Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1. You are the NACE Inspector on a tank lining project where a 50% solids epoxy tank
lining is being applied. After application of the 19 coat you notice small blisters in some
areas of the applied lining.
water freezes.
humidity decreases
condensation occurs.correct
the air is saturated.
3. If a contractor is using a poorly maintained compressor to supply air for abrasive blast
cleaning and conventional airspray, the coating inspector should perform a
review coating contractors' plans for storage of coating materials and confirm they meet
national, local and owners' fire and environmental regulations.
observe and document the amount of material and batch numbers.correct
observe aryl document that the applicator WFT at regular intervals during application.
observe and document time frame and environmental conditions between each coat.
5. Relative humidity is
Concrete
Fiberglass Reinforced Plastic
Metalcorrect
Wood
7. When applying Thermal Spray Coatings the specification is most likely to refence:
SSPC PA 2
NACE SP 0178
NACE SP 0188
SSPC-CS 23.00/AWS C2.23/NACE No. 12correct
8. What is the minimum recommended distance away from an edge that an inspector
should take a measurement with a dial-type magnetic pull-off Dry Film Thickness (DFT)
gauge?
1 cm (.39 inch)
2.5 cm (1 inch)correct
6.35 cm (2.5 inch)
2.5 millimeters (.10 inch)
Monomers telegraphing
Monomers joining togethercorrect
All thermoplastic coatings
All organic coatings
10. An exposed area of the substrate or previous coat of a conductive coating material,
often caused by poor application technique is called
cracking.
sagging.
holiday.correct
checking.
11. Checking is
an exposed area of the substrate or previous coat material, caused by poor application
technique.
a fine crack in the surface of a coating that rarely reaches the substratecorrect
a very small hole in a coating caused when air or solvent is trapped in porous film and then
escapes.
surface breaks in the film that often result from grease or oil contamination and revel the
substrate.
14. You have just received your NACE CIP Level 1 certification when you are asked to
supervise a team of uncertified field pipeline inspectors.
Your FIRST preferred course of action is to:
15. Good records can provide maintenance departments with detailed information about
ALL of the following EXCEPT
In every instance that an item does not meet the specification requirements
When the Inspector deems it to be a significant non-conforming item
When the Inspector and Contractor deem it to be a significant non-conforming
itemcorrect
In accordance with the specification's definition of a non-conformance
17. The initial steel condition is important to the NACE Inspector because:
18. The form of corrosion that has the largest potential for unexpected catastrophic failure
is:
General Corrosion
Atmospheric Corrosion
Galvanic Corrosioncorrect
Localized Corrosion
21. When performing tests for oil and grease using an ultra-violet light, the NACE
Inspector should be aware that:
Chloride salt may produce a false positive
Synthetic oil or grease may not be identifiedcorrect
Ultra-Violet light may contaminant the surface
Presence of weld spatter may produce a false positivewrong
22. To achieve consistently accurate results with ALL alt test equipment
23. When holiday testing is required the Inspector is always required to enforce NACE SP
0188:
Truecorrect
False
24. If the specifier does not identify a restriction level in accordance with SSPC PA 2, the
default restriction level is:
Level 1wrong
Level 2
Level 3correct
Level 4
25. Fine cracks in the surface of a coating that rarely reach the substrate are called
cracking.
alligatoring.
checking.correct
blistering.
26. It is good practice for the NACE Inspector to have instrument calibration certificates
available:
At all timescorrect
In the office only
In the field only
Only if the specification requires it
On every jobwrong
When ISO abrasive blast standards are specified
When NACE/SSPC abrasive blast standards are specified
When specifically identified in the owner's specificationcorrect
29. Common errors that may produce inaccurate readings when using a Dial-Type
Magnetic Pull-Off Dry Filth Thickness (DFT) gauge include:
Sleeve test
Potassium ferricyanide
Bresle patchcorrect
Soluble salts meter
32. Which one of these elements is not necessary for corrosion to occur:
Anode
Cathode
Reference Cellcorrect
Electrolyte
34. Using SSPC Vis 1 as a guide when performing a visual inspection of a steel surface
prior to surface preparation a NACE Inspector would assign which designations to the
surface condition:
37. Excess moisture during holiday testing can cause erroneous indications by creating a
path across the surface of the coating to pinholes previously detected, or directly to the
signal return connection.
telegraphing.correct
monitoringwrong
juxtaposing.
transitioning.
