Sei sulla pagina 1di 39

ENVIRONMENT CLEARANCE

(Conceptual Plan)
For
Integrated Exhibition cum Convention
Centre (IECC)

(Redevelopment of ITPO Complex at Pragti Maidan)

Submitted By
India Trade Promotion Organisation (ITPO)
Contents
Introduction..................................................................................................5

General......................................................................................................5

Brief about Project Proponent....................................................................5

Project Consultant.....................................................................................6

Brief about Project.....................................................................................6

Site Surroundings and Connectivity..............................................................7

Location.....................................................................................................7

Salient features of the site...........................................................................12

Area Details................................................................................................12

Ground Coverage and FAR Details............................................................14

Population Density......................................................................................15

During Construction Phase......................................................................15

During Operational Phase........................................................................15

Land Environment......................................................................................16

Topography..............................................................................................17

Water Environment.....................................................................................17

Construction Phase..................................................................................17

Operational Phase....................................................................................17

Wastewater Details...................................................................................20

Sewage Treatment Technology..................................................................23

Technology Proposed- MBR (Membrane Bio Reactor)..............................24

Process Description...............................................................................26

MBR Module.........................................................................................28

Operation..............................................................................................28

Sewer System........................................................................................29
Preventive measures to Avoid Leaching.....................................................29

Rainwater Harvesting and Strom Water Drain..........................................29

Need for Rainwater Harvesting.................................................................30

Rainwater Harvesting Network.................................................................30

Efficacy of Rain Water Harvesting............................................................32

Parking Details............................................................................................33

Electrical details.........................................................................................34

Power Details...........................................................................................34

D. G. Sets Details..................................................................................34

Lighting system........................................................................................34

Lighting Control through day lighting and sensor Motion.........................35

Integrated Fire Detection System..............................................................35

Solid Waste Details......................................................................................36

During Construction Phase of the Proposed Building...............................36

C & D waste of Existing Buildings............................................................37

During Operational Phase........................................................................37

Collection and Segregation of waste.......................................................39

Treatment of Waste................................................................................39

Disposal................................................................................................40

Landscape Details.......................................................................................41

Energy Conservation Measures...................................................................43

List of the construction Material Used.........................................................44

List of Figures
Figure 1: Google Map Showing Site and Its Surroundings (500 mtrs)..........10
Figure 2: Toposheet Map showing Site and Surroundings (5 km).................11
Figure 3 : Water Balance Diagram during Dry Season.................................21
Figure 4: Water Balance diagram during Monsoon Season..........................22
Figure 5: Schematic Diagram of MBR Technology........................................27
Figure 6: Rainwater Harvesting Structure...................................................32
Figure 7: Solid Waste Management for Construction Phase.........................37
Figure 8: Solid Waste Management Scheme -Domestic Waste......................41

List of Tables
Table 1: Project Consultants Involved............................................................6
Table 2: Geographical Co-ordinates of the site...............................................7
Table 3: Site Surroundings and Connectivity.................................................8
Table 4: Salient Features of the site.............................................................12
Table 5: Area Details of Retained (Existing) + Proposed Building.................13
Table 6: Ground Coverage and FAR details of Retained (Existing) building...14
Table 7: Ground Coverage and FAR Details of Proposed Building................14
Table 8: Population Details for Retained (Existing) Building.........................15
Table 9: Population Details for Proposed Building.......................................15
Table 10: Water Requirement during Operational Phase (Retained + Proposed) Building
...................................................................................................................19
Table 11: Design Parameters for Sewage Collection System.........................24
Table 12: Wastewater Details.......................................................................29
Table 13: Calculation for Strom Water Load for the Development of IECC....31
Table 14: ECS Required...............................................................................33
Table 15: Parking Proposed.........................................................................33
Table 16: D.G. sets location and their description.......................................34
Table 17: Calculation of Solid Waste Generation of Retained and Proposed Building 38
Table 18: Landscape Area Details................................................................41
Table 19: Plantation List.............................................................................43

Annexure
Annexure 1: Land Ownership Documents..................................................17

CONCEPTUAL PLAN
Introduction
General
 The Ministry of Environment, Forest and Climate Change has notified the

