mm load bearing concrete hollow block Tk. 60.00 each
685 250 x 250 mm grey engraved CC tiles Tk. 46.66 per sft
686 250 x 250 mm coloured engraved CC tiles Tk. 56.51 per sft
690 Transportation Solid block (215 x 100 x 65) mm Tk. 1.64 each
691 200 mm x 92 mm x 37.5 mm grey solid cladding block Tk. 13.00 each
693 200 mm x 92 mm x 37.5 mm coloured solid cladding block Tk. 15.00 each
698 418 mm x 330 mm x 17 mm red colour roof tiles Tk. 150.00 each
701 418 mm x 330 mm x 17 mm oriental colour roof tiles Tk. 42.56 each
702 418 mm x 330 mm x 17 mm antique red colour roof tiles Tk. 49.05 each
703 418 mm x 330 mm x 17 mm green colour roof tiles Tk. 53.36 each
706 100 mm non-load bearing concrete hollow block Tk. 30.68 each
714 418 mm x 330 mm x 17 mm brown colour roof tiles Tk. 49.45 each
715 418 mm x 330 mm x 17 mm Navy blue roof tiles Tk. 52.87 each
716 418 mm x 330 mm x 17 mm Mahogany colour roof tiles Tk. 56.00 each
Analysis of PWD SoR 2018 for Civil Works 29
717 418 mm x 330 mm x 17 mm Rust Gold colour roof tiles Tk. 56.00 each
718 All type concrete ridge: red colour Tk. 150.00 each
721 400 mm x 200 mm x100 mm sand cement hollow block (SCHB) Tk. 28.00 each
722 250 mm x 115 mm x 115 mm sand cement solid block Tk. 10.00 each
723 300 mm x 115 m x 115 mm size thermal block Tk. 22.00 each
724 240 mm x 115 mm x 70 mm size compressed stabilized earth block(CSEB) Tk. 7.00 each
725 300 mm x 115 mm x 70 mm size sand cement solid block (SCSB) Tk. 11.00 each
I. Misc. items
726 Water sealed heavy type 18" dia C.I. M.H. cover having locking arrangement Tk. 900.00 each
727 Water sealed heavy type 24" dia C.I. M.H. cover having locking arrangement Tk. 1,390.00 each
744 Special coloured commode: 465 x 340 x 415 mm Tk. 1,670.00 each
748 Special coloured low-down: 490 x 190 x 350 mm Tk. 1,600.00 each
749 32 mm dia plastic pipe for low-down connection Tk. 75.00 each
750 Light colour combicloset , Size 670 x 365 x 755 mm, 31kg Tk. 6,040.00 each
751 Coloured combicloset (Marbel shaded) :670 x 365 x 755mm, 31kg Tk. 7,850.00 each
752 Special coloured combicloset: (Deep colour) 670 x 365 x 755 mm, 31kg Tk. 9,060.00 each
Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde), 700 x 370 x 795 mm,
753 Tk. 7,130.00 each
32.5kg
754 Coloured (Marble shade) 700 x 370 x 795 mm, 32.5kg Tk. 9,270.00 each
755 Special coloured (Deep Blue, Ruby, Rain Forest, Green), 700 x 370 x 795 mm, 32.5kg Tk. 10,695.00 each
Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde), 700 x 360 x 785 mm, 38
756 Tk. 9,950.00 each
kg
757 Coloured (Marble Shade) 700 x 360 x 785 mm, 38 kg Tk. 13,935.00 each
758 Special coloured (Deep Blue, Ruby, Rain Forest, Green) 700 x 360 x 785 mm, 38 kg Tk. 14,925.00 each
759 White / Ivory colour 440 x 730 x 785 mm, 36.75 kg Tk. 11,825.00 each
760 White and Ivory colour 440 x 730 x 785 mm, 36.75 kg Tk. 11,825.00 each
761 White combicloset, 725 x 360 x 840 mm, 42.7kg Tk. 12,640.00 each
762 Coloured (Marble Shade) , 725 x 360 x 840 mm size, approx. 42.7 kg Tk. 16,430.00 each
Special coloured (Deep Blue, Ruby, Rain Forest, Green), 725 x 360 x 840 mm size,
763 Tk. 18,950.00 each
approx. 42.7 kg
764 White colour, 370 x 760 x 800 mm size, approx. 44.69 kg Tk. 13,990.00 each
White / Ivory colour glazed vitreous W/H wash basin excluding pedastal, 560 x 410 x 205
765 Tk. 3,150.00 each
mm, 7.90kg
Supplying, glazed vitreous W/H Wash Basin including pedastal approx (size 600 x 500 x
766 Tk. 4,650.00 each
855 mm, 26.92kg )
Light Colour Bangladesh pattern, long pan with foot-rest , Size 530 x 430 x 210 mm, 12.5
768 Tk. 887.00 each
kg
769 Coloured ( Marbel Shaded) long pan 530 x 430 x 210 mm, 12.5 kg Tk. 1,153.00 each
Special coloured (Deep colour) Bangladesh pattern, long pan with foot-rest, Size
770 Tk. 1,330.00 each
530x430x210 mm 12.5 kg
771 White colour, long pan with foot-rest, approx. 530 x 450 x 290 mm 14.5 kg Tk. 1,315.00 each
772 Coloured, long pan with foot-rest, approx. 530 x 450 x 290 mm 14.5 kg Tk. 1,643.00 each
773 Special, long pan with foot-rest, coloured approx. 530 x 450 x 290 mm 14.5 kg Tk. 1,972.00 each
774 White/coloured foot-rest, Size 280 x 140 x 30 mm size glazed porcelain foot rest, 1.5 kg Tk. 200.00 per pair
775 Light colour long pan (Bangladeshi) approx. 525 x 295 x 285 mm, 5.7kg or equivalent Tk. 550.00 each
Cabinet Basin
Analysis of PWD SoR 2018 for Civil Works 32
794 Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde), 500x450x180 mm , 9 kg Tk. 2,613.00 each
796 Special coloured (Deep Blue, Ruby, Rain Forest, Green) 500x450x180 mm, 9 kg Tk. 3,919.50 each
Corner Basin
797 Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde) 440x360x195 m, 7.0kg Tk. 788.00 each
798 Coloured ( Marble Shade) 440x360x195 mm, 7.0kg Tk. 1,024.40 each
799 Special coloured ( Deep Blue, Ruby, Rain Forest, Green), 440x360x195 mm, 7.0kg Tk. 1,182.00 each
800 Light colour W-basin including pedastal, , approx. size 660 x 545 x 850 mm, 29kg Tk. 3,295.00 each
801 Coloured ( Marble Shade), approx. size 660 x 545 x 850 mm, 29kg Tk. 4,280.00 each
Special coloured W-basin:( Deep Colour ),including pedasta, approx. size 660 x 545 x 850
802 Tk. 4,940.00 each
mm, 29kg
803 Light colour W-basin including pedastal : approx. 665 x 490 x 840 mm, 29.5 kg Tk. 4,760.00 each
804 Coloured ( Marble Shade) W-basin:approx. 665 x 490 x 840 mm, 29.5 kg Tk. 6,185.00 each
805 Special coloured ( Deep Colour ) W-basin: approx. 665 x 490 x 840 mm, 29.5 kg Tk. 7,135.00 each
807 125 mm dia Convex Cast Iron Grating Tk. 400.00 each
808 32 mm dia PVC waste pipe for W-Basin connection Tk. 150.00 each
Pedestal
810 White colour: approx. 670 x 186 x 170 mm, 6.5kg Tk. 1,345.00 each
811 Coloured (Marble shaded) approx. 670 x 186 x 170 mm, 6.5kg Tk. 1,750.00 each
812 Special coloured (Deep colour ): approx. 670 x 186 x 170 mm, 6.5kg Tk. 2,020.00 each
Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde) : approx. 670 x 186 x
813 Tk. 1,840.00 each
170 mm
814 Coloured (Marble Shaded) approx. 670 x 186 x 170 mm, 6.5kg Tk. 2,392.00 each
815 Special coloured (Deep Blue, Ruby, Rain Forest, Green) approx. 670 x 186 x 170 mm Tk. 2,760.00 each
Light colour (Ivory, Alpine White, Grey, Pink, Blue, Aqua Verde) : approx. 670 x 186 x
816 Tk. 1,980.00 each
170 mm
817 Coloured (Marble Shaded) approx. 670 x 186 x 170 mm Tk. 2,574.00 each
818 Special coloured (Deep Blue, Ruby, Rain Forest, Green ) approx. 670 x 186 x 170 mm Tk. 2,970.00 each
Analysis of PWD SoR 2018 for Civil Works 33
819 Light colour : approx 445 x 355 x 330 mm, 11.5kg Tk. 1,115.00 each
820 Coloured (Marble shaded) approx 445 x 355 x 330 mm, 11.5kg Tk. 1,450.00 each
821 Special coloured (Deep colour ) approx 445 x 355 x 330 mm, 11.5kg Tk. 1,670.00 each
822 Light colour :approx 445 x 355 x 330 mm, 10kg (partition Type) Tk. 1,650.00 each
823 Coloured (Marble shade approx 445 x 355 x 330 mm, 10kg (partition Type) Tk. 2,171.00 each
824 Special coloured (Deep colour ) approx 445 x 355 x 330 mm, 10kg (partition Type) Tk. 2,505.00 each
825 White colour flat/squatting bowl urinal: 510 x 380 x 85mm in size, approx. 9.5 kg Tk. 950.00 each
826 Coloured flat/squatting bowl urinal: 510 x 380 x 85mm in size, approx. 9.5 kg Tk. 1,000.00 each
827 Special coloured flat/squatting bowl urinal: 510 x 380 x 85 mm in size, approx. 9.5 kg Tk. 1,100.00 each
828 White porcelain sink, size (mm) 635 x 480 x 195 mm, 19.5kg Tk. 1,500.00 each
829 Coloured porcelain sink: 635 x 480 x 195 mm, 19.5kg Tk. 1,800.00 each
830 Stainless steel, single bowl sink: Singapore/M'Asia, size 450 mm x 1050 mm Tk. 2,500.00 each
831 Stainless steel, double bowl Sink: Singapore/M'Asia, Tk. 4,500.00 each
834 Super quality steel frame with brackets for 600 x 125 x 5 mm size glass shelf Tk. 600.00 each
835 Super quality coloured glass for 600 x 125 x 5 mm size glass shelf Tk. 400.00 each
836 Medium quality CP iron frame with brackets for 600 x 125 x 5 mm size glass shelf. Tk. 350.00 each
837 Medium quality glass for 600 x 125 x 5 mm size glass shelf Tk. 300.00 each
838 Super quality 600 x 20 mm dia size CP towel rail. Tk. 450.00 each
839 Medium quality CP Towel Rail 600 x 20 mm dia size Tk. 375.00 each
840 White porcelain toilet paper holder, size (mm) 150 x 150 x 126 Tk. 250.00 each
841 Coloured porcelain toilet paper holder, Size (mm) 150 x 150 x 126 Tk. 325.00 each
842 White special porcelain toilet paper holder Size (mm) 150 x 150 x 126 Tk. 320.00 each
843 Coloured special porcelain toilet paper holder Size (mm) 150 x 150 x 126 Tk. 420.00 each
844 Standard size stainless steel toilet paper holder with cover Tk. 400.00 each
845 Standard size CP toilet paper holder with pastic holder rod Tk. 245.00 per set
847 150 x 150 mm size stainless steel floor grating Tk. 740.00 each
849 62mm dia stainless steel floor grating Tk. 95.00 each
850 150 x 150mm size plastic-grating with hinged cover Tk. 75.00 each
851 Plastic low down complete set including internal and external fittings Tk. 900.00 per set
852 Internal and external fittings for plastic low down Tk. 540.00 per set
857 Surface mounted automatic liquid soap dispenser Tk. 5,500.00 each
872 Electro fusion welding joint(upto 110 mm) Tk. 400.00 each
Analysis of PWD SoR 2018 for Civil Works 35
873 Electro fusion welding joint(over 110 mm) Tk. 500.00 each
874 110 mm dia HDPE pipe for under-ground Tk. 167.00 per foot
875 110 mm HDPE plain Tee/T-Y for under-ground Tk. 646.00 each
876 110 mm HDPE plain Bend for under-ground Tk. 465.00 each
877 160 mm dia HDPE pipe for under-ground Tk. 307.00 per foot
878 160 mm HDPE plain Tee/T-Y for under-ground Tk. 916.00 each
879 160 mm HDPE plain bend for under-ground Tk. 802.00 each
880 200 mm dia HDPE pipe for under-ground Tk. 552.00 per foot
881 200 mm HDPE plain tee/T-Y for under-ground Tk. 2,274.00 each
882 200 mm HDPE plain bend for under-ground Tk. 1,527.00 each
883 250 mm dia HDPE pipe for under-ground Tk. 850.00 per foot
884 250 mm HDPE plain tee/T-Y for under-ground Tk. 4,541.00 each
885 250 mm HDPE plain bend for under-ground Tk. 3,054.00 each
886 280 mm dia HDPE pipe for under-ground Tk. 1,072.00 per foot
887 280 mm HDPE plain tee/T-Y for under-ground Tk. 5,465.00 each
888 280 mm HDPE plain bend for under-ground Tk. 3,960.00 each
889 315 mm dia HDPE pipe for under-ground Tk. 1,367.00 per foot
890 315 mm HDPE plain tee/T-Y for under-ground Tk. 7,320.00 each
891 315 mm HDPE plain bend for under-ground Tk. 5,402.00 each
892 400 mm dia HDPE pipe for under-ground Tk. 2,190.00 per foot
893 400 mm HDPE plain tee/T-Y for under-ground Tk. 14,057.00 each
894 400 mm HDPE plain bend for under-ground Tk. 10,780.00 each
895 630 mm dia HDPE pipe for under-ground Tk. 5,105.00 per foot
896 630 mm HDPE plain tee/T-Y for under-ground Tk. 40,555.00 each
897 630 mm HDPE plain bend for under-ground Tk. 31,042.00 each
898 710 mm dia HDPE pipe for under-ground Tk. 6,908.00 per foot
899 710 mm HDPE plain tee/T-Y for under-ground Tk. 50,689.00 each
900 710 mm HDPE plain bend for under-ground Tk. 42,570.00 each
Analysis of PWD SoR 2018 for Civil Works 36
901 900 mm dia HDPE pipe for under-ground Tk. 11,110.00 per foot
902 900 mm HDPE plain Tee/T-Y for under-ground Tk. 90,894.00 each
903 900 mm HDPE plain bend for under-ground Tk. 70,420.00 each
904 Butt fusion welding joint(75-355 mm dia HDPE pipe) Tk. 350.00 each
905 Butt fusion welding joint(400-560 mm dia HDPE pipe) Tk. 450.00 each
906 Butt fusion welding joint(630-1000 mm dia HDPE pipe) Tk. 600.00 each
(b) uPVC
930 50 mm dia uPVC pipe: 20 foot (6m) long Tk. 32.00 per foot
949 100 mm dia uPVC Pipe: 20 foot (6m) long Tk. 79.00 per foot
951 100 mm dia uPVC Tee/T-Y/Y (50 x 50 mm) Tk. 179.00 each
958 150 mm dia uPVC Pipe: 20 foot (6m) long Tk. 167.00 per foot
960 150 mm dia uPVC Tee/T-Y/Y (50 x 50 mm) Tk. 307.00 each
961 150 mm dia uPVC for under-ground Tk. 129.00 per foot
962 200 mm dia uPVC pipe for under-ground Tk. 257.00 per foot
963 250 mm dia uPVC pipe for under-ground Tk. 405.00 per foot
964 280 mm dia uPVC pipe for under-ground Tk. 540.00 per foot
965 315 mm dia uPVC pipe for under-ground Tk. 550.00 per foot
1028 62 mm dia stainless steel (2 mm thick) pipe Tk. 248.00 per foot
1029 50 mm dia stainless steel (2 mm thick) pipe Tk. 197.00 per foot
1030 40 mm dia stainless steel (2 mm thick) pipe Tk. 148.00 per foot
1031 25 mm dia stainless steel (2 mm thick) pipe Tk. 95.00 per foot
1032 20 mm dia stainless steel (2 mm thick) pipe Tk. 68.00 per foot
1033 12 mm dia stainless steel (2 mm thick) pipe Tk. 34.00 per foot
1034 6 mm dia stainless steel (1.5 mm thick) pipe Tk. 20.00 per foot
1055 SS pipe post with glass holder Tk. 300.00 per foot
(e) CPVC
PP-R Fittings
PP-R Union
PP-R Gate-Valve
1149 150 mm dia RCC pipe (stone-chips, 40 mm thickness. 6'-0" long) Tk. 1,017.00 each (6'-0")
1150 225 mm dia RCC pipe (stone-chips, 40 mm thickness. 6'-0" long) Tk. 1,575.00 each (6'-0")
1151 300 mm dia RCC pipe (stone-chips, 50 mm thickness. 6'-0" long) Tk. 2,743.00 each (6'-0")
1152 375 mm dia RCC pipe (stone-chips, 50 mm thickness. 6'-0" long) Tk. 3,580.00 each (6'-0")
1153 900 mm dia RCC pipe (stone-chips, 100 mm thickness. 6'-0" long) Tk. 13,190.00 each (6'-0")
v) G.I. Gate-Valve
viii) Float-Valve
X. Faucets
1202 12 mm plastic bip cock with internal brass thread Tk. 150.00 each
1218 CP shower mixture including shower head & faucet Tk. 4,250.00 each
1221 12 mm ordinary type (brass) for surface mount CP stop cock Tk. 300.00 each
1228 12 mm surface special heavy type angle stop cock Tk. 685.00 each
1230 12 mm medium quality concealed angle stop cock Tk. 715.00 each
1232 Special concealed type heavy stop cock Tk. 950.00 each
1233 12 mm CP medium quality surface & heavy type angle stop cock Tk. 625.00 each
1234 12 mm CP surface special heavy type stop cock Tk. 670.00 each
1235 100 mm dia CP fixed type cleansing shower rose Tk. 440.00 each
1236 100 mm dia CP moving type cleansing shower rose Tk. 900.00 each
1239 16 BWG GI 1200 x 1200 x 1200 mm size over-head water-tank Tk. 10,400.00 each
1240 18 BWG GI 1200 x 1200 x 1200 mm size over-head water-tank Tk. 10,200.00 each
1241 1000 litre food-grade Plastic over-head water-tank Tk. 7,100.00 each
1242 1500 litre food-grade Plastic over-head water-tank Tk. 10,650.00 each
1243 2000 litre food-grade Plastic over-head water-tank Tk. 14,200.00 each
1244 150 litre capacity plastic mini tank (loft tank) Tk. 1,875.00 each
Analysis of PWD SoR 2018 for Civil Works 49
1245 300 litre capacity plastic mini tank (loft tank) Tk. 2,550.00 each
1246 500 litre capacity plastic mini tank (loft tank) Tk. 3,400.00 each
1247 500 litre capacity stainless steel water tank Tk. 7,640.00 each
1248 1000 litre food-grade stainless steel water tank Tk. 14,036.00 each
1249 2000 litre food-grade stainless steel water-tank Tk. 24,056.00 each
1250 4000 litre food-grade stainless steel water tank Tk. 49,191.00 each
1251 6000 litre food-grade stainless steel water tank Tk. 53,481.00 each
1252 400 gallon capacity Ferro-cement water tank Tk. 6,320.00 each
1253 450 mm long metal cover connection pipe Tk. 100.00 each
1254 600 mm long metal cover connection pipe Tk. 120.00 each
1255 12 mm or 19 mm dia ball cock for water tank Tk. 130.00 each
1256 19 mm dia overflow pipe with jam-nut for plastic water tank Tk. 80.00 each
1257 12 mm dia & 450 mm long plastic flexible connection pipe Tk. 40.00 each
1258 12 mm dia & 600 mm long plastic flexible connection pipe Tk. 50.00 each
1261 75 GPD reverse osmosis water purifier ( Touch type) Tk. 20,000.00 each
1262 100 GPD reverse osmosis water purifier ( with hot cold & warm option) Tk. 55,000.00 each
1263 200 GPD reverse osmosis water purifier Tk. 40,000.00 each
1264 400 GPD reverse osmosis water purifier Tk. 60,000.00 each
1265 400 gal capacity ferro-cement water tank including installation Tk. 6,500.00 each
1282 16'-0" long muli bamboo (for split) Tk. 120.00 each
1283 25'-0" long muli bamboo (full size) Tk. 200.00 each
1299 Steel funna, 450 mm size wirth wooden handle Tk. 350.00 each
1304 22 BWG G.I. water can (2.5 gallon) Tk. 350.00 each
1307 400 mm blade Hand Lawn Mower, Model no 1403 – 16 (USA) Tk. 12,500.00 each
1308 4.5 h.p., 550 mm blade power lawn mower machine Tk. 44,500.00 each
1309 6.5 h.p., 550 mm blade power lawn mower machine Tk. 58,400.00 each
1310 22 h.p. 1150 mm cutting blade power riding lawn mower machine Tk.449,000.00 each
1316 Mobilization of equipment for drilling 38 mm dia test and observation well Tk. 6,553.16 LS
1318 Best quality heavy type hand type pump no 6 Tk. 2,330.46 each
1319 2.91 mm wall thick 38 mm dia G.I. pipe Tk. 534.06 meter
1320 38 mm dia water grade PVC pipe (D-Class or eqv.) including carriage Tk. 105.41 meter
1321 36 mm dia water grade PVC Strainer (D-Class or eqv.) including carriage Tk. 124.45 meter
1324 Complete development of the tube-well (test boring) up to 200 m depth. Tk. 5,817.24 LS
1328 Maintaining and filling and sealing test bore Tk. 3,295.65 each bore
1329 Mobilization of drilling rig for shrouded production wells of depth up to 100 m Tk. 32,491.42 LS
1354 125 mm dia PVC housing pipe Class C Tk. 625.00 meter
1355 125 mm dia PVC housing pipe Class D Tk. 783.33 meter
1356 125 mm dia PVC housing pipe Class E Tk. 933.33 meter
1357 150 mm dia PVC housing pipe Class C Tk. 916.67 meter
1358 150 mm dia PVC housing pipe Class D Tk. 1,250.00 meter
1359 150 mm dia PVC housing pipe Class E Tk. 1,500.00 meter
1360 200 mm dia PVC housing pipe Class C Tk. 1,400.00 meter
1361 200 mm dia PVC housing pipe Class D Tk. 1,875.00 meter
1362 200 mm dia PVC housing pipe Class E Tk. 2,200.00 meter
1363 250 mm dia PVC housing pipe Class C Tk. 2,200.00 meter
1364 250 mm dia PVC housing pipe Class D Tk. 3,083.00 meter
1365 250 mm dia PVC housing pipe Class E Tk. 3,666.67 meter
1372 Complete development of the tube-well up to 200 m depth (50 mm x 150 mm tube-well). Tk. 19,273.83 LS
1373 Complete development of the tube-well up to 200 m depth. (75 mm x 150 mm tube-well) Tk. 26,020.65 LS
1374 Complete development of the tube-well up to 200 m depth. (100 mm x 200 mm tube-well) Tk. 31,935.12 LS
1375 Complete development of the tube-well up to 200 m depth. (150 mm x 200 mm tube-well) Tk. 38,183.30 LS
1376 Complete development of the tube-well up to 200 m depth. (400 mm x 200 mm tube-well) Tk. 35,526.40 LS
1377 Hire charge of pump including spare and maintenance Tk. 267.26 hour
Analysis of PWD SoR 2018 for Civil Works 54
1378 Disinfections of tube-well using bleaching powder (for 50 mm x 125 mm tube-well) Tk. 1,030.37 LS
1379 150 mm dia and 4 mm thick M.S. pipe Tk. 2,326.85 meter
1380 200 mm dia and 6 mm thick M.S. pipe welded Tk. 3,305.41 meter
1381 200 mm dia and 6 mm thick M.S. pipe seamless Tk. 3,637.63 meter
1386 150 mm dia 4.85 mm thick G.I. pipe Tk. 2,826.21 meter
1388 150 mm dia stainless steel strainer of continuous slot Tk. 12,977.66 meter
1389 150 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 9,527.04 meter
1390 200 mm dia stainless steel strainer of continuous slot Tk. 15,212.20 meter
1391 200 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 10,084.79 meter
1392 75 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 5,648.28 meter
1393 100 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 5,717.85 meter
1394 50 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 4,927.94 meter
1395 75 mm dia 2.5 mm thick stainless steel bridge type strainer Tk. 6,674.32 meter
1396 200 mm x 200 mm dia 6 mm thick M.S. reducer Tk. 2,300.00 each
1397 150 mm x 300 mm dia 6 mm thick M.S. reducer Tk. 2,200.00 each
1402 (i) 300 mm dia 6 mm thick M.S. housing pipe welded Tk. 5,448.65 meter
1403 (ii) 300 mm dia 6 mm thick M.S. housing pipe seamless Tk. 7,500.00 meter
1404 (iii) 400 mm dia 6 mm thick M.S. housing pipe welded Tk. 8,565.72 meter
1405 (iv) 400 mm dia 6 mm thick M.S. housing pipe seamless Tk. 10,500.00 meter
Analysis of PWD SoR 2018 for Civil Works 55
1406 150 mm dia 6 mm thick M.S.housing pipe welded Tk. 4,000.00 meter
1407 150 mm dia 6 mm thick M.S. housing pipe seamless Tk. 3,500.00 meter
1412 EPI / RFL (medium) brand no 6 Pump with necessary fittings etc. Tk. 2,485.38 each
III. Testing of water including arsenic, collected from the test bore in BUET
Laboratory
1435 Sieve analysis for sand from different layer Tk. 1,200.00 per test
I. Operational cost
1436 Truck fare within 20 km including loading & un-loading Tk. 1,700.00 per trip
1437 Temporary camp at site for soil investigation work Tk. 1,053.00 per site
1438 Field Engineer including site allowances: 1-3yrs Exp, Membersip with IEB Tk. 1,800.00 per day
1439 Foundation Engineer: 5-10yrs exp , Membership with IEB Tk. 2,500.00 per day
1441 Rig operators including site allowances Tk. 600.00 per day
1442 Helper to rig operator/c site allowances Tk. 390.00 per day
1443 Unskilled labour including site allowances Tk. 320.00 per day
1454 Hydrometer, sieve analysis & sp. gr.,& Classification according to ASTM Tk. 1,200.00 per test
1459 Unit weight (wet & dry) Tk. 250.00 per test
1463 Consolidated quick test (direct shear test) Tk. 1,200.00 per test
1466 Visual Inspection & Classification of soil for engineering purposes Tk. 150.00 per test
C23 FITTINGS
1492 Best quality round lock/ rim lock Tk. 550.00 each
1495 250 mm long & 12 mm dia tower bolt Tk. 50.00 each
1499 150 mm long brass tower & socket bolt Tk. 250.00 each
1512 1.5 mm thick corrugated fiber glass Tk. 80.00 per sft
1513 1.5 mm thick fiber glass sheet ridging Tk. 142.00 per foot
Glass Door
1517 Top and bottom clamping device Tk. 1,177.00 per set
1532 EPS sheet (62mm thick) density 15 kg per cum Tk. 90.00 per cft
1535 Glass fiber mesh (10mmX10mm grid and weight 110gm/sqm) Tk. 7.00 per sft
Analysis of PWD SoR 2018 for Civil Works 60
Water proof, damp proof, dry & breathable cement STN-EN - 1015-11 , compressive
1536 strength 34 MPa), Max depth of water penetration into hardened plaster is < 1 mm (25 kg Tk. 1,500.00 per bag
bag)(Only for plaster work)
1537 Fire rated door complying standard specification Tk. 3,435.00 per sft
1538 Installation charge of fire rated door Tk. 215.00 per sft
1540 Empty gunny bags/ Polymer bag to fill sand for load test Tk. 10.00 each
1544 18 BWG galvanized wire mesh (2 mesh per 25mm) Tk. 20.00 per sft
1549 38 mm dia M.S. wheel for collapsible gate Tk. 28.00 each
1558 High performance elastomeric cementitious waterproof coating Tk. 280.00 per kg
1560 China made spring for rolling shutter Tk. 50.00 per foot
1564 150 mm long brass tower & socket bolt Tk. 250.00 each
1583 Single layer double bamboo tarja Tk. 130.00 per sqm
1593 2.44 m x 1.22 m size hard board Tk. 600.00 per piece
1595 Sign board including material, painting,lettering etc all complete Tk. 225.00 sft
1598 As built work survey & report Tk. 1,800.00 per day
1599 Providing expertised Architect 5years exp with registration in respective professional body Tk. 70,000.00 per month
1604 Engineer, Expertise in microsoft MS Project /Primavera and experience by min 5yrs Tk.120,000.00 permonth
1605 Engineer, min graduate in relevant field Tk. 1,800.00 per day
1606 Diploma Engineer, min 5yrs Exp Tk. 1,800.00 per day
1607 Diploma Engineer, min 1yrs Exp Tk. 1,000.00 per day
per
1608 Royality of Earth Tk. 1,715.00 thousand
cft
per
1609 Royality of Dredge material in the water body Tk. 800.00 thousand
cft
1611 Calibration of hydrauic jack & pressure gauge combined Tk. 33,100.00 per set
1613 Cutting by oxy-ace of 12 mm M.S plate, top & bott plate Tk. 36.00 per foot
1614 12 mm MS Plate Grinding to V bevel top & bott Tk. 50.00 per foot
Cutting by shearing granding and hole for steel jacket, 6 mm plate on 2U x ( top & bott) - C
1616 Tk. 13.00 per foot
or U form
1617 6 mm MS Plate Grinding to V bevel on faces of U legs for top & bott Tk. 70.00 per foot
1620 38 mm G.I / MS pipe for dowel bar Tk. 180.00 per foot
1622 Data logging engineer at hydraulic pile driver Tk. 1,800.00 per day
1623 Chief Mechanic, at hydraulic pile driver Tk. 1,400.00 per day
1624 Helper to mechanic, at hydraulic pile driver Tk. 390.00 per day
1626 Crane Operator, at hydraulic pile driver Tk. 800.00 per day
1627 Asst. Crane Operator, at hydraulic pile driver Tk. 600.00 per day
1628 Machine Operator, at hydraulic pile driver Tk. 600.00 per day
1629 Asst machine operator, at hydraulic pile driver Tk. 600.00 per day
1630 Helper to crane operator, at hydraulic pile driver Tk. 390.00 per day
1631 Helper to machine operator, at hydraulic pile driver Tk. 390.00 per day
1632 Generator Operator, at hydraulic pile driver Tk. 600.00 per day
1633 Surveyer to pile layout , at hydraulic pile driver Tk. 1,200.00 per day
1634 Helper to surveyer, at hydraulic pile driver Tk. 800.00 per day
1635 Skilled Labor, at hydraulic pile driver Tk. 390.00 per day
1636 ordinary labor, at hydraulic pile driver Tk. 320.00 per day
per 100km
1638 PIT : mobilization,demobilization, accomodation +12pile PIT Tk. 20,000.00 within
Dhaka
per pile
1639 Pile Integrity Test (PIT) Tk. 1,000.00 after 1st 12
pile
PIT expert engineer graduated in civil engg. And in geotech. engg. by profession , 10 yrs
1640 Tk.160,000.00 per month
experience
Analysis of PWD SoR 2018 for Civil Works 64
1641 Asst to PIT expert engineer: civil engr / geotech engineer by profession, 5yrs experience Tk.100,000.00 per month
1665 25 mm mesh expanded metal for using under patent stone Tk. 15.00 sft
1677 50 mm dia 100 mm long socket bolt (SS) Tk. 35.00 each
1681 50mm dia 200 mm long socket bolt(SS) Tk. 70.00 each
1682 50 mm dia 150 mm long brass socket bolt Tk. 110.00 each
1683 50 mm dia 200 mm long brass socket bolt Tk. 140.00 each
1684 50 mm dia 250 mm long brass socket bolt Tk. 180.00 each
1693 Materials for french polishing: 3 coats on new surface Tk. 800.00 % sft
1696 3 gal capacity C. I. Cistern (Not available in market) Tk. 1,260.00 each
gallon
1699 Aluminium paint Tk. 1,364.00
(U.K.)
1705 25mm dia G.I. Pipe for structural work Tk. 75.00 foot
1706 China made spring for rolling shutter Tk. 15.00 foot
1710 Vibrating roller Pedestrain (0.5 - 1 ton) Tk. 3,000.00 per day
Carriage of materials except bricks and bats by motor trucks bullock carts or any other
1713 means, including loading, unloading at both ends and stacking properly at site as per
direction of the Engineer.
(d) For each additional km beyond 5.0 kilometer and up to 30.0 kilometer Tk. 18.00 per M. ton
(e) For each additional km beyond 30.0 kilometer and up to 80.0 kilometer Tk. 13.00 per M. ton
1714 Weighing at both ends for items of steel materials only Tk. 105.00 per M. ton
Analysis of PWD SoR 2018 for Civil Works 67
Carriage of bricks or bats by motor truck, bullock carts or any other means including
1715 loading, unloading at both ends and stacking properly at site as per direction of the
Engineer.