In the USA
In North America
In Asia
When specifiedcorrect
40. When using a sling physchrometer a very large difference between the wet and dry
bulb readings indicates:
1. You are the NACE Coating Inspector on a tank lining project and are asked to perform a
high voltage holiday test after the coating applicators have completed their final repairs.
After meeting all the confined space entry permit you enter the tank and notice a very
strong odor of solvent.
2. You are working as an inspector in a galvanizing plant for the first time.
3. You are working as the only in-house NACE Level 2 Inspector in a shop setting when an
independent 3 rd party NACE Level 3 Inspector, representing the owner, presents you
with a copy of a Non Conformance Report (NCR) he has written for a NACE2/SSPC SP 10
centrifugal blast which you had previously approved.
It is always requiredcorrect
When the Coating Applicator requests one
When the Owner specifies one
When the Inspector requests one
9. You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress
where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is
behind schedule and you are asked to take DIY Film Thickness readings.
10. When conducting inspections the Inspector should follow which standards:
11. You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with
an additional requirement that no individual gauge reading shall be below a certain value.
12. The coating applicator has ignored a enface preparation hold point and applied
coating over the surface without a sign off from you as the inspector.
13. In the event of a conflict between the Product Data Sheet and the Specification:
14. From a corrosion perspective, the main difference between Ferrous and Non-Ferrous
Metals is:
Cost
Iron contentcorrect
Appearance
Safety
15. You are the NACY Coating Inspector on a tank lining project where desiccant
dehumidification is being used. Since the first shift of abrasive blasting your readings
have indicated relative humidity below 40%; however on the second shift of coating
application your readings are indicting 80%.
16. When environmental enclosures are being used an inspector needs to be concerned
about:
Lighting
Air changes
Structural integrity
a), b), and c)correct
True
Falsecorrect
Document the defect and the potential problems that could resultcorrect
Ignore the defect as the inspector can’t change the design
Request that the item be rebuilt with a better design for coating
Stop the job immediately
20. WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)
Truecorrect
False
22. The standards defining surface cleanliness achieved by centrifugal blast cleaning are:
23. You are NACE Level 2 Inspector working on a tank lining job where a mobile
centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The
Contractor has completed his final blast and has called for a hold point inspection. This is
the 1 st time you have seen field based centrifugal blast cleaning. You observe what
appears to be staining on the substrate however the Contractor assures you this is
normal when using centrifugal blast units and what you are seeing is what is defined in
the standard as an acceptable variation in appearance.
24. You are a NACE Level 2 in-house inspector working in a shop. Your in-house requires
you to perform a sleeve test to test for soluble salts; however the 3 rd party NACE Level 3
inspector, the owner, has a san smart meter and has achieved a very different result and
has rejected the pre-cleaning.
27. Differences in technique for abrasive blasting concrete versus steel require the
operator to:
Solvent Evaporation
Coalescencecorrect
Co-Reaction
Oxidationwrong
31. When performing a hardness test on a coating which has elastic properties the
inspector is likely to likely to observe:
32. External coatings applied to buried pipelines are generally tested for:
Gloss level
Chalking resistance
Cathodic disbondmentcorrect
Solvent resistance
33. You are the NACE Inspector on a project where a stationary floating structure is being
coated and you notice a self-smoothing anti-fouling coating has been specified.
It contains biocidecorrect
It doesn't contain biocide
The floating structure is stationarywrong
It will result in a very slippery surface
34. Eddy current DFT gauges are used to measure Dry Film Thickness in which of the
following situations:
35. When measuring the Dry Film Thickness Of liquid coatings applied to galvanized
ferrous substrates the most commonly used instrument is the:
36. The most likely area of failure on a buried external pipeline coating is the:
Mainline coating
Field joint coatingcorrect
Areas exposed to Ultra Violet light
Ground bed
37. The best choice of instrument for holiday testing of thick film concrete coatings is:
Barrier protectionwrong
Inhibitive protection
Sacrificial protectioncorrect
Thermal protection
40. When using a destructive Paint Inspection Gauge the NACE inspector must:
Determine the Dry Film Thickness of the coating prior to usecorrect
Ensure the glue on the dolly is properly applied prior to use
Consult SSPC Guide 1 prior to use
Select the appropriate hand wheel based on the measured Dry Film Thickness prior to us