Environmental Impact Assessment (EIA) Notification, 2006 under the provisions of the

Environment (Protection) Act, 1986, which regulates development and their

expansion/modernization of 39 sectors/activities listed in the Schedule to the EIA

Notification, 2006.
 As per the EIA Notification 2006, all the building construction projects/Area

Development projects and Township Projects comes under schedule 8 and projects

covering an area ≥ 50 ha and/or built up area ≥1,50,000 sq .mtrs they come under

schedule 8 (b). All projects under Item 8(b) shall be appraised as Category B1.
 The application for environmental clearance shall comprise submission of Form 1,

Form 1A, and Conceptual Plan along with EIA/EMP Report incorporated proposed ToR

in SEIAA. The EIA/EMP shall be prepared on the basis of Approved ToR issued from

SEAC and will be submitted to the SEAC for appraisal and due recommendation and

suggestions. Following the appraisal of the project to the satisfaction of the SEAC and

SEIAA, Environmental Clearance shall be granted.


Total Built up area of the proposed site is 3, 97,249.559 m2.

Brief about Project Proponent


 India Trade Promotion Organization (ITPO) is the nodal agency of the Government of

India under aegis of Ministry of Commerce and Industry (India) for promoting

country's external trade. ITPO is a Mini-Ratna Category-1 Central Public Sector

Enterprise (CPSE) with 100 percent shareholding of Government of India.


 ITPO, during its existence of more than 5 decades has played a proactive role in

catalysing trade, investment and technology transfer processes. Its promotional tools

include organising of fairs and exhibitions in India and abroad, Buyer-Seller Meets,

Contact Promotion Programmes, Product Promotion Programmes and Promotion

through Overseas Department Stores, Market Surveys and Information Dissemination.

Project Consultant
Details regarding Project consultants involved are given below;
Table 1: Project Consultants Involved

Project Team Details


Aedas Architects
Unit 133, Rectangle One,
D4 District Centre Saket,
New Delhi, Delhi 110017
Architects Arcop Associates (P)
Ltd.
A-15, Pamposh Enclave,
Greater Kailash - 1,
New Delhi-110048 India
Environment Envision Enviro
Consultant Technologies Pvt. Ltd.
A-73, Noida-201301
Landscape Architect Pravin Khot
MEP Consultant Meinhardt India Pvt Ltd
A-8 , Sector 16
Noida-201301
Project Management NBCC (India) Limited
Agency (PMA) NBCC Bhawan, Lodhi
Road
New Delhi - 110 003,
India

Brief about Project

 Pragati Maidan is a venue for large exhibitions and conventions in New Delhi with

65,000 m2 of existing exhibition space is now re-develop into Integrated Exhibition-

cum-Convention Centre (IECC) with Approx. 3,61,688.809 m2 of built up area having

Convention Center & Exhibition Halls building development in Phases-1 facilities like

car parking for visitors a single basement also planned. Proposed development will

become Delhi's & North India's largest exhibition centre owned and managed by India

Trade Promotion Organization (ITPO)


 The design comprises of an iconic convention centre& exhibition- halls. Considerations

have been made for the use of environment friendly materials to achieve Green

Building Features. Overall layout of the project includes convention centre, exhibition

halls, Restaurants, Business centre, open exhibition space with parking basement.
 The existing buildings were constructed and also became operational prior to the

publication of EIA Notification 2006. Therefore, the existing buildings did not attract

applicability of to obtain Environmental Clearance from SEIAA/MoEFCC and no

environmental clearance was issued. Accordingly, the issuance of certified monitoring

report by Regional Director of MoEFCC is not applicable for the existing buildings. The

construction of existing buildings was done after getting approval from concerned

departments of Delhi.

Site Surroundings and Connectivity


Location
The proposed site is connected to Delhi, Noida, and other NCR regions. It is surrounded by

places such as Supreme Court, Purana Qila and National Sports Club, Mandi House, Bappa

Nagar, Balmiki Basti and kaka Nagar within 5km of the area of the site.