(d) For each additional km beyond 5.0 kilometer and up to 30.0 kilometer Tk. 28.00 per % 0 nos
(e) For each additional km beyond 30.0 kilometer and up to 80.0 kilometer Tk. 18.00 per % 0 nos
CONCRETE
A. Labour, machinery, fuel and lubricant for casting CONCRETE using one concrete mixture machine (10 cft) per 1000cft /day
(a) Head mason 1 no @ Tk. 600.00 each = Tk. 600.00
(b) Mason 2 nos @ Tk. 500.00 each = Tk. 1,000.00
(c) Skilled labour:
(i) Feeding cement 0.2 no
(ii) Feeding sand 2 nos
(iii) Feeding chips 2 nos
Total = 4.2 nos @ Tk. 390.00 each = Tk. 1,638.00
(d) Ordinary labour
(i) Bag cutting 0.5 no
(ii) Belcha 3 nos
(iii) Lifting 4 nos
(iv) Pouring 4 nos
(v) On the way 4 nos
(vi) Poking 2 nos
(vii) Watering 0.5 no
Total = 18 nos @ Tk. 320.00 each = Tk. 5,760.00
(e) Mixture machine hire charge 1 day @ Tk. 1,200.00 per day = Tk. 1,200.00
(f) Vibrator machine hire charge 1 day @ Tk. 600.00 per day = Tk. 600.00
(g) Fuel and lubricant for mixture
machine & vibrator 1 day @ Tk. 1,200.00 per day = Tk. 1,200.00
Total = Tk. 11,998.00
A-1 Cost for placing 100 cft concrete using 1 mixer machine @ 1200 cft per day = Tk. 999.83
A-2 Cost for placing 100 cft concrete using 1 mixer machine @ 1000 cft per day = Tk. 1,199.80
A-3 Cost for placing 100 cft concrete using 1 mixer machine @ 800 cft per day = Tk. 1,499.75
A-4 Cost for placing 100 cft concrete using 1 mixer machine @ 600 cft per day = Tk. 1,999.67
A-5 Cost for placing 100 cft concrete using 1 mixer machine @ 500 cft per day = Tk. 2,399.60
B-1. Concrete (1:3:6) work using BRICK CHIPS and sand of F.M. 1.2
Considering 100 cft of work
(a) Bricks for chips
(@ 90 cft for % cft concrete). 765 nos @ Tk. 8,700.00 %0 nos = Tk. 6,655.50
(b) Breaking chips in/c screening 90 cft @ Tk. 950.00 % cft = Tk. 855.00
(c) Sand (F.M. 1.2) 45 cft @ Tk. 1,400.00 % cft = Tk. 630.00
(d) Cement: CEM-II/A,52.5 13 bags @ Tk. 395.00 bag = Tk. 5,135.00
(e) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Tk. 13,595.50
135.96
B-2. Concrete (1:2:4) work using BRICK CHIPS with sand of F.M. 1.2
Considering 100 cft of work
(a) Bricks for chips
(@ 90 cft for % cft concrete). 765 nos @ Tk. 8,700.00 %0 nos = Tk. 6,655.50
(b) Breaking chips in/c screening 90 cft @ Tk. 950.00 % cft = Tk. 855.00
(c) Sand (F.M. 1.2) 45 cft @ Tk. 1,400.00 % cft = Tk. 630.00
(d) Cement: CEM- I,52.5 18 bags @ Tk. 415.00 bag = Tk. 7,470.00
(e) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total = Tk. 15,930.50
159.31
B-3 Concrete (1:2:4) work using BRICK CHIPS (sand of F.M. 1.2 and 2.2 in equal proportion)
(f) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total = Tk. 16,628.00
166.28
B-4 Concrete (1:2:4) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2
Considering 100 cft of work
(a) 19 mm down size
crushed stone chips 87 cft @ Tk. 19,500.00 per % cft = Tk. 16,965.00
(b) Sand (F.M. 2.2) 43.5 cft @ Tk. 4,500.00 per % cft = Tk. 1,957.50
(c) Cement: OPC, Type-1 (CEM-I),52.5 18 bags @ Tk. 415.00 per bag = Tk. 7,470.00
(d) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total of A. = Tk. 26,712.50
267.13
B-5 Concrete (1:1.5:3) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2
Considering 100 cft of work
(a) 19 mm down crushed stone chips 83 cft @ Tk. 19,500.00 per % cft = Tk. 16,185.00
(b) Sand (F.M. 2.2) 41.5 cft @ Tk. 4,500.00 per % cft = Tk. 1,867.50
(c) Cement: OPC, Type-1 (CEM-I), 52.5 22 bags @ Tk. 415.00 per bag = Tk. 9,130.00
(d) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total (A) = Tk. 27,502.50
275.03
B-6 Concrete (1:1.25:2.5) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2
Break-up for 100 cft
(a) 19 mm down well graded
crushed stone chips 80 cft @ Tk. 19,500.00 per % cft = Tk. 15,600.00
(b) Well graded Sylhet sand (F.M. 2.2) 40 cft @ Tk. 4,500.00 per % cft = Tk. 1,800.00
(c) Cement: OPC, Type-1 (CEM-I),52.5 25.25 bags @ Tk. 415.00 Per bag = Tk. 10,478.75
(d) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
= Tk. 28,198.75
281.9875 pcft
B-7 Concrete (1:1:2) work with CRUSHED STONE CHIPS and 100% sand of F.M. 2.2
Break-up for 100 cft
(a) 19 mm down well graded
crushed stone chips 76 cft @ Tk. 19,500.00 per % cft = Tk. 14,820.00
(b) Well graded Sylhet sand (F.M. 2.2) 38 cft @ Tk. 4,500.00 per % cft = Tk. 1,710.00
(c) Cement: OPC, Type-1 (CEM-I),52.5 30 bags @ Tk. 415.00 Per bag = Tk. 12,450.00
(d) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
= Tk. 29,300.00
293 pcft
B-8 Fair-Face Concrete (1:1.5:3) work with CRUSHED STONE CHIPS, 75% grey cement, 25% white cement and 100% sand of F.M. 2.2
Considering 100 cft of work
(a) 19 mm down crushed stone chips 83 cft @ Tk. 19,500.00 per % cft = Tk. 16,185.00
(b) Sand (F.M. 2.2) 41.5 cft @ Tk. 4,500.00 per % cft = Tk. 1,867.50
(c) Cement: OPC, Type-1 (CEM-I), 52.5 16.5 bags @ Tk. 415.00 per bag = Tk. 6,847.50
(d) White Cement 275 kg @ Tk. 26.00 per kg = Tk. 7,150.00
(e) Colouring Pigment LS Tk. 840.00
(f) Local carriage, sundries, T & P, water, laboratory charge etc. LS = Tk. 320.00
Total (A) = Tk. 33,210.00
332.10 pcft
C-7 CORNICE, DROP-WALLS, RAILINGS, LOUVER and FINS etc. using WOODEN shutter
Assuming 3" thick 10'-0" x 3'-0" size dropwall
Shuttering Area: 62.5 sft
(i) Planks and batten
2 x 10'-0" x 3'-0" x 0'-1" = 5.00 cft
2 x 3 x 3'-0" x 0'-3" x 0'-2" = 0.75 cft
1 x 10'-0" x 5" x 1"= 0.34 cft
3 x 1'-6" x 0'-3" x 0'-2" = 0.19 cft
= 6.28 cft
Add 5% wastage = 0.31 cft
6.59 cft @ Tk. 500.00 per cft
Using 8 times @ Tk. 62.50 per cft = Tk. 411.88
(ii) Bamboo struts in/c inclined supports 8.0 nos @ Tk. 73.85 each
Using 8 times @ Tk. 9.23 each = Tk. 73.84
(iii) Nails and wires 0.5 kg @ Tk. 65.00 per kg = Tk. 32.50
(iv) Labour for shuttering in/c making, placing & removing:
2 x 10'-0'' x 3'-0" = 60 sft
1 x 10'-0" x 3"= 2.5 sft
= 62.5 sft @ Tk. 15.00 per sft = Tk. 937.50
(v) Supplying & fixing rupban or equivalent sheet
and necessary hessian tape for
making water-tight sufficiently 62.5 sft @ Tk. 2.50 per sft = Tk. 156.25
(vi) Curing for 28 days for surface area 62.5 sft @ Tk. 2.67 per sft = Tk. 166.88
Total = Tk. 1,778.85
Cost per sft = Tk. 28.46
Cost per sqm = Tk. 306.34
C-13 PADESTALS, COLUMN CAPITALS, LIFT WALLS and WALLS using STEEL shutter
Assuming 10'-0" x 12" x 12" Column
Shuttering Area: 40 sft
(i) 1.5" x 1.5" x 3/16" angle for frame
4 x 2 x 10'-0"= 80.00 rft
2 x 3 x 1'-4"= 7.98 rft
2 x 3 x 1'-0"= 6.00 rft
93.98 rft
Add 5% wastage = 4.699 rft
= 98.68 rft
1.79 Ibs per rft = 176.64 Ibs @ Tk. 24.94 per Ib = Tk. 4,405.40
(ii) 1" x3/16" F.I. bar for stiffner
2 x 8 x 1'-4"= 21.28 rft
Analysis of PWD SoR 2018 for Civil Works 76
and locking arrangements etc.: 1.00 no @ Tk. 600.00 each = Tk. 600.00
Total for 1 set Prop. = Tk. 2,385.00
Cost for 88 nos prop = Tk. 209,880.00
(e) 2" dia M.S. pipe for cross bracing:
9 x 18'-0"= 162.00 rft @ Tk. 140.00 per rft = Tk. 22,680.00
Sub-total = Tk. 232,560.00
Considering 50 times use = Tk. 4,651.20
(f) Labour cost for fitting fixing steel shutter and props
in position and removing etc.:
20'-0" x 16'-0"= 320.00 sft
2 x (20'-0" + 16'-0") x 5"= 30.00 sft
= 350.00 sft @ Tk. 15.00 per sft = Tk. 5,250.00
(g) Hessian tap for making shutter
water-tight 350.00 sft @ Tk. 1.25 per sft = Tk. 437.50
(i) Curing for 28 days for surface area 350.00 sft @ Tk. 2.67 per sft = Tk. 934.50
Grand total = Tk. 14,325.67
Cost per sft = Tk. 40.93
Cost per sqm = Tk. 440.57
Angle truss of max depth 400 mm at midspan and 150 mm at ends, top cord curved as required arranged radially @30 degree c/c, top and bottom cord of the truss
shall be 50X50X5 mm angle and diagonal and vertical shall be 40X40X4 mm angle (5% wastage)
D. supply, fabrication and Fixing of dia 20 mm rebar as purlin perpendicular to the truss frame @600 mm c/c
3.14X2.6X5=40.82 m@2.47 kg per m= 105.87 kg @ Tk. 60.50 per kg = Tk. 6,405.14
Deduct the resale value 30 % of the original = Tk. 1,921.54
Total = Tk. 4,483.60
For single use Cost per sqm = Tk. 79.33
E. Hessian tap for making shutter
water-tight 56.52 sqm @ Tk. 13.45 per sqm = Tk. 760.19
F. Curing for 28 days for surface area 56.52 sqm @ Tk. 28.69 per sqm = Tk. 1,621.56
Grand total = Tk. 2,381.75
For single use Cost per sqm = Tk. 42.14
(i) Formwork/shuttering, prop and necessary supports etc. (steel)(for single use) per sqm = Tk. 1,515.18
(ii) Formwork/shuttering, prop and necessary supports etc. (steel)(for 2-times use) per sqm = Tk. 1,060.63
(iii) Formwork/shuttering, prop and necessary supports etc. (steel)(for 3-times use) per sqm = Tk. 757.59
(iv) Formwork/shuttering, prop and necessary supports etc. (steel)(for more than 3-times use use) per sqm = Tk. 530.31
(v) Formwork/shuttering, prop and necessary supports etc. (steel)(exceedind 8 m span) per sqm = Tk. 378.80
1. Cost for taking and editing photographs 1 day @ Tk. 1,100.00 per day = 1,100.00
2. Printing & sundries 10 copies @ Tk. 7.00 per copy = 70.00
Sub - Total = 1,170.00
Profit 10.00% = Tk. 117.00
Overhead 3.50% = Tk. 40.95
Total = Tk. 1,327.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 84.76
Grand Total = Tk. 1,412.71
1. Planning implementation schedule & micro 7 day @ Tk. 120,000.00 per month = Tk. 28,000.00
networking using M.S. Project software or in
equivalent software
2. Developing hard-copy of networking 0.5 day @ Tk. 1,800.00 per day = Tk. 900.00
3 Printing of hard copy in 3 set 12.08 sft @ Tk. 18.00 per sft = Tk. 217.44
Sub - Total = Tk. 29,117.44
Profit 10.00% = Tk. 2,911.74
Overhead 3.50% = Tk. 1,019.11
Total = Tk. 33,048.29
Analysis of PWD SoR 2018 for Civil Works 88
1. Updating implementation schedule prepared 3 day @ Tk. 120,000.00 per month = Tk. 12,000.00
in M.S. Project software
2. Printing : 3 set 12.08 sft @ Tk. 18.00 per sft = Tk. 217.44
Sub - Total = Tk. 12,217.44
Profit 10.00% = Tk. 1,221.74
Overhead 3.50% = Tk. 427.61
Total = Tk. 13,866.79
Add VAT with adjustment factor 1.06383 6.00% = Tk. 885.11
Grand Total = Tk. 14,751.90
Item No.- 01.5 Rate is directly taken from basic material rate
Item No.- 01.6 Rate is directly taken from basic material rate
Item No.- 01.7 Rate is directly taken from basic material rate
Cost per month considering 21 months year project period hire charge will be applicable for half of = Tk. 49,880.00
the project period
4. Maintenance and operation cost
a) Trained operator LS = Tk. 10,000.00
b) Maintenance & Electricity bill LS = Tk. 2,500.00
3. Skilled labour 2.5 nos @ Tk. 390.00 per day = Tk. 975.00
4. Tools and plant, protecting and maintaining trench dry LS = Tk. 133.33
Sub - Total = Tk. 4,433.33
Profit 10.00% = Tk. 443.33
Overhead 3.50% = Tk. 155.17
Total = Tk. 5,031.83
Add VAT with adjustment factor 1.06383 6.00% = Tk. 321.18
Grand Total = Tk. 5,353.01
Rate per cft = Tk. 5.35
Rate per cum = Tk. 188.94
3. Nails, gozzal & wire etc. 5.00 kg @ Tk. 65.00 per kg = Tk. 325.00
4. Labour for cutting and straightening drum sheet, placing and fixing
the same with bamboo post and runner etc. complete.
(a) Skilled labour 2.00 nos @ Tk. 390.00 per day = Tk. 780.00
(b) Ordinary labour 3.00 nos @ Tk. 320.00 per day = Tk. 960.00
5. Local carriage LS = Tk. 640.00
Sub - Total = Tk. 6,005.00
Profit 10.00% = Tk. 600.50
Overhead 3.50% = Tk. 210.18
Total = Tk. 6,815.68
Add VAT with adjustment factor 1.06383 6.00% = Tk. 435.04
Grand Total = Tk. 7,250.72
Rate per sft = Tk. 48.34
Rate per sqm = Tk. 520.33
1. Fine sand (F.M. 0.8) 100.00 cft @ Tk. 900.00 per % cft = Tk. 900.00
2. Labour for mixing sand and cutting loose sludge
in/c spreading and stacking 12.00 nos @ Tk. 320.00 per day = Tk. 3,840.00
3. Labour cutting dried sludge in/c loading, 7.00 nos @ Tk. 320.00 per day = Tk. 2,240.00
unloading and truck/cart etc.
4. Hire charge of truck 7.00 trip @ Tk. 1,700.00 per trip = Tk. 11,900.00
5. Tools and plant, sundries, incidental etc. LS = Tk. 1,733.33
Sub - Total = Tk. 20,613.33
Profit 10.00% = Tk. 2,061.33
Overhead 3.50% = Tk. 721.47
Total = Tk. 23,396.13
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,493.37
Grand Total = Tk. 24,889.50
Rate per cft = Tk. 24.89
Rate per cum = Tk. 878.99
1. Royalty for earth 1150 cft @ Tk. 1,715.00 per % 0 cft = Tk. 1,972.25
2 Truck hire charge including cost of labour for 6 Trucks @ Tk. 800.00 per truck = Tk. 4,800.00
loading and unloading
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 6 nos @ Tk. 320.00 per day = Tk. 1,920.00
(b) Skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
4 Sundries, T & P etc. LS = 136.23
Sub - Total = Tk. 9,218.48
Profit 10.00% = Tk. 921.85
Overhead 3.50% = Tk. 322.65
Total = Tk. 10,462.98
Add VAT with adjustment factor 1.06383 6.00% = Tk. 667.85
Grand Total = Tk. 11,130.83
Rate per cft = Tk. 11.13
Rate per cum = Tk. 393.06
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in 0.50% = 1,005.00 cft
saturated condition
1. Royalty for Earth 1,005.00 cft @ Tk. 1,715.00 per % 0 cft = Tk. 1,723.58
2 Carriage of earth including cost of labour for 1150 cft @ Tk. 6.00 per cft = Tk. 6,900.00
loading and unloading
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
4 Sundries, T & P etc. LS = Tk. 130.55
Sub - Total = Tk. 8,834.13
Profit 10.00% = Tk. 883.41
Overhead 3.50% = Tk. 309.19
Total = Tk. 10,026.73
Add VAT with adjustment factor 1.06383 6.00% = Tk. 640.00
Grand Total = Tk. 10,666.73
Rate per cft = Tk. 10.67
Rate per cum = Tk. 376.81
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in 0.50% = 1,005.00 cft
saturated condition
1. Royalty for dredge material 1,005.00 cft @ Tk. 800.00 per % 0 cft = Tk. 804.00
2 Carriage of earth including cost of labour for 1150 cft @ Tk. 4.20 per cft = Tk. 4,830.00
loading and unloading
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
4 Sundries, T & P etc. LS = Tk. 85.71
Sub - Total = Tk. 5,799.71
Profit 10.00% = Tk. 579.97
Overhead 3.50% = Tk. 202.99
Total = Tk. 6,582.67
Add VAT with adjustment factor 1.06383 6.00% = Tk. 420.17
Grand Total = Tk. 7,002.84
Rate per cft = Tk. 7.00
Rate per cum = Tk. 247.21
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in 0.50% = 1,005.00 cft
saturated condition
1. Royalty for Earth 1,005.00 cft @ Tk. 1,715.00 per % 0 cft = Tk. 1,723.58
2 Carriage of earth including cost of labour for 1150 cft @ Tk. 5.50 per cft = Tk. 6,325.00
3 loading for
Labour andlocal
unloading
carriage, levelling & compacting etc.
(a) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
4 Sundries, T & P etc. LS = Tk. 121.93
Sub - Total = Tk. 8,250.51
Profit 10.00% = Tk. 825.05
Analysis of PWD SoR 2018 for Civil Works 103
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in 0.50% = 1,005.00 cft
saturated condition
1. Royalty for dredge material 1,005.00 cft @ Tk. 800.00 per % 0 cft = Tk. 804.00
2 Carriage of earth including cost of labour for 1150 cft @ Tk. 3.85 per cft = Tk. 4,427.50
loading and unloading
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
4 Sundries, T & P etc. LS = Tk. 79.67
Sub - Total = Tk. 5,391.17
Profit 10.00% = Tk. 539.12
Overhead 3.50% = Tk. 188.69
Total = Tk. 6,118.98
Add VAT with adjustment factor 1.06383 6.00% = Tk. 390.57
Grand Total = Tk. 6,509.55
Rate per cft = Tk. 6.51
Rate per cum = Tk. 229.90
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
wastage, no shrinkage as it is coming & placing in 0.50% = 1,005.00 cft
saturated condition
1. Royalty for Earth 1,005.00 cft @ Tk. 1,715.00 per % 0 cft = Tk. 1,723.58
2 Carriage of earth including cost of labour for 1150 cft @ Tk. 4.50 per cft = Tk. 5,175.00
loading and unloading
3 Labour for local carriage, levelling & compacting etc. complete:
(a) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
4 Sundries, T & P etc. LS = Tk. 104.68
Sub - Total = Tk. 7,083.26
Profit 10.00% = Tk. 708.33
Overhead 3.50% = Tk. 247.91
Total = Tk. 8,039.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 513.16
Grand Total = Tk. 8,552.66
Rate per cft = Tk. 8.55
Rate per cum = Tk. 301.94
Considering 1000 cft of work in/c dressing and local carriage 1000 cft
Analysis of PWD SoR 2018 for Civil Works 104
2.18.2 For each additional lift of one foot beyond 5'-0" and upto 10'-0"
Considering 1000 cft of excavation work
(i) Extra labour 1/2 no @ Tk. 320.00 per day = Tk. 160.00
Profit 10.00% = Tk. 16.00
Overhead 3.50% = Tk. 5.60
Total = Tk. 181.60
Add VAT with adjustment factor 1.06383 6.00% = Tk. 11.59
Grand Total = Tk. 193.19
Rate per cft = Tk. 0.19
Rate per cum = Tk. 6.71
2.18.3 For each additional lift of one foot beyond 10'-0" and upto 15'-0"
Considering 1000 cft of excavation work
(i) Extra labour 3/4 no @ Tk. 320.00 per day = Tk. 240.00
Profit 10.00% = Tk. 24.00
Overhead 3.50% = Tk. 8.40
Total = Tk. 272.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 17.39
Grand Total = Tk. 289.79
Rate per cft = Tk. 0.29
Rate per cum = Tk. 10.24
2.18.4 For each additional lift of one foot beyond 15'-0" and upto 20'-0"
Considering 1000 cft of excavation work
(i) Extra labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Profit 10.00% = Tk. 32.00
Overhead 3.50% = Tk. 11.20
Total = Tk. 363.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.18
Grand Total = Tk. 386.38
Rate per cft = Tk. 0.39
Rate per cum = Tk. 13.77
2.19.2 Bailing-out water using 1 cusec pump electricity operated pump set
Considering 1 day operation = 8 Hrs.
(i) Hire charge of pump including suction
and delivery pipe, connection, switch 1 day @ Tk. 800.00 per day = Tk. 800.00
(ii) Electricity, lubricant, spares, maintenance etc. LS = Tk. 300.00
(iii) Pump operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(iv) Helper 1 no @ Tk. 390.00 per day = Tk. 390.00
(v) Skilled labour for maintaining drainage 1 no @ Tk. 390.00 per day = Tk. 390.00
(vi) Provide drainage facilities and connection to discharge facilities LS = Tk. 250.00
(viii) Tools and plant, sundries etc. LS = Tk. 150.00
Sub - Total = Tk. 2,880.00
Profit 10.00% = Tk. 288.00
Overhead 3.50% = Tk. 100.80
Total = Tk. 3,268.80
Add VAT with adjustment factor 1.06383 6.00% = Tk. 196.13
Grand Total = Tk. 3,464.93
Rate per hour = Tk. 433.12
DIVISION 04 : BRICKWORKS, PATENT STONEF IN FLOOR AND FANCY SCREEN BLOCK WORKS
Item No.- 04.1
Brick work with first class bricks in foundation (1:6)
Considering 100 cft work
1. Bricks 1100 nos @ Tk. 8,700.00 per % 0 nos = Tk. 9,570.00
2. Sand (F.M 1.2) in/c wastage 36 cft @ Tk. 1,400.00 per % cft = Tk. 504.00
3. Cement 4 bags @ Tk. 395.00 per bag = Tk. 1,580.00
4. Head mason 0.10 nos @ Tk. 600.00 per day = Tk. 60.00
5. Mason 1 no @ Tk. 500.00 per day = Tk. 500.00
6. Skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
7. Ordinary labour 1.5 nos @ Tk. 320.00 per day = Tk. 480.00
8. Labour for soaking &
cleaning bricks 2 nos @ Tk. 320.00 per day = Tk. 640.00
9. Labour for 7 days curing
@ 1/8 labour per day: 0.875 no @ Tk. 320.00 per day = Tk. 280.00
10. Local carriage, sundries, T & P etc. LS = Tk. 160.00
Sub - Total = Tk. 14,164.00
Profit 10.00% = Tk. 1,416.40
Overhead 3.50% = Tk. 495.74
Total = Tk. 16,076.14
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,026.14
Grand Total = Tk. 17,102.28
Rate per cft = Tk. 171.02
Rate per cum = Tk. 6,039.57
2. Sand (F.M. 1.2) in/c wastage 14 cft @ Tk. 1,400.00 per % cft = Tk. 196.00
3. Cement in/c for pointing 2.75 bags @ Tk. 395.00 per bag = Tk. 1,086.25
4. Head mason 1 no @ Tk. 600.00 per day = Tk. 600.00
5. Mason 2 nos @ Tk. 500.00 per day = Tk. 1,000.00
6. Skilled labour 1.5 nos @ Tk. 390.00 per day = Tk. 585.00
7. Ordinary labour 1.5 nos @ Tk. 320.00 per day = Tk. 480.00
8. Labour for 7 days curing
@ 1/8 labour per day 0.875 no @ Tk. 320.00 per day = Tk. 280.00
9. Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
10. Washing of sand, local carriage, storage & sundries etc. LS = Tk. 320.00
Sub - Total = Tk. 19,556.25
Profit 10.00% = Tk. 1,955.63
Overhead 3.50% = Tk. 684.47
Total = Tk. 22,196.35
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,416.79
Grand Total = Tk. 23,613.14
(i) Ground floor Rate per sft = Tk. 236.13
Rate per sqm = Tk. 2,541.70
04.21.1 Add for each addl. floor up to 5th floor (@ 0.75 No. lab per % sft) per sqm = Tk. 31.00
04.21.2 Add for each addl. floor for 6th floor to 9th floor (@ 1 No. lab per % sft) per sqm = Tk. 42.00
04.21.3 Add for each addl. floor 10th floor and above (@ 1.25 nos lab per % sft) per sqm = Tk. 52.00
'@ 1/8 labour per day. 0.875 no @ Tk. 320.00 per day = Tk. 280.00
7. Local carriage & storage, sundries etc. LS = Tk. 160.00
Sub - Total = Tk. 17,813.50
Profit 10.00% = Tk. 1,781.35
Overhead 3.50% = Tk. 623.47
Total = Tk. 20,218.32
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,290.53
Grand Total = Tk. 21,508.85
Rate per sft = Tk. 215.09
Rate per sqm = Tk. 2,315.23
A. Materials
1. White cement 140 kg @ Tk. 26.00 per kg = Tk. 3,640.00
2. Pakistani onix mosaic chips 140 kg @ Tk. 20.00 per kg = Tk. 2,800.00
3. Minar stone 1/3 no @ Tk. 420.00 each = Tk. 140.00
4. 5 x 20 mm glass strip 120 rft @ Tk. 10.00 per rft = Tk. 1,200.00
5. Cost of patent stone excluding cost of cement for
neat finish and 1/4 No. mason 100 sft @ Tk. 2,543.41 per % sft = Tk. 2,543.41
B. Labour:
Same as 05.1.1 100 sft @ Tk. 4,232.50 per % sft = Tk. 4,232.50
Sub - Total = Tk. 14,555.91
Profit 10.00% = Tk. 1,455.59
Overhead 3.50% = Tk. 509.46
Total = Tk. 16,520.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,054.53
Grand Total = Tk. 17,575.49
(i) Ground floor Rate per sft = Tk. 175.75
Rate per sqm = Tk. 1,891.77
(b) For cutting mosaic mosaic wall surface with mumic stone:
1. Skilled labour 10 nos @ Tk. 390.00 per day = Tk. 3,900.00
2. Pumic stone 2.5 nos @ Tk. 175.00 each = Tk. 437.50
(c) For spreading oxalic acid and washing:
1. Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Sub-total (b) = Tk. 5,870.00
Cost for laying floor tiles: Same as item No. 6.1.1 per % sft = Tk. 5,523.60
(i) For ground floor
06.2.1 GP (mirror polished) 400 mm x 400 mm floor tiles country made
Considering 100 sft work
1. Cost of tiles 100 sft @ Tk. 80.00 per sft = Tk. 8,000.00
Add wastage 5% = Tk. 400.00
Analysis of PWD SoR 2018 for Civil Works 148
2. Laying cost 100 sft @ Tk. 5,441.10 per % sft = Tk. 5,441.10
Sub - Total = Tk. 13,841.10
Profit 10.00% = Tk. 1,384.11
Overhead 3.50% = Tk. 484.44
Total Tk. 15,709.65
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,002.74
Grand Total = Tk. 16,712.39
Rate per sft = Tk. 167.12
Rate per sqm = Tk. 1,798.88
Item No.-06.5.1
Supplying, fitting and fixing matt or rustic floor tiles on cement mortar base (1:4):
Matt or rustic floor tiles of size 600 mm x 600 mm and minimum thickness 9.8 mm foreign
Considering 100 sft work
1. Cost of tiles 100 sft @ Tk. 170.00 per sft = Tk. 17,000.00
Add wastage 5% = Tk. 850.00
2. Laying cost 100 sft @ Tk. 5,441.10 per % sft = Tk. 5,441.10
Sub - Total = Tk. 23,291.10
Profit 10.00% = Tk. 2,329.11
Overhead 3.50% = Tk. 815.19
Total = Tk. 26,435.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,687.37
Grand Total = Tk. 28,122.77
Rate per sft = Tk. 281.23
Rate per sqm = Tk. 3,027.16
B. Labour cost:
1. Head mason 2.00 nos @ Tk. 600.00 each = Tk. 1,200.00
2. Mason 2.00 nos @ Tk. 500.00 each = Tk. 1,000.00
3. Skilled labour 3.00 nos @ Tk. 390.00 each = Tk. 1,170.00
4. Ordinary labour 3.00 nos @ Tk. 320.00 each = Tk. 960.00
5. Local carriage, sundries, T & P & washing of sand etc. LS = Tk. 320.00
Total = Tk. 5,580.67
Laying cost per % sft = Tk. 5,580.67
(i) Ground floor
(a) Wall tiles less than, equal or equivalent to 250 mm x 330 mm in sizes
Considering 100 sft of work
1. Cost of tiles 100 sft @ Tk. 40.00 per sft = Tk. 4,000.00
Add wastage 5% = Tk. 200.00
2. Laying cost 100 sft @ Tk. 5,580.67 per % sft = Tk. 5,580.67
Sub - Total = Tk. 9,780.67
Profit 10.00% = Tk. 978.07
Overhead 3.50% = Tk. 342.32
Total = Tk. 11,101.06
Add VAT with adjustment factor 1.06383 6.00% = Tk. 708.58
Grand Total = Tk. 11,809.64
Rate per sft = Tk. 118.10
Rate per sqm = Tk. 1,271.23
b) Labour cost:
i) Head mason 0.75 nos @ Tk. 600.00 each = Tk. 450.00
ii) Mason 1.50 nos @ Tk. 500.00 each = Tk. 750.00
iii) Skilled labour 1.50 nos @ Tk. 390.00 each = Tk. 585.00
iv) Ordinary labour 1.50 nos @ Tk. 320.00 each = Tk. 480.00
v) Local carriage, sundries, T & P & washing of sand etc. LS = Tk. 100.00
Sub-total (A) = Tk. 3,496.00
Laying cost per % sft = Tk. 3,496.00
c) Cost of tiles
GP Glazed homogeneous floor tiles 100.00 sft @ Tk. 70.00 per sft = Tk. 7,000.00
Add: Wastage 5% = Tk. 350.00
Sub-total (B) = Tk. 7,350.00
Sub Total = Tk. 14,342.00
Profit (A+B)
10.00% = Tk. 1,434.20
Overhead 3.50% = Tk. 501.97
Total = Tk. 16,278.17
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,039.03
Grand Total = Tk. 17,317.20
Rate per sft = Tk. 173.17
Rate per sqm = Tk. 1,864.00
2. Laying cost 100 sft @ Tk. 3,496.00 per % sft = Tk. 3,496.00
Sub - Total = Tk. 11,896.00
Profit 10.00% = Tk. 1,189.60
Overhead 3.50% = Tk. 416.36
Total = Tk. 13,501.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 861.83
Grand Total = Tk. 14,363.79
Rate per sft = Tk. 143.64
Rate per sqm = Tk. 1,546.14
Item No.-06.16.1
20 to 25 mm thick machine made cement pavment tiles
Considering 100 sft work
1. Cost of tiles 100 sft @ Tk. 130.00 per sft = Tk. 13,000.00
Add wastage 5% = Tk. 650.00
2. Laying cost 100 sft @ Tk. 5,441.10 per % sft = Tk. 5,441.10
Sub - Total = Tk. 19,091.10
Profit 10.00% = Tk. 1,909.11
Overhead 3.50% = Tk. 668.19
Total = Tk. 21,668.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,383.09
Analysis of PWD SoR 2018 for Civil Works 159
2. Laying cost 100 sft @ Tk. 5,940.67 per % sft = Tk. 5,940.67
Sub - Total = Tk. 22,320.67
Profit 10.00% = Tk. 2,232.07
Overhead 3.50% = Tk. 781.22
Total = Tk. 25,333.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,617.06
Grand Total = Tk. 26,951.02
Rate per sft = Tk. 269.51
Rate per sqm = Tk. 2,901.01
07.1.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,628.00
(ii) Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. 17,627.83
Profit 10.00% = Tk. 1,762.78
Overhead 3.50% = Tk. 616.97
Total = Tk. 20,007.58
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,277.08
Grand Total = Tk. 21,284.66
Rate per cft = Tk. 212.85
Rate per cum = Tk. 7,516.80
07.1.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,628.00
(ii) Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total = Tk. 18,127.75
Profit 10.00% = Tk. 1,812.78
Overhead 3.50% = Tk. 634.47
Total = Tk. 20,575.00
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,313.30
Grand Total = Tk. 21,888.30
Rate per cft = Tk. 218.88
Rate per cum = Tk. 7,729.75
07.1.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,628.00
(ii) Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day) = Tk. 1,199.80
(From Secondary Input : Item A-2) Sub - Total = Tk. 17,827.80
Profit 10.00% = Tk. 1,782.78
Overhead 3.50% = Tk. 623.97
Total = Tk. 20,234.55
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,291.57
Grand Total = Tk. 21,526.12
Rate per cft = Tk. 215.26
Rate per cum = Tk. 7,601.91
07.1.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-3) = Tk. 16,628.00
(ii) Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67
(From Secondary Input : Item A-4) Sub - Total = Tk. 18,627.67
Profit 10.00% = Tk. 1,862.77
Overhead 3.50% = Tk. 651.97
Total = Tk. 21,142.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,349.52
Grand Total = Tk. 22,491.93
Analysis of PWD SoR 2018 for Civil Works 171
07.2.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. 26,712.50
(ii) Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. 27,712.33
Profit 10.00% = Tk. 2,771.23
Overhead 3.50% = Tk. 969.93
Total = Tk. 31,453.49
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,007.67
Grand Total = Tk. 33,461.16
Rate per cft = Tk. 334.61
Rate per cum = Tk. 11,816.75
07.2.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. 26,712.50
(ii) Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75
(From Secondary Input : Item A-2) Sub - Total = Tk. 28,212.25
Profit 10.00% = Tk. 2,821.23
Overhead 3.50% = Tk. 987.43
Total = Tk. 32,020.91
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,043.89
Grand Total = Tk. 34,064.80
Rate per cft = Tk. 340.65
Rate per cum = Tk. 12,030.05
07.2.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie beam, lintels, stair case slab and steps etc.
upto ground Floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. 26,712.50
(ii) Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day) = Tk. 1,199.80
(From Secondary Input : Item A-1) Sub - Total = Tk. 27,912.30
Profit 10.00% = Tk. 2,791.23
Overhead 3.50% = Tk. 976.93
Total = Tk. 31,680.46
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,022.16
Grand Total = Tk. 33,702.62
Rate per cft = Tk. 337.03
Rate per cum = Tk. 11,902.21
07.2.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-4) = Tk. 26,712.50
(ii) Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67
(From Secondary Input : Item A-3) Sub - Total = Tk. 28,712.17
Profit 10.00% = Tk. 2,871.22
Overhead 3.50% = Tk. 1,004.93
Analysis of PWD SoR 2018 for Civil Works 172
07.3.1 Cost of concrete for individual and combined footings, pile cap, raft/mat floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. 27,502.50
(ii) Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total = Tk. 28,502.33
Profit 10.00% = Tk. 2,850.23
Overhead 3.50% = Tk. 997.58
Total = Tk. 32,350.14
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,064.90
Grand Total = Tk. 34,415.04
Rate per cft = Tk. 344.15
Rate per cum = Tk. 12,153.66
07.3.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. 27,502.50
(ii) Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total = Tk. 29,002.25
Profit 10.00% = Tk. 2,900.23
Overhead 3.50% = Tk. 1,015.08
Total = Tk. 32,917.56
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,101.12
Grand Total = Tk. 35,018.68
Rate per cft = Tk. 350.19
Rate per cum = Tk. 12,366.96
07.3.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. 27,502.50
(ii) Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day) = Tk. 1,199.80
(From Secondary Input : Item A-2 Sub - Total = Tk. 28,702.30
Profit 10.00% = Tk. 2,870.23
Overhead 3.50% = Tk. 1,004.58
Total = Tk. 32,577.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,079.39
Grand Total = Tk. 34,656.50
Rate per cft = Tk. 346.57
Rate per cum = Tk. 12,239.12
07.3.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-5) = Tk. 27,502.50
(ii) Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67
Analysis of PWD SoR 2018 for Civil Works 173
07.4.1 Cost of concrete for individual and Combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. 28,198.75
(ii) Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total Tk. 29,198.58
Profit 10.00% = Tk. 2,919.86
Overhead 3.50% = Tk. 1,021.95
Total = Tk. 33,140.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,115.34
Grand Total = Tk. 35,255.73
Rate per cft = Tk. 352.56
Rate per cum = Tk. 12,450.66
07.4.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. 28,198.75
(ii) Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75
(From Secondary Input : Item A-3) Sub - Total Tk. 29,698.50
Profit 10.00% = Tk. 2,969.85
Overhead 3.50% = Tk. 1,039.45
Total = Tk. 33,707.80
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,151.56
Grand Total = Tk. 35,859.36
Rate per cft = Tk. 358.59
Rate per cum = Tk. 12,663.61
07.4.3 Cost of concrete for floor / roof slab, tee beams, ell beams and rectangular beams, tie Beam, lintels, stair case slab and steps etc.
upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. 28,198.75
(ii) Laying/placing concrete (@ 1000 cft concreting using 1 mixer machine in one day) = Tk. 1,199.80
(From Secondary Input : Item A-2) Sub - Total Tk. 29,398.55
Profit 10.00% = Tk. 2,939.86
Overhead 3.50% = Tk. 1,028.95
Total = Tk. 33,367.36
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,129.83
Grand Total = Tk. 35,497.19
Rate per cft = Tk. 354.97
Rate per cum = Tk. 12,535.77
07.4.4 Cost of concrete for cornice, railing, drop walls, louver, fins, sunshade, false ceiling, waffle and ribbed floor slab etc. up to ground
floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-6) = Tk. 28,198.75
(ii) Laying/placing concrete (@ 600 cft concreting using 1 mixer machine in one day) = Tk. 1,999.67
(From Secondary Input : Item A-4) Sub - Total Tk. 30,198.42
Profit 10.00% = Tk. 3,019.84
Overhead 3.50% = Tk. 1,056.94
Total = Tk. 34,275.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,187.78
Grand Total = Tk. 36,462.98
Rate per cft = Tk. 364.63
Rate per cum = Tk. 12,876.91
07.5.1 Cost of concrete for individual and combined footings, pile cap, raft/mat Floor slab, foundation beam up to plinth level
Considering 100 cft
(i) Materials (From Secondary Input : Item B-7) = Tk. 29,300.00
(ii) Laying/placing concrete (@ 1200 cft concreting using 1 mixer machine in one day) = Tk. 999.83
(From Secondary Input : Item A-1) Sub - Total Tk. 30,299.83
Profit 10.00% = Tk. 3,029.98
Overhead 3.50% = Tk. 1,060.49
Total = Tk. 34,390.30
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,195.13
Grand Total = Tk. 36,585.43
Rate per cft = Tk. 365.85
Rate per cum = Tk. 12,919.99
07.5.2 Cost of concrete for padestals, column, column capitals, lift walls and walls upto ground floor
Considering 100 cft
(i) Materials (From Secondary Input : Item B-7) = Tk. 29,300.00
(ii) Laying/placing concrete (@ 800 cft concreting using 1 mixer machine in one day) = Tk. 1,499.75
(From Secondary Input : Item A-2) Sub - Total Tk. 30,799.75
Profit 10.00% = Tk. 3,079.98
Overhead 3.50% = Tk. 1,077.99
Total = Tk. 34,957.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,231.34
Grand Total = Tk. 37,189.06
Rate per cft = Tk. 371.89
Rate per cum = Tk. 13,133.30
07.9.2 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 359.09
In raft/mat/floor slab up to plinth level Profit 10.00% = Tk. 35.91
(From Secondary Input : Item C-11) Overhead 3.50% = Tk. 12.57
Total = Tk. 407.57
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.02
Grand Total = Tk. 433.59
07.9.3 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 314.09
Foundation Beam Profit 10.00% = Tk. 31.41
(From Secondary Input : Item C-12) Overhead 3.50% = Tk. 10.99
Total = Tk. 356.49
Add VAT with adjustment factor 1.06383 6.00% = Tk. 22.75
Grand Total = Tk. 379.24
07.9.4 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 337.13
Padestals, column, column capitals, lift wall and walls upto Ground Floor Profit 10.00% = Tk. 33.71
(From Secondary Input : Item C-13) Overhead 3.50% = Tk. 11.80
Total = Tk. 382.64
Add VAT with adjustment factor 1.06383 6.00% = Tk. 24.42
Grand Total = Tk. 407.06
07.9.5 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 346.28
Tie beam and lintels : Ground Floor Profit 10.00% = Tk. 34.63
(From Secondary Input : Item C-14) Overhead 3.50% = Tk. 12.12
Total = Tk. 393.03
Add VAT with adjustment factor 1.06383 6.00% = Tk. 25.09
Grand Total = Tk. 418.12
07.9.6 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 376.42
Tee beams, Ell beams and Rectangular Profit 10.00% = Tk. 37.64
beamsSecondary
(From etc upto Ground FloorC-15)
Input : Item Overhead 3.50% = Tk. 13.17
Total = Tk. 427.23
Add VAT with adjustment factor 1.06383 6.00% = Tk. 27.27
Grand Total = Tk. 454.50
07.9.7 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 440.57
Floor and roof slab upto Ground Floor Profit 10.00% = Tk. 44.06
(From Secondary Input : Item C-16) Overhead 3.50% = Tk. 15.42
Total = Tk. 500.05
Add VAT with adjustment factor 1.06383 6.00% = Tk. 31.92
Grand Total = Tk. 531.97
07.9.8 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 320.34
Cornice, railing, drop walls, louver, fins etc. : Ground Floor Profit 10.00% = Tk. 32.03
(From Secondary Input : Item C-17) Overhead 3.50% = Tk. 11.21
Total = Tk. 363.58
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.21
Grand Total = Tk. 386.79
07.9.9 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 362.21
Sunshade, false ceiling : Ground Floor Profit 10.00% = Tk. 36.22
(From Secondary Input : Item C-18) Overhead 3.50% = Tk. 12.68
Total = Tk. 411.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.24
Grand Total = Tk. 437.35
07.9.11 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 477.97
Waffle or Ribbed floor upto Ground Floor Profit 10.00% = Tk. 47.80
(From Secondary Input : Item C-20) Overhead 3.50% = Tk. 16.73
Total = Tk. 542.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 34.63
Grand Total = Tk. 577.13
07.9.12.1 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 1,515.18
Arch, domes, vaults upto 8m span(for single use) Profit 10.00% = Tk. 151.52
(From Secondary Input : Item C-21(i)) Overhead 3.50% = Tk. 53.03
Total = Tk. 1,719.73
Add VAT with adjustment factor 1.06383 6.00% = Tk. 109.77
Grand Total = Tk. 1,829.50
07.9.12.2 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 1,060.63
Arch, domes, vaults upto 8m span(for 2-times use) Profit 10.00% = Tk. 106.06
(From Secondary Input : Item C-21(ii)) Overhead 3.50% = Tk. 37.12
Total = Tk. 1,203.81
Add VAT with adjustment factor 1.06383 6.00% = Tk. 76.84
Grand Total = Tk. 1,280.65
07.9.12.3 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 757.59
Arch, domes, vaults upto 8m span(for 3-times use) Profit 10.00% = Tk. 75.76
(From Secondary Input : Item C-21(iii)) Overhead 3.50% = Tk. 26.52
Total = Tk. 859.87
Add VAT with adjustment factor 1.06383 6.00% = Tk. 54.89
Grand Total = Tk. 914.76
07.9.12.4 Formwork/shuttering, prop and necessary supports etc. (steel) per sqm = Tk. 530.31
Arch, domes, vaults upto 8m span(for more than 3-times use) Profit 10.00% = Tk. 53.03
(From Secondary Input : Item C-21(iv)) Overhead 3.50% = Tk. 18.56
Total = Tk. 601.90
Add VAT with adjustment factor 1.06383 6.00% = Tk. 38.42
Grand Total = Tk. 640.32
7.14
Extra cost for making ' fair-faced’ surface of the reinforced cement concrete
Considering 1.0 sqm fair-face surface area of concrete
07.15.2 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 315.49
Foundation Beam Profit 10.00% = Tk. 31.55
(From Secondary Input : Item C-2) Overhead 3.50% = Tk. 11.04
Total = Tk. 358.08
Add VAT with adjustment factor 1.06383 6.00% = Tk. 22.86
Grand Total = Tk. 380.94
07.15.3 Formwork / shuttering, prop and necessary supports etc. (WOODEN) per sqm = Tk. 354.89
Padestals, column, column capitals, lift wall Profit 10.00% = Tk. 35.49
and walls
(From Secondary Input : Item C-3) Overhead 3.50% = Tk. 12.42
Total = Tk. 402.80
Add VAT with adjustment factor 1.06383 6.00% = Tk. 25.71
Grand Total = Tk. 428.51
07.15.4 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 344.88
Tie beam and lintels Profit 10.00% = Tk. 34.49
(From Secondary Input : Item C-4) Overhead 3.50% = Tk. 12.07
Total = Tk. 391.44
Add VAT with adjustment factor 1.06383 6.00% = Tk. 24.99
Grand Total = Tk. 416.43
07.15.5 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 342.19
Tee beams, Ell beams and Rectangular Profit 10.00% = Tk. 34.22
beamsSecondary
(From etc upto Ground FloorC-5)
Input : Item Overhead 3.50% = Tk. 11.98
Total = Tk. 388.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 24.79
Grand Total = Tk. 413.18
07.15.6 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 377.06
Floor and roof slab Profit 10.00% = Tk. 37.71
(From Secondary Input : Item C-6) Overhead 3.50% = Tk. 13.20
Total = Tk. 427.97
Add VAT with adjustment factor 1.06383 6.00% = Tk. 27.32
Grand Total = Tk. 455.29
07.15.7 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 306.34
Cornice, railing, drop walls, louver, fins etc. Profit 10.00% = Tk. 30.63
(From Secondary Input : Item C-7) Overhead 3.50% = Tk. 10.72
Total = Tk. 347.69
Add VAT with adjustment factor 1.06383 6.00% = Tk. 22.19
Grand Total = Tk. 369.88
07.15.8 Formwork / shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 329.92
Sunshade, false ceiling Profit 10.00% = Tk. 32.99
(From Secondary Input : Item C-8) Overhead 3.50% = Tk. 11.55
Total = Tk. 374.46
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.90
Grand Total = Tk. 398.36
07.15.9 Formwork/shuttering, prop and necessary supports etc. (wooden) per sqm = Tk. 320.44
Stair case slab and steps Profit 10.00% = Tk. 32.04
(From Secondary Input : Item C-9) Overhead 3.50% = Tk. 11.22
Total = Tk. 363.70
Add VAT with adjustment factor 1.06383 6.00% = Tk. 23.21
Grand Total = Tk. 386.91
j) Hire Charge of mud silo 1 no @ Tk. 1,000.00 per day = Tk. 1,000.00
k) Hire Charge of dump truck 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00
l) Hire Charge of Water bowser 1 no @ Tk. 5,000.00 per day = Tk. 5,000.00
3) Fuel Consumption
a) Fuel Consumption for rig set LS = Tk. 10,000.00
b) Fuel Consumption for crane, air compressor, excavator LS = Tk. 20,000.00
c) Fuel Consumption for generator, Dump LS = Tk. 20,000.00
truck, wheel loader, wheel bowser
4) Bentonite 39 kg/cum @ Tk. 20.00 per kg = Tk. 19,843.20
Sub - Total = Tk. 252,503.20
Profit 10.00% = Tk. 25,250.32
Overhead 3.50% = Tk. 8,837.61
Total = Tk. 286,591.13
Add VAT with adjustment factor 1.06383 6.00% = Tk. 18,293.05
Grand Total = Tk. 304,884.18
Rate per meter = Tk. 3,387.60
3) Fuel Consumption
a) Fuel Consumption for rig set LS = Tk. 10,000.00
b) Fuel Consumption for crane, air compressor, excavator LS = Tk. 20,000.00
c) Fuel Consumption for generator, Dump LS = Tk. 20,000.00
truck, wheel loader, wheel bowser
4) Bentonite 39 kg/cum @ Tk. 20.00 per kg = Tk. 19,843.20
Sub - Total = Tk. 252,503.20
Profit 10.00% = Tk. 25,250.32
Overhead 3.50% = Tk. 8,837.61
Total = Tk. 286,591.13
Add VAT with adjustment factor 1.06383 6.00% = Tk. 18,293.05
Grand Total = Tk. 304,884.18
Rate per meter = Tk. 4,065.12
3) Fuel Consumption
a) Fuel Consumption for rig set LS = Tk. 10,000.00
a) Fuel Consumption for crane, air compressor, excavator LS = Tk. 20,000.00
c) Fuel Consumption for generator, Dump truck, wheel loader, wheel bowser LS = Tk. 20,000.00
1. Hire charge of 3HP mud pump 1/4 day @ Tk. 600.00 per day = Tk. 150.00
2. Hire charge of MS steel tank 1 trip @ Tk. 350.00 per trip = Tk. 350.00
3. (6'-6"charge
Hire x 10'-0"ofxtruck
4'-0") 1 trip @ Tk. 1,700.00 per trip = Tk. 1,700.00
4. Pump operator 1/4 no @ Tk. 600.00 per nos = Tk. 150.00
5. Ordinary labour 1/2 no @ Tk. 320.00 per nos = Tk. 160.00
6. Sundries and incidental cost LS = Tk. 100.00
Total (A+B) = Tk. 2,610.00
Profit 10.00% = Tk. 261.00
Overhead 3.50% = Tk. 91.35
Total = Tk. 2,962.35
Add VAT with adjustment factor 1.06383 6.00% = Tk. 189.09
Grand Total = Tk. 3,151.44
Rate per cft = Tk. 15.76
Rate per cum = Tk. 556.56
Tk. 570 .00 meter of weld Say, Tk. 14.49 per inch of two face
Item No.- 09.7
Labour for breaking head of cast-in-situ bored pile/pre-cast driven pile
Considering 1 cum of work
(a) Skilled labour 7 nos @ Tk. 390.00 each = Tk. 2,730.00
(b) Ordinary labour 2 nos @ Tk. 320.00 each = Tk. 640.00
(c) Repairing of pile head in/c materials LS = Tk. 250.00
(d) Straightening and bending of pile bars,
tools & plant, sundries etc. LS = Tk. 250.00
Sub - Total = Tk. 3,870.00
Profit 10.00% = Tk. 387.00
Overhead 3.50% = Tk. 135.45
Total = Tk. 4,392.45
Add VAT with adjustment factor 1.06383 6.00% = Tk. 280.37
Grand Total = Tk. 4,672.82
(d) Platform making: crib wall per ton Tk. 275.00 Tk. 13,750.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 6 nos @ Tk. 390.00 each = Tk. 2,340.00
(iii) Ordinary labour 10 nos @ Tk. 320.00 each = Tk. 3,200.00
(c) Hire charge of load testing equipment (joist,
jacks and other necessary devices in/c 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
charges, hydraulic fluid etc.)
(d) Cost of empty gunny bags
(taking 2 times use) 911.45 bags @ Tk. 5.00 per bag = Tk. 4,557.25
(e) Cost of local sand as loading
materials (taking 2 times use) 911.45 cft @ Tk. 450.00 per % cft = Tk. 4,101.53
(f) Labour for bag filling,
stitching, loading & unloading: 1822.90 bags @ Tk. 10.00 per bag = Tk. 18,229.00
(h) Preparation of test result in standard form in
triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charge LS = Tk. 960.00
Sub - Total = Tk. 60,737.78
Profit 10.00% = Tk. 6,073.78
Overhead 3.50% = Tk. 2,125.82
Total = Tk. 68,937.38
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,400.26
Grand Total = Tk. 73,337.64
09.8.4
For 100 ton load for 1 No. of test 100 116 Mton (working volume)
sand = 3645.7 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 27,500.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 6 nos @ Tk. 390.00 each = Tk. 2,340.00
(iii) Ordinary labour 12 nos @ Tk. 320.00 each = Tk. 3,840.00
(c) Hire charge of load testing equipment (joist,
jacks and other necessary devices in/c 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
caliberation charges, hydraulic fluid etc.)
(d) Cost of empty gunny bags
Analysis of PWD SoR 2018 for Civil Works 193
(taking 2 times use) 1822.85 bags @ Tk. 5.00 per bag = Tk. 9,114.25
(e) Cost of local sand as loading
materials (taking 2 times use) 1822.85 cft @ Tk. 450.00 per % cft = Tk. 8,202.83
(f) Labour for bag filling,
stitching, loading & unloading: 3645.7 bags @ Tk. 10.00 per bag = Tk. 36,457.00
(h) Preparation of result in
standard form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 960.00
Sub - Total = Tk. 102,014.08
Profit 10.00% = Tk. 10,201.41
Overhead 3.50% = Tk. 3,570.49
Total = Tk. 115,785.98
Add VAT with adjustment factor 1.06383 6.00% = Tk. 7,390.60
Grand Total = Tk. 123,176.58
09.8.5
For 150 ton load for 1 No. of test 150 174 Mton (working volume)
sand sand = 5468.57 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 41,250.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 6 nos @ Tk. 390.00 each = Tk. 2,340.00
(iii) Ordinary labour 12 nos @ Tk. 320.00 each = Tk. 3,840.00
(c) Hire charge of load testing equipment (joist,
jacks and other necessary devices in/c 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
caliberation charges, hydraulic fluid etc.)
(d) Cost of empty gunny bags
(taking 2 times use) 2734.29 bags @ Tk. 5.00 per bag = Tk. 13,671.45
(e) Cost of local sand as loading
materials (taking 2times use) 2734.29 cft @ Tk. 450.00 per % cft = Tk. 12,304.31
(f) Labour for bag filling,
stitching, loading & unloading: 5468.57 bags @ Tk. 10.00 per bag = Tk. 54,685.70
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 1,600.00
Sub - Total = Tk. 143,291.46
Profit 10.00% = Tk. 14,329.15
Overhead 3.50% = Tk. 5,015.20
Total = Tk. 162,635.81
Add VAT with adjustment factor 1.06383 6.00% = Tk. 10,381.01
Grand Total = Tk. 173,016.82
09.8.6
For 200 tone load for 1 No. test 200 232 Mton (working volume)
sand = 7291.43 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 55,000.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 8 nos @ Tk. 390.00 each = Tk. 3,120.00
(iii) Ordinary labour 16 nos @ Tk. 320.00 each = Tk. 5,120.00
(c) Hire charge of load testing equipment (joist,
jacks and other necessary devices in/c 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
caliberation charges, hydraulic fluid etc.)
(d) Cost of empty gunny bags
(taking 2 times use) 3645.715 bags @ Tk. 5.00 per bag = Tk. 18,228.58
Analysis of PWD SoR 2018 for Civil Works 194
09.8.7
For 250 tonne load for 1 No. test 250 290 Mton (working volume)
sand = 9114.29 bags Wt of sand = 35 kg/bag
(d) Platform making: crib wall per ton Tk. 275.00 Tk. 68,750.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 8 nos @ Tk. 390.00 each = Tk. 3,120.00
(iii) Ordinary labour 16 nos @ Tk. 320.00 each = Tk. 5,120.00
(c) Hire charge of load testing equipment (joist,
jacks and other necessary devices in/c 1 test @ Tk. 8,000.00 per test = Tk. 8,000.00
caliberation charges, hydraulic fluid etc.)
(d) Cost of empty gunny bags
(taking 2 times use) 4557.145 bags @ Tk. 5.00 per bag = Tk. 22,785.73
(e) Cost of local sand as loading
materials (taking 2 times use) 4557.145 cft @ Tk. 450.00 per % cft = Tk. 20,507.15
(f) Labour for bag filling,
stitching, loading & unloading: 9114.29 bags @ Tk. 10.00 per bag = Tk. 91,142.90
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 1,600.00
Sub - Total = Tk. 228,625.78
Profit 10.00% = Tk. 22,862.58
Overhead 3.50% = Tk. 8,001.90
Total = Tk. 259,490.26
Add VAT with adjustment factor 1.06383 6.00% = Tk. 16,563.21
Grand Total = Tk. 276,053.47
09.8.8
For 300 tonne load for 1 No. of test 300 348 Mton (working volume)
sand = 10937.14 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 82,500.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 8 nos @ Tk. 390.00 each = Tk. 3,120.00
(iii) Ordinary labour 16 nos @ Tk. 320.00 each = Tk. 5,120.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 8,000.00 per test = Tk. 8,000.00
(d) Cost of empty gunny bags
(taking 2 times use) 5468.57 bags @ Tk. 5.00 per bag = Tk. 27,342.85
(e) Cost of local sand as loading
materials (taking 2 times use) 5468.57 cft @ Tk. 450.00 per % cft = Tk. 24,608.57
(f) Labour for bag filling,
Analysis of PWD SoR 2018 for Civil Works 195
stitching, loading & unloading: 10937.14 bags @ Tk. 10.00 per bag = Tk. 109,371.40
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 1,600.00
Sub - Total = Tk. 269,262.82
Profit 10.00% = Tk. 26,926.28
Overhead 3.50% = Tk. 9,424.20
Total = Tk. 305,613.30
Add VAT with adjustment factor 1.06383 6.00% = Tk. 19,507.24
Grand Total = Tk. 325,120.54
09.8.9
For 350 tonne load for 1 No. of test 350 406 Mton (working volume)
sand = 12760.00 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 96,250.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 8 nos @ Tk. 390.00 each = Tk. 3,120.00
(iii) Ordinary labour 16 nos @ Tk. 320.00 each = Tk. 5,120.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 8,000.00 per test = Tk. 8,000.00
(d) Cost of empty gunny bags
(taking 2 times use) 6380 bags @ Tk. 5.00 per bag = Tk. 31,900.00
(e) Cost of local sand as loading
materials (taking 2 times use) 6380 cft @ Tk. 450.00 per % cft = Tk. 28,710.00
(f) Labour for bag filling,
stitching, loading & unloading: 12760 bags @ Tk. 10.00 per bag = Tk. 127,600.00
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 1,600.00
Sub - Total = Tk. 309,900.00
Profit 10.00% = Tk. 30,990.00
Overhead 3.50% = Tk. 10,846.50
Total = Tk. 351,736.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 22,451.27
Grand Total = Tk. 374,187.77
09.8.10
For 400 tonne load for 1 No. of test 400 464 Mton (working volume)
sand = 14582.86 bags Wt of sand = 35 kg/bag
(b) Platform making: crib wall per ton Tk. 275.00 Tk. 110,000.00
(i) Foreman 2 nos @ Tk. 800.00 each = Tk. 1,600.00
(ii) Skilled labour 8 nos @ Tk. 390.00 each = Tk. 3,120.00
(iii) Ordinary labour 16 nos @ Tk. 320.00 each = Tk. 5,120.00
(c) Hire charge of load testing equipment (joist, jacks
and other necessary devices in/c caliberation
charges, hydraulic fluid etc.) 1 test @ Tk. 8,000.00 per test = Tk. 8,000.00
(d) Cost of empty gunny bags
(taking 2 times use) 7291.43 bags @ Tk. 5.00 per bag = Tk. 36,457.15
(e) Cost of local sand as loading
materials (taking 2 times use) 7291.43 cft @ Tk. 450.00 per % cft = Tk. 32,811.44
(f) Labour for bag filling,
stitching, loading & unloading: 14582.86 bags @ Tk. 10.00 per bag = Tk. 145,828.60
(h) Preparation of result in standard
form in triplicate 1 test @ Tk. 6,000.00 per test = Tk. 6,000.00
(i) Other incidental charges LS = Tk. 1,600.00
Analysis of PWD SoR 2018 for Civil Works 196
12 x 40'-0" x 1'-0"= 480.00 sft @ Tk. 75.00 per sft = Tk. 36,000.00
Total = Tk. 153,848.93
Using 16 times = Tk. 9,615.56
(vi) Labour for fitting & fixing steel shuttering
in position as required 480.00 sft @ Tk. 10.00 per sft = Tk. 4,800.00
(vii) Hessian tap for making
shutter water-proof. 480.00 sft @ Tk. 1.25 per sft = Tk. 600.00
(viii) Curing 480.00 sft @ Tk. 2.67 per sft = Tk. 1,281.60
Total for 440 cft = Tk. 16,297.16
Cost for 100 cft = Tk. 3,703.90
D. Cost of bed preparation:
Area of bed: 1 x 45'-0" x 15'-0"= 675.00 sft
(a) One layer brick flat soling: 675.00 sft @ Tk. 0.32 per sft = Tk. 216.00
(b) 1/2" thick cement finishing with
neat cement finishing 675.00 sft @ Tk. 21.58 per sft = Tk. 14,566.50
Total for 440 cft = Tk. 14,782.50
Cost for 100 cft of work = Tk. 3,359.66
Using 8 times = Tk. 419.96
E. Polythene as separator between pile layers
during casting concrete 675.00 sft @ Tk. 319.44 per % sft = Tk. 2,156.22
Cost for 100 cft of work = Tk. 490.05
Abstract of cost for 100 cft of work
A. Cost of concrete = Tk. 28,198.75
B. Labour, machinery, fuel and lubricant for casting = Tk. 1,199.80
C. Cost of shuttering = Tk. 3,703.90
D. Cost of bed preparation = Tk. 419.96
E. Polythene = Tk. 490.05
Sub - Total = Tk. 34,012.46
Profit 10.00% = Tk. 3,401.25
Overhead 3.50% = Tk. 1,190.44
Total = Tk. 38,604.15
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,464.10
Grand Total = Tk. 41,068.25
Rate per cft = Tk. 410.68
Rate per rft = Tk. 410.68
Rate per rm = Tk. 1,347.44
= 1078.00 sft
@ 3.05 Ib per sft= 3287.90 Ibs @ Tk. 27.44 per Ib = Tk. 90,219.98
(ii) 1.5 x 1.5 x 3/16" angle for frame:
Sides: 2 x 12 x 55'-0"= 1320.00 rft
Supports: 12 x 56 x 1'-4"= 896.00 rft
= 2216.00 rft
Add wastage 5%= 110.80 rft
2326.80 rft
@ 1.79 Ib per rft= 4164.97 Ibs @ Tk. 24.94 per Ib = Tk. 103,874.35
(d) Skilled labour 6 nos @ Tk. 390.00 per day = Tk. 2,340.00
Sub - Total = Tk. 34,860.00
Profit 10.00% = Tk. 3,486.00
Overhead 3.50% = Tk. 1,220.10
Total = Tk. 39,566.10
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,525.50
Grand Total = Tk. 42,091.60
Rate per meter = Tk. 862.89
1 Stone Chips (12mm down Graded) 7.56 cft @ Tk. 165.00 per cft = Tk. 1,247.40
2 Sand (F.M. 2.2) 5.50 cft @ Tk. 45.00 per cft = Tk. 247.50
3 Cement 2.00 bag @ Tk. 415.00 per bag = Tk. 830.00
4 MS Rod (fy = 400 Mpa, Cold-Drawn Wire) 23.60 kg @ Tk. 60.50 per kg = Tk. 1,427.80
5 20 BWG (M.S. Sheet) Pile Shoe 1.00 no @ Tk. 122.24 per no = Tk. 122.24
6 24 No. G.I. wire 0.50 Kg @ Tk. 120.00 per kg = Tk. 60.00
7 Steel Shuttering and Tensioning 29.00 sft @ Tk. 4.11 per sft = Tk. 119.19
(i) Fromwork/Shuttering LS Tk. 350.00
(ii) Mechnical Vibration and Tensioning LS Tk. 200.00
8 Hire charge of mixture machine including oil 0.12 no @ Tk. 2,004.00 per day = Tk. 240.48
& operator
9 Hire charge of Vibrator table including Oil & 0.12 no @ Tk. 996.00 per day = Tk. 119.52
Operator
10 Head Mason 0.08 no @ Tk. 600.00 each = Tk. 48.00
11 Mason 0.17 no @ Tk. 500.00 each = Tk. 85.00
12 Rod binder 0.17 no @ Tk. 500.00 each = Tk. 85.00
13 Skilled Labour 1.00 no @ Tk. 390.00 each = Tk. 390.00
14 Ordinary Labour 0.50 no @ Tk. 320.00 each = Tk. 160.00
15 Ordinary Labour for 7 days curing & 1/8 0.875 no @ Tk. 320.00 each = Tk. 280.00
labour par day
16 Local Carriage, Sundries, T & P, water etc. 1.00 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 6,332.13
Profit 10.00% = Tk. 633.21
Overhead 3.50% = Tk. 221.62
Total = Tk. 7,186.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 458.74
Grand Total = Tk. 7,645.70
Rate per pile = Tk. 305.83
Rate per rft = Tk. 1,003.12
Rate per rm = Tk. 1,003.00
Mobilization & demobilization in/c 1st 12 piles Tk. 20,000.00 per 100km = Tk. 20,000.00
09.25.2.1
Consider 14 nos 12"x12" Pile (40'-0" each)= 170.73 meter driving in 1 day
1. Hire charge of complete rig set per day = Tk. 75,000.00
3 Generator,Fuel, lubricant etc. per day = Tk. 20,000.00
4 Maintenance, insurance etc. LS per day = Tk. 5,000.00
5 Labour
(a) Data logging Engineer 1 no @ Tk. 1,800.00 per day = Tk. 1,800.00
(b) Chief Mechanic 1 no @ Tk. 1,400.00 per day = Tk. 1,400.00
(c) Helper to mechanic 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Foreman 1 no @ Tk. 800.00 per day = Tk. 800.00
(e) Crane Operator 1 no @ Tk. 800.00 per day = Tk. 800.00
(f) Helper to crane operator 1 no @ Tk. 390.00 per day = Tk. 390.00
(g) Machine Operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(h) Helper to machine operator 1 no @ Tk. 390.00 per day = Tk. 390.00
(i) Generator Operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(j) Surveyer to pile layout 1 no @ Tk. 1,200.00 per day = Tk. 1,200.00
(k) Helper to surveyer 1 no @ Tk. 800.00 per day = Tk. 800.00
(l) Skilled Labor 3 nos @ Tk. 390.00 per day = Tk. 1,170.00
(m) Ordinary Labour 6 nos @ Tk. 320.00 per day = Tk. 1,920.00
7 Compilation of driving Report, Pile Capacity 1 copy @ Tk. 2,000.00 each = Tk. 2,000.00
log & submission to PE on signing it.
Sub - Total = Tk. 114,260.00
Profit 10.00% = Tk. 11,426.00
Overhead 3.50% = Tk. 3,999.10
Total = Tk. 129,685.10
Add VAT with adjustment factor 1.06383 6.00% = Tk. 8,277.77
Grand Total = Tk. 137,962.87
Rate per meter = Tk. 808.08
09.25.2.2
Consider 13 nos 14"x14" Pile (40'-0" each)= 158.53 meter driving in 1 day
1. Hire charge of complete rig set per day = Tk. 75,000.00
3 Generator,Fuel, lubricant etc. per day = Tk. 20,000.00
4 Maintenance, insurance etc. LS per day = Tk. 5,000.00
5 Labour
(a) Data logging Engineer 1 no @ Tk. 1,800.00 per day = Tk. 1,800.00
(b) Chief Mechanic 1 no @ Tk. 1,400.00 per day = Tk. 1,400.00
(c) Helper to mechanic 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Foreman 1 no @ Tk. 800.00 per day = Tk. 800.00
(e) Crane Operator 1 no @ Tk. 800.00 per day = Tk. 800.00
(f) Helper to crane operator 1 no @ Tk. 390.00 per day = Tk. 390.00
Analysis of PWD SoR 2018 for Civil Works 216
09.25.2.3
Consider 12 nos 16"x16" Pile (40'-0" each)= 146.34 meter driving in 1 day
1. Hire charge of complete rig set per day = Tk. 75,000.00
3 Generator,Fuel, lubricant etc. per day = Tk. 20,000.00
4 Maintenance, insurance etc. LS per day = Tk. 5,000.00
5 Labour
(a) Data logging Engineer 1 no @ Tk. 1,800.00 per day = Tk. 1,800.00
(b) Chief Mechanic 1 no @ Tk. 1,400.00 per day = Tk. 1,400.00
(c) Helper to mechanic 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Foreman 1 no @ Tk. 800.00 per day = Tk. 800.00
(e) Crane Operator 1 no @ Tk. 800.00 per day = Tk. 800.00
(f) Helper to crane operator 1 no @ Tk. 390.00 per day = Tk. 390.00
(g) Machine Operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(h) Helper to machine operator 1 no @ Tk. 390.00 per day = Tk. 390.00
(i) Generator Operator 1 no @ Tk. 600.00 per day = Tk. 600.00
(j) Surveyer to pile layout 1 no @ Tk. 1,200.00 per day = Tk. 1,200.00
(k) Helper to surveyer 1 no @ Tk. 800.00 per day = Tk. 800.00
(l) Skilled Labor 3 nos @ Tk. 390.00 per day = Tk. 1,170.00
(m) Ordinary Labour 6 nos @ Tk. 320.00 per day = Tk. 1,920.00
7 Compilation of driving Report, Pile Capacity 1 copy @ Tk. 2,000.00 each = Tk. 2,000.00
log & submission to PE on signing it.
Sub - Total = Tk. 114,260.00
Profit 10.00% = Tk. 11,426.00
Overhead 3.50% = Tk. 3,999.10
Total = Tk. 129,685.10
Add VAT with adjustment factor 1.06383 6.00% = Tk. 8,277.77
Grand Total = Tk. 137,962.87
Rate per meter = Tk. 942.76
09.25.2.4
Consider 11.5 nos 18"x18" Pile (40'-0" each)= 140.24 meter driving in 1 day
1. Hire charge of complete rig set LS. per day = Tk. 75,000.00
3 Generator,Fuel, lubricant etc. LS. per day = Tk. 20,000.00
4 Maintenance, insurance etc. LS per day = Tk. 5,000.00
5 Labour
(a) Data logging Engineer 1 no @ Tk. 1,800.00 per day = Tk. 1,800.00
(b) Chief Mechanic 1 no @ Tk. 1,400.00 per day = Tk. 1,400.00
(c) Helper to mechanic 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Foreman 1 no @ Tk. 800.00 per day = Tk. 800.00
Analysis of PWD SoR 2018 for Civil Works 217
i) 40 x 40 x 6 mm M.S Angle.
TOP 1 X 18 X 13'-8" = 246.06 rft
BOTTOM 1 X 18 X 12'-2" = 219.06 rft
WALL SIDE 1 X 18 X 1'-6" = 27.00 rft
VERTICAL TIE 1 X 18 X 1'-2" = 21.06 rft
VERTICAL TIE 1 X 18 X 0'-10" = 14.94 rft
VERTICAL TIE 1 X 18 X 0'-6" = 9.00 rft
VERTICAL TIE(END) 1 X 18 X 2'-4" = 41.94 rft
DIVISION 11. WOOD WORKS IN DOOR AND WINDOW FRAME, ROOF TRUSS AND RAILINGS
Item No.- 11.1.1
Supply and making door and window frames with seasoned wood
Considering 1 No. door frame
Considering for door size: 3'-4" x 7'-0"
Wood reqd.: (2 x 7'-0" + 3'-4") x 0'-2.5" x 0'-5" = 1.5 cft (finished)
= (2 x 7'-0" + 3'-6") x 0'-2.75" x 0'-5.25" = 1.75 cft (gross)
For Mehgoni
(a) Cost of wood 1.75 cft @ Tk. 1,800.00 per cft = Tk. 3,150.00
(b) Coaltaring: 2 coats 7.5 sft @ Tk. 7.00 per sft = Tk. 52.50
(c) Labour for making frame
(i) Carpenter 0.75 no @ Tk. 600.00 per day = Tk. 450.00
(ii) Carpenter helper 1.0 no @ Tk. 390.00 per day = Tk. 390.00
(d) Labour for fitting, fixing in position LS = Tk. 195.00
Sub - Total = Tk. 4,237.50
Profit 10.00% = Tk. 423.75
Overhead 3.50% = Tk. 148.31
Total = Tk. 4,809.56
Add VAT with adjustment factor 1.06383 6.00% = Tk. 306.99
Grand Total = Tk. 5,116.55
Rate per cft = Tk. 3,411.03
Rate per cum = Tk. 120,460.52
(ii) Carpenter helper 1.0 no @ Tk. 390.00 per day = Tk. 390.00
(d) Labour for fitting, fixing in position LS = Tk. 195.00
Sub - Total = Tk. 5,445.00
Profit 10.00% = Tk. 544.50
Overhead 3.50% = Tk. 190.58
Total = Tk. 6,180.08
Add VAT with adjustment factor 1.06383 6.00% = Tk. 394.47
Grand Total = Tk. 6,574.55
Rate per cft = Tk. 4,383.03
Rate per cum = Tk. 154,786.70
2. Labour for fabrication: 50.43 Ibs @ Tk. 300.00 per 50 kg = Tk. 137.22
3. Cost of welding:
Frame: 2 x 4 x 1.5" = 12.00 inch
Clamp: 6 x 4 x 1.5" = 36.00 inch
Hinge: 6 x (2 x 2"+4") = 48.00 inch
= 96.00 inch @ Tk. 6.00 Per inch = Tk. 576.00
4. Labour for fitting fixing in position, making @ 6 nos of holes in
existing brick work or making special arrangement
for fixing with concrete work 1 no @ Tk. 291.67 per day = Tk. 291.67
5. Cost of C.C. (1:2:4) in/c mending good the damages:
6 x 5" x 5" x 6" = 0.52 cft @ Tk. 175.63 per cft = Tk. 91.33
6. Local carriage & carriage from workshop to site LS = Tk. 96.00
Sub - Total = Tk. 2,773.94
Profit 10.00% = Tk. 277.39
Overhead 3.50% = Tk. 97.09
Total = Tk. 3,148.42
Add VAT with adjustment factor 1.06383 6.00% = Tk. 200.96
Grand Total = Tk. 3,349.38
Rate per rft = Tk. 186.08
Rate per rm = Tk. 610.53
A) Cost of materials
Ctg. Teak Wood
5 1/4" X 1 1/2" X 6'-10" X 2 nos = 0.87 cft
9 1/4" X 3 3/4" X 3'-0" X 1 no = 0.34 "
6 1/4" X 1 3/4" X 3'-0" X 2 nos = 0.46 "
For foreign 4 1/4" X 1 3/4" X 1'-0" X 1 no = 0.05 "
Panel 7 1/2" X 1 3/4" X 3'-0" X 4 nos = 1.09 "
7 1/2" X 1 3/4" X 2'-6" X 4 nos = 0.91 "
= 3.72 cft Tk. 4,390.00 per cft = Tk. 16,330.80
B) Cost of labour
i) Carpenter 3 nos @ Tk. 600.00 per day = Tk. 1,800.00
ii) Carpenter helper 5 nos @ Tk. 390.00 per day = Tk. 1,950.00
iii) Extra cost for design
a) Carpenter 3 nos @ Tk. 600.00 per day = Tk. 1,800.00
b) Carpenter helper 2 nos @ Tk. 390.00 per day = Tk. 780.00
C) Fitting
i) 10" long brass tower bolt 1 no @ Tk. 50.00 each = Tk. 50.00
ii) 8" long brass socket bolt 1 no @ Tk. 300.00 each = Tk. 300.00
iii) Brass Hasp bolt 1 no @ Tk. 375.00 each = Tk. 375.00
iv) 4" long brass hinges 4 nos @ Tk. 150.00 each = Tk. 600.00
v) Brass Handle 2 nos @ Tk. 100.00 each = Tk. 200.00
vi) Brass screws 1 dozens @ Tk. 20.00 per dozens = Tk. 20.00
vii) Hinged cleat & buffer block 1 set @ Tk. 62.00 per set = Tk. 62.00
Sub - Total = Tk. 24,267.80
Profit 10.00% = Tk. 2,426.78
Overhead 3.50% = Tk. 849.37
Total = Tk. 27,543.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,758.12
Grand Total = Tk. 29,302.07
Rate per sft = Tk. 1,430.07
Rate per sqm = Tk. 15,393.27
12.7.2
For Champ veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as- 12.7.1 = Tk. 657.00
(b) Labour: Same as- 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty. Same as 12.7.1 20.5 sft @ Tk. 240.00 = Tk. 4,920.00
Sub - Total = Tk. 5,922.00
Profit 10.00% = Tk. 592.20
Overhead 3.50% = Tk. 207.27
Total = Tk. 6,721.47
Add VAT with adjustment factor 1.06383 6.00% = Tk. 429.03
Grand Total = Tk. 7,150.50
Rate per sft = Tk. 348.80
Rate per sqm = Tk. 3,754.48
12.7.3
For Chapalish veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 657.00
(b) Labour: Same as 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty. Same as 12.7.1 20.5 sft @ Tk. 240.00 = Tk. 4,920.00
Sub - Total = Tk. 5,922.00
Profit 10.00% = Tk. 592.20
Overhead 3.50% = Tk. 207.27
Total = Tk. 6,721.47
Add VAT with adjustment factor 1.06383 6.00% = Tk. 429.03
Grand Total = Tk. 7,150.50
Rate per sft = Tk. 348.80
Rate per sqm = Tk. 3,754.48
12.7.4
For Garjan veneered
For 1 No. shutter
Considering 6'-10" x 3'-0"= 20.5 sft (single leaf)
(a) Fittings: Same as 12.7.1 = Tk. 657.00
(b) Labour: Same as 12.7.1 = Tk. 345.00
(c) Cost of shutter
Qty.: Same as 12.7.1 20.5 sft @ Tk. 250.00 = Tk. 5,125.00
Sub - Total = Tk. 6,127.00
Profit 10.00% = Tk. 612.70
Overhead 3.50% = Tk. 214.45
Total = Tk. 6,954.15
Add VAT with adjustment factor 1.06383 6.00% = Tk. 443.88
Grand Total = Tk. 7,398.03
Rate per sft = Tk. 360.88
Rate per sqm = Tk. 3,884.51
= 5.25 rft
= 2.22 Ibs @ Tk. 24.94 per Ib = Tk. 55.37
(b) Fittings
(i) Stopper handle 2 nos @ Tk. 20.00 each = Tk. 40.00
(ii) 12" long iron cleats 2 nos @ Tk. 30.00 each = Tk. 60.00
(iii) 2" long pin hinges 4 nos @ Tk. 25.00 each = Tk. 100.00
(iv) 6" long clamp for chowkat 4 nos @ Tk. 35.00 each = Tk. 140.00
(c) Workshop charges:
Manufacturing including fabrication,
revetting, welding in/c supply of all
necessary incidental materials. 15 sft @ Tk. 65.00 per sft = Tk. 975.00
(d) Labour charges
Labour charges for fitting fixing in position finished window shutter
and frames in the building including embeding clamp in
CC (1:2:4) & making grooves and mending
good the damage etc. complete. 1 no @ Tk. 172.87 per sft = Tk. 172.87
(e) Carriage charges:
Carriage charge for iron materials from market
to workshop & carrying the finished window
from workshop to building site. 1 no @ Tk. 70.00 each = Tk. 70.00
(f) Glass panes:
(i) 3 mm glass panes in/c wastage etc. 15 sft @ Tk. 40.00 per sft = Tk. 600.00
(ii) Fitting fixing of glass panes with necessary
iron pins & pucca putty 15 sft @ Tk. 16.00 per sft = Tk. 240.00
Sub - Total = Tk. 3,835.92
Profit 10.00% = Tk. 383.59
Overhead 3.50% = Tk. 134.26
Total = Tk. 4,353.77
Add VAT with adjustment factor 1.06383 6.00% = Tk. 277.90
Grand Total = Tk. 4,631.67
Rate per sft = Tk. 308.78
Rate per sqm = Tk. 3,323.71
Item No.-12.26
Supplying, fitting and fixing approved best quality foreign made door Viewer /Eye view made in foreign .