Geographical co-ordinates of the site are given in Table

Table 2: Geographical Co-ordinates of the site

Lattitude Longitude
Centre of the Plot 28°37'2.39"N 77°14'36.70"E
Corner-1 28°36'47.50"N 77°14'52.64"E
Corner-2 28°36'47.08"N 77°14'26.39"E
Corner-3 28°37'7.91"N 77°14'25.95"E
Corner-4 28°37'10.93"N 77°14'44.46"E
Corner-5 28°37'25.43"N 77°14'34.90"E
Corner-6 28°37'25.95"N 77°14'26.18"E

Site is well connected to transport facilities as well as surrounded by densely populated

areas. Pragati Maidan is flanked by Mathura Road to its West and Bhairon Road on the

South. To its east runs the main railway line to Central and Southern India. Pragati Maidan

is situated in Central Delhi and directly connected to India Gate and Purana Qila Road. On

the adjacent side, Pragati Maidan metro station and Pragati Maidan Bus terminal are

located.

Site surroundings and site connectivity within 15 km are shown in below table
Table 3: Site Surroundings and Connectivity

S.No. Particulars Name Distance ‘n’

Direction
1. Nearest Railway  Pragati Maidan Halt 0.3 Km in E
Station  Tilak Bridge 0.8 Km in NW
2. Nearest Airport  Indira Gandhi 15.5 Km in SW
International Airport
 Safdarjung Airport 5 km in SW
3. Nearest  Chandni Chowk 2.9 Km in N
 Patparganj 4.0 Km in E
Populated Area
 Government Officer 0.5 Km in NW
Colony
4. State Boundary  Delhi-UP state 17.22 km in E
Boundary
5. Nearest Highway  NH-24 2.5 km in ESE
 SH-57
2.45 km in N
6. Nearest Road  Mahatama Gandhi 0.57 km, E
Marg Adjacent, W
 Mathura Road
7. Nearest Metro  Pragti Maidan Adjacent to the site
 Inderprasth
station 0.6 km in NE
8. Nearest School  Modern School 1.73 km in NW
 Mater Dei School
0.69 km in SW
 St. Coloumbia School
 Free School Under the 3.7 km in W
bridge 3.23 km in E
9. Nearest Hospital  Dr. Ram Manohar Lohia 4 km in WNW3.3 km
Hospital in NW
 Dr. Shroff Charity Eye
Hospital
10. Place of worship  Akshardham Temple 3.10 km in E
 Bangla Sahib
3.5 km in NW
Gurudwara
11. Water Bodies  Yamuna River 1.2 km in E
 Old fort Lake
0.2 km in SW
12. Forest  Southern Ridge Forest 5.1 km in W
(Source: Google Earth Pro)

Google map and topographical map showing site and surroundings are given below.
Figure 1: Google Map Showing Site and Its Surroundings (500 mtrs)
Salient features of the site
The salient features of the project are as follow. The Pragati Maidan complex having Existing

building (retained) comprises of 7 Exhibition Halls (Hall No. 7 to Hall No. 13) however

proposed building is having 6 Exhibition halls. Buildings of various shapes and sizes; Eating

Figure 2: Toposheet Map showing Site and Surroundings (5 km)


Outlets & Restaurants; Open Theatre and Auditorium for Performing Arts, Rock Concerts

and Cultural events;


Table 4: Salient Features of the site

S. No. Description Proposed


1. Plot Area 4,99,829.28 m2
2. Proposed Built Up Area (Retained + 3,97,249.559 m2

Proposed)
3. Maximum Height with Mumty 36.0mtrs
4. Maximum No. of Floors G+5
5. Cost of Project
6. Expected Population (Retained + 1, 68,676

Proposed)
7. Total Water Requirement 3,975 KLD
8. STP Capacity and Technology 2,200 KLD (MBR)
9. No. of RWH Proposed 10
10. Parking Proposed 4,806 ECS
11. Solid Waste Generation 26,835.26 kg/day
12. Total Power Requirement 17.51 MVA
13. D.G. Set Back Up 18,740 kVA

Area Details
This is re development of existing exhibition space to integrated Exhibition-cum-Convention

Centre (IECC). Total area of the IECC site is Site is having plot area of 4, 99,829.28 m 2 (49.98

Hectare).The retained (existing) building having 7 No. of blocks (From Hall No. 7-13) with
maximum height of G+1 (13.35 mtrs) however the proposed building is having 06 nos. of

blocks with maximum height of G+5 (36.0 mtrs).Total built up area of the site (Retained +

Proposed) Building is 3, 97,249.559 m2

Area details are given in table below.