Considering of = 1 No. door view
(a) Materials:
(i) 38 x 6 mm F.I.bars (@ 1.28 Ibs per rft) for outer members
4 x 4'-6" = 18.00 rft
2 x 6'-6" = 13.00 rft
31.00 rft
Add 5% wastage 1.55 rft
32.55 rft
= 41.66 lbs @ Tk. 24.94 per Ib = Tk. 1,039.00
(ii) 25 x 6 mm F.I.bars (@ 0.850 Ibs per rft) for clamp
4 x 2 x 0'-6" = 4.00 rft
= 3.4 lbs @ Tk. 24.94 per Ib = Tk. 84.80
(iii) 12 x 12 mm M.S hollow square box (Made with 16 BG MS Plate) (2.55 lb/sft weight)
(perimeter of Plate 44.45 mm)
13 x 6'-6" = 84.50 rft
Add 5% wastage = 4.23 rft
= 88.73 rft
= 12.94 sft
= 33.00 lb @ Tk. 24.94 per Ib = Tk. 823.02
(b) Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. 29.25 sft @ Tk. 45.00 per sft Tk. 1,316.25
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) mason 1 no @ Tk. 600.00 per day = Tk. 600.00
(ii) skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
(d) Carriage charge for steel materials from market to
workshop and carrying the window grill
from workshop to building site. 1 no @ Tk. 80.00 each = Tk. 80.00
(e) Cost of CC, curing, incidental, sundries L.S = Tk. 172.64
Sub - Total = Tk. 4,505.71
Analysis of PWD SoR 2018 for Civil Works 278
(ii) Cost of M.S. clamp 24 nos @ Tk. 35.00 each = Tk. 840.00
(b) Workshop charge:
Labour cost for manufacturing, welding
including supply of necessary electrode, cutting steel
to required sizes etx complete. 33.75 sft @ Tk. 45.00 per sft Tk. 1,518.75
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) mason 0.7 no @ Tk. 600.00 per day = Tk. 420.00
(ii) skilled labour 0.7 no @ Tk. 390.00 per day = Tk. 273.00
(d) Carriage charge for steel materials from market to
workshop and carrying the window grill
from workshop to building site. 1 no @ Tk. 48.00 each = Tk. 48.00
(e) Cost of CC, curing, incidental, sundries L.S = Tk. 110.00
Sub - Total = Tk. 4,581.70
Profit 10.00% = Tk. 458.17
Overhead 3.50% = Tk. 160.36
Total = Tk. 5,200.23
Add VAT with adjustment factor 1.06383 6.00% = Tk. 331.93
Grand Total = Tk. 5,532.16
Rate per sft = Tk. 163.92
Rate per sqm = Tk. 1,764.43
(ii) 3/8" dia M.S. rod (@ 0.376 Ibs per rft) for inner members:
Vertical: 23 x 4'-0" = 92 rft
Horizontal: 11 x 8'-0" = 88 rft
= 180 rft
Add wastage 5%= 9 rft
= 189.00 rft
= 71.06 Ibs @ Tk. 26.30 per Ib = Tk. 1,868.88
(iii) Cost of F.I. bar clamps: 6" long 8.00 nos @ Tk. 35.00 each = Tk. 280.00
(b) Workshop charge:
Labour cost for manufacturing, welding including
supply of necessary electrode, cutting steel to
required sizes etc. complete. 32 sft @ Tk. 45.00 per sft Tk. 1,440.00
(c) Labour charges:
Labour charges for fitting and fixing in position of grills
(i) Skilled labour 0.50 no @ Tk. 390.00 per day = Tk. 195.00
(ii) Mason 0.50 nos @ Tk. 500.00 per day = Tk. 250.00
(d) Cost of CC (1:2:4) in/c mending good the damages:
8 x 0'-6" x 0'-6" x 0'-3" = 0.5 cft @ Tk. 177.64 per cft = Tk. 88.82
(e) Carriage charge for steel materials from market to
workshop and carrying the window grill from
workshop to building site. 1 no @ Tk. 80.00 each = Tk. 80.00
Sub - Total = Tk. 5,139.20
Profit 10.00% = Tk. 513.92
Overhead 3.50% = Tk. 179.87
Total = Tk. 5,832.99
Add VAT with adjustment factor 1.06383 6.00% = Tk. 372.32
Grand Total = Tk. 6,205.31
Rate per sft = Tk. 193.92
Rate per sqm = Tk. 2,087.35
(2) Swing door lock 1 set. @ Tk. 625.00 per set = Tk. 625.00
(3) Swing door mohiar 14 rft @ Tk. 5.00 per rft = Tk. 70.00
(4) Bolts and screws in/c sealants LS = Tk. 236.25
Sub total (B) = Tk. 3,631.25
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 no @ Tk. 1,000.00 each = Tk. 750.00
(2) Semi- skilled technician 3/4 no @ Tk. 600.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. LS = Tk. 480.00
Sub total (C) = Tk. 1,680.00
Total (A+B+C) = Tk. 12,282.29
Profit 10.00% = Tk. 1,228.23
Overhead 3.50% = Tk. 429.88
Total = Tk. 13,940.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 889.81
Grand Total = Tk. 14,830.21
Rate per sft = Tk. 605.31
Rate per sqm = Tk. 6,515.56
of 1.8 mm thick
1 x 7'-0"= 7 rft @ Tk. 131.00 per rft = Tk. 917.00
5. 101.60 mm closure cover
of 1.5 mm thick
1 x 7'-0"= 7 rft @ Tk. 45.00 per rft = Tk. 315.00
6. 101.60 mm, 12.70 mm floor bottom
of 4 mm thick
1 x 7'-0"= 7 rft @ Tk. 133.00 per rft = Tk. 931.00
7. 51 mm, 43.99 mm shutter top
of 1.8 mm thick
1 x 7'-0"= 7 rft @ Tk. 142.00 per rft = Tk. 994.00
8. 82.60 mm, 43.99 mm shutter bottom
of 1.8 mm thick
1 x 7'-0"= 7 rft @ Tk. 173.00 per rft = Tk. 1,211.00
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 3'-0"= 3 rft @ Tk. 183.00 per rft = Tk. 549.00
10. 101.60 mm, 44.45 mm top & side
of 1.5 mm thick
2 x 10'-0" = 20 rft
1 x 15-0" = 15 rft
1 x 3'-0"= 3 rft
= 38 rft @ Tk. 176.00 per rft = Tk. 6,688.00
11. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
2 x 8'-0"= 16 rft @ Tk. 90.00 per rft = Tk. 1,440.00
12. 44.32 mm ,19.61 mm bottom cover
of 1.5 m thick
2 x 8'-0"= 16 @ Tk. 52.00 per rft = Tk. 832.00
13. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 8'-0"= 16 rft
1 x 15-0" = 15 rft
= 31 rft @ Tk. 79.00 per rft = Tk. 2,449.00
14. 39.09 mm, 14.81 mm fixed glass protector
of 1.00 mm thick
1 x 7'-0"= 7 rft
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 25.00 per rft = Tk. 325.00
15. 15.75 mm, 14.81 mm fixed glass protector
bit of 0.99 mm thick
1 x 7'-0"= 7 rft
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 18.00 per rft = Tk. 234.00
= Tk. 24,229.00
Cutting wastage 3% = Tk. 726.87
Sub total (A) = Tk. 24,955.87
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,700.00 per set = Tk. 5,400.00
(2) Swing door lock 1 set @ Tk. 625.00 per set = Tk. 625.00
(3) Swing door mohiar 21 rft @ Tk. 5.00 per rft = Tk. 105.00
(4) Flush bolt 2 sets @ Tk. 320.00 per set = Tk. 640.00
(5) Bolts and screws in/c sealants LS = Tk. 626.02
Sub total (B) = Tk. 7,396.02
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 no @ Tk. 1,000.00 each = Tk. 3,000.00
(2) Semi- skilled technician 3 no @ Tk. 600.00 each = Tk. 1,800.00
(3) Tools and plant, sundries etc. LS = Tk. 1,600.00
Sub total (C) = Tk. 6,400.00
Total (A+B+C) = Tk. 38,751.89
Profit 10.00% = Tk. 3,875.19
Overhead 3.50% = Tk. 1,356.32
Analysis of PWD SoR 2018 for Civil Works 291
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 24.00 per rft = Tk. 312.00
15. 15.75 mm, 14.81 mm fixed glass protector bit
of 0.99 mm thick
1 x 7'-0"= 7 rft
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 17.00 per rft = Tk. 221.00
= Tk. 23,395.00
Cutting wastage 3% = Tk. 701.85
Sub total (A) = Tk. 24,096.85
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,700.00 per set = Tk. 5,400.00
(2) Swing door lock 1 set @ Tk. 625.00 per set = Tk. 625.00
(3) Swing door mohiar 21 rft @ Tk. 5.00 per rft = Tk. 105.00
(4) Flush bolt 2 sets @ Tk. 320.00 per set = Tk. 640.00
(5) Bolts and screws in/c sealants LS = Tk. 626.02
Sub total (B) = Tk. 7,396.02
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 no @ Tk. 1,000.00 each = Tk. 3,000.00
(2) Semi- skilled technician 3 no @ Tk. 600.00 each = Tk. 1,800.00
(3) Tools and plant, sundries etc. LS = Tk. 1,600.00
Sub total (C) = Tk. 6,400.00
Total (A+B+C) = Tk. 37,892.87
Profit 10.00% = Tk. 3,789.29
Overhead 3.50% = Tk. 1,326.25
Total = Tk. 43,008.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,745.22
Grand Total = Tk. 45,753.63
Rate per sft = Tk. 305.02
Rate per sqm = Tk. 3,283.24
of 1.8 mm thick
1 x 7'-0"= 7 rft @ Tk. 186.00 per rft = Tk. 1,302.00
9. 101.60 mm, 38.10 mm, 25.4 mm handle (short)
of 2.3 mm, 2.3 mm, 4.01 mm thick
1 x 3'-0"= 3 rft @ Tk. 197.00 per rft = Tk. 591.00
10. 101.60 mm, 44.45 mm top & side
1.5 mm thick
2 x 10'-0" = 20 rft
1 x 15-0" = 15 rft
1 x 3'-0"= 3 rft
= 38 rft @ Tk. 187.00 per rft = Tk. 7,106.00
11. 101.35 mm, 44.45 mm bottom
of 1.5 mm thick
2 x 8'-0"= 16 rft @ Tk. 96.00 per rft = Tk. 1,536.00
12. 44.32 mm, 19.61 mm bottom cover
of 1.5 m thick
2 x 8'-0"= 16 rft @ Tk. 55.00 per rft = Tk. 880.00
13. 83.21 mm, 16.00 mm grouve cover
of 1.5 mm thick
2 x 8'-0"= 16 rft
1 x 15-0" = 15 rft
= 31 rft @ Tk. 83.00 per rft = Tk. 2,573.00
14. 39.09 mm, 14.81 mm fixed glass protector
of 1.00 mm thick
1 x 7'-0"= 7 rft
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 27.00 per rft = Tk. 351.00
15. 15.75 mm, 14.81 mm fixed glass protector bit
of 0.99 mm thick
1 x 7'-0"= 7 rft
2 x 3'-0"= 6 rft
= 13 rft @ Tk. 21.00 per rft = Tk. 273.00
= Tk. 25,757.00
Cutting wastage 3% = Tk. 772.71
Sub total (A) = Tk. 26,529.71
(B) Cost of accessories:
(1) Swing door clouser 2 sets @ Tk. 2,700.00 per set = Tk. 5,400.00
(2) Swing door lock 1 set @ Tk. 625.00 per set = Tk. 625.00
(3) Swing door mohiar 21 rft @ Tk. 5.00 per rft = Tk. 105.00
(4) Flush bolt 2 sets @ Tk. 320.00 per set = Tk. 640.00
(5) Bolts and screws in/c sealants LS = Tk. 626.02
Sub total (B) = Tk. 7,396.02
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3 no @ Tk. 1,000.00 each = Tk. 3,000.00
(2) Semi- skilled technician 3 no @ Tk. 600.00 each = Tk. 1,800.00
(3) Tools and plant, sundries etc. LS = Tk. 1,600.00
Sub total (C) = Tk. 6,400.00
Total (A+B+C) = Tk. 40,325.73
Profit 10.00% = Tk. 4,032.57
Overhead 3.50% = Tk. 1,411.40
Total = Tk. 45,769.70
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,921.47
Grand Total = Tk. 48,691.17
Rate per sft = Tk. 324.61
Rate per sqm = Tk. 3,494.10
of 1.5 mm thick
1 x 7'-0"= 7 rft @ Tk. 92.00 per rft = Tk. 644.00
3. 33 mm, 26.80 mm, 22 mm shutter top
of 1.5 mm thick
1 x 6'-9"= 6.75 rft @ Tk. 62.00 per rft = Tk. 418.50
4. 60 mm, 24 mm shutter bottom
of 1.5 mm thick
1 x 6'-9"= 6.75 rft @ Tk. 87.00 per rft = Tk. 587.25
5. 75.50 mm, 19.90 mm outer side
of 1.5 mm thick
2 x 7'-0"= 14 rft @ Tk. 77.00 per rft = Tk. 1,078.00
6. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft @ Tk. 80.00 per rft = Tk. 1,120.00
7. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 7'-0"= 14 rft @ Tk. 83.00 per rft = Tk. 1,162.00
8. 31.75 mm shutter divider
of 1.5 mm thick
1 x 6'-9"= 6.75 rft @ Tk. 66.00 per rft
= Tk. 445.50
= Tk. 5,889.25
Cutting wastage 3% = Tk. 176.68
Sub total (A) = Tk. 6,065.93
(B) Cost of accessories:
(1) Sliding door key lock 2 sets @ Tk. 200.00 per set = Tk. 400.00
(2) Sliding door wheel 4 nos @ Tk. 70.00 each = Tk. 280.00
(3) Sliding door mohiar 50 rft @ Tk. 1.30 per rft = Tk. 65.00
(4) Sliding door neoprene 50 rft @ Tk. 2.70 per rft = Tk. 135.00
(5) Bolts and screws in/c sealants LS = Tk. 83.02
Sub total (B) = Tk. 963.02
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2 no @ Tk. 1,000.00 each = Tk. 2,000.00
(2) Semi- skilled technician 2 no @ Tk. 600.00 each = Tk. 1,200.00
(3) Tools and plant, sundries etc. LS = Tk. 480.00
Sub total (C) = Tk. 3,680.00
Total (A+B+C) = Tk. 10,708.95
Profit 10.00% = Tk. 1,070.90
Overhead 3.50% = Tk. 374.81
Total = Tk. 12,154.66
Add VAT with adjustment factor 1.06383 6.00% = Tk. 775.83
Grand Total = Tk. 12,930.49
Rate per sft = Tk. 263.89
Rate per sqm = Tk. 2,840.51
(1) Sliding window key lock 2 set @ Tk. 80.00 per set = Tk. 160.00
(2) Sliding window wheel 4 nos @ Tk. 70.00 each = Tk. 280.00
(3) Sliding window mohiar 33 rft @ Tk. 1.30 per rft = Tk. 42.90
(4) Sliding neoprene 28 rft @ Tk. 2.70 per rft = Tk. 75.60
(5) Bolts and screws in/c sealants LS = Tk. 107.35
Total (B) = Tk. 665.85
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/2 no @ Tk. 1,000.00 each = Tk. 500.00
(2) Semi- skilled technician 1/2 no @ Tk. 600.00 each = Tk. 300.00
(3) Tools and plant, sundries etc. LS = Tk. 384.00
Sub total (C) = Tk. 1,184.00
Total (A+B+C) = 6,167.35
Profit 10.00% = Tk. 616.74
Overhead 3.50% = Tk. 215.86
Total = Tk. 6,999.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 446.81
Grand Total = Tk. 7,446.76
Rate per sft = Tk. 330.97
Rate per sqm = Tk. 3,562.56
of 1.5 mm thick
2 x 4'-6"= 9 rft @ Tk. 80.00 per rft = Tk. 720.00
7. 34.40 mm, 32.10 mm, 25.4 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft @ Tk. 83.00 per rft = Tk. 747.00
8. 42.20 mm, 13.20 mm net section
of 1.5 mm thick
2 x 4'-6"= 9 rft
2 x 2'-6"= 5 rft
14 rft @ Tk. 55.00 per rft = Tk. 770.00
9. Fibre net mesh
2'-6" x 4'-6"= 11.25 sft @ Tk. 17.00 per sft = Tk. 191.25
Total = Tk. 5,097.75
Cutting wastage 3% = Tk. 152.93
Sub total (A) = Tk. 5,250.68
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 80.00 per set = Tk. 160.00
(2) Sliding window wheel 4 no @ Tk. 70.00 each = Tk. 280.00
(3) Sliding window mohiar 33 rft @ Tk. 1.30 per rft = Tk. 42.90
(4) Sliding window neoprene 28 rft @ Tk. 2.70 per rft = Tk. 75.60
(5) Sealant 100 gm @ Tk. 3.00 per gm = Tk. 300.00
(6) Bolts and screws in/c sealants LS = Tk. 192.00
Sub total (B) = Tk. 1,050.50
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 no @ Tk. 1,000.00 each = Tk. 750.00
(2) Semi- skilled technician 3/4 no @ Tk. 600.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 1,520.00
Total (A+B+C) = 7,821.18
Profit 10.00% = Tk. 782.12
Overhead 3.50% = Tk. 273.74
Total = Tk. 8,877.04
Add VAT with adjustment factor 1.06383 6.00% = Tk. 566.62
Grand Total = Tk. 9,443.66
Rate per sft = Tk. 419.72
Rate per sqm = Tk. 4,517.87
1.5 mm thick
2 x 4'-6"= 9 rft
2 x 2'-1"= 4.17 rft
= 13.17 rft @ Tk. 55.00 per rft = Tk. 724.35
9. Fibre net mesh
2'-6" x 4'-6"= 9.36 sft @ Tk. 17.00 per sft= Tk. 159.12
= Tk. 4,713.68
Cutting wastage 3% = Tk. 141.41
Sub total (A) = Tk. 4,855.09
(B) Cost of Accessories:
(1) Sliding window key lock 2 sets @ Tk. 80.00 per set = Tk. 160.00
(2) Sliding window wheel 4 nos @ Tk. 70.00 each = Tk. 280.00
(3) Sliding window mohiar 22 rft @ Tk. 1.30 per rft = Tk. 28.60
(4) Sliding window neoprene 22 rft @ Tk. 2.70 per rft = Tk. 59.40
(5) Sealant 100 gm @ Tk. 3.00 per gm = Tk. 300.00
(6) Bolts and screws in/c sealants LS = Tk. 160.00
Sub total (B) = Tk. 988.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 no @ Tk. 1,000.00 each = Tk. 750.00
(2) Semi- skilled technician 3/4 no @ Tk. 600.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 1,520.00
Total (A+B+C) = 7,363.09
Profit 10.00% = Tk. 736.31
Overhead 3.50% = Tk. 257.71
Total = Tk. 8,357.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 533.43
Grand Total = Tk. 8,890.54
Rate per sft = Tk. 474.92
Rate per sqm = Tk. 5,112.04
2 x 4'-6"= 9 rft
2 x 2'-1"= 4.17 rft
= 13.17 rft @ Tk. 53.00 per rft = Tk. 698.01
9. Fibre net mesh
2'-6" x 4'-6"= 9.36 sft @ Tk. 15.00 per sft = Tk. 140.40
Total = Tk. 4,569.09
Cutting wastage 3% = Tk. 137.07
Sub total (A) = Tk. 4,706.16
(B) Cost of accessories:
(1) Sliding window key lock 2 set @ Tk. 80.00 per set = Tk. 160.00
(2) Sliding window wheel 4 nos @ Tk. 70.00 each = Tk. 280.00
(3) Sliding window mohiar 22 rft @ Tk. 1.30 per rft = Tk. 28.60
(4) Sliding window neoprene 22 rft @ Tk. 2.70 per rft = Tk. 59.40
(5) Sealant 100 gm @ Tk. 3.00 per gm = Tk. 300.00
(6) Bolts and screws LS = Tk. 160.00
Sub total (B) = Tk. 988.00
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 3/4 No. @ Tk. 1,000.00 each = Tk. 750.00
(2) Semi- skilled technician 3/4 No. @ Tk. 600.00 each = Tk. 450.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 1,520.00
Total (A+B+C) = 7,214.16
Profit 10.00% = Tk. 721.42
Overhead 3.50% = Tk. 252.50
Total = Tk. 8,188.08
Add VAT with adjustment factor 1.06383 6.00% = Tk. 522.64
Grand Total = Tk. 8,710.72
Rate per sft = Tk. 465.32
Rate per sqm = Tk. 5,008.70
1'-3" x 2'-0"= 2.5 sft @ Tk. 15.00 per sft = Tk. 37.50
Total = Tk. 2,265.00
Cutting wastage 3% = Tk. 67.95
Sub total (A) = Tk. 2,332.95
(B) Cost of accessories:
(1) Sliding window key lock 2 sets @ Tk. 80.00 per set = Tk. 160.00
(2) Sliding window wheel 4 nos @ Tk. 70.00 each = Tk. 280.00
(3) Sliding window mohiar 10 rft @ Tk. 1.30 per rft = Tk. 13.00
(4) Sliding window neoprene 8 rft @ Tk. 2.70 per rft = Tk. 21.60
(5) Sealant 50 gm @ Tk. 3.00 per gm = Tk. 150.00
(6) Bolts and screws LS = Tk. 96.00
Sub total (B) = Tk. 720.60
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1/3 no @ Tk. 1,000.00 each = Tk. 333.33
(2) Semi- skilled technician 1/3 no @ Tk. 600.00 each = Tk. 200.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 853.33
Total (A+B+C) = 3,906.88
Profit 10.00% = Tk. 390.69
Overhead 3.50% = Tk. 136.74
Total = Tk. 4,434.31
Add VAT with adjustment factor 1.06383 6.00% = Tk. 283.04
Grand Total = Tk. 4,717.35
Rate per sft = Tk. 943.47
Rate per sqm = Tk. 10,155.51
of 1.5 mm thick
2 x 4'-6"= 9 rft @ Tk. 74.00 per rft = Tk. 666.00
6. 31.00 mm, 26.00 mm sliding fixed side
of 1.5 mm thick
1 x 4'-6"= 4.5 rft @ Tk. 44.00 per rft = Tk. 198.00
7. 49.20 mm, 26.20 mm shutter lock
of 1.5 mm thick
1 x 4'-6"= 4.5 rft @ Tk. 78.00 per rft = Tk. 351.00
8. 34.40 mm, 32.10 mm inter lock
of 1.5 mm thick
2 x 4'-6"= 9 rft @ Tk. 81.00 per rft = Tk. 729.00
9. 37.78 mm, 31.78 mm bottom cover
of 1.5 mm thick
1 x 5'-0"= 5 rft @ Tk. 38.00 per rft = Tk. 190.00
10. 76.20 mm, 38.10 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft @ Tk. 112.00 per rft = Tk. 560.00
11. 57.15 mm, 15.80 mm grouve cover
of 1.5 mm thick
1 x 5'-0"= 5 rft @ Tk. 57.00 per rft = Tk. 285.00
12. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
1 x 5'-0"= 5 rft
3 x 2'-6"= 7.5 rft
= 12.5 rft @ Tk. 125.00 per rft = Tk. 1,562.50
= Tk. 6,110.50
Cutting wastage 3% = Tk. 183.32
Total (A) = Tk. 6,293.82
(B) Cost of accessories:
(1) Sliding window key lock 1 set @ Tk. 80.00 per set = Tk. 80.00
(2) Sliding window wheel 2 nos @ Tk. 70.00 each = Tk. 140.00
(3) Sliding window mohiar 33 rft @ Tk. 1.30 per rft = Tk. 42.90
(4) Sliding neoprene 28 rft @ Tk. 2.70 per rft = Tk. 75.60
(5) Bolts and screws in/c sealants LS = Tk. 81.33
Total (B) = Tk. 419.83
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.25 no @ Tk. 1,000.00 each = Tk. 1,250.00
(2) Semi- skilled technician 1.25 no @ Tk. 600.00 each = Tk. 750.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 2,320.00
Total (A+B+C) = 9,033.65
Profit 10.00% = Tk. 903.37
Overhead 3.50% = Tk. 316.18
Total = Tk. 10,253.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 654.46
Grand Total = Tk. 10,907.66
Rate per sft = Tk. 311.65
Rate per sqm = Tk. 3,354.60
4 x 4'-0"= 16
2 x 3'-0"= 6
= 22 rft @ Tk. 25.00 per rft = Tk. 550.00
4. 1" x 1" square pipe 4 rft @ Tk. 38.00 per rft Tk. 152.00
= Tk. 3,410.00
Cutting wastage 3% = Tk. 102.30
Total (A) = Tk. 3,512.30
(B) Cost of accessories:
(1) 4-bar hinge 4 nos @ Tk. 700.00 per set = Tk. 2,800.00
(2) Casement handle 2 nos @ Tk. 260.00 each = Tk. 520.00
(3) Bolts and screws in/c sealants LS = Tk. 585.88
Total (B) = Tk. 3,905.88
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 1.50 no @ Tk. 1,000.00 each = Tk. 1,500.00
(2) Semi- skilled technician 1.50 no @ Tk. 600.00 each = Tk. 900.00
(3) Tools and plant, sundries etc. LS = Tk. 320.00
Sub total (C) = Tk. 2,720.00
Total (A+B+C) = 10,138.18
Profit 10.00% = Tk. 1,013.82
Overhead 3.50% = Tk. 354.84
Total = Tk. 11,506.84
Add VAT with adjustment factor 1.06383 6.00% = Tk. 734.48
Grand Total = Tk. 12,241.32
Rate per sft = Tk. 1,020.11
Rate per sqm = Tk. 10,980.46
of 1.2 mm thick
3 x 10'-0"= 30 rft @ Tk. 40.00 per rft = Tk. 1,200.00
2. 76.20 mm, 38.10 mm grouve cover
of 1.2 mm thick
3 x 10'-0"= 30 rft @ Tk. 90.00 per rft = Tk. 2,700.00
3. 57.15 mm, 15.80 mm grouve cover
of 1.2 mm thick
2 x 7'-0"= 14 rft
2 x 10'-0"= 20 rft
= 34 rft @ Tk. 60.00 per rft = Tk. 2,040.00
4. 76.20 mm, 38.10 mm, 57.15 mm top
& side of 1.5 mm thick
4 x 7'-0"= 28 rft
1 x 10'-0"= 10 rft
= 38 rft @ Tk. 118.00 per rft = Tk. 4,484.00
5. 7.14 mm span drel of 1.5 mm thick
22 x 7'-0"= 154 rft @ Tk. 90.00 per rft
= Tk. 13,860.00
= Tk. 24,284.00
Cutting wastage 5% = Tk. 1,214.20
Sub total (A) = Tk. 25,498.20
(B) Cost of accessories:
(1) Rivet 100 pcs @ Tk. 5.00 per pc = Tk. 500.00
(2) Screws 14 pcs @ Tk. 1.00 per pc = Tk. 14.00
(3) Fixed neoprene 204 rft @ Tk. 2.70 per rft = Tk. 550.80
Sub total (B) = Tk. 1,064.80
(C) Labour charge for fabrication, assembling and fitting-fixing in position
(1) Skilled technician 2.75 no @ Tk. 1,000.00 each = Tk. 2,750.00
(2) Semi- skilled technician 2.75 no @ Tk. 600.00 each = Tk. 1,650.00
(3) Tools and plant, sundries etc. LS = Tk. 640.00
Sub total (C) = Tk. 5,040.00
Total (A+B+C) = 31,603.00
Profit 10.00% = Tk. 3,160.30
Overhead 3.50% = Tk. 1,106.11
Total = Tk. 35,869.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 2,289.54
Grand Total = Tk. 38,158.95
Rate per sft = Tk. 545.13
Rate per sqm = Tk. 5,867.78
= 19.00 rft
Add wastage 3%= 0.57 rft
= 19.570 rft @ Tk. 77.00 per rft = Tk. 1,506.89
ii) 38mm x 12mm and 1.5 mm thick Aluminium frame of Netting shutter top,
Horizontal 2 x 2 x 2'-3"= 9.00 rft
Vertical 2 x 2 x 5'-0"= 20.00 rft
= 29.00 rft
Add wastage 3%= 0.87 rft
= 29.870 rft @ Tk. 69.00 per rft = Tk. 2,061.03
iii) Mosquito Net (plastic)
1 x 5'-0" x 4'-6"= 22.50 sft
Add wastage 3%= 0.68 sft
= 23.180 sft @ Tk. 19.00 per sft = Tk. 440.42
iv) Wheel 8 nos @ Tk. 70.00 each = Tk. 560.00
v) Sealant 50 rft @ Tk. 3.00 per gm = Tk. 150.00
vi) Rubber 1x 2x 14'-0" 28.00 rft @ Tk. 1.90 per rft = Tk. 53.20
v) Bolts & screws etc. LS = Tk. 40.00
b) Fitting and fixing of accessories
i) Skilled Technician 1/4 no @ Tk. 1,000.00 each = Tk. 250.00
ii) Semi skilled technician 1/4 no @ Tk. 600.00 each = Tk. 150.00
iii) Tools, plants and sundrise etc. LS = Tk. 60.00
Sub - Total = Tk. 5,271.54
Profit 10.00% = Tk. 527.15
Overhead 3.50% = Tk. 184.50
Total = Tk. 5,983.19
Add VAT with adjustment factor 1.06383 6.00% = Tk. 381.91
Grand Total = Tk. 6,365.10
Rate per sft = Tk. 282.89
Rate per sqm = Tk. 3,045.03
C a) Labour Charge:
i) Skilled Technician 10 nos @ Tk. 1,000.00 each = Tk. 10,000.00
ii) Semi-Skilled Technician 10 nos @ Tk. 600.00 each = Tk. 6,000.00
iii) Machineries LS = Tk. 600.00
b) Labour cost for civil work
i) Mason 3 nos @ Tk. 500.00 each = Tk. 1,500.00
ii) Ordinary Labour 3 nos @ Tk. 320.00 each = Tk. 960.00
D Cost of high scaffolding LS = Tk. 300.00
E Carriage and Sundries LS = Tk. 700.00
Total (A+B+C+D+E)= Tk. 61,298.30
Profit 10.00% = Tk. 6,129.83
Overhead 3.50% = Tk. 2,145.44
Total = Tk. 69,573.57
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,440.87
Grand Total = Tk. 74,014.44
Rate per sft = Tk. 858.44
Rate per sqm = Tk. 9,240.25
(i) For ground floor Say, Tk. 141 .00 per sqm
Item No.- 15.8
Ruled pointing with cement mortar (1:2) to walls
Considering 100 sft of work
(a) Sand (F.M. 1.2) 1.5 cft @ Tk. 1,400.00 Per % cft = Tk. 21.00
(b) Cement 0.5 bag @ Tk. 395.00 per bag = Tk. 197.50
(c) Labour
(i) Head mason 0.25 no @ Tk. 600.00 per day = Tk. 150.00
(ii) Mason 1 no @ Tk. 500.00 per day = Tk. 500.00
(iii) Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
(d) Washing of sand, scaffolding, curing, sundries, local carriage etc. LS = Tk. 192.00
Sub - Total = Tk. 1,380.50
Profit 10.00% = Tk. 138.05
Overhead 3.50% = Tk. 48.32
Total = Tk. 1,566.87
Add VAT with adjustment factor 1.06383 6.00% = Tk. 100.01
Grand Total = Tk. 1,666.88
Rate per sft = Tk. 16.67
Rate per sqm = Tk. 179.44
(i) For ground floor Say, Tk. 179 .00 per sqm
Item No.- 15.9
Raised / Tack pointing with cement mortar (1:2) to walls
Considering 100 sft of work
(a) Sand (F.M. 1.2) 3 cft @ Tk. 1,400.00 per % cft = Tk. 42.00
(b) Cement 1 bag @ Tk. 395.00 per bag = Tk. 395.00
(c) Cost of pumic stone 0.25 no @ Tk. 175.00 each Tk. 43.75
(d) Labour
(i) Head mason 0.5 no @ Tk. 600.00 per day = Tk. 300.00
(ii) Mason 2 nos @ Tk. 500.00 per day = Tk. 1,000.00
(iii) Skilled labour 2 nos @ Tk. 390.00 per day Tk. 780.00
(iv) Ordinary labour 2 nos @ Tk. 320.00 per day = Tk. 640.00
(e) Washing of sand, scaffolding, curing, sundries, local carriage etc. LS = Tk. 192.00
Sub - Total = Tk. 3,392.75
Profit 10.00% = Tk. 339.28
Overhead 3.50% = Tk. 118.75
Total = Tk. 3,850.78
Add VAT with adjustment factor 1.06383 6.00% = Tk. 245.79
Grand Total = Tk. 4,096.57
Rate per sft = Tk. 40.97
Rate per sqm = Tk. 441.00
(i) For ground floor Say, Tk. 441 .00 per sqm
Analysis of PWD SoR 2018 for Civil Works 354
(a) 0'-3" x 0'-3" Brick work (1:6) 6.25 cft @ Tk. 151.09 per cft = Tk. 944.31
(b) Extra labour for brick moulding
& plastering 100 rft @ Tk. 32.00 per rft = Tk. 3,200.00
(c) (3" + 3" + 3")= 9" width
and 1/2" thick cement plaster (1:6) 75 sft @ Tk. 17.55 per sft = Tk. 1,316.25
Sub - Total = Tk. 5,460.56
Profit 10.00% = Tk. 546.06
Overhead 3.50% = Tk. 191.12
Total = Tk. 6,197.74
Add VAT with adjustment factor 1.06383 6.00% = Tk. 395.60
Grand Total = Tk. 6,593.34
Rate per rft = Tk. 65.93
Rate per rm = Tk. 216.32
DIVISION 17: LIME TERRACING, ROOF TOP WATER PROOFING FOR GARDEN AND SWIMMIMG POOL
Item No.- 17.1
Non-toxic two component acrylic polymer modified cementitious coating (minimum 1.5mm thickness) For water proofing
Considering 100 sft of work
(a) High performance elastomeric cementitious 16.5 kg @ Tk. 280.00 per kg = Tk. 4,620.00
waterproof coating
(b) Labour
(i) Skilled Technician 0.5 no @ Tk. 1,000.00 each = Tk. 500.00
(ii) Skilled labour 1.00 no @ Tk. 390.00 each = Tk. 390.00
(iii) Local carriage, sundries, T&P etc. LS = Tk. 320.00
Sub - Total = Tk. 5,830.00
Profit 10.00% = Tk. 583.00
Overhead 3.50% = Tk. 204.05
Total = Tk. 6,617.05
Add VAT with adjustment factor 1.06383 6.00% = Tk. 422.36
Grand Total = Tk. 7,039.41
Rate per sft = Tk. 70.39
Rate per sqm = Tk. 757.68
Item No.-17.5.1
Ferrocement Treatment of Roof for Water Proofing
3 Sand (F.M. 2.2) 16.00 cft @ Tk. 4,500.00 per % cft = Tk. 720.00
4 Cement 5.50 bags @ Tk. 415.00 per bag = Tk. 2,282.50
5 20 BWG galvanized wire mesh 2 mesh per 120.00 sft @ Tk. 25.00 per sft = Tk. 3,000.00
25mm
6 Wire Nail 0.50 kg @ Tk. 90.00 per kg = Tk. 45.00
7 24 No. G.I. wire 0.50 kg @ Tk. 120.00 per kg = Tk. 60.00
8 Head Mason 0.25 no @ Tk. 600.00 each = Tk. 150.00
9 Mason 0.50 no @ Tk. 500.00 each = Tk. 250.00
10 Skilled Labour 1.00 no @ Tk. 390.00 each = Tk. 390.00
11 Ordinary Labour 2.00 nos @ Tk. 320.00 each = Tk. 640.00
12 Ordinary Labour for 7 days curing & 1/8 0.88 no @ Tk. 320.00 each = Tk. 281.60
labour par day
13 Local Carriage, Sundries, T & P, water etc. 0.20 no @ Tk. 320.00 each = Tk. 64.00
Sub - Total = Tk. 9,740.10
Profit 10.00% = Tk. 974.01
Overhead 3.50% = Tk. 340.90
Total = Tk. 11,055.01
Add VAT with adjustment factor 1.06383 6.00% = Tk. 705.64
Grand Total = Tk. 11,760.65
Rate per sft = Tk. 117.61
Rate per sqm = Tk. 1,265.48
Item No.17.5.2
Ferrocement Treatment of Roof for Heat & Water Proofing
(c) 1" L-section 63.00 rft @ Tk. 21.00 per rft = Tk. 1,323.00
(d) Revit LS = Tk. 221.50
(e) G.I. wire 1.50 kg @ Tk. 120.00 per sft = Tk. 180.00
(f) 1.5" screw 10.50 doz. @ Tk. 20.00 Per doz. = Tk. 210.00
(g) Rowel plug 120.00 nos @ Tk. 1.00 each = Tk. 120.00
(h) Wall bit 2.00 nos @ Tk. 40.00 each = Tk. 80.00
(B) Labour
(i) Carpenter 6.00 nos @ Tk. 600.00 each = Tk. 3,600.00
(ii) Helper to carpenter 6.00 nos @ Tk. 390.00 each = Tk. 2,340.00
(iii) Carrying to site in/c sundries LS = Tk. 640.00
Sub - Total = Tk. 21,724.50
Profit 10.00% = Tk. 2,172.45
Overhead 3.50% = Tk. 760.36
Total = Tk. 24,657.31
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,573.87
Grand Total = Tk. 26,231.18
Rate per sft = Tk. 163.94
Rate per sqm = Tk. 1,764.65
(b) Labour
(i) Skilled technician 5.00 nos @ Tk. 1,000.00 each = Tk. 5,000.00
(ii) Skilled labour 5.00 nos @ Tk. 390.00 each = Tk. 1,950.00
(iii) Ordinary labour 5.00 nos @ Tk. 320.00 each = Tk. 1,600.00
(iv) Scaffolding 100.00 sft. @ Tk. 9.00 per sft = Tk. 900.00
Total = Tk. 22,590.00
Profit 10.00% = Tk. 2,259.00
Overhead 3.50% = Tk. 790.65
= Tk. 25,639.65
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,636.57
Grand total = Tk. 27,276.22
Rate per sft = Tk. 272.76
Rate per sqm = Tk. 2,935.99
iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail)
and locking arrangement: @ 1.70 Ibs per rft
4 x 8'-6"= 34 rft
2 x 2 x 0'-6"= 2 rft
36 rft
Add wastage 5%= 1.8 rft
= 37.8 rft @ Tk. 200.00 per rft = Tk. 7,560.00
iii) 2" x 1/4" F.I. bar to make Tee (top & bottom rail)
and locking arrangement: @ 1.70 Ibs per rft
4 x 8'-6"= 34 rft
2 x 2 x 0'-6"= 2 rft
36 rft
Add wastage 5%= 1.8 rft
= 37.8 rft @ Tk. 200.00 per rft = Tk. 7,560.00
9i) Making holes 14.00 nos @ Tk. 19.50 each = Tk. 273.00
(ii) Making groove (channel) on floor:
1 x 8'-0"= 8.00 rft @ Tk. 19.50 per rft = Tk. 156.00
(iii) Cost of CC (1:2:4):
14 x 6" x 4" x 4"= 1.00 cft (say) @ Tk. 17,763.63 per % cft = Tk. 177.64
(iv) 1/2" thick plaster (1:4)
3 x 8'-0" x 1'-0"= 24.00 sft @ Tk. 1,755.00 per % sft = Tk. 421.20
(v) Repairing floor and plaster with neat cement finish:
1 x 8'-0" x 1'-6"= 12.00 sft @ Tk. 2,158.00 per % sft = Tk. 258.96
(g) Labour for fitting-fixing the gate:
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 per day = Tk. 195.00
Sub - Total = Tk. 22,129.47
Profit 10.00% = Tk. 2,212.95
Overhead 3.50% = Tk. 774.53
Total = Tk. 25,116.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,603.21
Grand Total = Tk. 26,720.16
Rate per sft = Tk. 417.50
Rate per sqm = Tk. 4,493.97
= 26.67 rft
Add wastage 5%= 1.33 rft
= 28.00 rft
= 89.32 Ibs @ Tk. 24.94 per Ib = Tk. 2,227.64
(ii) 7/8" M.S. rod: @ 2.04 Ibs per rft:
10 x 6'-11.5"= 69.60 rft
Add wastage 5%= 3.48 rft
= 73.08 rft
= 149.08 Ibs @ Tk. 24.94 per Ib = Tk. 3,718.06
(iii) 2" x 1/4" F.I. bar: @ 1.7 Ibs per rft
Horizontal: 4 x 3'-3.5= 15.71 rft
Rails: 2 x 3.142 x 3'-4"= 20.93 rft
36.64 rft
Add wastage 5%= 1.83 rft
38.47 rft
= 65.40 Ibs @ Tk. 24.94 per Ib = Tk. 1,631.08
(iv) 1/8" thick M.S. plate: @ 5.10 lbs per sft
1 x 2'-0" x 3'-0"= 6.00 sft
Add wastage 5%= 0.3 sft
= 6.30 sft
= 32.13 Ibs @ Tk. 27.44 per Ib = Tk. 881.65
(b) Fittings and consumables
(i) Hinges for pocket gate: 2 nos @ Tk. 68.00 each = Tk. 136.00
(ii) 1.5" dia heavy duty wheel 2 nos @ Tk. 160.00 each = Tk. 320.00
(iii) Locking arrangement 2 nos @ Tk. 275.00 each = Tk. 550.00
(iv) Clamp with huskel dumney 3 nos @ Tk. 144.00 each = Tk. 432.00
(v) Clamp for rails 6 nos @ Tk. 35.00 each = Tk. 210.00
(vi) Electrodes 98 Pc. @ Tk. 10.00 each = Tk. 980.00
(c) Making steel gate in work-shop
(i) Welder / fabricator 3 nos @ Tk. 600.00 each = Tk. 1,800.00
(ii) Helper 3 nos @ Tk. 390.00 each = Tk. 1,170.00
(iii) Ordinary labour 3 nos @ Tk. 320.00 each = Tk. 960.00
(d) Carrying materials to work-shop & gate to site LS = Tk. 169.60
Sub-total = Tk. 15,186.03
(e) Work-shop charges 10% = Tk. 1,518.60
Total = Tk. 16,704.63
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 80 nos @ Tk. 16.25 each = Tk. 1,300.00
(ii) Plain concrete: (1:2:4)
2 x 10" x 6" x 6"=0.41 cft
3'-4" x 6" x 4"=0.55 cft
2 x 3 x 6" x 4"=0.99 cft
1.95 cft @ Tk. 17,763.63 per % cft = Tk. 346.39
(g) Labour charge for hoisting the gate in position
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Mason helper 1 no @ Tk. 390.00 per day = Tk. 390.00
(iii) Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Sub - Total = Tk. 19,311.02
Profit 10.00% = Tk. 1,931.10
Overhead 3.50% = Tk. 675.89
Total = Tk. 21,918.01
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,399.02
Grand Total = Tk. 23,317.03
Rate per sft = Tk. 1,000.30
Rate per sqm = Tk. 10,767.23
(vii) 1/8" thick M.S. plate for punkha & folded plate: @ 5.10 lbs per sft
2 x 1'-3" x 1'-0"= 2.50 sft
1 x 6'-0" x 0'-3"= 1.50 sft
= 4.00 sft
Add 5% wastage= 0.20 sft
4.20 sft
= 12.75 Ibs @ Tk. 27.44 per Ib = Tk. 349.86
(b) Fittings, hardwares and consumables
(i) Best quality china made
spring: 3 x 11'-0"= 33 rft @ Tk. 50.00 per rft = Tk. 1,650.00
(ii) Spring box 3 nos @ Tk. 70.00 each = Tk. 210.00
(iii) Nut bolt, 1/2" dia maximum 2.5" long 18 nos @ Tk. 12.00 each = Tk. 216.00
(iv) Rivet:
Side patty= 176 nos
For fixing top tail= 9 nos
For fixing lower plate= 40 nos
= 225 nos @ Tk. 0.30 each = Tk. 67.50
For guide channel= 20 nos @ Tk. 0.45 each = Tk. 9.00
(v) 1" x 1/4" x 0'-9" clamps 8 nos @ Tk. 35.00 each = Tk. 280.00
(vi) Electrodes 30 nos @ Tk. 10.00 each = Tk. 300.00
(vii) Lubricant, greese: 1 Ibs @ Tk. 56.00 per Ib = Tk. 56.00
(c) Labour:
Cutting, folding both sides, rolling, locking individual strip, stitching
or riveting side patty etc. 44 pcs @ Tk. 19.20 Per piece = Tk. 844.80
Making other component of rolling shutter and assembling:
(i) Welder/fabricator 2 nos @ Tk. 600.00 per day = Tk. 1,200.00
(ii) Welder helper 2 nos @ Tk. 390.00 per day = Tk. 780.00
(iii) Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
(d) Carrying materials to work-shop and shutter to site LS = Tk. 480.00
Sub-total = Tk. 21,158.65
(e) Work-shop charges 10% = Tk. 2,115.87
Sub-total = Tk. 23,274.52
(f) Ancillary work for fitting-fixing the gate:
(i) Making holes 8 nos @ Tk. 16.25 each = Tk. 130.00
(ii) Plain concrete: (1:2:4)
8 x 6" x 6" x 6"= 1.00 cft @ Tk. 17,763.63 per % cft = Tk. 177.64
(iii) 1/2" plaster (1:4) to repair walls.
3 x 10'-0" x 1'-0"= 30 sft @ Tk. 1,755.00 per % sft = Tk. 526.50
(g) Labour charge for hoisting and commissioning the gate in position
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Mason helper 0.5 no @ Tk. 390.00 per day = Tk. 195.00
(iii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
(iv) Welder/ fabricator 0.5 no @ Tk. 600.00 per day = Tk. 300.00
(v) Welder helper 0.5 no @ Tk. 390.00 per day = Tk. 195.00
Sub - Total = Tk. 25,208.66
Profit 10.00% = Tk. 2,520.87
Overhead 3.50% = Tk. 882.30
Total = Tk. 28,611.83
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,826.29
Grand Total = Tk. 30,438.12
Rate per sft = Tk. 507.30
Rate per sqm = Tk. 5,460.58
2 x 2 x 7'-9"= 31 rft
Add wastage 5%= 1.55 rft
= 32.55 rft
@ 2.33916 rft/lbs
= 76.140 Ibs @ Tk. 24.94 per Ib = Tk. 1,898.93
(ii) 25mm x 25mm x 6mm M.S. angle
8 x 2 x 7'-9"= 124.00 rft
2 x 2 x 2 x 1 '-10.5"= 14.96 rft
2 x 2 x 2 x 1'-11"= 15.36 rft
= 154.32 rft
Add wastage 5%= 7.72 rft
= 162.04 rft
@ 1.489 rft/lbs
= 241.278 Ibs @ Tk. 24.94 per Ib = Tk. 6,017.47
(iii) 12mm x 12mm M.S. Solid square bar
2 X 22 x 1'-10.5"= 82.5 rft
2 X 22 x 1'-11"= 84.33 rft
166.83 rft
Add wastage 5%= 8.3415 rft
= 175.1715 rft
@ 0.851 rft/lbs
= 149.071 Ibs @ Tk. 24.94 per Ib = Tk. 3,717.83
(b) Fittings and consumables:
i) Hinges 3" long 12.00 nos @ Tk. 10.00 each = Tk. 120.00
ii) Locking arrangement 2.00 nos @ Tk. 275.00 each = Tk. 550.00
iii) Clamp (6" long) 6 nos @ Tk. 30.00 each = Tk. 180.00
iv) Electrodes 200 Pc @ Tk. 10.00 per pc = Tk. 2,000.00
(c) Making steel gate in work-shop
(i) Welder/ fabricator 6 nos @ Tk. 600.00 per day = Tk. 3,600.00
(ii) Helper 5 nos @ Tk. 390.00 per day = Tk. 1,950.00
(iii) Ordinary labour 5 nos @ Tk. 320.00 per day = Tk. 1,600.00
(d) Carrying cost: materials & finished gate. LS = Tk. 50.00
Sub-total = Tk. 21,684.23
(e) Workshop charge 10% = Tk. 2,168.42
Sub-total = Tk. 23,852.65
(f) Ancillary work for fitting-fixing the gate:
i) Making holes LS = Tk. 256.00
ii) Cost of CC (1:2:4):
6 x 10" x 6" x 6"= 1.25 cft @ Tk. 177.64 per cft = Tk. 222.05
(g) Labour for fitting-fixing the gate:
i) Mason 1 no @ Tk. 500.00 per day = Tk. 500.00
ii) Skilled labour 2 nos @ Tk. 390.00 per day = Tk. 780.00
iii) Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Sub - Total = Tk. 25,930.70
Profit 10.00% = Tk. 2,593.07
Overhead 3.50% = Tk. 907.57
Total = Tk. 29,431.34
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,878.60
Grand Total = Tk. 31,309.94
Rate per sft = Tk. 475.33
Rate per sqm = Tk. 5,116.45
= 0.29 sft
= 2.96 Ibs @ Tk. 27.44 Per lb. = Tk. 81.22
(iii) 1.5" x 1/4" M.S. F.I. bar: @ 1.28 Ibs per rft
1 x 9'-9"= 9.75 rft
Add wastage 5%= 0.49 rft
= 10.24 rft
= 13.11 lbs @ Tk. 24.94 per Ib = Tk. 326.96
(b) Fittings, hardwares and consumables:
(i) Electrodes: 10.00 nos @ Tk. 10.00 each = Tk. 100.00
(c) Labour for fabrication and making post and railing support etc.
(i) Welder / fabricator 0.50 nos @ Tk. 600.00 per day = Tk. 300.00
(ii) Welder helper 0.75 nos @ Tk. 390.00 per day = Tk. 292.50
(iii) Ordinary labour 1.00 nos @ Tk. 320.00 per day = Tk. 320.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 100.00
Sub-total = Tk. 3,202.36
(e) Work-shop charges: 10% = Tk. 320.24
Sub-Total = Tk. 3,522.60
(f) Ancillary works for fitting -fixing the railing:
(i) Labour charge for cutting: 2" x 2" x 6" size grooves
20 nos @ Tk. 13.00 each = Tk. 260.00
(ii) CC (1:2:4): 20 x 2" x 2" x 6"= 0.28 cft @ Tk. 17,763.63 per % cft = Tk. 49.74
(g) Labour charge for fitting fixing the stair railing at site
(i) Mason 0.25 no @ Tk. 500.00 per day = Tk. 125.00
(ii) Mason helper 0.50 no @ Tk. 390.00 per day = Tk. 195.00
(iii) Ordinary labour 0.50 no @ Tk. 320.00 per day = Tk. 160.00
(iv) Welder/fabricator 0.25 no @ Tk. 600.00 per day = Tk. 150.00
(v) Welder helper 0.50 no @ Tk. 390.00 per day = Tk. 195.00
Sub - Total = Tk. 4,657.34
Profit 10.00% = Tk. 465.73
Overhead 3.50% = Tk. 163.01
Total = Tk. 5,286.08
Add VAT with adjustment factor 1.06383 6.00% = Tk. 337.41
Grand Total = Tk. 5,623.49
Rate per sft = Tk. 203.75
Rate per sqm = Tk. 2,193.17
3 Carrying of Materials from market to work shop and workshop to site LS = Tk. 150.00
Sub Total = Tk. 13,508.34
4 Polishing work in/c all materials 10% = Tk. 1,350.83
Sub - Total = Tk. 14,859.17
Profit 10.00% = Tk. 1,485.92
Overhead 3.50% = Tk. 472.79
Total = Tk. 16,817.88
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,073.48
Grand Total = Tk. 17,891.36
Rate per sft = Tk. 498.09
Rate per sqm = Tk. 5,361.44
82.34 sft
(a) Materials:
(i) 50 mm dia SS pipe (2 mm thick)
1 x 18'-6" = 18.50 rft
2 x 1'-9" = 3.5 rft
= 22.00 rft
Add wastage 5%= 1.10 rft
= 23.10 rft @ Tk. 197.00 per rft = Tk. 4,550.70
(ii) 20 mm dia SS pipe: (2 mm thick)
5 x 18'-6" = 92.50 rft
2 x 5 x 1'-9" = 17.50 rft
= 110.00 rft
Add wastage 5%= 5.50 rft
= 115.50 rft @ Tk. 68.00 per rft = Tk. 7,854.00
1. Cost of SS materials
a) 62 mm dia SS pipe
1 x 17'-0" = 17.00 rft
Add 5% wastage 0.85 rft
= 17.85 rft @ Tk. 248.00 per rft = Tk. 4,426.80
b) 50 x 62 x 2mm SS pipe post with glass 17.5 rft @ Tk. 300.00 per rft = Tk. 5,250.00
holder
c) Base plate (65x55x6 mm) 5 nos @ Tk. 150.00 each = Tk. 750.00
d) Royal bolt 20 nos @ Tk. 50.00 each = Tk. 1,000.00
e) SS base cup 1.5" 5 nos @ Tk. 200.00 each = Tk. 1,000.00
2 Fabrication and making post of railing support etc.
i) Welder / Fabricator 1.30 nos @ Tk. 600.00 per day = Tk. 780.00
ii) Welder helper 2.60 nos @ Tk. 390.00 per day = Tk. 1,014.00
iii) Ordinay labour 2.60 nos @ Tk. 320.00 per day = Tk. 832.00
3 Scaffolding 100.00 sft @ Tk. 9.00 per sft = Tk. 900.00
4 Welding Rod(Electrode) 60.00 nos @ Tk. 10.00 each = Tk. 600.00
5 Argon gas, Filler rod, Tungsten rod Gardening disk electricity, woven mop 240 GRT etc LS = Tk. 3,500.00
Analysis of PWD SoR 2018 for Civil Works 396
Considering 10 steps
Total rft of nosing: 10 x 3'-6"= 35 rft
(a) Cost of cutting @ 3 nos of grooves per steps
for fixing 1.5" x 1.5" x 3.5" size clamps
(i) Mason 0.25 No. @ Tk. 500.00 per day = Tk. 125.00
(ii) Skilled labour 0.5 No. @ Tk. 390.00 per day = Tk. 195.00
(b) Cost of CC (1:2:4) with smaller size of chips for fixing clamps:
30 x 1.5" x1.5" x3.5"= 0.14 cft @ Tk. 17,763.63 per % cft = Tk. 24.87
(c) Cost of 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft
10 x 3'-6"= 35 rft
Add wastage 5%= 1.75 rft
= 36.75 rft
= 86.00 Ibs @ Tk. 24.94 per Ib = Tk. 2,144.84
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft
10 x 3 x 3"= 7.5 rft
Add wastage 5%= 0.375 rft
= 7.875 rft
= 2.52 Ibs @ Tk. 24.94 per Ib = Tk. 62.85
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & P. 10 nos @ Tk. 8.00 each = Tk. 80.00
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on the other end. 30 nos @ Tk. 8.00 each = Tk. 240.00
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
Sub - Total = Tk. 3,282.56
Profit 10.00% = Tk. 328.26
Overhead 3.50% = Tk. 114.89
Total = Tk. 3,725.71
Add VAT with adjustment factor 1.06383 6.00% = Tk. 237.81
Grand Total = Tk. 3,963.52
Rate per rft = Tk. 113.24
Rate per rm = Tk. 371.54
10 x 3'-6"= 35 rft
Add wastage 5%= 1.75 rft
= 36.75 rft @ Tk. 270.00 per rft = Tk. 9,922.50
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft
10 x 3 x 3"= 7.5 rft
Add wastage 5%= 0.375 rft
= 7.875 rft
= 2.52 Ibs @ Tk. 24.94 per Ib = Tk. 62.85
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & P. 10 nos @ Tk. 8.00 each = Tk. 80.00
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on the other end. 30 nos @ Tk. 8.00 each = Tk. 240.00
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
Sub - Total = Tk. 11,060.22
Profit 10.00% = Tk. 1,106.02
Overhead 3.50% = Tk. 387.11
Total = Tk. 12,553.35
Add VAT with adjustment factor 1.06383 6.00% = Tk. 801.28
Grand Total = Tk. 13,354.63
Rate per rft = Tk. 381.56
Rate per rm = Tk. 1,251.90
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft
10 x 3 x 3"= 7.5 rft
Add wastage 5%= 0.375 rft
= 7.875 rft
= 2.52 Ibs @ Tk. 24.94 per Ib = Tk. 62.85
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & P. 10 nos @ Tk. 8.00 each = Tk. 80.00
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on the other end. 30 nos @ Tk. 8.00 each = Tk. 240.00
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
Sub - Total = Tk. 8,855.22
Profit 10.00% = Tk. 885.52
Overhead 3.50% = Tk. 309.93
Total = Tk. 10,050.67
Add VAT with adjustment factor 1.06383 6.00% = Tk. 641.53
Analysis of PWD SoR 2018 for Civil Works 400
(d) Cost of 3/4" x 1/8" F.I. bar for clamps: @ 0.32 Ibs per rft
10 x 3 x 3"= 7.5 rft
Add wastage 5%= 0.375 rft
= 7.875 rft
= 2.52 Ibs @ Tk. 24.94 per Ib = Tk. 62.85
(e) Cutting charge of M.S. angle as per required measurement
in/c cost of T & P. 10 nos @ Tk. 8.00 each = Tk. 80.00
(f) Cost of welding of 3/4" x 1/8" F.I. bar for fixing one end with angle including
bifercating on the other end. 30 nos @ Tk. 8.00 each = Tk. 240.00
(g) Labour charge for fixing up the M.S. angle in the nosing of steps to
keep the angles in level and parallel with each of the steps properly
(i) Mason 0.5 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
Sub - Total = Tk. 8,120.22
Profit 10.00% = Tk. 812.02
Overhead 3.50% = Tk. 284.21
Total = Tk. 9,216.45
Add VAT with adjustment factor 1.06383 6.00% = Tk. 588.28
Grand Total = Tk. 9,804.73
Rate per rft = Tk. 280.14
Rate per rm = Tk. 919.14
(iii) 3/4" x 3/4" x 1/4" M.S. angle for box: @ 0.585 lbs per rft
: 22 x 2 x 3'-0"= 132.00 rft
Add wastage 5%= 6.60 rft
= 138.60 rft
= 81.08 lbs @ Tk. 24.94 per Ib = Tk. 2,022.14
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 140.00 nos @ Tk. 10.00 each = Tk. 1,400.00
(c) Labour for making grill fencing
(i) Welder / fabricator 3.00 nos @ Tk. 600.00 per day = Tk. 1,800.00
(ii) Welder helper 3.00 nos @ Tk. 390.00 per day = Tk. 1,170.00
(iii) Ordinary labour 3.00 nos @ Tk. 320.00 per day = Tk. 960.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 480.00
Sub-total = Tk. 11,359.65
(e) Work-shop charges: L.S 10% = Tk. 1,135.97
Sub-Total = Tk. 12,495.62
(f) Ancillary works for fitting-fixing the grill fencing:
(i) Labour charge for cutting
3" x 3" x 12" size grooves 4 nos @ Tk. 32.00 each = Tk. 128.00
(ii) CC (1:2:4):
4 x 3" x 3" x 12"= 0.25 cft @ Tk. 17,763.63 per % cft = Tk. 44.41
(g) Labour charge for fitting-fixing the grill fencing:
(i) Mason 0.50 no @ Tk. 500.00 per day = Tk. 250.00
(ii) Mason helper 0.50 no @ Tk. 390.00 per day = Tk. 195.00
Sub - Total = Tk. 13,113.03
Profit 10.00% = Tk. 1,311.30
Overhead 3.50% = Tk. 458.96
Total = Tk. 14,883.29
Add VAT with adjustment factor 1.06383 6.00% = Tk. 950.00
Grand Total = Tk. 15,833.29
Rate per sft = Tk. 435.22
Rate per sqm = Tk. 4,684.71
(a) Materials:
(i) 1.5" x 1.5" x 1/4" M.S. angle: @ 2.34 Ibs per rft
2 x 3'-3"= 6.50 rft
Horizontal: 2 x 7'-9"= 15.50 rft
= 22 rft
Add wastage 5%= 1.1 rft
23.1 rft
= 54.05 Ibs @ Tk. 24.94 Per lb. = Tk. 1,348.01
(ii) 1/4" dia M.S. rod: @ 0.167 lbs per rft
20 x 3'-3"= 65.00 rft
8 x 7'-9"= 62.00 rft
127.00 rft
Add wastage 5%= 6.35 rft
= 133.35 rft
= 22.27 lbs @ Tk. 26.30 per Ib = Tk. 585.70
(b) Fittings, hardwares and consumables:
(i) Electrodes in/c electricity 35.00 nos @ Tk. 10.00 each = Tk. 350.00
(c) Labour for making grill fencing
(i) Welder / fabricator 1.00 no @ Tk. 600.00 per day = Tk. 600.00
(ii) Welder helper 1.00 no @ Tk. 390.00 per day = Tk. 390.00
(iii) Ordinary labour 1.00 no @ Tk. 320.00 per day = Tk. 320.00
(d) Carrying of materials to work-shop and fabricated materials to site: = Tk. 240.00
Analysis of PWD SoR 2018 for Civil Works 404
(ii) Barbed wire works: 12 BWG 2 ply 4 points; @ 950 rft Per cwt.
40 x 6'-4" = 253.2 rft
Add wastage 5% = 12.66 rft
= 265.86 rft
= 0.28 cwt @ Tk. 6,000.00 per cwt = Tk. 1,680.00
(g) Labour charge for Setting 12 BWG barbed wire hoisting the position
(i) Mason 0.5 nos @ Tk. 500.00 per day = Tk. 250.00
(ii) Mason helper 0.5 nos @ Tk. 390.00 per day = Tk. 195.00
(iii) Ordinary labour 0.5 nos @ Tk. 320.00 per day = Tk. 160.00
Sub-total(b) = Tk. 702.72
(b) Sand filling 20 cft @ Tk. 900.00 per % sft = Tk. 180.00
(c) Cement concrete(1:3:6) at 3 nos joint 3.93 cft @ Tk. 15,428.63 per % cft = Tk. 606.35
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Mason 0.25 no @ Tk. 500.00 each = Tk. 125.00
(iii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
Sub - Total = Tk. 6,176.35
Profit 10.00% = Tk. 617.64
Overhead 3.50% = Tk. 216.17
Total = Tk. 7,010.16
Add VAT with adjustment factor 1.06383 6.00% = Tk. 447.46
Grand Total = Tk. 7,457.62
Rate per rft = Tk. 414.31
Rate per rm = Tk. 1,359.35
(b) Sand filling 25 cft @ Tk. 900.00 per % sft = Tk. 225.00
(c) Cement concrete(1:3:6) at 2 nos junctions 4.82 cft @ Tk. 15,428.63 per % cft = Tk. 743.66
(d) Labour charge for laying pipe maintaining proper
slope in/c cost of gasket etc.
(i) Head mason 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Mason 0.25 no @ Tk. 500.00 each = Tk. 125.00
(iii) Skilled labour 1.5 nos @ Tk. 390.00 each = Tk. 585.00
Sub - Total = Tk. 10,057.72
Profit 10.00% = Tk. 1,005.77
Overhead 3.50% = Tk. 352.02
Total = Tk. 11,415.51
Add VAT with adjustment factor 1.06383 6.00% = Tk. 728.65
Grand Total = Tk. 12,144.16
Rate per rft = Tk. 674.68
Rate per rm = Tk. 2,213.63
1 6mm well graded down Stone chips 1 cft @ Tk. 140.00 per cft = Tk. 140.00
2 Sand (FM 1.2) 0.65 cft @ Tk. 14.00 per cft = Tk. 9.10
3 Sand (F.M. 2.2) 0.65 cft @ Tk. 45.00 per cft = Tk. 29.25
4 Cement 0.48 bag @ Tk. 415.00 per bag = Tk. 199.20
5 6mm MS Rod (fy = 400 Mpa) 6.14 Kg @ Tk. 60.50 per kg = Tk. 371.47
6 100 mm long iron hinges with welding to 4 nos @ Tk. 54.00 Per no. = Tk. 216.00
6mm M.S. rod
Analysis of PWD SoR 2018 for Civil Works 423
8 Formworks / Shuttering (Steel) 17.33 rft @ Tk. 2.00 rft = Tk. 34.66
23.1.1 For ground floor, span up to 3810 mm for floor/roof slab. = Tk. 2,354.00
23.1.2.1 Add for each additional span length of 150mm long direction (3810 mm<span ≤ 4800mm) = Tk. 9.00
23.1.2.2 Add for each additional floor up to 5th floor = Tk. 35.00
23.1.2.3 Add for each additional floor from 6th floor = Tk. 40.00
Item No.- 23.2
Ferrocement folded plate for roof
Considering 100 sft of work
1 Sand (F.M. 1.2) 2.70 cft @ Tk. 14.00 per cft = Tk. 37.80
2 Sand (F.M. 2.2) 10.00 cft @ Tk. 45.00 per cft = Tk. 450.00
3 Cement 4.50 bags @ Tk. 415.00 per bag = Tk. 1,867.50
4 MS Rod (fy = 400 Mpa) 60.94 Kg @ Tk. 60.50 per kg = Tk. 3,686.87
5 20 BWG galvanized wire mesh (2 mesh per 150.00 sft @ Tk. 25.00 per sft = Tk. 3,750.00
25mm)
6 Jute hassian 75.00 sft @ Tk. 2.50 per sft = Tk. 187.50
7 Polythene sheet 75.00 sft @ Tk. 2.50 per sft = Tk. 187.50
8 24 BWG G.I. wire 2.00 kg @ Tk. 120.00 per kg = Tk. 240.00
9 Shuttering (Steel) LS = Tk. 200.00
10 Hire charge of Mixture machine including Oil 0.25 no @ Tk. 2,004.00 per day = Tk. 501.00
& Operator
Analysis of PWD SoR 2018 for Civil Works 425
11 Hire charge of Vibrator table including Oil & 0.25 no @ Tk. 996.00 per day = Tk. 249.00
Operator
12 Head Mason 0.125 no @ Tk. 600.00 each = Tk. 75.00
13 Mason 1.00 no @ Tk. 500.00 each = Tk. 500.00
14 Rod binder 0.50 no @ Tk. 500.00 each = Tk. 250.00
15 Skilled Labour for casting 1.00 no @ Tk. 390.00 each = Tk. 390.00
16 Skilled Labour for assembling 2.00 nos @ Tk. 390.00 each = Tk. 780.00
17 Helper to Rod binder 1.00 no @ Tk. 390.00 each = Tk. 390.00
18 Ordinary Labour 2.00 nos @ Tk. 320.00 each = Tk. 640.00
19 Local Carriage, Sundries, T&P water etc. 0.50 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 14,542.17
Profit 10.00% = Tk. 1,454.22
Overhead 3.50% = Tk. 508.98
Total = Tk. 16,505.37
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,053.53
Grand Total = Tk. 17,558.90
Rate per sft = Tk. 175.59
Rate per sqm = Tk. 1,889.35
4 MS Rod (fy = 400 Mpa) 41.51 Kg @ Tk. 60.50 per kg = Tk. 2,511.36
5 20 BWG galvanized wire mesh 2 mesh per 110.00 sft @ Tk. 25.00 per sft = Tk. 2,750.00
25mm
6 24 No. G.I. wire 0.10 Kg @ Tk. 120.00 per kg = Tk. 12.00
7 Shuttering (Steel) 144.60 sft @ Tk. 2.00 per sft = Tk. 289.20
8 Hire charge of Mixture machine including Oil 0.20 no @ Tk. 2,004.00 per day = Tk. 400.80
& Operator
9 Hire charge of Vibrator table including Oil & 0.25 no @ Tk. 996.00 per day = Tk. 249.00
Operator
10 Head Mason 0.125 no @ Tk. 600.00 each = Tk. 75.00
11 Mason 0.25 no @ Tk. 500.00 each = Tk. 125.00
12 Rod binder 0.50 no @ Tk. 500.00 each = Tk. 250.00
13 Skilled Labour 0.50 no @ Tk. 390.00 each = Tk. 195.00
14 Helper to Rod binder 0.50 no @ Tk. 390.00 each = Tk. 195.00
15 Ordinary Labour 1.00 no @ Tk. 320.00 each = Tk. 320.00
16 Ordinary Labour for 7 days curing 0.88 no @ Tk. 320.00 each = Tk. 280.00
17 Local Carriage, Sundries, T&P water etc. 0.50 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 11,108.61
Profit 10.00% = Tk. 1,110.86
Overhead 3.50% = Tk. 388.80
Total = Tk. 12,608.27
Add VAT with adjustment factor 1.06383 6.00% = Tk. 804.78
Grand Total = Tk. 13,413.05
Rate per sft = Tk. 127.74
Rate per sqm = Tk. 1,374.48
(iii) Diesel 0.16 litre @ Tk. 68.00 per litre = Tk. 10.88
(iv) Lubricants 0.0160 litre @ Tk. 220.00 per litre = Tk. 3.52
Sub-Total (c) = Tk. 114.40
(ii) Skilled labour 0.12 no @ Tk. 390.00 per day = Tk. 46.80
(iii) Ordinary labour 0.5 no @ Tk. 320.00 per day = Tk. 160.00
(iv) Sundries and T & P LS = Tk. 106.67
Sub-Total (b) = Tk. 323.47
(c) Equipment Charges:
(i) Hire Charge of Vibratory
(Ride On) Roller 2 Steel Drum Compactor (3- 0.01 day @ Tk. 5,000.00 per day = Tk. 50.00
(ii) 5 tons)
Hire Charge of Pneumatic
Multiple Tired Roller (7 tires, 8-10 tons) 0.01 day @ Tk. 5,000.00 per day = Tk. 50.00
(iii) Diesel 0.16 litre @ Tk. 68.00 per litre = Tk. 10.88
(iv) Lubricants 0.0160 litre @ Tk. 220.00 per litre = Tk. 3.52
Sub-Total (c) = Tk. 114.40
26.1.2 Coloured commode (Bangladeshi), size 465 x 340 x 415 mm, wt.: 14 kg or equivalent
Considering 1 No. of fixture
1. Coloured commode 1 no @ Tk. 1,530.00 each = Tk. 1,530.00
2. Accessories:
(a) Seat cover 1 no @ Tk. 510.00 each = Tk. 510.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,695.50
Profit 10.00% = Tk. 269.55
Overhead 3.50% = Tk. 94.34
Total = Tk. 3,059.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 195.28
Grand Total = Tk. 3,254.67
Rate per No. = Tk. 3,254.67
26.1.3 Special coloured commode (Bangladeshi), size 465 x 340 x 415 mm, wt.: 14 kgor equivalent
Considering 1 No. of fixture
1. Special coloured commode 1 no @ Tk. 1,670.00 each = Tk. 1,670.00
2. Accessories:
(a) Seat cover 1 no @ Tk. 510.00 each = Tk. 510.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
Analysis of PWD SoR 2018 for Civil Works 450
(b) Nuts with Washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,835.50
Profit 10.00% = Tk. 283.55
Overhead 3.50% = Tk. 99.24
Total = Tk. 3,218.29
Add VAT with adjustment factor 1.06383 6.00% = Tk. 205.42
Grand Total = Tk. 3,423.71
Rate per No. = Tk. 3,423.71
26.2.2 Coloured low -down (Bangladeshi), size 490 x 190 x 350 mm, wt.: 14 kg or equivalent
Considering 1 No. of fixture
1. Coloured low-down 1 no @ Tk. 1,400.00 each = Tk. 1,400.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 no @ Tk. 75.00 each = Tk. 75.00
3. Fitting fixing materials:
(a) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(i) 50 mm rowel plug with screws 4 nos @ Tk. 9.00 each = Tk. 36.00
(ii) 75 mm screw, rowel plug 3 nos @ Tk. 13.00 each = Tk. 39.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
Sub - Total = Tk. 1,995.00
Profit 10.00% = Tk. 199.50
Overhead 3.50% = Tk. 69.83
Total = Tk. 2,264.33
Add VAT with adjustment factor 1.06383 6.00% = Tk. 144.53
Grand Total = Tk. 2,408.86
Rate per No. = Tk. 2,408.86
26.2.3 Special coloured low -down (Bangladeshi), size 490 x 190 x 350 mm, wt.: 14 kg or equivalent
Considering 1 No. of fixture
1. Special coloured low-down 1 no @ Tk. 1,600.00 each = Tk. 1,600.00
2. Accessories:
(a) 32 mm dia plastic pipe 1 no @ Tk. 75.00 each = Tk. 75.00
3. Fitting fixing materials:
(a) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(i) 50 mm rowel plug with screws 4 nos @ Tk. 9.00 each = Tk. 36.00
(ii) 75 mm screw, rowel plug 3 nos @ Tk. 13.00 each = Tk. 39.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
Sub - Total = Tk. 2,195.00
Profit 10.00% = Tk. 219.50
Overhead 3.50% = Tk. 76.83
Total = Tk. 2,491.33
Add VAT with adjustment factor 1.06383 6.00% = Tk. 159.02
Grand Total = Tk. 2,650.35
Rate per No. = Tk. 2,650.35
Item No.- 26.3 Supplying, fitting and fixing European type glazed porcelain Combi closet
26.3.1 Supplying, fitting and fixing European type glazed porcelain Combi closet, in/c plastic seat cover, cistern system
26.3.1.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde) 670 x 365 x 755 mm, 31.0 kg or equivalent
Considering 1 No. of fixture
1. White Combicloset 1 no @ Tk. 6,040.00 each = Tk. 6,040.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 6,890.50
Profit 10.00% = Tk. 689.05
Overhead 3.50% = Tk. 241.17
Total = Tk. 7,820.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 499.19
Grand Total = Tk. 8,319.91
Rate per No. = Tk. 8,319.91
26.3.1.2 Coloured combicloset Coloured (Marble Shade), 670 x 365 x 755 mm,31.0 kg or equivalent
Considering 1 No. of fixture
1. Coloured combicloset: 1 no @ Tk. 7,850.00 each = Tk. 7,850.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 8,700.50
Profit 10.00% = Tk. 870.05
Overhead 3.50% = Tk. 304.52
Analysis of PWD SoR 2018 for Civil Works 452
26.3.1.3 Special coloured combicloset Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 670 x 365 x 755 mm,31.0 kg or equivalent
or equivalent
Considering 1 No. of fixture
1. Special coloured combicloset: 1 no @ Tk. 9,060.00 each = Tk. 9,060.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 9,910.50
Profit 10.00% = Tk. 991.05
Overhead 3.50% = Tk. 346.87
Total = Tk. 11,248.42
Add VAT with adjustment factor 1.06383 6.00% = Tk. 717.98
Grand Total = Tk. 11,966.40
Rate per No. = Tk. 11,966.40
26.3.2.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde), 700x370x795mm, 32.5kg or Equivalent
Considering 1 No. of fixture
1. White Combicloset 1 no @ Tk. 7,130.00 each = Tk. 7,130.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 7,980.50
Profit 10.00% = Tk. 798.05
Overhead 3.50% = Tk. 279.32
Total = Tk. 9,057.87
Add VAT with adjustment factor 1.06383 6.00% = Tk. 578.16
Grand Total = Tk. 9,636.03
Rate per No. = Tk. 9,636.03
26.3.3.3 Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 700x360x785 mm, 38 kg
Considering 1 No. of fixture
1. White Combicloset 1 no @ Tk. 14,925.00 each = Tk. 14,925.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 15,775.50
Profit 10.00% = Tk. 1,577.55
Overhead 3.50% = Tk. 552.14
Total = Tk. 17,905.19
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,142.88
Grand Total = Tk. 19,048.07
Rate per No. = Tk. 19,048.07
26.3.4 Supplying, fitting and fixing European type glazed porcelain Combi closet, approx. 340x730x785 mm size, approx. 36.75 kg by
weigh White / Ivory colour in/c plastic seat cover
Considering 1 No. of fixture
1. White Combicloset 1 no @ Tk. 11,825.00 each = Tk. 11,825.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 12,675.50
Profit 10.00% = Tk. 1,267.55
Overhead 3.50% = Tk. 443.64
Total = Tk. 14,386.69
Add VAT with adjustment factor 1.06383 6.00% = Tk. 918.30
Grand Total = Tk. 15,304.99
Rate per No. = Tk. 15,304.99
Item No.- 26.4 Supplying, fitting and fixing European type glazed combi closet
26.4.1 Supplying, fitting and fixing European type glazed combi closet, 725x360x840 mm size, 42.7 kg by weight in/c plastic seat cover
26.4.1.1 Light colour (Ivory/ Alpine White/ Grey/ Pink/ Blue/ Aqua Verde), 725x360x840 mm size, 42.7 kg
Considering 1 No. of fixture
1. White combicloset 1 no @ Tk. 12,640.00 each = Tk. 12,640.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 13,490.50
Profit 10.00% = Tk. 1,349.05
Overhead 3.50% = Tk. 472.17
Total = Tk. 15,311.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 977.34
Grand Total = Tk. 16,289.06
Rate per No. = Tk. 16,289.06
26.4.1.3 Special coloured (Deep Blue/ Ruby/ Rain Forest/ Green), 725x360x840 mm size, 42.7 kg
Considering 1 No. of fixture
1. White combicloset 1 no @ Tk. 18,950.00 each = Tk. 18,950.00
2 Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
(b) Nuts with washer 4 nos @ Tk. 26.00 each = Tk. 104.00
4. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 19,800.50
Profit 10.00% = Tk. 1,980.05
Analysis of PWD SoR 2018 for Civil Works 456
26.4.2 Supplying, fitting and fixing European type glazed combi closet, White colour 370x760x800 mm size, 44.69 kg by weight, in/c
plastic seat cover
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
3. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 1,704.50
Profit 10.00% = Tk. 170.45
Overhead 3.50% = Tk. 59.66
Total = Tk. 1,934.61
Add VAT with adjustment factor 1.06383 6.00% = Tk. 123.49
Grand Total = Tk. 2,058.10
Rate per No. = Tk. 2,058.10
26.5.1.3 Special coloured long pan with foot-rest 530x430x210 mm 12.5 kg or equivalent
Considering 1 No. of fixture
1. Special coloured long pan: 1 no @ Tk. 1,330.00 each = Tk. 1,330.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
3. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 1,881.50
Profit 10.00% = Tk. 188.15
Overhead 3.50% = Tk. 65.85
Total = Tk. 2,135.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 136.31
Grand Total = Tk. 2,271.81
Rate per No. = Tk. 2,271.81
(i) Cement 0.1 bag @ Tk. 395.00 per bag = Tk. 39.50
(ii) Sand (F.M. 1.2) 0.5 cft @ Tk. 1,400.00 per % cft = Tk. 7.00
3. Labour:
(a) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(b) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,194.50
Profit 10.00% = Tk. 219.45
Overhead 3.50% = Tk. 76.81
Total = Tk. 2,490.76
Add VAT with adjustment factor 1.06383 6.00% = Tk. 158.98
Grand Total = Tk. 2,649.74
Rate per No. = Tk. 2,649.74
26.9.2 595x430x190mm,10kg
26.9.2.1 White colour
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 966.00 each = Tk. 966.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,911.65
Profit 10.00% = Tk. 191.17
Overhead 3.50% = Tk. 66.91
Total = Tk. 2,169.73
Add VAT with adjustment factor 1.06383 6.00% = Tk. 138.49
Grand Total = Tk. 2,308.22
Rate per No. = Tk. 2,308.22
26.9.2.2 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 1,167.00 each = Tk. 1,167.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 2,112.65
Profit 10.00% = Tk. 211.27
Overhead 3.50% = Tk. 73.94
Total = Tk. 2,397.86
Add VAT with adjustment factor 1.06383 6.00% = Tk. 153.05
Grand Total = Tk. 2,550.91
Rate per No. = Tk. 2,550.91
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 2,345.65
Profit 10.00% = Tk. 234.57
Overhead 3.50% = Tk. 82.10
Total = Tk. 2,662.32
Add VAT with adjustment factor 1.06383 6.00% = Tk. 169.94
Grand Total = Tk. 2,832.26
Rate per No. = Tk. 2,832.26
26.9.3.2 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 984.00 each = Tk. 984.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,929.65
Profit 10.00% = Tk. 192.97
Overhead 3.50% = Tk. 67.54
Analysis of PWD SoR 2018 for Civil Works 463
26.9.4.2 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 698.00 each = Tk. 698.00
Analysis of PWD SoR 2018 for Civil Works 464
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,643.65
Profit 10.00% = Tk. 164.37
Overhead 3.50% = Tk. 57.53
Total = Tk. 1,865.55
Add VAT with adjustment factor 1.06383 6.00% = Tk. 119.08
Grand Total = Tk. 1,984.63
Rate per No. = Tk. 1,984.63
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,549.65
Profit 10.00% = Tk. 154.97
Overhead 3.50% = Tk. 54.24
Total = Tk. 1,758.86
Add VAT with adjustment factor 1.06383 6.00% = Tk. 112.27
Grand Total = Tk. 1,871.13
Rate per No. = Tk. 1,871.13
26.9.5.2 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 635.00 each = Tk. 635.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,580.65
Profit 10.00% = Tk. 158.07
Overhead 3.50% = Tk. 55.32
Total = Tk. 1,794.04
Add VAT with adjustment factor 1.06383 6.00% = Tk. 114.51
Grand Total = Tk. 1,908.55
Rate per No. = Tk. 1,908.55
26.9.6.2 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 1,014.00 each = Tk. 1,014.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 1,959.65
Profit 10.00% = Tk. 195.97
Overhead 3.50% = Tk. 68.59
Total = Tk. 2,224.21
Add VAT with adjustment factor 1.06383 6.00% = Tk. 141.97
Grand Total = Tk. 2,366.18
Rate per No. = Tk. 2,366.18
26.9.6.3 Coloured
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 1,064.00 each = Tk. 1,064.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
Analysis of PWD SoR 2018 for Civil Works 467
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 2,009.65
Profit 10.00% = Tk. 200.97
Overhead 3.50% = Tk. 70.34
Total = Tk. 2,280.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 145.59
Grand Total = Tk. 2,426.55
Rate per No. = Tk. 2,426.55
26.9.7 Supplying, fitting and fixing White or Ivory colour , 560x410x205mm,7.90 kg glazed vitreous W/H Wash Basin excluding pedastal
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 3,150.00 each = Tk. 3,150.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 4,095.65
Profit 10.00% = Tk. 409.57
Overhead 3.50% = Tk. 143.35
Total = Tk. 4,648.57
Add VAT with adjustment factor 1.06383 6.00% = Tk. 296.72
Grand Total = Tk. 4,945.29
Rate per No. = Tk. 4,945.29
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 2,127.65
Profit 10.00% = Tk. 212.77
Overhead 3.50% = Tk. 74.47
Total = Tk. 2,414.89
Add VAT with adjustment factor 1.06383 6.00% = Tk. 154.14
Grand Total = Tk. 2,569.03
Rate per No. = Tk. 2,569.03
26.10.2 Supplying, glazed vitreous W/H Wash Basin in/c pedastal size 600 x 500 x 855 mm, 26.92kg or equivalent
Considering 1 No. of fixture
1. Coloured wash-basin 1 no @ Tk. 4,650.00 each = Tk. 4,650.00
2. Accessories:
(a) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(b) Grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(c) CP chain with rubber plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
(b) CI brakets 1 pair @ Tk. 115.00 per pair = Tk. 115.00