Table 5: Area Details of Retained (Existing) + Proposed Building

S. Particulars Retained Proposed Area Total Area

No (Existing) (m2) (m2)

. Area (m2)
1. Plot Area (As per the Lease area) 4,99,829.28
2. Total Ground Coverage (A+B) 2,49,914.642

 Permissible Ground Coverage (@40% of PA) (A) 1,99,931.714


 Add. G.C. for atrium (@10 % of PA)(B)
49,982.928
3. Total ground 1,24,573.389

coverage (Proposed) @ 24.92 %

 Proposed Ground 28,654.750 92,357.115 Plot area

Coverage
 Atrium Ground
- 3,561.524
coverage

4. Permissible FAR @1.2 5,99,795.141


5. Proposed FAR @ 0.45 1,96,544.137 2,28,520.887
 FAR of Halls (No.

7-13) 31,976.750
 FAR of Halls (No.
1,33,831.162
1-6)
 FAR of

Convention Hall 54,265.906


 FAR for Admin

Building 8,293.095
 Gate House

153.974
6. Basement area - 1,65,144.672 1,65,144.672

 Parking area 1,47,392.521


 Service area
17,752.151
7. Podium area 3,584 - 3,584
8. Built Up Area 35,560.75 3,61,688.809 3,97,249.559
9. Open area 471,174.53 3,75,255.895 3,75,255.895
10. Road and Paved area 1,14,066.200

Area under Surface Parking 5234.02


11. Landscape (51.20 % of Plot Area) 2,55,955.675
12. Maximum Height of 13.35 36.0

the Building (mtrs)

Ground Coverage and FAR Details


Ground coverage and floor wise details of each block (existing and proposed) blocks are given
in table.

Table 6: Ground Coverage and FAR details of Retained (Existing) building

Block No. Storey Gr. Coverage F.A.R Height (mtrs)


Hall no-07 G+1 8,495.000 9,885.000 13.35
Hall no-08 G+1 460.400 1,113.400 13.00
Hall no-09 G+1 2,853.95 3,406.950 13.00
Hall no-10 GR. FLOOR 1,818 1,818.000 13.00
Hall no-11 G+1 6,682.4 7,408.400 13.00
Hall no-12 GR. FLOOR 1,807 1,807.000 13.00
Hall no-13 GR. FLOOR 6,538 6,538.000 13.00
Total 28,654.75 31,976.75

Table 7: Ground Coverage and FAR Details of Proposed Building

Block No. Height


Storey Gr. Coverage F.A.R
(mtrs)
Convention-hall G+4 25,898.774 54,265.906 31.500
Hall-A1 G+1 9,853.919 20,621.058 29.100
Hall A2 G+1 9,853.919 20,621.058 29.100
Hall A3-A5 G+1 32,077.252 65,500.500 29.100
Hall A6 G+1 13,136.220 27,088.546 29.100
Admin building G+5 1,383.058 8,293.095 30.000
Gate house Gr. Floor 153.97 153.974 4.500
1,96,544.13
Total 92,357.115 7

Population Density
During Construction Phase
The total manpower requirement during construction phase of the site will be an
approximate 250-300 person which includes workmen, labourers, supervisors, engineers,
architect and Manager.