4. Labour:
(a) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(c) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 5,595.65
Profit 10.00% = Tk. 559.57
Overhead 3.50% = Tk. 195.85
Total = Tk. 6,351.07
Add VAT with adjustment factor 1.06383 6.00% = Tk. 405.39
Grand Total = Tk. 6,756.46
Rate per No. = Tk. 6,756.46
(d) Labour:
(i) Plumber 0.15 no @ Tk. 600.00 each = Tk. 90.00
(ii) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
(iii) Ordinary labour 0.4 no @ Tk. 320.00 each = Tk. 128.00
Sub - Total = Tk. 3,277.00
Profit 10.00% = Tk. 327.70
Overhead 3.50% = Tk. 114.70
Total = Tk. 3,719.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 237.41
Grand Total = Tk. 3,956.81
Rate per No. = Tk. 3,956.81
26.14.2 Coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg or equivalent
Considering 1 No. of fixture
1. Coloured flat/squatting urinal 1 no @ Tk. 1,000.00 each = Tk. 1,000.00
2. Fitting fixing materials:
(a) Cement mortar (1:4)
(i) Cement 0.2 bag @ Tk. 395.00 per bag = Tk. 79.00
(ii) Sand (F.M. 1.2) 0.1 cft @ Tk. 1,400.00 per % cft = Tk. 1.40
3. Labour:
(a) Plumber 0.2 no @ Tk. 600.00 each = Tk. 120.00
(b) Skilled labour 0.25 no @ Tk. 390.00 each = Tk. 97.50
(c) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 1,457.90
Profit 10.00% = Tk. 145.79
Overhead 3.50% = Tk. 51.03
Total = Tk. 1,654.72
Add VAT with adjustment factor 1.06383 6.00% = Tk. 105.62
Grand Total = Tk. 1,760.34
Rate per No. = Tk. 1,760.34
26.14.3 Special coloured flat/squatting urinal (Bangladeshi), size 510 x 380 x 85 mm, wt. 9.5 kg
26.15.2 Coloured porcelain sink (Bangladeshi), size 625 x 490 x 224 mm, wt. 19.5 kg
Considering 1 No. of fixture
1. Coloured porcelain sink 1 no @ Tk. 1,800.00 each = Tk. 1,800.00
2. Accessories:
(a) CP grating with brass coupling 1 no @ Tk. 300.00 each = Tk. 300.00
(b) 32 mm dia PVC waste pipe 1 no @ Tk. 150.00 each = Tk. 150.00
(c) CP chain with plug 1 no @ Tk. 80.00 each = Tk. 80.00
3. Fitting fixing materials:
(a) CI braket: heavy type 1 pair @ Tk. 158.00 per pair = Tk. 158.00
(b) Cement mortar (1:4):
(i) Cement 0.015 bag @ Tk. 395.00 per bag = Tk. 5.93
(ii) Sand 0.075 cft @ Tk. 1,400.00 per % cft = Tk. 1.05
4. Labour:
(a) Plumber 0.2 no @ Tk. 600.00 each = Tk. 120.00
(b) Skilled labour 0.3 no @ Tk. 390.00 each = Tk. 117.00
Sub - Total = Tk. 2,731.98
Profit 10.00% = Tk. 273.20
Analysis of PWD SoR 2018 for Civil Works 480
(a) Super quality CP towel rail 1 no @ Tk. 450.00 each = Tk. 450.00
(b) Fitting fixing materials:
(i) Rowel plug and screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(c) Labour:
(i) Plumber 0.04 no @ Tk. 600.00 each = Tk. 24.00
(ii) Skilled labour 0.08 no @ Tk. 390.00 each = Tk. 31.20
(iii) Ordinary labour 0.15 no @ Tk. 320.00 each = Tk. 48.00
Sub - Total = Tk. 589.20
Profit 10.00% = Tk. 58.92
Overhead 3.50% = Tk. 20.62
Total = Tk. 668.74
Add VAT with adjustment factor 1.06383 6.00% = Tk. 42.69
Grand Total = Tk. 711.43
Rate per No. = Tk. 711.43
1. White porcelain toilet paper holder 1 no @ Tk. 250.00 each = Tk. 250.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
3. Labour:
(a) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
(b) Skilled labour 0.05 no @ Tk. 390.00 each = Tk. 19.50
(c) Ordinary labour 0.01 no @ Tk. 320.00 each = Tk. 3.20
Sub - Total = Tk. 292.35
Profit 10.00% = Tk. 29.24
Overhead 3.50% = Tk. 10.23
Total = Tk. 331.82
Add VAT with adjustment factor 1.06383 6.00% = Tk. 21.18
Grand Total = Tk. 353.00
Rate per No. = Tk. 353.00
26.24.2 Special colour porcelain toilet paper holder (Bangladeshi), size 150 x 150 x 128 mm or equivalent
Considering 1 No. of fixture
1. Special Coloure paper holder 1 no @ Tk. 325.00 each = Tk. 325.00
2. Fitting fixing materials:
(a) Cement mortar (1:4):
(i) Cement 0.01 bag @ Tk. 395.00 per bag = Tk. 3.95
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
3. Labour:
(a) Plumber 0.025 no @ Tk. 600.00 each = Tk. 15.00
(b) Skilled labour 0.05 no @ Tk. 390.00 each = Tk. 19.50
(c) Ordinary labour 0.01 no @ Tk. 320.00 each = Tk. 3.20
Sub - Total = Tk. 367.35
Profit 10.00% = Tk. 36.74
Overhead 3.50% = Tk. 12.86
Total = Tk. 416.95
Add VAT with adjustment factor 1.06383 6.00% = Tk. 26.61
Grand Total = Tk. 443.56
Rate per No. = Tk. 443.56
Item No 26.27
26.27.1 Surface Mounted Automatic Liquid Soap Dispenser
Considering one work
(a) Material 1 pcs @ Tk. 5,500.00 per pcs = Tk. 5,500.00
(d) Labour
(i) Skilled Labour 0.25 no @ Tk. 390.00 per day = Tk. 97.50
(ii) Ordinary labour 0.25 no @ Tk. 320.00 per day = Tk. 80.00
(d) Others LS = Tk. 200.00
Sub - Total = Tk. 5,877.50
Profit 10.00% = Tk. 587.75
Overhead 3.50% = Tk. 205.71
Total = Tk. 6,670.96
Add VAT with adjustment factor 1.06383 6.00% = Tk. 425.81
Grand Total = Tk. 7,096.77
Rate per pcs = Tk. 7,096.77
1. 125 mm dia stainless steel grating 1 no @ Tk. 150.00 each = Tk. 150.00
Analysis of PWD SoR 2018 for Civil Works 487
(ii) Sand (F.M. 1.2) 0.05 cft @ Tk. 1,400.00 per % cft = Tk. 0.70
3. Labour:
(a) Skilled labour 0.1 no @ Tk. 390.00 each = Tk. 39.00
Sub - Total = Tk. 138.65
Profit 10.00% = Tk. 13.87
Overhead 3.50% = Tk. 4.85
Total = Tk. 157.37
Add VAT with adjustment factor 1.06383 6.00% = Tk. 10.04
Grand Total = Tk. 167.41
Rate per No. = Tk. 167.41
(a) 100 mm dia 20'-0" long pipe: 20 ft. @ Tk. 79.00 per ft = Tk. 1,580.00
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 no @ Tk. 146.00 each = Tk. 146.00
(ii) Tee/T-Y/Y 1 no @ Tk. 179.00 each = Tk. 179.00
(c) Jointing & fixing materials
(i) Solvent cement 30 ml @ Tk. 0.70 per ml = Tk. 21.00
(ii) Clamp 8 nos @ Tk. 50.00 each = Tk. 400.00
(iii) Rowel plug & screw 16 nos @ Tk. 13.00 each = Tk. 208.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.5 no @ Tk. 600.00 each = Tk. 300.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(iii) Ordinary labour 0.8 no @ Tk. 320.00 each = Tk. 256.00
Sub - Total = Tk. 3,540.00
Profit 10.00% = Tk. 354.00
Overhead 3.50% = Tk. 123.90
Total = Tk. 4,017.90
Add VAT with adjustment factor 1.06383 6.00% = Tk. 256.46
Grand Total = Tk. 4,274.36
Rate per ft = Tk. 213.72
Rate per m = Tk. 701.22
26.32.1.2 Supplying, laying, fitting , fixing 160 mm/6" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
(d) Labour:
(i) Plumber 0.5 no @ Tk. 600.00 per day = Tk. 300.00
(ii) Skilled labour 1 no @ Tk. 390.00 per day = Tk. 390.00
(iii) Ordinary labour 1 no @ Tk. 320.00 per day = Tk. 320.00
Sub - Total = Tk. 8,858.10
Profit 10.00% = Tk. 885.81
Overhead 3.50% = Tk. 310.03
Total = Tk. 10,053.94
Add VAT with adjustment factor 1.06383 6.00% = Tk. 641.74
Grand Total = Tk. 10,695.68
Rate per ft = Tk. 534.78
Rate per m = Tk. 1,754.61
26.32.1.3 Supplying, laying, fitting , fixing 200 mm/8" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.1.4 Supplying, laying, fitting , fixing 250 mm/10" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.1.5 Supplying, laying, fitting , fixing 280 mm/11" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.1.6 Supplying, laying, fitting , fixing 315 mm/13" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.1.7 Supplying, laying, fitting , fixing 400 mm/16" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
(b) Fittings:
(i) 400 mm HDPE Plain Tee/T-Y 0.25 no @ Tk. 14,057.00 each = Tk. 3,514.25
(ii) 400 mm HDPE Plain Bend 0.5 no @ Tk. 10,780.00 each = Tk. 5,390.00
(c) Jointing & fixing Materials
Butt fusion welding joint 1 Tk. 450.00 each = Tk. 450.00
(d) Excavation (underground) 87.5 cft @ Tk. 2,958.33 per % cft = Tk. 2,588.54
(e) Bedding by sand (FM 0.8) (underground) 52.5 cft @ Tk. 1,400.00 per % cft = Tk. 735.00
(d) Labour:
(i) Plumber 1 no @ Tk. 600.00 per day = Tk. 600.00
(ii) Skilled labour 0.25 no @ Tk. 390.00 per day = Tk. 97.50
(iii) Ordinary labour 2 no @ Tk. 320.00 per day = Tk. 640.00
Sub - Total = Tk. 57,815.29
Profit 10.00% = Tk. 5,781.53
Overhead 3.50% = Tk. 2,023.54
Total = Tk. 65,620.36
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,188.53
Grand Total = Tk. 69,808.89
Rate per ft = Tk. 3,490.44
Rate per m = Tk. 11,452.13
26.32.1.8 Supplying, laying, fitting , fixing 630 mm/24" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.1.9 Supplying, laying, fitting , fixing 710 mm/28" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
(iii) Ordinary labour 3 nos @ Tk. 320.00 per day = Tk. 960.00
Sub - Total = Tk. 178,787.87
Profit 10.00% = Tk. 17,878.79
Overhead 3.50% = Tk. 6,257.58
Total = Tk. 202,924.24
Add VAT with adjustment factor 1.06383 6.00% = Tk. 12,952.61
Grand Total = Tk. 215,876.85
Rate per ft = Tk. 10,793.84
Rate per m = Tk. 35,414.59
26.32.1.10 Supplying, laying, fitting , fixing 900 mm/38" outer diameter PE-100, PN-6 , HDPE Soil, Waste & Ventilation Pipe
26.32.2.2 Supplying, laying, fitting , fixing 160 mm/6" outside diameter PE-100, PN-6, SDR 26 HDPE Soil, Waste & Ventilation Pipe
26.32.2.3 Supplying, laying, fitting , fixing 200 mm/8" outside diameter PE-100, PN-6, SDR 26 HDPE Soil, Waste & Ventilation Pipe
26.32.2.4 Supplying, laying, fitting , fixing 250 mm/10" outside diameter PE-100, PN-6, SDR 26 HDPE Soil, Waste & Ventilation Pipe
Item No - 26.33
50 mm dia uPVC pipe
Considering 20 ft. long one pipe
(a) 50 mm dia 20'-0" long pipe: 20 ft. @ Tk. 32.00 per ft = Tk. 640.00
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 no @ Tk. 23.00 each = Tk. 23.00
(ii) Tee/T-Y/Y 1 no @ Tk. 99.00 each = Tk. 99.00
(c) Jointing & fixing materials
(i) Solvent cement 20 ml @ Tk. 0.70 per ml = Tk. 14.00
(ii) Clamp 4 nos @ Tk. 50.00 each = Tk. 200.00
(iii) Rowel plug & screw 8 nos @ Tk. 9.00 each = Tk. 72.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.5 no @ Tk. 600.00 each = Tk. 300.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(iii) Ordinary labour 0.8 no @ Tk. 320.00 each = Tk. 256.00
Sub - Total = Tk. 2,054.00
Profit 10.00% = Tk. 205.40
Overhead 3.50% = Tk. 71.89
Total = Tk. 2,331.29
Add VAT with adjustment factor 1.06383 6.00% = Tk. 148.81
Grand Total = Tk. 2,480.10
Rate per ft = Tk. 124.01
Rate per m = Tk. 406.88
Item No - 26.34
100 mm dia uPVC pipe
Considering 20 ft. long one pipe
(a) 100 mm dia 20'-0" long pipe: 20 ft. @ Tk. 79.00 per ft = Tk. 1,580.00
(b) Fittings:
(i) Bend/45O bend/off-set/cowel 1 no @ Tk. 146.00 each = Tk. 146.00
(ii) Tee/T-Y/Y 1 no @ Tk. 179.00 each = Tk. 179.00
(c) Jointing & fixing materials
(i) Solvent cement 54 ml @ Tk. 0.70 per ml = Tk. 37.80
(ii) Clamp 4 nos @ Tk. 50.00 each = Tk. 200.00
(iii) Rowel plug & screw 8 nos @ Tk. 9.00 each = Tk. 72.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.75 no @ Tk. 600.00 each = Tk. 450.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
Sub - Total = Tk. 3,114.80
Profit 10.00% = Tk. 311.48
Overhead 3.50% = Tk. 109.02
Total = Tk. 3,535.30
Add VAT with adjustment factor 1.06383 6.00% = Tk. 225.66
Grand Total = Tk. 3,760.96
Rate per ft = Tk. 188.05
Rate per m = Tk. 616.99
26.36.2 20 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 20 mm dia G.I. pipe: 20 ft. @ Tk. 48.00 per ft = Tk. 960.00
(b) Fittings:
Analysis of PWD SoR 2018 for Civil Works 497
26.36.3 25 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 25 mm dia G.I. pipe: 20 ft. @ Tk. 66.00 per ft = Tk. 1,320.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 49.00 each = Tk. 49.00
(ii) Tee 1 no @ Tk. 54.00 each = Tk. 54.00
(iii) Nipple 1 no @ Tk. 34.00 each = Tk. 34.00
(iv) Plug 1 no @ Tk. 21.00 each = Tk. 21.00
(v) Reducer 1 no @ Tk. 38.00 each = Tk. 38.00
(vi) Socket 1 no @ Tk. 30.00 each = Tk. 30.00
(c) Jointing & fixing materials
(i) Teflon tape 4.2 pcs @ Tk. 16.00 per pcs = Tk. 67.20
(ii) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(ii) Skilled labour 0.25 no @ Tk. 390.00 each = Tk. 97.50
(iii) Ordinary labour 0.5 no @ Tk. 320.00 each = Tk. 160.00
Sub - Total = Tk. 2,141.70
Profit 10.00% = Tk. 214.17
Overhead 3.50% = Tk. 74.96
Total = Tk. 2,430.83
Add VAT with adjustment factor 1.06383 6.00% = Tk. 155.16
Grand Total = Tk. 2,585.99
Rate per ft = Tk. 129.30
Rate per m = Tk. 424.23
26.36.4 32 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 32 mm dia G.I. pipe: 20 ft. @ Tk. 84.00 per ft = Tk. 1,680.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 63.00 each = Tk. 63.00
(ii) Tee 1 no @ Tk. 80.00 each = Tk. 80.00
Analysis of PWD SoR 2018 for Civil Works 498
26.36.5 40 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 40 mm dia G.I. pipe: 20 ft. @ Tk. 104.00 per ft = Tk. 2,080.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 82.00 each = Tk. 82.00
(ii) Tee 1 no @ Tk. 82.00 each = Tk. 82.00
(iii) Nipple 1 no @ Tk. 74.00 each = Tk. 74.00
(iv) Plug 1 no @ Tk. 37.00 each = Tk. 37.00
(v) Reducer 1 no @ Tk. 82.00 each = Tk. 82.00
(vi) Socket 1 no @ Tk. 55.00 each = Tk. 55.00
(c) Jointing & fixing materials
(i) Teflon tape 6.3 pcs @ Tk. 16.00 per pcs = Tk. 100.80
(ii) Clamp 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 3,378.80
Profit 10.00% = Tk. 337.88
Overhead 3.50% = Tk. 118.26
Total = Tk. 3,834.94
Add VAT with adjustment factor 1.06383 6.00% = Tk. 244.78
Grand Total = Tk. 4,079.72
Rate per ft = Tk. 203.99
Rate per m = Tk. 669.29
26.36.6 50 mm dia G.I. pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 50 mm dia G.I. pipe: 20 ft. @ Tk. 125.00 per ft = Tk. 2,500.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 122.00 each = Tk. 122.00
(ii) Tee 1 no @ Tk. 98.00 each = Tk. 98.00
(iii) Nipple 1 no @ Tk. 74.00 each = Tk. 74.00
(iv) Plug 1 no @ Tk. 46.00 each = Tk. 46.00
Analysis of PWD SoR 2018 for Civil Works 499
26.36.7 62 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 62 mm dia G.I. pipe: 20 ft. @ Tk. 191.00 per ft = Tk. 3,820.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 222.00 each = Tk. 222.00
(ii) Tee 1 no @ Tk. 322.00 each = Tk. 322.00
(iii) Nipple 1 no @ Tk. 176.00 each = Tk. 176.00
(iv) Plug 1 no @ Tk. 60.00 each = Tk. 60.00
(v) Reducer 1 no @ Tk. 126.00 each = Tk. 126.00
(vi) Socket 1 no @ Tk. 148.00 each = Tk. 148.00
(c) Jointing & fixing materials
(i) Teflon tape 10.5 pcs @ Tk. 16.00 per pcs = Tk. 168.00
(ii) Clamp (F.I. bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.5 no @ Tk. 600.00 each = Tk. 300.00
(ii) Skilled labour 1.5 nos @ Tk. 390.00 each = Tk. 585.00
(iii) Ordinary labour 2 nos @ Tk. 320.00 each = Tk. 640.00
Sub - Total = Tk. 6,763.00
Profit 10.00% = Tk. 676.30
Overhead 3.50% = Tk. 236.71
Total = Tk. 7,676.01
Add VAT with adjustment factor 1.06383 6.00% = Tk. 489.96
Grand Total = Tk. 8,165.97
Rate per ft = Tk. 408.30
Rate per m = Tk. 1,339.63
26.36.8 75 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 75 mm dia G.I. pipe: 20 ft. @ Tk. 215.00 per ft = Tk. 4,300.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 400.00 each = Tk. 400.00
(ii) Tee 1 no @ Tk. 322.00 each = Tk. 322.00
(iii) Nipple 1 no @ Tk. 176.00 each = Tk. 176.00
(iv) Plug 1 no @ Tk. 135.00 each = Tk. 135.00
(v) Reducer 1 no @ Tk. 153.00 each = Tk. 153.00
(vi) Socket 1 no @ Tk. 147.00 each = Tk. 147.00
Analysis of PWD SoR 2018 for Civil Works 500
26.36.9 100 mm dia G.I pipe: connection including nipple, elbow, reducers, plug, Tee etc. complete.
Considering 20 ft. long one pipe
(a) 100 mm dia G.I. pipe: 20 ft. @ Tk. 310.00 per ft = Tk. 6,200.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 612.00 each = Tk. 612.00
(ii) Tee 1 no @ Tk. 785.00 each = Tk. 785.00
(iii) Nipple 1 no @ Tk. 395.00 each = Tk. 395.00
(iv) Plug 1 no @ Tk. 252.00 each = Tk. 252.00
(v) Reducer 1 no @ Tk. 342.00 each = Tk. 342.00
(vi) Socket 1 no @ Tk. 348.00 each = Tk. 348.00
(c) Jointing & fixing materials
(i) Teflon tape 16.75 pcs @ Tk. 16.00 per pcs = Tk. 268.00
(ii) Clamp (F.I. bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
(iii) Ordinary labour 2 nos @ Tk. 320.00 each = Tk. 640.00
Sub - Total = Tk. 11,418.00
Profit 10.00% = Tk. 1,141.80
Overhead 3.50% = Tk. 399.63
Total = Tk. 12,959.43
Add VAT with adjustment factor 1.06383 6.00% = Tk. 827.20
Grand Total = Tk. 13,786.63
Rate per ft = Tk. 689.33
Rate per m = Tk. 2,261.69
(d) Labour:
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
(iii) Ordinary labour 2 nos @ Tk. 320.00 each = Tk. 640.00
Sub - Total = Tk. 3,101.50
Profit 10.00% = Tk. 310.15
Overhead 3.50% = Tk. 108.55
Total = Tk. 3,520.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 224.69
Grand Total = Tk. 3,744.89
Rate per ft = Tk. 31.21
Rate per m = Tk. 102.40
26.39.2 3/4" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 3/4" Dia PP-R Pipe 20 ft. @ Tk. 20.50 per ft = Tk. 410.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 10.50 each = Tk. 10.50
(ii) Tee 1 no @ Tk. 13.00 each = Tk. 13.00
(iii) End Cap 1 no @ Tk. 9.75 each = Tk. 9.75
(iv) Plug 1 no @ Tk. 7.50 each = Tk. 7.50
(v) Reducer 1 no @ Tk. 27.00 each = Tk. 27.00
(vi) Socket 1 no @ Tk. 8.00 each = Tk. 8.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 1,378.75
Profit 10.00% = Tk. 137.88
Overhead 3.50% = Tk. 48.26
Total = Tk. 1,564.89
Add VAT with adjustment factor 1.06383 6.00% = Tk. 99.89
Grand Total = Tk. 1,664.78
Rate per ft = Tk. 83.24
Rate per m = Tk. 273.11
26.39.3 1" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1" Dia PP-R Pipe 20 ft. @ Tk. 29.50 per ft = Tk. 590.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 17.25 each = Tk. 17.25
(ii) Tee 1 no @ Tk. 19.25 each = Tk. 19.25
(iii) End Cap 1 no @ Tk. 16.00 each = Tk. 16.00
(iv) Plug 1 no @ Tk. 14.00 each = Tk. 14.00
(v) Reducer 1 no @ Tk. 30.00 each = Tk. 30.00
(vi) Socket 1 no @ Tk. 18.00 each = Tk. 18.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 1,597.50
Profit 10.00% = Tk. 159.75
Overhead 3.50% = Tk. 55.91
Analysis of PWD SoR 2018 for Civil Works 508
26.39.4 1.25" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1.25" Dia PP-R Pipe 20 ft. @ Tk. 49.00 per ft = Tk. 980.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 58.50 each = Tk. 58.50
(ii) Tee 1 no @ Tk. 61.00 each = Tk. 61.00
(iii) End Cap 1 no @ Tk. 36.75 each = Tk. 36.75
(iv) Plug 1 no @ Tk. 36.00 each = Tk. 36.00
(v) Reducer 1 no @ Tk. 66.00 each = Tk. 66.00
(vi) Socket 1 no @ Tk. 21.75 each = Tk. 21.75
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 2,153.00
Profit 10.00% = Tk. 215.30
Overhead 3.50% = Tk. 75.36
Total = Tk. 2,443.66
Add VAT with adjustment factor 1.06383 6.00% = Tk. 155.98
Grand Total = Tk. 2,599.64
Rate per ft = Tk. 129.98
Rate per m = Tk. 426.46
26.39.5 1.5" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 1.5" Dia PP-R Pipe 20 ft. @ Tk. 61.50 per ft = Tk. 1,230.00
(b) Fittings:
(i) Elbow 1 No. @ Tk. 77.00 each = Tk. 77.00
(ii) Tee 1 No. @ Tk. 81.00 each = Tk. 81.00
(iii) End Cap 1 No. @ Tk. 93.00 each = Tk. 93.00
(iv) Plug 1 No. @ Tk. 18.00 each = Tk. 18.00
(v) Reducer 1 No. @ Tk. 102.00 each = Tk. 102.00
(vi) Socket 1 No. @ Tk. 41.00 each = Tk. 41.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar) 2 nos @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & screw 4 nos @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 2,535.00
Profit 10.00% = Tk. 253.50
Overhead 3.50% = Tk. 88.73
Total = Tk. 2,877.23
Add VAT with adjustment factor 1.06383 6.00% = Tk. 183.65
Analysis of PWD SoR 2018 for Civil Works 509
26.39.6 2" Dia PP-R Pipe : Connection including nipple, elbow, reducers, Tee etc. Complete for in-house drinking water.
Considering 20 ft. Long one pipe
(a) 2" Dia PP-R Pipe 20 ft. @ Tk. 95.00 per ft = Tk. 1,900.00
(b) Fittings:
(i) Elbow 1 no @ Tk. 137.00 each = Tk. 137.00
(ii) Tee 1 no @ Tk. 149.00 each = Tk. 149.00
(iii) End Cap 1 no @ Tk. 140.00 each = Tk. 140.00
(iv) Plug 1 no @ Tk. 20.00 each = Tk. 20.00
(v) Reducer 1 no @ Tk. 131.00 each = Tk. 131.00
(vi) Socket 1 no @ Tk. 61.00 each = Tk. 61.00
( c) Jointing & fixing Materials
(i) Teflon Tape 2 pcs @ Tk. 16.00 per pcs = Tk. 32.00
(ii) Clamp (F.I. Bar) 2 no @ Tk. 50.00 each = Tk. 100.00
(iii) Rowel Plug & screw 4 no @ Tk. 9.00 each = Tk. 36.00
(iv) Scaffolding 20 ft. @ Tk. 3.00 per ft = Tk. 60.00
(d) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 nos @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 nos @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 3,431.00
Profit 10.00% = Tk. 343.10
Overhead 3.50% = Tk. 120.09
Total = Tk. 3,894.19
Add VAT with adjustment factor 1.06383 6.00% = Tk. 248.57
Grand Total = Tk. 4,142.76
Rate per ft = Tk. 207.14
Rate per m = Tk. 679.63
(d) Labour:
(i) Plumber 0.03 no @ Tk. 600.00 each = Tk. 18.00
(ii) Skilled labour 0.08 nos @ Tk. 390.00 each = Tk. 31.20
(iii) Ordinary labour 0.06 nos @ Tk. 320.00 each = Tk. 19.20
Sub - Total = Tk. 253.40
Profit 10.00% = Tk. 25.34
Overhead 3.50% = Tk. 8.87
Total = Tk. 287.61
Add VAT with adjustment factor 1.06383 6.00% = Tk. 18.36
Grand Total = Tk. 305.97
26.45.4 uPVC waste pipe 280 mm dia wall thickness 6.9 mm - 8.6 mm for underground laying.
Considering 20 ft. long one pipe
(a) 280 mm uPVC pipe: 20 ft. @ Tk. 540.00 per ft = Tk. 10,800.00
(b) Jointing materials
(i) Solvent cement 330 ml @ Tk. 0.70 per ml = Tk. 231.00
(c) Excavation 87.5 cft @ Tk. 2,958.33 per % 0 cft = Tk. 258.85
(d) Bedding by sand (F.M. 0.8) 52.5 cft @ Tk. 1,400.00 per cft = Tk. 735.00
(e) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 12,689.85
Profit 10.00% = Tk. 1,268.99
Overhead 3.50% = Tk. 444.14
Total = Tk. 14,402.98
Add VAT with adjustment factor 1.06383 6.00% = Tk. 919.34
Grand Total = Tk. 15,322.32
Rate per ft = Tk. 766.12
Rate Per m = Tk. 2,513.64
Say, Tk. 2,514 .00 per meter
26.45.5 uPVC waste pipe 315 mm dia wall thickness 7.7 mm - 9.7 mm for underground laying
Considering 20 ft. long one pipe
(a) 315 mm uPVC pipe: 20 ft. @ Tk. 550.00 per ft = Tk. 11,000.00
(b) Jointing materials
(i) Solvent cement 330 ml @ Tk. 0.70 per ml = Tk. 231.00
(c) Excavation 87.5 cft @ Tk. 2,958.33 per % 0 cft = Tk. 258.85
(d) Bedding by sand (F.M. 0.8) 52.5 cft @ Tk. 1,400.00 per cft = Tk. 735.00
(e) Labour:
(i) Plumber 0.25 no @ Tk. 600.00 each = Tk. 150.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 12,889.85
Profit 10.00% = Tk. 1,288.99
Overhead 3.50% = Tk. 451.14
Total = Tk. 14,629.98
Add VAT with adjustment factor 1.06383 6.00% = Tk. 933.83
Grand Total = Tk. 15,563.81
Rate per ft = Tk. 778.19
Rate Per m = Tk. 2,553.24
(c) Labour:
(i) Plumber 0.09 no @ Tk. 600.00 each = Tk. 54.00
(ii) Skilled labour 0.14 no @ Tk. 390.00 each = Tk. 54.60
(iii) Ordinary labour 0.17 no @ Tk. 320.00 each = Tk. 54.40
Sub - Total = Tk. 2,304.92
Profit 10.00% = Tk. 230.49
Overhead 3.50% = Tk. 80.67
Total = Tk. 2,616.08
Add VAT with adjustment factor 1.06383 6.00% = Tk. 166.98
Grand Total = Tk. 2,783.06
Rate per No. = Tk. 2,783.06
type fancy angle stop cock 1 no @ Tk. 625.00 each = Tk. 625.00
(b) Fitting-fixing materials
(i) Teflon tape 0.53 pcs @ Tk. 16.00 per pcs = Tk. 8.48
(c) Labour:
(i) Plumber 0.0125 no @ Tk. 600.00 each = Tk. 7.50
(ii) Skilled labour 0.025 no @ Tk. 390.00 each = Tk. 9.75
(iii) Ordinary labour 0.048 no @ Tk. 320.00 each = Tk. 15.36
Sub - Total = Tk. 666.09
Profit 10.00% = Tk. 66.61
Overhead 3.50% = Tk. 23.31
Total = Tk. 756.01
Add VAT with adjustment factor 1.06383 6.00% = Tk. 48.26
Grand Total = Tk. 804.27
Rate per No. = Tk. 804.27
(ii) Nipple with jam-nuts 4 nos @ Tk. 60.00 each = Tk. 240.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
(iii) Ordinary labour 1 no @ Tk. 320.00 each = Tk. 320.00
Sub - Total = Tk. 12,667.20
Profit 10.00% = Tk. 1,266.72
Overhead 3.50% = Tk. 443.35
Total = Tk. 14,377.27
Add VAT with adjustment factor 1.06383 6.00% = Tk. 917.70
Grand Total = Tk. 15,294.97
Rate per No. = Tk. 15,294.97
26.68.2 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 300 litre capacity
Considering 1 No. of fixture
Analysis of PWD SoR 2018 for Civil Works 544
(a) 300 litreplastic water tank 1 no @ Tk. 2,550.00 each = Tk. 2,550.00
(b) Carrying up to site LS = Tk. 240.00
(c) Fitting-fixing materials
(i) Teflon tape 4.2 pcs @ Tk. 16.00 per pcs = Tk. 67.20
(ii) 3/4" dia ball cock 1 no @ Tk. 130.00 each = Tk. 130.00
(iii) Nipple with jam-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 0.5 no @ Tk. 600.00 each = Tk. 300.00
(ii) Skilled labour 0.5 no @ Tk. 390.00 each = Tk. 195.00
Sub - Total = Tk. 3,542.20
Profit 10.00% = Tk. 354.22
Overhead 3.50% = Tk. 123.98
Total = Tk. 4,020.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 256.62
Grand Total = Tk. 4,277.02
Rate per No. = Tk. 4,277.02
26.68.3 Food-grade plastic internal mini water tank for the use in kitchen, bathroom & toilet for
emergency storage and supply of water: 500 litre capacity
Considering 1 No. of fixture
(a) 500 litre plastic water tank 1 no @ Tk. 3,400.00 each = Tk. 3,400.00
(b) Carrying up to site LS = Tk. 598.40
(c) Fitting-fixing materials
(i) Teflon tape 4.2 pcs @ Tk. 16.00 per pcs = Tk. 67.20
(ii) 3/4" dia ball cock 1 no @ Tk. 130.00 each = Tk. 130.00
(iii) Nipple with jam-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 1 no @ Tk. 390.00 each = Tk. 390.00
Sub - Total = Tk. 5,245.60
Profit 10.00% = Tk. 524.56
Overhead 3.50% = Tk. 183.60
Total = Tk. 5,953.76
Add VAT with adjustment factor 1.06383 6.00% = Tk. 380.03
Grand Total = Tk. 6,333.79
Rate per No. = Tk. 6,333.79
26.69.2 Food-grade foreign made stainless steel water tank: 1000 litre capacity
Considering 1 No. of fixture
(a) 1000 litre stainless steel water tank 1 no @ Tk. 14,036.00 each = Tk. 14,036.00
(b) Carrying up to site LS = Tk. 240.00
(c) Ffitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. pipe with jum-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 320.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 16,166.00
Profit 10.00% = Tk. 1,616.60
Overhead 3.50% = Tk. 565.81
Total = Tk. 18,348.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,171.18
Grand Total = Tk. 19,519.59
Rate per No. = Tk. 19,519.59
26.69.3 Food-grade foreign made stainless steel water tank: 2000 litre capacity
Considering 1 No. of fixture
(a) 2000 litre stainless steel water tank 1 no @ Tk. 24,056.00 each = Tk. 24,056.00
(b) Carrying LS = Tk. 480.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. pipe with jum-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 480.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 26,586.00
Profit 10.00% = Tk. 2,658.60
Overhead 3.50% = Tk. 930.51
Total = Tk. 30,175.11
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,926.07
Grand Total = Tk. 32,101.18
Rate per No. = Tk. 32,101.18
26.69.4 Food-grade foreign made stainless steel water tank: 4000 litre capacity
Considering 1 No. of fixture
(a) 4000 litre stainless steel tank 1 no @ Tk. 49,191.00 each = Tk. 49,191.00
(b) Carrying up to site LS = Tk. 800.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. pipe with jum-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 640.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 52,201.00
Profit 10.00% = Tk. 5,220.10
Overhead 3.50% = Tk. 1,827.04
Total = Tk. 59,248.14
Add VAT with adjustment factor 1.06383 6.00% = Tk. 3,781.80
Grand Total = Tk. 63,029.94
Rate per No. = Tk. 63,029.94
26.69.5 Food-grade foreign made stainless steel water tank: 6000 litre capacity
Considering 1 No. of fixture
(a) 6000 litre stainless steel water tank 1 no @ Tk. 53,481.00 each = Tk. 53,481.00
(b) Carrying up to site LS = Tk. 960.00
(c) Fitting-fixing materials
(i) 1/2" ball cock 1 no @ Tk. 130.00 per ft = Tk. 130.00
(ii) 1/2" dia G.I. pipe with jum-nuts 1 no @ Tk. 60.00 each = Tk. 60.00
(iii) Other small fittings in/c out-let pipe & flange etc. LS = Tk. 800.00
(d) Labour for lifting, installation & connecting pipes
(i) Plumber 1 no @ Tk. 600.00 each = Tk. 600.00
(ii) Skilled labour 2 nos @ Tk. 390.00 each = Tk. 780.00
Sub - Total = Tk. 56,811.00
Profit 10.00% = Tk. 5,681.10
Overhead 3.50% = Tk. 1,988.39
Total = Tk. 64,480.49
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,115.78
Grand Total = Tk. 68,596.27
Rate per No. = Tk. 68,596.27
01 nos Automatic hand drier 1.00 no @ Tk. 4,500.00 each = Tk. 4,500.00
Fittings fixing materials LS = Tk. 100.00
Labour =
Skilled Technician 0.25 no @ Tk. 1,000.00 each = Tk. 250.00
Skilled Labour 0.30 no @ Tk. 390.00 each = Tk. 117.00
Ordinary Labour 0.25 no @ Tk. 320.00 each = Tk. 80.00
Others LS Tk. 250.00
Analysis of PWD SoR 2018 for Civil Works 552
26.80.2 Inspection pit of internal size: 525 x 525 mm & depth 675 to 825 mm (av. 750 mm)
for single 9" dia size RCC or 300 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3-7" x 3'-7" x 3'-0"= 38.45 cft @ Tk. 2,958.33 per % 0 cft = Tk. 113.75
2. Brick-flat soling:
1 x 3'-5" x 3'-5"= 11.7 sft @ Tk. 32.34 Per % sft = Tk. 3.78
3. C.C. (1:3:6) on soling:
1 x 3'-5" x 3'-5" x 0'-3"= 2.92 cft @ Tk. 15,428.63 per % cft = Tk. 450.52
4. C.C. (1:3:6) for invert:
1 x 1'-9" x 1'-9" x 0'-2"= 0.51 cft @ Tk. 15,428.63 per % cft = Tk. 78.69
5. Brick-work (1:6):
2 x (3'-5" + 1'-9") x 2'-6" x 0'-10"= 21.46 cft @ Tk. 14,164.00 per % cft = Tk. 3,039.59
6. 12 mm plaster with n.c.f.:
4 x (1'-9" x 2'-6") + 1'-9" x 1'-9"= 20.56 sft @ Tk. 2,158.00 per % sft = Tk. 443.68
7. Extra labour for making invert & side back-filling:
a) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
b) Skilled labour 0.2 no @ Tk. 390.00 each = Tk. 78.00
c) Ordinary labour 0.235 no @ Tk. 320.00 each = Tk. 75.20
Sub - Total = Tk. 4,358.21
Analysis of PWD SoR 2018 for Civil Works 553
26.80.3 Inspection pit of internal size: 600 x 600 mm & depth 750 to 900 mm (av. 825 mm)
for single 300mm dia size RCC or 375 mm plastic/PVC pipes
Considering 1 No. pit
1. Earth-work:
1 x 3'-11" x 3'-11" x 3'-3"= 49.94 cft @ Tk. 2,958.33 per % 0 cft = Tk. 147.74
2. Brick-flat soling:
1 x 3'-8" x 3'-8"= 13.47 sft @ Tk. 32.34 Per % sft = Tk. 4.36
3. C.C. (1:3:6) on soling:
1 x 3'-8" x 3'-8" x 0'-3"= 3.37 cft @ Tk. 15,428.63 per % cft = Tk. 519.94
4. C.C. (1:3:6) for invert:
1 x 2'-0" x 2'-0" x 0'-2"= 0.67 cft @ Tk. 15,428.63 per % cft = Tk. 103.37
5. Brick-work (1:6):
2 x (3'-8" + 2'-0") x 2'-9" x 0'-10"=
31.19 cft @ Tk. 14,164.00 per % cft = Tk. 4,417.75
6. 12 mm plaster with n.c.f.:
4 x (2'-0" x 2'-9") + 2'-6" x 2'-6"= 28.25 sft @ Tk. 2,158.00 per % sft = Tk. 609.64