During Operational Phase


The total population of the project (Retained building + Proposed) will be 1,68,676 persons
that include staff as well as Visitor population .The detailed population breakup including
Staff members as well as visitors is given in table below

Table 8: Population Details for Retained (Existing) Building

S. Description Floor Area Occupant Load, Total


2
No. (m ) Floor Area in Population
2
m /Person
1. 1.5
9,885.000 6,590
Hall no-07
2. 1.5
1,113.400 742
Hall no-08
3. Hall no-09 3,406.950 1.5 2,271
4. 1.5
1,818.000 1,212
Hall no-10
5. 1.5
7,408.400 4,939
Hall no-11
6. 1.5
1,807.000 1,205
Hall no-12
7. 1.5
6,538.000 4,359
Hall no-13
Total Population 21,318

Table 9: Population Details for Proposed Building

S. Description Floor Area Occupant Total


No. (m2) Load, Floor Populatio
Area in n
m2/Person
1. MAIN HALLS n ADMIN
BUILDING
G-G Plenary Hall (Axial
0.6 5,410
& Radial Partition) 3,246
Pre-function 3,234 0.6 5,390
Support facilities 1,662 10 166
Circulation 1,920 0.6 3,200
B-B Function Hall 5,495 0.6 9,158
Pre-function 1,280 0.6 2,133
Support facilities 1,774 10 177
Meeting spaces 15,030 0.6 25,050
Support Facilities and Amenities
Management Offices 147 10 15
VIP Lounges 246 10 25
Café 352 1.5 235
Reception 5,722 10 572
Business Centre 196 10 20
First aid rooms 38 10 4
Cloak rooms 60 10 6
Amphitheater Green 10
17
rooms A 168
Amphitheater Green 10
21
rooms B 212
Driver’s quarters 340 10 34
Additional Circulation 1,277 10 128
Security and Docks 410 10 41
quarters
Pantry 75 10 8
Green Rooms 170 10 17
Additional room within
10 135
Convention Centre 1,350
F& B 4,184 1.5 2,789
Business Centre 2,167 10 217
Amphitheatre 3,510 1.5 2,340
Admin building 8,293.095 10 829
25. EXHIBITION HALLS
Halls A1-A6 1,33,831.16
1.5 89,221
2
Total Population (1+2) 1,47,358

Total population of Integrated Exhibition cum Convention Centre (IECC) will be 1,


68,676.

Land Environment
 The site has been allotted to India Trade Promotion Organisation (ITPO), the premier

trade promotion agency of the Ministry of Commerce & Industry, Govt. of India for

conducting large exhibitions and conventions at Pragti Maidan, New Delhi.


 Perpetual lease has been made between President of India acting through Land &

Development Officer, Nirman Bhawan, New Delhi and Indian Trade Promotion

Organisation, Pragti Maidan, New Delhi.

Annexure 1: Land Ownership Documents

Topography
 Physically the natural capital territory of Delhi can be divided into 3 segments - the

Yamuna flood plain, the Ridge and the Plain. The entire area of the national capital

territory of Delhi is categorized as Bangar or the plain. The land of the plain is mostly

fertile
 The entire area of the site is monotonously flat. The project area possesses plain terrain.

Highest elevation levels is 692 feet & the lowest levels is 685 feet

Water Environment
(Requirement and Consumption)
Construction Phase
During the construction phase the water requirement (approx. 1900 ML) will be met from

Private water or treated wastewater from Nearby STP. No ground water will be extracted.

Hence, there will be no impacts on ground water environment during construction phase.

Operational Phase
Total water requirement for redevelopment of IECC Project (Existing + Proposed) is 3,975

KLD. Total domestic water requirement is approx 1,574KLD. The main sources fresh water

will be

 DJB
 Registered tube wells within ITPO Complex.

However the secondary sources of the water are

 Tanker supply (For Emergency Use only)


 Treated Effluent from an external centralized sewage treatment Plant

The existing source of water for the project is DJB. There are two existing metered tapings

from 450 mm diameter water pipe line, one of the connections is of 50 mm diameter and is

near gate no. 3 of ITPO while the other connection is of 150 mm diameter and is near gate

no.7. Water is supplied 24 x 7 to Pragati Maidan. There are existing 5 bore well and

additional 2 bore well will be dug to fulfill the present water demand.

Detail of water requirements for various uses is given in below table. Efficient dual flushing

fixtures will be provided for conservation of fresh water. The demand may vary depending on

the water conservation methods employed by the facility, which may include use of water

efficient fixture, use of dishwashers, water auditing and metering etc

Total quantity of wastewater generation will likely to be 2,295KLD. The generated sewage will

be collected and treated in the in-house Sewage Treatment Plant of 2,200 KLD capacity. The

treated wastewater will be re used for flushing and gardening and HVAC cooling. Water

Balance diagram during Non Rainy season and Rainy season are shown below.