7. Extra labour for making invert & side back-filling:
(a) Plumber 0.14 no @ Tk. 600.00 each = Tk. 84.00
(b) Skilled labour 0.23 no @ Tk. 390.00 each = Tk. 89.70
(c) Ordinary labour 0.27 no @ Tk. 320.00 each = Tk. 86.40
Sub - Total = Tk. 6,062.90
Profit 10.00% = Tk. 606.29
Overhead 3.50% = Tk. 212.20
Total = Tk. 6,881.39
Add VAT with adjustment factor 1.06383 6.00% = Tk. 439.24
Grand Total = Tk. 7,320.63
Rate per No. = Tk. 7,320.63
26.80.4 Master-pit of Size: 600 x 500 mm & average depth 750 mm for Septic tank.
Considering 1 No. pit
1. Earth-work:
1 x 2'-3" x 4'-0" x 3'-0"= 27.96 cft @ Tk. 2,958.33 per % 0 cft = Tk. 82.71
2. Brick-flat soling:
1 x 3'-8" x 2'-6"= 9.175 sft @ Tk. 32.34 Per % sft = Tk. 2.97
3. C.C. (1:3:6) on soling:
1 x 1'-6" x 2'-0" x 0'-3"= 0.94 cft @ Tk. 15,428.63 per % cft = Tk. 145.03
4. C.C. (1:3:6) for channel making:
1 x 1'-6" x 2'-6" x 0'-4"= 1.24 cft @ Tk. 15,428.63 per % cft = Tk. 191.32
5. Brick-work (1:6):
2 x 1'-8" x 2'-2" x 0'-10"= 6.02 cft
1 x 3' - 8" x 2' - 2" x 10" = 6.61 cft
12.63 cft @ Tk. 14,164.00 per % cft = Tk. 1,788.91
6. 12 mm plaster with n.c.f.:
(2' - 0" + 1' - 8" + 1' - 8") x 2' - 2" = 11.5661 sft
(2' - 6" + 2' - 6" + 3' - 8") x 1' - 0" = 8.67 sft
1' - 6" x 2' - 6" = 3.75 sft
23.99 sft @ Tk. 2,158.00 per % sft = Tk. 517.70
7. Extra labour for making channel & back-fill to side:
(a) Plumber 0.125 no @ Tk. 600.00 each = Tk. 75.00
(b) Skilled labour 0.125 no @ Tk. 390.00 each = Tk. 48.75
(c) Ordinary labour 0.125 no @ Tk. 320.00 each = Tk. 40.00
Analysis of PWD SoR 2018 for Civil Works 554
26.82.2 1050 x 1050 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-5" x 3'-5"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
2.48 cft @ Tk. 17,827.80 Per % cft = Tk. 442.13
2. 1% re-inforcement in/c fabrication 12.15 Ibs @ Tk. 29.74 per Ibs = Tk. 361.34
3. 12 mm plaster with n.c.f.:
4 x (3'-5" x 0'-3" + 3'-5" x 3'-5" - 0.785 x 1'-6" x 1'-6") =
13.35 sft @ Tk. 2,158.00 per % sft = Tk. 288.09
4. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 no @ Tk. 900.00 each = Tk. 900.00
5. Extra labour for placing pit cover
Ordinary labour 0.1 no @ Tk. 320.00 each = Tk. 32.00
Sub - Total = Tk. 2,023.56
Profit 10.00% = Tk. 202.36
Overhead 3.50% = Tk. 70.82
Total = Tk. 2,296.74
Add VAT with adjustment factor 1.06383 6.00% = Tk. 146.60
Grand Total = Tk. 2,443.34
Rate per No. = Tk. 2,443.34
26.82.3 1100 x 1100 x 75 mm size pit cover with 18" dia C.I. man-hole cover.
Considering 1 No. pit cover with man-hole cover
1. R.C.C. (1:2:4) for slab:
1 x (3'-8" x 3'-8"- 0.785 x 1'-6" x 1'-6") x 0'-3" =
Analysis of PWD SoR 2018 for Civil Works 556
26.83.2 525 x 525 mm and depth 675 - 825 mm, average 750 mm for single 225 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
= Tk. 7,705
Say, Tk. 7,705 .00 each
26.83.3 600 x 600 mm and depth 750 - 900 mm, average 825 mm for single 300 mm dia RCC pipes and 400 mm
dia PVC pipe with pitcover and 450 mm dia C.I. Man-hole cover
= Tk. 9,993.00
Say, Tk. 9,993 .00 each
1 x 11' - 6" x 5' - 0" x 4" = 18.98 cft @ Tk. 17,827.80 per % cft = Tk. 3,383.72
7. Formwork 70.00 sft @ Tk. 35.03 per sft = Tk. 2,452.10
8. Brick-work (1:6):
2 x 11' - 6" x 2'-0" x 10" = 38.18 cft
2 x 11' - 6" x 1'-0" x 5" = 9.66 cft
2 x (11' - 6" + 3' - 2") x 5' - 8" x 10" = 138.08 cft
Total = 185.92 cft @ Tk. 14,164.00 per % cft = Tk. 26,333.71
9. 5" thick brick-work (1:6)
1 x 2' - 6" x 3'-5" = 8.55 sft @ Tk. 7,054.25 per % sft = Tk. 603.14
10. 12 mm plaster with n.c.f.:
Floor: 1 x 9' - 0" x 2' - 6" =
22.50 sft
Walls: 2 x (9' - 0" + 2'-1") x 5' - 8" =
125.65 sft
Tie: 1 x 2' - 7" x 2' - 5" =
6.24 sft
Outside: 2 x (11'-6" + 5'-0") x 1'-6" =
49.50 sft
203.89 sft @ Tk. 2,158.00 per % sft = Tk. 4,399.95
11. RCC Tees 2 nos @ Tk. 425.00 each = Tk. 850.00
12. 40 grade re-inforcement & fabrication 432.00 Ibs @ Tk. 29.74 per Ibs = Tk. 12,847.68
13. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 2 nos @ Tk. 900.00 each = Tk. 1,800.00
14. Side filling, dressing, inside cleaning etc. LS = Tk. 960.00
Sub - Total = Tk. 70,392.51
Profit 10.00% = Tk. 7,039.25
Overhead 3.50% = Tk. 2,463.74
Total = Tk. 79,895.50
Add VAT with adjustment factor 1.06383 6.00% = Tk. 5,099.71
Grand Total = Tk. 84,995.21
Rate per No. = Tk. 84,995.21
(excluding cost of re-inforcement) 14.78 cft @ Tk. 17,827.80 per % cft = Tk. 2,634.95
3. 10" Honeycomb brick-work (1:6) in cement mortar
(87.57% of solid b/work). 113.95 cft @ Tk. 12,403.41 per % cft = Tk. 14,133.69
4. 10" solid brick-work (1:6) 117.75 cft @ Tk. 14,164.00 per % cft = Tk. 16,678.11
5. R.C.C. (1:2:4) in curb well with 1.25% re-inforcement
(excluding cost of reinforcement) 11.52 cft @ Tk. 17,827.80 per % cft = Tk. 2,053.76
6. 40 grade re-inforcement &
fabrication 1.25% 161.09 Ibs @ Tk. 29.74 per Ibs = Tk. 4,790.82
7. 18" dia water sealed heavy type C.I. man-hole cover with locking
arrangement in/c making holes. 1 no @ Tk. 900.00 each = Tk. 900.00
8. Supply and filling graded
khoa and sand. 295 cft @ Tk. 94.02 per cft = Tk. 27,735.90
Sub - Total = Tk. 71,281.41
Profit 10.00% = Tk. 7,128.14
Overhead 3.50% = Tk. 2,494.85
Total = Tk. 80,904.40
Add VAT with adjustment factor 1.06383 6.00% = Tk. 5,164.11
Grand Total = Tk. 86,068.51
Rate per No. = Tk. 86,068.51
khoa and sand. 188.4 cft @ Tk. 94.02 per cft = Tk. 17,713.37
Sub - Total = Tk. 53,352.47
Profit 10.00% = Tk. 5,335.25
Overhead 3.50% = Tk. 1,867.34
Total = Tk. 60,555.06
Add VAT with adjustment factor 1.06383 6.00% = Tk. 3,865.22
Grand Total = Tk. 64,420.28
Rate per No. = Tk. 64,420.28
27.4.1.2 Development using 2 test tube-wells 150% = Say, Tk. 10,536 .00
27.4.1.3 Development using 3 test tube-wells 200% = Say, Tk. 14,048 .00
Analysis of PWD SoR 2018 for Civil Works 570
27.4.2.1 For 1 test tube-wells 115% Say, Tk. 40 .00 per meter
27.4.2.2 For 2 test tube-wells 115% Say, Tk. 61 .00 per meter
27.4.2.3 For 3 test tube-wells 115% Say, Tk. 81 .00 per meter
(1) Cost for furnishing design of tube-well considering 2 bore = Tk. 22,400.00
(2) Testing of water collected from 2 test bore = Tk. 21,200.00
(3) Sieve analysis for sand
from different layers 6 tests @ Tk. 1,200.00 per test = Tk. 7,200.00
(3) Maintaining the bore holes and tools and plants etc. at site untill
satisfactory results are obtained from laboratory, filling and sealing
the bore holes 2 nos @ Tk. 4,800.00 per test bore = Tk. 9,600.00
Sub - Total Tk. 60,400.00
Profit 10.00% = Tk. 6,040.00
Overhead 3.50% = Tk. 2,114.00
Total = Tk. 68,554.00
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,375.79
Grand Total = Tk. 72,929.79
(1) Cost for furnishing design of tube-well considering 3 bore = Tk. 33,600.00
Analysis of PWD SoR 2018 for Civil Works 571
PRODUCTION WELL
27.13.2 Development of tube well for the depth beyond 200 m: = Tk. 29,477.87
27.21.2 Development of tube well for the depth beyond 200 m: = Tk. 37,702.26
(b) Making slot and cleaning 1 meter @ Tk. 38.40 per meter = Tk. 38.40
(c) Carriage of materials LS = Tk. 25.60
Sub - Total = Tk. 709.83
Profit 10.00% = Tk. 70.98
Overhead 3.50% = Tk. 24.84
Total = Tk. 805.65
Add VAT with adjustment factor 1.06383 6.00% = Tk. 51.42
Grand Total = Tk. 857.07
Rate per rm = Tk. 857.07
27.29.2 Development of tube well for the depth beyond 200 m: = Tk. 46,271.95
27.37.2 Development of tube well for the depth beyond 200 m: = Tk. 52,251.55
Say, Tk. 52,252 .00 each
(b) Fuel: @ 4.375 liter per hour 315 liter @ Tk. 89.00 per liter = Tk. 28,035.00
(c) Foreman: @ 1 No. per 8 hrs 9 nos @ Tk. 800.00 each = Tk. 7,200.00
(d) Skilled labour 6 nos @ Tk. 390.00 each = Tk. 2,340.00
(e) Local carriage, T & P LS = Tk. 1,120.00
Sub - Total = Tk. 66,757.00
Profit 10.00% = Tk. 6,675.70
Overhead 3.50% = Tk. 2,336.50
Total = Tk. 75,769.20
Add VAT with adjustment factor 1.06383 6.00% = Tk. 4,836.33
Grand Total = Tk. 80,605.53
Rate per hour = Tk. 1,119.52
27.45.2 Development of tube well for the depth beyond 200 m: = Tk. 52,251.55
27.52.2 Development of tube well for the depth beyond 200 m: = Tk. 47,942.85
@ 4.8 liter per hour 345 liter @ Tk. 89.00 per liter = Tk. 30,705.00
(c) Foreman: @ 1 No. per 8 hrs 9 nos @ Tk. 800.00 each = Tk. 7,200.00
(d) Skilled labour 6 nos @ Tk. 390.00 each = Tk. 2,340.00
(e) Local carriage, T & P LS = Tk. 1,120.00
Sub - Total = Tk. 71,431.48
Profit 10.00% = Tk. 7,143.15
Overhead 3.50% = Tk. 2,500.10
Total = Tk. 81,074.73
Add VAT with adjustment factor 1.06383 6.00% = Tk. 5,174.98
Grand Total = Tk. 86,249.71
Rate per hour = Tk. 1,197.91
(b) Carriage, welding, fabrication and other necessary cost LS = Tk. 384.00
Sub - Total = Tk. 1,486.80
Profit 10.00% = Tk. 148.68
Overhead 3.50% = Tk. 52.04
Total = Tk. 1,687.52
Add VAT with adjustment factor 1.06383 6.00% = Tk. 107.71
Grand Total = Tk. 1,795.23
Rate each. = Tk. 1,795.23
27.59.2 Development of tube well for the depth beyond 200 m: = Tk. 26,375.07
27.66.2 Development of tube well for the depth beyond 200 m: = Tk. 35,607.69
27.73.2 Development of tube well for the depth beyond 200 m: = Tk. 43,701.29
DIVISION 30 : CONCRETE HOLLOW BLOCK, FACINGS AND PAVING STONE, NON FIRE BLOCK
Item No.- 30.1
70 mm thick non-load bearing partition wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration 100 sft of work
(a) Material
(i) 70 mm block (390 x 70 x 190 mm)
in/c wastage 116 nos @ Tk. 24.00 per block = Tk. 2,784.00
(ii) Cement 0.4 bag @ Tk. 395.00 per bag = Tk. 158.00
(iii) Lime 11.25 kg @ Tk. 20.00 per kg = Tk. 225.00
(iv) Sand (F.M. 1.2) 3.00 cft @ Tk. 1,400.00 per % cft = Tk. 42.00
(v) Transportation of block 116 nos @ Tk. 3.66 each = Tk. 424.56
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1 no @ Tk. 500.00 each = Tk. 500.00
(iii) Ordinary Labour 2.5 nos @ Tk. 320.00 each = Tk. 800.00
(c) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(d) Local carriage, curing & sundries etc LS. = Tk. 160.00
Sub - Total = Tk. 5,378.56
Profit 10.00% = Tk. 537.86
Overhead 3.50% = Tk. 188.25
Total = Tk. 6,104.67
Add VAT with adjustment factor 1.06383 6.00% = Tk. 389.66
Grand Total = Tk. 6,494.33
Rate per sft = Tk. 64.94
30.1.1 Ground floor Rate per sqm = Tk. 699.01
30.1.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) per sqm = Tk. 31
30.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.1.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.2.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) per sqm = Tk. 31
30.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.2.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
Item No.- 30.3
90 mm thick non-load bearing partition wall with concrete hollow block:
cement : lime : sand (1 : 1 : 6)
Consideration for 100 sft
(a) Material
(i) 90 mm block (390 x 90 x 190 mm)
in/c wastage 116 nos @ Tk. 36.00 per block = Tk. 4,176.00
(ii) Cement 0.5 bag @ Tk. 395.00 per bag = Tk. 197.50
(iii) Lime 11.25 kg @ Tk. 20.00 per kg = Tk. 225.00
(iv) Sand (F.M. 1.2) 3.80 cft @ Tk. 1,400.00 per % cft = Tk. 53.20
(v) Transportation of block 116 nos @ Tk. 3.00 each = Tk. 348.00
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1 no @ Tk. 500.00 each = Tk. 500.00
(iii) Ordinary Labour 2.75 nos @ Tk. 320.00 each = Tk. 880.00
(c) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(d) Local carriage, curing & sundries etc LS. = Tk. 160.00
Sub - Total = Tk. 6,824.70
Profit 10.00% = Tk. 682.47
Overhead 3.50% = Tk. 238.86
Total = Tk. 7,746.03
Add VAT with adjustment factor 1.06383 6.00% = Tk. 494.43
Grand Total = Tk. 8,240.46
Rate per sft = Tk. 82.40
30.3.1 Ground floor Rate per sqm = Tk. 886.95
30.3.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) per sqm = Tk. 31
30.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.3.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
Item No.- 30.4
90 mm thick non-load bearing partition wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration 100 sft of work
(a) Material
(i) 90 mm block (390 x 90 x 190 mm)
in/c wastage 116 nos @ Tk. 53.00 per block = Tk. 6,148.00
(ii) Cement 0.6 bag @ Tk. 395.00 per bag = Tk. 237.00
(iii) Mortar mix 0.018 liter @ Tk. 281.08 per liter = Tk. 5.06
(iv) Sand (F.M. 1.2) 4.50 cft @ Tk. 1,400.00 per % cft = Tk. 63.00
(v) Transportation of block 116 nos @ Tk. 3.00 each = Tk. 348.00
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1 no @ Tk. 500.00 each = Tk. 500.00
(iii) Ordinary Labour 2.75 nos @ Tk. 320.00 each = Tk. 880.00
(c) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(d) Local carriage, curing & sundries etc LS. = Tk. 160.00
Sub - Total = Tk. 8,626.06
Profit 10.00% = Tk. 862.61
Overhead 3.50% = Tk. 301.91
Total = Tk. 9,790.58
Add VAT with adjustment factor 1.06383 6.00% = Tk. 624.93
Grand Total = Tk. 10,415.51
Rate per sft = Tk. 104.16
30.4.1 Ground floor Rate per sqm = Tk. 1,121.18
30.4.2 Add for each addl. floor up to 5th floor (@ 0.75 No. lab. per % sft) per sqm = Tk. 31
30.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.4.4 Add for each addl floor for 10th floor and above (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.5.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) per sqm = Tk. 42
30.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 52
30.5.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
Item No.- 30.6
140 mm thick non-load bearing external wall with concrete hollow block:
cement : sand (1 : 6) with mortar mix.
Consideration 100 sft of work
(a) Material
(i) 140 mm block (390 x 140 x 190 mm)
in/c wastage 116 nos @ Tk. 53.00 per block = Tk. 6,148.00
(ii) Cement 0.8 bag @ Tk. 395.00 per bag = Tk. 316.00
(iii) Mortar mix 0.024 liter @ Tk. 281.08 per liter = Tk. 6.75
(iv) Sand (F.M. 1.2) 6.00 cft @ Tk. 1,400.00 per % cft = Tk. 84.00
(iv) Transportation of block 116 nos @ Tk. 7.87 each = Tk. 912.92
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1.5 nos @ Tk. 500.00 each = Tk. 750.00
(iii) Ordinary Labour 3.25 nos @ Tk. 320.00 each = Tk. 1,040.00
(c) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(d) Local carriage, curing & sundries etc. LS. = Tk. 160.00
Sub - Total = Tk. 9,702.67
Profit 10.00% = Tk. 970.27
Overhead 3.50% = Tk. 339.59
Total = Tk. 11,012.53
Add VAT with adjustment factor 1.06383 6.00% = Tk. 702.93
Grand Total = Tk. 11,715.46
Rate per sft = Tk. 117.15
30.6.1 Ground floor Rate per sqm = Tk. 1,261.00
30.6.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) per sqm = Tk. 42
30.6.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 52
30.6.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.7.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) per sqm = Tk. 42
30.7.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 52
30.7.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.8.2 Add for each addl. floor up to 5th floor (@ 1 lab. per % sft) per sqm = Tk. 42
30.8.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 52
30.8.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.10.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 52
30.10.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft) per sqm = Tk. 62
30.10.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft) per sqm = Tk. 73
Item No.30.11.1
Sand Cement Hollow Block (SCHB) for Internal Wall
30.11.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % sft) per sqm = Tk. 25.00
30.11.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % sft) per sqm = Tk. 37.00
30.11.4 Add for each addl floor for 10th floor and above (@ 1.75 nos lab. per % sft) per sqm = Tk. 45.00
30.12.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % pc.) each = Tk. 4
30.12.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 No. lab. per % pc.) each = Tk. 5
30.12.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % pcs) each = Tk. 6
30.13.2 Add for each addl. floor up to 5th floor (@ 1.25 No. lab. per % pc.) each = Tk. 5
30.13.3 Add for each addl floor for 6th floor to 9th floor (@ 1.5 No. lab. per % pc.) each = Tk. 9
30.13.4 Add for each addl floor for 6th floor to 9th floor (@ 1.75 No. lab. per % pc.) each = Tk. 10
30.14.2 Add for each addl. floor up to 5th floor (1/3 lab. per % sft) per sqm = Tk. 14
30.14.3 Add for each addl. from 6th floor to 9th floor (1/2 lab. per % sft) per sqm = Tk. 21
30.14.4 Add for each addl. floor above 9th floor (2/3 lab. per % sft) per sqm = Tk. 28
(d) Local carriage, storage & sundries etc. LS. = Tk. 96.00
Sub - Total = Tk. 8,267.28
Profit 10.00% = Tk. 826.73
Overhead 3.50% = Tk. 289.35
Total = Tk. 9,383.36
Add VAT with adjustment factor 1.06383 6.00% = Tk. 598.94
Grand Total = Tk. 9,982.30
Rate per sft = Tk. 99.82
Rate per sqm = Tk. 1,074.46
(b) Labour
(i) Head mason 0.1 no @ Tk. 600.00 each = Tk. 60.00
(ii) Mason 1 no @ Tk. 500.00 each = Tk. 500.00
(iii) Ordinary Labour 2 nos @ Tk. 320.00 each = Tk. 640.00
(d) Tools & machinery 100 sft @ Tk. 3.20 per sft = Tk. 320.00
(e) Local carriage, storage & sundries etc. LS. = Tk. 96.00
Sub - Total = Tk. 13,699.28
Profit 10.00% = Tk. 1,369.93
Overhead 3.50% = Tk. 479.47
Total = Tk. 15,548.68
Add VAT with adjustment factor 1.06383 6.00% = Tk. 992.47
Grand Total = Tk. 16,541.15
Rate per sft = Tk. 165.41
Rate per sqm = Tk. 1,780.47
30.19.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.19.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.19.1.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.19.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.19.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.19.2.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
Analysis of PWD SoR 2018 for Civil Works 649
30.20.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.20.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.20.1.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.20.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.20.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.20.2.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
Item No.30.21
Sand-Cement Solid Block (1:6) Wall
30.21.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 32.00
30.21.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 40.00
30.21.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 50.00
30.22.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 18.00
30.22.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 24.00
30.22.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 28.00
Item No.--30.23
Compressed Stabilized Earth Block (1:6) (CSEB) Wall
30.23.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 30.00
30.23.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 39.00
30.23.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 50.00
Item No.-30.24
Soil-Cement Stabilization bed for Floor & Foundation
30.26.1.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.26.1.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.26.1.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.26.2.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.26.2.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.26.2.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
(a) Materials
(i) Grey split cladding block in/c wastage 220 nos @ Tk. 16.61 each = Tk. 3,654.20
(ii) Cement 2.60 bags @ Tk. 395.00 per bag = Tk. 1,027.00
(iii) Sand 16.25 cft @ Tk. 1,400.00 per % cft = Tk. 227.50
(iv) Transportation 220 nos @ Tk. 2.00 each = Tk. 440.00
(b) Labour
(i) Cladding work in/c screening sand & curing 100 sft @ Tk. 24.90 per sft = Tk. 2,490.00
(ii) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(iii) Tools and machinery 100 sft @ Tk. 3.20 per sft Tk. 320.00
(iv) Labour for local carriagesundries etc. 0.75 no @ Tk. 320.00 each = Tk. 240.00
Sub - Total = Tk. 8,623.70
Profit 10.00% = Tk. 862.37
Overhead 3.50% = Tk. 301.83
Total = Tk. 9,787.90
Add VAT with adjustment factor 1.06383 6.00% = Tk. 624.76
Grand Total = Tk. 10,412.66
Rate per sft = Tk. 104.13
30.26.3.1 Ground floor Rate per sqm = Tk. 1,120.86
30.26.3.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.26.3.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.26.3.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
30.26.4.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.26.4.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.26.4.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
(iii) Sand 12.5 cft @ Tk. 1,400.00 per % cft = Tk. 175.00
(iv) Transportation 67 nos @ Tk. 2.00 each = Tk. 134.00
(b) Labour
(i) Cladding work in/c screening sand & curing 100 sft @ Tk. 19.52 per sft = Tk. 1,952.00
(ii) Scaffolding 25 sft @ Tk. 9.00 per sft = Tk. 225.00
(iii) Tools and machinery 100 sft @ Tk. 3.20 per sft Tk. 320.00
(iv) Labour for local carriagesundries etc. 0.75 no @ Tk. 320.00 each = Tk. 240.00
Sub - Total = Tk. 6,195.07
Profit 10.00% = Tk. 619.51
Overhead 3.50% = Tk. 216.83
Total = Tk. 7,031.41
Add VAT with adjustment factor 1.06383 6.00% = Tk. 448.81
Grand Total = Tk. 7,480.22
Rate per sft = Tk. 74.80
30.26.5.1 Ground floor Rate per sqm = Tk. 805.15
30.26.5.2 Add for each addl. floor up to 5th floor (@ 1 No. lab. per % sft) per sqm = Tk. 42
30.26.5.3 Add for each addl floor for 6th floor to 9th floor (@ 1.25 nos lab. per % sft) per sqm = Tk. 52
30.26.5.4 Add for each addl floor for 10th floor and above (@ 1.5 nos lab. per % sft) per sqm = Tk. 62
Item No.- 30.27.1
Providing 418 x 330 x 17 mm red/brown colour roof tiles on prefabricated truss
Consideration of 100 nos
(a) Materials
(i) Red/brown colour concrete
roof tiles in/c wastage 102.0 nos @ Tk. 150.00 each = Tk. 15,300.00
(ii) J-hook with nut & washer 60.00 nos @ Tk. 10.35 each = Tk. 621.00
(iii) Transportation 102 nos @ Tk. 3.45 each = Tk. 351.90
(b) Labour
(i) Lifting & placing on shutter 102.0 nos @ Tk. 3.20 per sft = Tk. 326.40
(c) Tools and machinery for 102.0 nos @ Tk. 4.80 per sft Tk. 489.60
Sub - Total = Tk. 17,088.90
Profit 10.00% = Tk. 1,708.89
Overhead 3.50% = Tk. 598.11
Total = Tk. 19,395.90
Add VAT with adjustment factor 1.06383 6.00% = Tk. 1,238.04
Grand Total = Tk. 20,633.94
Rate each. = Tk. 206.34
c) Collection of disturbed/ undisturbed samples, visual soil classification & mentioned relevent lab test
(i) Collection of disturbed/undisturbed samples 10 nos @ Tk. 150.00 each = Tk. 1,500.00
(ii) Visual Soil Classification 10 nos @ Tk. 150.00 each = Tk. 1,500.00
(iii) Sp. Gravity test 4 nos @ Tk. 125.00 each = Tk. 500.00
(iv) Grain Size Analysis 4 nos @ Tk. 1,200.00 each = Tk. 4,800.00
(v) Ground Water table location 1 no @ Tk. 500.00 each = Tk. 500.00
(vi) Unconfined Compression Test 2 nos @ Tk. 1,500.00 each = Tk. 3,000.00
Analysis of PWD SoR 2018 for Civil Works 657
(vii) Atterberg Limit Test 2 nos @ Tk. 600.00 each = Tk. 1,200.00
(viii) Direct Shear Test 1 no @ Tk. 1,200.00 each = Tk. 1,200.00
(ix) Natural Moisture Content 1 no @ Tk. 200.00 each = Tk. 200.00
(x) Unit Weight(Wet/Dry) 1 no @ Tk. 250.00 each = Tk. 250.00
Sub-Total = Tk. 14,650.00
in/c boatman & helper, 1 no @ Tk. 1,000.00 Per day = Tk. 1,000.00
(v) Tools & plant, sundries, consumables, local LS = Tk. 1,280.00
carrying Sub - Total = Tk. 5,568.50
Profit 10.00% = Tk. 556.85
Overhead 3.50% = Tk. 194.90
Total = Tk. 6,320.25
Add VAT with adjustment factor 1.06383 6.00% = Tk. 403.42
Grand Total = Tk. 6,723.67
Re-use to other bore point 0.8 Rate per Point = Tk. 5,378.94
31.6.2 Additional charge per km outside Dhaka city (two ways) for mobilization & demobilization
Additional charge per km outside Dhaka city (two ways) for mobilization & demobilization = Tk. 160.00
Profit 10% = Tk. 16.00
Overhead 3.50% = Tk. 5.60
Total = Tk. 181.60
Add VAT with adjustment factor 1.06383 6.00% = Tk. 10.63
Grand Total = Tk. 192.23
(a) Skilled labour 1.25 nos @ Tk. 390.00 each = Tk. 487.50
(b) Ordinary labour 1.25 nos @ Tk. 320.00 each = Tk. 400.00
(c) Brooming, cleaning etc. LS = Tk. 32.00
(d) T & P, scaffolding, ladder, sundries etc. LS = Tk. 160.00
SubTotal = Tk. 1,079.50
Contractor's profit 10% = Tk. 107.95
Overhead expenses 3.50% = Tk. 37.78
Total = Tk. 1,225.23
VAT with adjustment factor 1.06383 6.00% = Tk. 78.21
Grand Total = Tk. 1,303.44
Rate per cum = Tk. 434.48
(a) Skilled labour 0.50 nos @ Tk. 390.00 each = Tk. 195.00
(b) Ordinary labour 0.50 nos @ Tk. 320.00 each = Tk. 160.00
(c) Brooming, cleaning etc. LS = Tk. 16.00
(d) T & P, scaffolding, ladder, sundries etc. LS = Tk. 64.00
SubTotal = Tk. 435.00
Contractor's profit 10% = Tk. 43.50
Analysis of PWD SoR 2018 for Civil Works 664
(a) Skilled labour 1.50 nos @ Tk. 390.00 each = Tk. 585.00
(b) Ordinary labour 1.00 no @ Tk. 320.00 each = Tk. 320.00
(c) Brooming, cleaning etc. LS = Tk. 32.00
(d) T & P, sundries etc. LS = Tk. 160.00
SubTotal = Tk. 1,097.00
Contractor's profit 10% = Tk. 109.70
Overhead expenses 3.50% = Tk. 38.40
Total = Tk. 1,245.10
VAT with adjustment factor 1.06383 6.00% = Tk. 79.47
Grand Total = Tk. 1,324.57
Rate per cum = Tk. 1,324.57
(a) Skilled labour 3.00 nos @ Tk. 390.00 each = Tk. 1,170.00
(b) Ordinary labour 2.00 no @ Tk. 320.00 each = Tk. 640.00
(c) Scaffolding 2.50 sqm @ Tk. 96.84 per sqm = Tk. 242.10
(d) Brooming, cleaning etc. LS = Tk. 80.00
(e) T & P, sundries etc. LS = Tk. 640.00
SubTotal = Tk. 2,772.10
Contractor's profit 10% = Tk. 277.21
Overhead expenses 3.50% = Tk. 97.02
Total = Tk. 3,146.33
VAT with adjustment factor 1.06383 6.00% = Tk. 200.83
Grand Total = Tk. 3,347.16
Rate per cum = Tk. 3,347.16
(a) Skilled labour 1.00 nos @ Tk. 390.00 each = Tk. 390.00
(b) Ordinary labour 2.00 no @ Tk. 320.00 each = Tk. 640.00
(c) Scaffolding 2.50 sqm @ Tk. 96.84 per sqm = Tk. 242.10
(d) Brooming, cleaning etc. LS = Tk. 80.00
(e) T & P, sundries etc. LS = Tk. 160.00
SubTotal = Tk. 1,512.10
Contractor's profit 10% = Tk. 151.21
Overhead expenses 3.50% = Tk. 52.92
Total = Tk. 1,716.23
VAT with adjustment factor 1.06383 6.00% = Tk. 109.55
Grand Total = Tk. 1,825.78
Rate per cum = Tk. 182.58
(a) Skilled labour 2.50 nos @ Tk. 390.00 each = Tk. 975.00
(b) Ordinary labour 1.00 no @ Tk. 320.00 each = Tk. 320.00
(c) Scaffolding/safety prop etc. 2.50 sqm @ Tk. 118.36 per sqm = Tk. 295.90
(d) Brooming, cleaning etc. LS = Tk. 80.00
(e) T & P, sundries etc. LS = Tk. 640.00
SubTotal = Tk. 2,310.90
Contractor's profit 10% = Tk. 231.09
Overhead expenses 3.50% = Tk. 80.88
Total = Tk. 2,622.87
VAT with adjustment factor 1.06383 6.00% = Tk. 167.42
Grand Total = Tk. 2,790.29
Rate per cum = Tk. 2,790.29
(a) Ordinary labour 3.00 nos @ Tk. 320.00 each = Tk. 960.00
(c) T & P, sundries etc. LS = Tk. 96.00
SubTotal = Tk. 1,056.00
Contractor's profit 10% = Tk. 105.60
Overhead expenses 3.50% = Tk. 36.96
Total = Tk. 1,198.56
VAT with adjustment factor 1.06383 6.00% = Tk. 76.50
Grand Total = Tk. 1,275.06
Rate per % 0 nos = Tk. 1,275.06
(a) Ordinary labour 2.00 nos @ Tk. 320.00 each = Tk. 640.00
(c) T & P, sundries etc. LS = Tk. 32.00
SubTotal = Tk. 672.00
Contractor's profit 10% = Tk. 67.20
Overhead expenses 3.50% = Tk. 23.52
Total = Tk. 762.72
VAT with adjustment factor 1.06383 6.00% = Tk. 48.68
Grand Total = Tk. 811.40
Rate per % 0 nos = Tk. 811.40
Considering 1 cum
(a) Skilled labour 1.00 nos @ Tk. 390.00 each = Tk. 390.00
(b) White cement LS = Tk. 32.00
(c) Colour LS Tk. 32.00
(d) T & P, sundries, curing etc. ` LS = Tk. 80.00
SubTotal = Tk. 534.00
Contractor's profit 10% = Tk. 53.40
Overhead expenses 3.50% = Tk. 18.69
Total = Tk. 606.09
VAT with adjustment factor 1.06383 6.00% = Tk. 38.69
Grand Total = Tk. 644.78
Rate per sqm = Tk. 64.48
(a) brick chips 0.0285 cum @ Tk. 2,944.12 per cum = Tk. 83.91
(b) Stone lime 6.14 kg @ Tk. 16.00 per kg = Tk. 98.24
(c) Surki 0.013 cum @ Tk. 1,250.00 per cum = Tk. 16.25
(d) Mason 0.50 no @ Tk. 500.00 each = Tk. 250.00
(e) Skilled labour 0.50 no @ Tk. 390.00 each = Tk. 195.00
(f) Ordinary labour 0.50 no @ Tk. 320.00 each = Tk. 160.00
Analysis of PWD SoR 2018 for Civil Works 669
(a) Labour for taking out Chowkat Same as Item No. 32.17 = Tk. 227.00
(b) Labour for re-fitting or refixing in position
i) Mason 0.25 no @ Tk. 500.00 each = Tk. 125.00
ii) Ordinary labour 0.25 no @ Tk. 320.00 each = Tk. 80.00
iii) Carpenter for repair 0.25 no @ Tk. 600.00 each = Tk. 150.00
(c) Screws LS Tk. 32.00
(d) Paint on clamp & side of Chowkat in contact woth wall LS = Tk. 64.00
(e) T & P, sundries etc. LS = Tk. 32.00
SubTotal = Tk. 710.00
Contractor's profit 10% = Tk. 71.00
Overhead expenses 3.50% = Tk. 24.85
Total = Tk. 805.85
VAT with adjustment factor 1.06383 6.00% = Tk. 51.44
Grand Total = Tk. 857.29
Rate per No. = Tk. 857.29
(a) Cost of glass in/c 15% wastage 1.05 sqm @ Tk. 430.40 sqm = Tk. 451.92
(b) Cost of bead and putty LS = Tk. 59.97
(c) Labour for cleaning LS = Tk. 80.00
Analysis of PWD SoR 2018 for Civil Works 674
(a) Cost of glass in/c 15% wastage 1.05 sqm @ Tk. 710.16 per sqm = Tk. 745.67
(b) Cost of bead and putty /neoprene/sealant LS = Tk. 54.27
(c) Labour LS = Tk. 80.00
(d) T & P, sundries etc. LS = Tk. 32.00
SubTotal = Tk. 911.94
Contractor's profit 10% = Tk. 91.19
Overhead expenses 3.50% = Tk. 31.92
Total = Tk. 1,035.05
VAT with adjustment factor 1.06383 6.00% = Tk. 66.07
Grand Total = Tk. 1,101.12
Rate per sqm = Tk. 1,101.12
(a) Net in/c lap & wastage 4.50 sqm @ Tk. 100.00 per sqm = Tk. 450.00
(b) Nails, screws etc. LS = Tk. 33.33
(c) 6" long clamps 4.00 nos @ Tk. 30.00 each = Tk. 120.00
(d) Labour charge for fitting-fixing 4.00 sqm @ Tk. 375.00 LS = Tk. 1,500.00
(e) T & P, scaffolding & sundries LS = Tk. 80.00
SubTotal = Tk. 2,183.33
Contractor's profit 10% = Tk. 218.33
Overhead expenses 3.50% = Tk. 76.42
Total = Tk. 2,478.08
VAT with adjustment factor 1.06383 6.00% = Tk. 158.18
Grand Total = Tk. 2,636.26
Rate per sqm = Tk. 659.07
(a) Net in/c lap & wastage 4.50 sqm @ Tk. 140.00 per sqm = Tk. 630.00
(b) Nails, screws etc. LS = Tk. 33.33
(c) 6" long clamps 4.00 nos @ Tk. 30.00 each = Tk. 120.00
(d) Labour charge for fitting-fixing 4.00 sqm @ Tk. 375.00 LS = Tk. 1,500.00
(e) T & P, scaffolding & sundries LS = Tk. 80.00
Sub Total = Tk. 2,363.33
Contractor's profit 10% = Tk. 236.33
Overhead expenses 3.50% = Tk. 82.72
Total = Tk. 2,682.38
VAT with adjustment factor 1.06383 6.00% = Tk. 171.22
Grand Total = Tk. 2,853.60
Rate per sqm = Tk. 713.40
(a) Net including lap & wastage 1.75 sqm @ Tk. 100.00 per kg = Tk. 175.00
(b) Nails, screws etc. LS = Tk. 13.33
(c) Labour charge 1.50 sqm @ Tk. 375.00 LS = Tk. 562.50
(e) T & P, scaffolding & sundries LS = Tk. 32.00
SubTotal = Tk. 782.83
Contractor's profit 10% = Tk. 78.28
Overhead expenses 3.50% = Tk. 27.40
Total = Tk. 888.51
VAT with adjustment factor 1.06383 6.00% = Tk. 56.71
Grand Total = Tk. 945.22
Rate per sqm = Tk. 630.15
(a) Net in/c wastage 1.75 sqm @ Tk. 100.00 per kg = Tk. 175.00
(b) Nails, screws etc. LS = Tk. 13.33
Analysis of PWD SoR 2018 for Civil Works 676
(a) Hard board in/c wastage 1.05 no @ Tk. 600.00 each = Tk. 630.00
(b) Nails, screws, clamps etc. LS = Tk. 40.00
(c) Labour charge 2.98 sqm @ Tk. 225.00 each = Tk. 670.50
(d) T & P, scaffolding & sundries LS = Tk. 80.00
SubTotal = Tk. 1,420.50
Contractor's profit 10% = Tk. 142.05
Overhead expenses 3.50% = Tk. 49.72
Total = Tk. 1,612.27
VAT with adjustment factor 1.06383 6.00% = Tk. 102.91
Grand Total = Tk. 1,715.18
Rate per sqm = Tk. 575.56
(a) 75 mm long catch hook 1.00 no @ Tk. 4.00 each = Tk. 4.00
(b) Labour charge LS = Tk. 7.50
SubTotal = Tk. 11.50
Contractor's profit 10% = Tk. 1.15
Overhead expenses 3.50% = Tk. 0.40
Analysis of PWD SoR 2018 for Civil Works 678
(a) 100 mm long catch hook 1.00 no @ Tk. 6.00 each = Tk. 6.00
(b) Labour charge LS = Tk. 7.50
SubTotal = Tk. 13.50
Contractor's profit 10% = Tk. 1.35
Overhead expenses 3.50% = Tk. 0.47
Total = Tk. 15.32
VAT with adjustment factor 1.06383 6.00% = Tk. 0.98
Grand Total = Tk. 16.30
Rate for each = Tk. 16.30
(a) 150 mm long catch hook 1.00 no @ Tk. 8.00 each = Tk. 8.00
(b) Labour charge LS = Tk. 7.50
SubTotal = Tk. 15.50
Contractor's profit 10% = Tk. 1.55
Overhead expenses 3.50% = Tk. 0.54
Total = Tk. 17.59
VAT with adjustment factor 1.06383 6.00% = Tk. 1.12
Grand Total = Tk. 18.71
Rate for each = Tk. 18.71
(a) 200 mm long catch hook 1.00 no @ Tk. 10.00 each = Tk. 10.00
(b) Labour charge LS = Tk. 7.50
SubTotal = Tk. 17.50
Contractor's profit 10% = Tk. 1.75
Overhead expenses 3.50% = Tk. 0.61
Total = Tk. 19.86
VAT with adjustment factor 1.06383 6.00% = Tk. 1.27
Grand Total = Tk. 21.13
Rate for each = Tk. 21.13
(a) 225 mm long catch hook 1.00 no @ Tk. 15.00 each = Tk. 15.00
(b) Labour charge LS = Tk. 7.50
SubTotal = Tk. 22.50
Analysis of PWD SoR 2018 for Civil Works 679
(a) 75 mm long iron hinge 1.00 no @ Tk. 25.00 each = Tk. 25.00
(b) 12 mm long screws 0.50 dz. @ Tk. 8.00 per dz. = Tk. 4.00
(c) Labour charge LS = Tk. 9.38
SubTotal = Tk. 38.38
Contractor's profit 10% = Tk. 3.84
Overhead expenses 3.50% = Tk. 1.34
Total = Tk. 43.56
VAT with adjustment factor 1.06383 6.00% = Tk. 2.78
Grand Total = Tk. 46.34
Rate for each = Tk. 46.34
(a) 100 mm long iron hinge 1.00 no @ Tk. 50.00 each = Tk. 50.00
(b) 12 mm long screws 0.67 dz. @ Tk. 8.00 per dz. = Tk. 5.36
(c) Labour charge LS = Tk. 9.38
SubTotal = Tk. 64.74
Contractor's profit 10% = Tk. 6.47
Overhead expenses 3.50% = Tk. 2.27
Total = Tk. 73.48
VAT with adjustment factor 1.06383 6.00% = Tk. 4.69
Grand Total = Tk. 78.17
Rate for each = Tk. 78.17
(a) 75 mm long brass hinge 1.00 no @ Tk. 110.00 each = Tk. 110.00
(b) 12 mm long screws 0.50 dz. @ Tk. 14.00 per dz. = Tk. 7.00
(c) Labour charge LS = Tk. 9.38
SubTotal = Tk. 126.38
Contractor's profit 10% = Tk. 12.64
Overhead expenses 3.50% = Tk. 4.42
Total = Tk. 143.44
VAT with adjustment factor 1.06383 6.00% = Tk. 9.16
Grand Total = Tk. 152.60
Rate for each = Tk. 152.60
(a) 100 mm long brass hinge 1.00 no @ Tk. 150.00 each = Tk. 150.00
(b) 12 mm long screws 0.67 dz. @ Tk. 14.00 per dz. = Tk. 9.38
(c) Labour charge LS = Tk. 9.38
SubTotal = Tk. 168.76
Contractor's profit 10% = Tk. 16.88
Overhead expenses 3.50% = Tk. 5.91
Total = Tk. 191.55
VAT with adjustment factor 1.06383 6.00% = Tk. 12.23
Grand Total = Tk. 203.78
Rate for each = Tk. 203.78
(a) 75 mm dia brass ring 1.00 no @ Tk. 40.00 each = Tk. 40.00
(b) Labour charge LS = Tk. 9.38
SubTotal = Tk. 49.38
Contractor's profit 10% = Tk. 4.94
Overhead expenses 3.50% = Tk. 1.73
Total = Tk. 56.05
VAT with adjustment factor 1.06383 6.00% = Tk. 3.58
Grand Total = Tk. 59.63
Rate for each = Tk. 59.63
(a) 1" expanded mesh metal net 3.80 sqm @ Tk. 100.00 per kg = Tk. 380.00
(b) 4"x 1.5" x 1/8" size clamp 4.00 nos @ Tk. 14.00 each = Tk. 56.00
(c) Welding, reveting etc. LS = Tk. 300.00
(d) 1" x 0.25" F.I. Bar
12 x 6'-0"= 72.00 rft
@ 0.85 Ibs per rft= 61.20 Ibs
Add 5% wastage = 3.06 Ibs
64.26 Ibs @ Tk. 24.94 per Ibs = Tk. 1,602.64
(e) Labour charge for making
& fitting-fixing 3.35 sqm @ Tk. 675.00 LS = Tk. 2,261.25
(f) T & P, local carriage, sundries LS = Tk. 80.00
SubTotal = Tk. 4,679.89
Contractor's profit 10% = Tk. 467.99
Overhead expenses 3.50% = Tk. 163.80
Total = Tk. 5,311.68
Analysis of PWD SoR 2018 for Civil Works 684
iii) Painter for colour washing 0.5 no @ Tk. 600.00 each = Tk. 300.00
iv) Ordinary Labour for
colour washing 0.5 no @ Tk. 320.00 each = Tk. 160.00
SubTotal Tk. 1,586.34
Contractor's profit 10% = Tk. 158.63
Overhead expenses 3.50% = Tk. 55.52
Total = Tk. 1,800.49
VAT with adjustment factor 1.06383 6.00% = Tk. 114.92
Grand Total = Tk. 1,915.41
Rate per sqm = Tk. 19.15
(a) 300 mm long clamp 1.00 no @ Tk. 22.00 each = Tk. 22.00
(b) C.C. (1:2:4) with brick-chips Item No. 3.5.2 0.0056 cum @ Tk. 6,267.01 per cum = Tk. 35.10
(c) Labour charge LS = Tk. 22.40
SubTotal = Tk. 79.50
Contractor's profit 10% = Tk. 7.95
Overhead expenses 3.50% = Tk. 2.78
Total = Tk. 90.23
VAT with adjustment factor 1.06383 6.00% = Tk. 5.76
Grand Total = Tk. 95.99
Rate per No. = Tk. 95.99
(a) 150 mm long clamp 1.00 no @ Tk. 12.00 each = Tk. 12.00
(b) C.C. (1:2:4) with brick-chips Item No. 3.5.2 0.0028 cum @ Tk. 6,267.01 per cum = Tk. 17.55
Analysis of PWD SoR 2018 for Civil Works 697
(a) Labour for cutting light jungles 1.00 no @ Tk. 320.00 each = Tk. 320.00
(b) Labour for removing jungles 1/3 no @ Tk. 320.00 each = Tk. 106.67
(c) Tools and plant, incidental, sundries etc. LS = Tk. 80.00
SubTotal = Tk. 506.67
Contractor's profit 10% = Tk. 50.67
Overhead expenses 3.50% = Tk. 17.73
Total = Tk. 575.07
VAT with adjustment factor 1.06383 6.00% = Tk. 36.71
Grand Total = Tk. 611.78
Rate per sqm = Tk. 6.12
Considering 1 kg
Considering 1 kg
Cost of Bone mele in/c carriage 1.00 kg @ Tk. 40.00 per kg = Tk. 40.00
Contractor's profit 10% = Tk. 4.00
Overhead expenses 3.50% = Tk. 1.40
Total = Tk. 45.40
VAT with adjustment factor 1.06383 6.00% = Tk. 2.90
Grand Total = Tk. 48.30
Rate per kg = Tk. 48.30
Considering 1No.
Considering 1 kg
Cost of fertilizer in/c carriage 1.00 kg @ Tk. 20.00 per kg = Tk. 20.00
Contractor's profit 10% = Tk. 2.00
Overhead expenses 3.50% = Tk. 0.70
Total = Tk. 22.70
VAT with adjustment factor 1.06383 6.00% = Tk. 1.45
Grand Total = Tk. 24.15
Rate per kg = Tk. 24.15
Considering 1 kg
Cost of fertilizer in/c carriage 1.00 kg @ Tk. 20.00 per kg = Tk. 20.00
Contractor's profit 10% = Tk. 2.00
Overhead expenses 3.50% = Tk. 0.70
Total = Tk. 22.70
VAT with adjustment factor 1.06383 6.00% = Tk. 1.45
Grand Total = Tk. 24.15
Rate per kg = Tk. 24.15
(l) Supply of T. S. P.
Considering 1 kg
Cost of fertilizer in/c carriage 1.00 kg @ Tk. 30.00 per kg = Tk. 30.00
Contractor's profit 10% = Tk. 3.00
Overhead expenses 3.50% = Tk. 1.05
Total = Tk. 34.05
VAT with adjustment factor 1.06383 6.00% = Tk. 2.17
Grand Total = Tk. 36.22
Rate per kg = Tk. 36.22
Considering 1 No.
Considering 1 No.
Considering 1 No.
Cost of hand hoe 1.00 no @ Tk. 90.00 each = Tk. 90.00
Contractor's profit 10% = Tk. 9.00
Overhead expenses 3.50% = Tk. 3.15
Total = Tk. 102.15
VAT with adjustment factor 1.06383 6.00% = Tk. 6.52
Grand Total = Tk. 108.67
Rate per No. = Tk. 108.67
Considering 1 No.
Considering 1 No.
Considering 1 No.
Considering 1 rft
Cost of plastic hose pipe 1.00 rft @ Tk. 18.00 per rft = Tk. 18.00
Contractor's profit 10% = Tk. 1.80
Overhead expenses 3.50% = Tk. 0.63
Total = Tk. 20.43
VAT with adjustment factor 1.06383 6.00% = Tk. 1.30
Grand Total = Tk. 21.73
Rate per No. = Tk. 21.73
Cost of perfecthion 40 EC 100ml 1.00 bottle @ Tk. 230.00 each = Tk. 230.00
Contractor's profit 10% = Tk. 23.00
Overhead expenses 3.50% = Tk. 8.05
Total = Tk. 261.05
VAT with adjustment factor 1.06383 6.00% = Tk. 16.66
Grand Total = Tk. 277.71
Rate per No. = Tk. 277.71
Cost of Redomil gold 68WG 500gm 1.00 pack @ Tk. 720.00 each = Tk. 720.00
Analysis of PWD SoR 2018 for Civil Works 704
Cost of Ripcord 400EC 1.00 bottle @ Tk. 200.00 each = Tk. 200.00
Contractor's profit 10% = Tk. 20.00
Overhead expenses 3.50% = Tk. 7.00
Total = Tk. 227.00
VAT with adjustment factor 1.06383 6.00% = Tk. 14.49
Grand Total = Tk. 241.49
Rate per No. = Tk. 241.49
(w) Supply of Proclaim 5SG(emamectin benzoet) 1 box, (10 pack, each pack 10gm)
Vertimec 018ECG 50ml 1.00 bottle @ Tk. 120.00 each = Tk. 120.00
Contractor's profit 10% = Tk. 12.00
Overhead expenses 3.50% = Tk. 4.20
Total = Tk. 136.20
VAT with adjustment factor 1.06383 6.00% = Tk. 8.69
Grand Total = Tk. 144.89
Rate per No. = Tk. 144.89
Considering 1 No.
Considering 1 No.
(a) Skilled labour for Grass cutting 1.50 no @ Tk. 390.00 per cum = Tk. 585.00
Analysis of PWD SoR 2018 for Civil Works 706
(b) Labour for levelling-dressing 1.00 no @ Tk. 320.00 each = Tk. 320.00
(c) Tools and plant, incidental, sundries etc. LS = Tk. 320.00
SubTotal = Tk. 1,225.00
Contractor's profit 10% = Tk. 122.50
Overhead expenses 3.50% = Tk. 42.88
Total = Tk. 1,390.38
VAT with adjustment factor 1.06383 6.00% = Tk. 88.75
Grand Total = Tk. 1,479.13
Rate per sqm = Tk. 14.79
(a) Labour for spading, pulversing 1.00 no @ Tk. 320.00 each = Tk. 320.00
(b) Tools and plant, incidental, sundries etc. LS = Tk. 80.00
SubTotal = Tk. 400.00
Contractor's profit 10% = Tk. 40.00
Overhead expenses 3.50% = Tk. 14.00
Total = Tk. 454.00
VAT with adjustment factor 1.06383 6.00% = Tk. 28.98
Grand Total = Tk. 482.98
Rate per sqm = Tk. 4.83
Cost of unfinished wood 1.00 cft @ Tk. 2,000.00 per cft = Tk. 2,000.00
Contractor's profit 10% = Tk. 200.00
Overhead expenses 3.50% = Tk. 70.00
Total = Tk. 2,270.00
VAT with adjustment factor 1.06383 6.00% = Tk. 144.89
Grand Total = Tk. 2,414.89
Rate per cum = Tk. 85,281.84
Cost of unfinished wood 1.00 cft @ Tk. 1,800.00 per cft = Tk. 1,800.00
Contractor's profit 10% = Tk. 180.00
Overhead expenses 3.50% = Tk. 63.00
Total = Tk. 2,043.00
VAT with adjustment factor 1.06383 6.00% = Tk. 130.40
Grand Total = Tk. 2,173.40
Rate per cum = Tk. 76,753.62
Cost of unfinished wood 1.00 cft @ Tk. 2,490.00 per cft = Tk. 2,490.00
Contractor's profit 10% = Tk. 249.00
Overhead expenses 3.50% = Tk. 87.15
Total = Tk. 2,826.15
Analysis of PWD SoR 2018 for Civil Works 708
Cost of unfinished wood 1.00 cft @ Tk. 3,400.00 per cft = Tk. 3,400.00
Contractor's profit 10% = Tk. 340.00
Overhead expenses 3.50% = Tk. 119.00
Total = Tk. 3,859.00
VAT with adjustment factor 1.06383 6.00% = Tk. 246.32
Grand Total = Tk. 4,105.32
Rate per cum = Tk. 144,979.38
Cost of unfinished wood 1.00 cft @ Tk. 4,390.00 per cft = Tk. 4,390.00
Contractor's profit 10% = Tk. 439.00
Overhead expenses 3.50% = Tk. 153.65
Total = Tk. 4,982.65
VAT with adjustment factor 1.06383 6.00% = Tk. 318.04
Grand Total = Tk. 5,300.69
Rate per cum = Tk. 187,193.87
Cost of unfinished wood 1.00 cft @ Tk. 2,250.00 per cft = Tk. 2,250.00
Contractor's profit 10% = Tk. 225.00
Overhead expenses 3.50% = Tk. 78.75
Total = Tk. 2,553.75
VAT with adjustment factor 1.06383 6.00% = Tk. 163.01
Grand Total = Tk. 2,716.76
Rate per cum = Tk. 95,942.38
Cost of unfinished wood 1.00 cft @ Tk. 1,700.00 per cft = Tk. 1,700.00
Contractor's profit 10% = Tk. 170.00
Overhead expenses 3.50% = Tk. 59.50
Total = Tk. 1,929.50
VAT with adjustment factor 1.06383 6.00% = Tk. 123.16
Grand Total = Tk. 2,052.66
Rate per cum = Tk. 72,489.69
Cost of unfinished wood 1.00 cft @ Tk. 2,390.00 per cft = Tk. 2,390.00
Contractor's profit 10% = Tk. 239.00
Overhead expenses 3.50% = Tk. 83.65
Total = Tk. 2,712.65
VAT with adjustment factor 1.06383 6.00% = Tk. 173.15
Grand Total = Tk. 2,885.80
Rate per cum = Tk. 101,912.03
Cost of unfinished wood 1.00 cft @ Tk. 2,600.00 per cft = Tk. 2,600.00
Contractor's profit 10% = Tk. 260.00
Overhead expenses 3.50% = Tk. 91.00
Total = Tk. 2,951.00
VAT with adjustment factor 1.06383 6.00% = Tk. 188.36
Grand Total = Tk. 3,139.36
Rate per cum = Tk. 110,866.50
Cost of unfinished wood 1.00 cft @ Tk. 6,500.00 per cft = Tk. 6,500.00
Contractor's profit 10% = Tk. 650.00
Overhead expenses 3.50% = Tk. 227.50
Total = Tk. 7,377.50
VAT with adjustment factor 1.06383 6.00% = Tk. 470.90
Grand Total = Tk. 7,848.40
Rate per cum = Tk. 277,166.25
Cost of unfinished wood 1.00 cft @ Tk. 1,800.00 per cft = Tk. 1,800.00
Contractor's profit 10% = Tk. 180.00
Overhead expenses 3.50% = Tk. 63.00
Total = Tk. 2,043.00
VAT with adjustment factor 1.06383 6.00% = Tk. 130.40
Grand Total = Tk. 2,173.40
Rate per cum = Tk. 76,753.62
Considering 1 rft
Cost of pipe 1 rft @ Tk. 148.00 per rft = Tk. 148.00
Contractor's profit 10% = Tk. 14.80
Overhead expenses 3.50% = Tk. 5.18
Total = Tk. 167.98
VAT with adjustment factor 1.06383 6.00% = Tk. 10.72
Grand Total = Tk. 178.70
Rate per meter = Tk. 586.31
Considering 1 rft
Considering 1 rft
Considering 1 rft
Considering 1 rft
Cost of China made spring 1 rft @ Tk. 15.00 per rft = Tk. 15.00
Contractor's profit 10% = Tk. 1.50
Overhead expenses 3.50% = Tk. 0.53
Total = Tk. 17.03
VAT with adjustment factor 1.06383 6.00% = Tk. 1.09
Grand Total = Tk. 18.12
Rate per meter = Tk. 59.45
Considering 1 No.
(a) brick chips 0.32 cum @ Tk. 2,944.12 per cum = Tk. 942.12
(b) Sand (f.m. 1.2) 0.28 cum @ Tk. 494.34 per cum = Tk. 138.42
(c) Cement 3.00 bags @ Tk. 395.00 per bag = Tk. 1,185.00
(d) Labour
i) Mason 3.00 nos @ Tk. 500.00 each = Tk. 1,500.00
ii) Labour 3.00 nos @ Tk. 320.00 each = Tk. 960.00
(e) T & P and sundries LS = Tk. 64.00
SubTotal = Tk. 4,789.54
Contractor's profit 10% = Tk. 478.95
Overhead expenses 3.50% = Tk. 167.63
Total = Tk. 5,436.12
VAT with adjustment factor 1.06383 6.00% = Tk. 346.99
Grand Total = Tk. 5,783.11
Rate per meter = Tk. 192.77
(a) Sweeper for odd job 0.80 no @ Tk. 800.00 each = Tk. 640.00
(e) T & P and sundries LS = Tk. 64.00
SubTotal = Tk. 704.00
Contractor's profit 10% = Tk. 70.40
Overhead expenses 3.50% = Tk. 24.64
Total = Tk. 799.04
VAT with adjustment factor 1.06383 6.00% = Tk. 51.00
Grand Total = Tk. 850.04
Rate per meter = Tk. 28.33
(a) Sweeper FOR ODD JOB 2.00 use @ Tk. 800.00 per use = Tk. 1,600.00
(e) T & P and sundries LS = Tk. 64.00
SubTotal = Tk. 1,664.00
Contractor's profit 10% = Tk. 166.40
Overhead expenses 3.50% = Tk. 58.24
Total = Tk. 1,888.64
VAT with adjustment factor 1.06383 6.00% = Tk. 120.55
Grand Total = Tk. 2,009.19
Rate per No. = Tk. 2,009.19
(a) Sweeper FOR ODD JOB 1.00 use @ Tk. 800.00 per use = Tk. 800.00
(b) Hire charge of cart 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 1,620.00
Contractor's profit 10% = Tk. 162.00
Overhead expenses 3.50% = Tk. 56.70
Total = Tk. 1,838.70
VAT with adjustment factor 1.06383 6.00% = Tk. 117.36
Grand Total = Tk. 1,956.06
Rate per No. = Tk. 1,956.06
(a) Sweeper FOR ODD JOB 2.00 use @ Tk. 800.00 per use = Tk. 1,600.00
(b) Hire charge of cart 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 2,420.00
Contractor's profit 10% = Tk. 242.00
Overhead expenses 3.50% = Tk. 84.70
Total = Tk. 2,746.70
VAT with adjustment factor 1.06383 6.00% = Tk. 175.32
Grand Total = Tk. 2,922.02
Rate per No. = Tk. 2,922.02
(a) Sweeper FOR ODD JOB 2.50 use @ Tk. 800.00 per use = Tk. 2,000.00
(b) Hire charge of cart 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 2,820.00
Contractor's profit 10% = Tk. 282.00
Overhead expenses 3.50% = Tk. 98.70
Total = Tk. 3,200.70
VAT with adjustment factor 1.06383 6.00% = Tk. 204.30
Grand Total = Tk. 3,405.00
Rate per No. = Tk. 3,405.00
(a) Sweeper FOR ODD JOB 4.00 use @ Tk. 800.00 per use = Tk. 3,200.00
(b) Hire charge of cart 2.00 trip @ Tk. 500.00 per trip = Tk. 1,000.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 4,520.00
Contractor's profit 10% = Tk. 452.00
Overhead expenses 3.50% = Tk. 158.20
Total = Tk. 5,130.20
VAT with adjustment factor 1.06383 6.00% = Tk. 327.46
Grand Total = Tk. 5,457.66
Rate per No. = Tk. 5,457.66
(a) Sweeper FOR ODD JOB 7.00 use @ Tk. 800.00 per use = Tk. 5,600.00
(b) Hire charge of cart 4.00 trip @ Tk. 500.00 per trip = Tk. 2,000.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 7,920.00
Contractor's profit 10% = Tk. 792.00
Overhead expenses 3.50% = Tk. 277.20
Total = Tk. 8,989.20
Analysis of PWD SoR 2018 for Civil Works 717
(a) Sweeper FOR ODD JOB 12.00 use @ Tk. 800.00 per use = Tk. 9,600.00
(b) Hire charge of cart 8.00 trip @ Tk. 500.00 per trip = Tk. 4,000.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 13,920.00
Contractor's profit 10% = Tk. 1,392.00
Overhead expenses 3.50% = Tk. 487.20
Total = Tk. 15,799.20
VAT with adjustment factor 1.06383 6.00% = Tk. 1,008.46
Grand Total = Tk. 16,807.66
Rate per No. = Tk. 16,807.66
(a) Sweeper FOR ODD JOB 2.00 use @ Tk. 800.00 per use = Tk. 1,600.00
(b) Hire charge of cart 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
(e) T & P, consumables and sundries LS = Tk. 320.00
SubTotal = Tk. 2,420.00
Contractor's profit 10% = Tk. 242.00
Overhead expenses 3.50% = Tk. 84.70
Total = Tk. 2,746.70
VAT with adjustment factor 1.06383 6.00% = Tk. 175.32
Grand Total = Tk. 2,922.02
Rate per cum = Tk. 1,461.01
(a) Sweeper FOR ODD JOB 0.50 use @ Tk. 800.00 per use = Tk. 400.00
(b) T & P, consumables and sundries LS = Tk. 16.00
SubTotal = Tk. 416.00
Contractor's profit 10% = Tk. 41.60
Overhead expenses 3.50% = Tk. 14.56
Total = Tk. 472.16
VAT with adjustment factor 1.06383 6.00% = Tk. 30.14
Grand Total = Tk. 502.30
Rate per No. = Tk. 502.30
(a) Sweeper FOR ODD JOB 2.50 use @ Tk. 800.00 per use = Tk. 2,000.00
(b) Hire charge of cart 1.00 trip @ Tk. 500.00 per trip = Tk. 500.00
Analysis of PWD SoR 2018 for Civil Works 718
(a) Tube-well mistry 2.00 nos @ Tk. 500.00 each = Tk. 1,000.00
(b) Ordinary labour 4.00 nos @ Tk. 320.00 each = Tk. 1,280.00
(c) T & P, consumables and sundries LS = Tk. 256.00
SubTotal = Tk. 2,536.00
Contractor's profit 10% = Tk. 253.60
Overhead expenses 3.50% = Tk. 88.76
Total = Tk. 2,878.36
VAT with adjustment factor 1.06383 6.00% = Tk. 183.73
Grand Total = Tk. 3,062.09
Rate per meter = Tk. 102.07
(a) Tube-well Head mistry 0.50 no @ Tk. 600.00 each = Tk. 300.00
(b) Tube-well mistry 4.00 nos @ Tk. 500.00 each = Tk. 2,000.00
(c) Ordinary labour 12.00 nos @ Tk. 320.00 each = Tk. 3,840.00
(d) T & P and sundries LS = Tk. 640.00
SubTotal = Tk. 6,780.00
Contractor's profit 10% = Tk. 678.00
Overhead expenses 3.50% = Tk. 237.30
Total = Tk. 7,695.30
VAT with adjustment factor 1.06383 6.00% = Tk. 491.19
Grand Total = Tk. 8,186.49
Rate per meter = Tk. 272.88
(a) Cost of Check Valve 1.00 no @ Tk. 570.00 each = Tk. 570.00
(b) Labour for fitting-fixing LS = Tk. 160.00
SubTotal = Tk. 730.00
Contractor's profit 10% = Tk. 73.00
Overhead expenses 3.50% = Tk. 25.55
Total = Tk. 828.55
VAT with adjustment factor 1.06383 6.00% = Tk. 52.89
Grand Total = Tk. 881.44
Rate per No. = Tk. 881.44
(a) 37 mm dia PVC pipe 2.00 rft @ Tk. 14.50 per rft = Tk. 29.00
(b) Labour for making hole & fitting-fixing etc. LS = Tk. 96.00
(c) Cost of mending damage LS = Tk. 48.00
(d) Sundries LS = Tk. 16.00
SubTotal = Tk. 189.00
Contractor's profit 10% = Tk. 18.90
Overhead expenses 3.50% = Tk. 6.62
Total = Tk. 214.52
VAT with adjustment factor 1.06383 6.00% = Tk. 13.69
Grand Total = Tk. 228.21
Rate per No. = Tk. 228.21
(a) 25 mm dia PVC pipe 1.50 rft @ Tk. 11.70 per rft = Tk. 17.55
(b) Labour for making hole & fitting-fixing etc. LS = Tk. 96.00
(c) Cost of mending damage LS = Tk. 48.00
(d) Sundries LS = Tk. 16.00
SubTotal = Tk. 177.55
Contractor's profit 10% = Tk. 17.76
Overhead expenses 3.50% = Tk. 6.21
Total = Tk. 201.52
VAT with adjustment factor 1.06383 6.00% = Tk. 12.86
Grand Total = Tk. 214.38
Rate per No. = Tk. 214.38
(a) Plastic Low-down (complete set) 1.00 no @ Tk. 800.00 each = Tk. 800.00
(b) Labour charge
(i) Plumber 0.50 no @ Tk. 600.00 each = Tk. 300.00
(ii) Ordinary labour 0.30 no @ Tk. 320.00 each = Tk. 96.00
(c) Sundries LS = Tk. 80.00
SubTotal = Tk. 1,276.00
Contractor's profit 10% = Tk. 127.60
Overhead expenses 3.50% = Tk. 44.66
Total = Tk. 1,448.26
VAT with adjustment factor 1.06383 6.00% = Tk. 92.44
Grand Total = Tk. 1,540.70
Rate per No. = Tk. 1,540.70
a) Sand (F.M. 1.2) 5 cft @ Tk. 1,400 per % cft = Tk. 70.00
b) Cement 1.5 bag @ Tk. 395.00 per bag = Tk. 592.50
(c) Mason FOR ODD JOB 0.25 no @ Tk. 1,000.00 each = Tk. 250.00
(d) Skilled labour FOR ODD JOB 1.25 nos @ Tk. 780.00 each = Tk. 975.00
(e) Ordinary labour FOR ODD JOB 1.25 nos @ Tk. 640.00 each = Tk. 800.00
(f) Washing of sand, local carriage, curing, & sundries etc. LS = Tk. 320.00
SubTotal = Tk. 3,007.50
Contractor's profit 10% = Tk. 300.75
Overhead expenses 3.50% = Tk. 105.26
Total = Tk. 3,413.51
VAT with adjustment factor 1.06383 6.00% = Tk. 217.88
Grand Total = Tk. 3,631.39
Rate per sft = Tk. 36.31
Rate per sqm = Tk. 390.84
a) Hire charge of welding set 1 no @ Tk. 700.00 per day = Tk. 7.00
b) Welder cum fabricator 1 no @ Tk. 600.00 each = Tk. 600.00
(c) Helper to welder 1 no @ Tk. 390.00 each = Tk. 390.00
(d) Carrying LS = Tk. 160.00
SubTotal = Tk. 1,157.00
Contractor's profit 10% = Tk. 115.70
Overhead expenses 3.50% = Tk. 40.50
Total = Tk. 1,313.20
VAT with adjustment factor 1.06383 6.00% = Tk. 83.82
Grand Total = Tk. 1,397.02
Rate per day = Tk. 1,397.02
a)
Scaffolding including safety provision 1 no @ Tk. 220.00 per day = Tk. 220.00
(d) Carrying LS = Tk. 96.00
SubTotal = Tk. 316.00
Contractor's profit 10% = Tk. 31.60
Overhead expenses 3.50% = Tk. 11.06
Total = Tk. 358.66
VAT with adjustment factor 1.06383 6.00% = Tk. 22.89
Grand Total = Tk. 381.55
Rate per day = Tk. 381.55
Cost of Swing door clouser 1 no @ Tk. 2,700.00 per set = Tk. 2,700.00
Contractor's profit 10% = Tk. 270.00
Overhead expenses 3.50% = Tk. 94.50
Total = Tk. 3,064.50
VAT with adjustment factor 1.06383 6.00% = Tk. 195.61
Grand Total = Tk. 3,260.11
Rate per set = Tk. 3,260.11
Cost of Swing door lock 1 no @ Tk. 625.00 per set = Tk. 625.00
Contractor's profit 10% = Tk. 62.50
Overhead expenses 3.50% = Tk. 21.88
Total = Tk. 709.38
VAT with adjustment factor 1.06383 6.00% = Tk. 45.28
Grand Total = Tk. 754.66
Rate per set = Tk. 754.66
Cost of Swing door Mohiar 1 meter @ Tk. 16.41 per meter = Tk. 16.41
Contractor's profit 10% = Tk. 1.64
Overhead expenses 3.50% = Tk. 0.57
Total = Tk. 18.62
VAT with adjustment factor 1.06383 6.00% = Tk. 1.19
Grand Total = Tk. 19.81
Rate per meter = Tk. 19.81
Cost of Fixed Neoprene 1 meter @ Tk. 8.53 per meter = Tk. 8.53
Contractor's profit 10% = Tk. 0.85
Analysis of PWD SoR 2018 for Civil Works 724
Sliding door /window key lock 1 no @ Tk. 200.00 per set = Tk. 200.00
Contractor's profit 10% = Tk. 20.00
Overhead expenses 3.50% = Tk. 7.00
Total = Tk. 227.00
VAT with adjustment factor 1.06383 6.00% = Tk. 14.49
Grand Total = Tk. 241.49
Rate per set = Tk. 241.49
Sliding door /window wheel 1 no @ Tk. 70.00 per set = Tk. 70.00
Contractor's profit 10% = Tk. 7.00
Overhead expenses 3.50% = Tk. 2.45
Total = Tk. 79.45
VAT with adjustment factor 1.06383 6.00% = Tk. 5.07
Grand Total = Tk. 84.52
Rate per set = Tk. 84.52
Sliding door /window Mohiar 1 meter @ Tk. 4.27 per meter = Tk. 4.27
Contractor's profit 10% = Tk. 0.43
Overhead expenses 3.50% = Tk. 0.15
Total = Tk. 4.85
VAT with adjustment factor 1.06383 6.00% = Tk. 0.31
Grand Total = Tk. 5.16
Rate per meter = Tk. 5.16