Table 10: Water Requirement during Operational Phase (Retained + Proposed) Building

S.No. Description Population/ water Total water Wat


area (m2) consumption required (KLD) Domes
(litres/capita (K
/day)
1. Exhibition Halls (A1-13) 1,10,539 15
1,658.09 994

2. Main Halls
0.00 0.0

G-G Plenary Hall (Axial &


5,410 15 81.15 48.
Radial Partition)
Pre-function 5,390 15 80.85 48.
Support facilities (Staff) 166 45 7.47 4.9
Circulation 3,200 15 48.00 28.
B-B Function Hall 9,158 15 137.37 82.
Pre-function 2,133 15 32.00 19.
Support facilities (Staff) 177 45 7.97 5.3
Meeting spaces 25,050 15 375.75 225
Management Offices 15 45 0.68 0.4
VIP Lounges 25 45 1.13 0.7
Café 235 45 10.58 7.0
Reception 572 45 25.74 17.
Business Centre 20 45 0.90 0.6
First aid rooms 4 45 0.18 0.1
Cloak rooms 6 45 0.27 0.1
Amphitheatre Green rooms 38 45 1.71 1.1
Other staff 363 45 16.34 10.
Business Centre 217 45 9.77 6.5
F&B 2,789 15 41.84 25.
Amphitheatre visitors 2,340 15 35.10 21.
Admin Building 829 45 37.31 24.
Sub Total (1+2) 2,610.2 1,574
3. OTHER AREAS

Landscape (51.20 % of Plot 1 ltrs/day 256


2,55,955.675
Area)
HVAC** 11,445 TR 1,075
D.G. Cooling* 18,740 kVA 0.9l/kVA/hr 101
Total (1+2+3) 3,975 KLD say
3.9 MLD
*(D.G. sets operational hours are 6-8 hrs)

** HVAC cooling required fresh water demand during dry season in 632 KLD and 376 KLD
during Monsoon.

Wastewater Details
S.No. Details Water (KLD)
1.
Fresh Water Requirement 1,574
2. Wastewater to be generated from domestic 1,259
use (@80% of domestic wastewater)
3.
Water Requirement for Flushing Purposes 1,036
Wastewater to be generated from Flushing
4.
(@100 % of Flushing Requirement) 1,036

Total Wastewater Generated (80% of fresh


5.
wastewater + 100% Flushing wastewater) 2,295 or say 2.2 MLD

FHTDWT T r o e t
Vlroaa. r a t le
AuersdG W a
CsatW. t t e a r
he t i R e
tC e r
iecw q u i
ndW(oua r 1 e
ga8ot m l 3 e
Wt6let n t
aeKiur L
rDnr t )
e
gr
Figure 3 : Water Balance Diagram during Dry Season
FHTDWT T r o e t
Vlraa. r a t le
AuesdG W a
CsatW. t e a r
he t R e
tC e r
iew q u i
ndW(oa r 1 e
ga8ot m 3 e
Wt6le n t
aeKir L
rDn t )
e
gr
Figure 4: Water Balance diagram during Monsoon Season

During Construction Phase

The quantity of sewage generation during the construction phase will be approx. approx. 11

KLD. Thus the sewage will be treated by providing small septic tanks, soak trenches and

sulabh shauchalaya type mobile toilets.

During Operational Phase

Quantity of sewage generated during operational phase shall be 2,295KLD. Thus the sewage

will be treated through sewage treatment plant of capacity 2,200 KLD. The treated sewage

will be re used for flushing (1,036 KLD) greenbelt development (256 KLD) and for HVAC (632

KLD during Non Monsoon Season and 376 KLD during Monsoon Season).
Sewage Treatment Technology
The design of sewage network shall be done in accordance with the CPHEEO guideline, NBC

guidelines and reverent Indian Standards. Sewage generation is assumed to be 100% of

flushing water and 80% of domestic water.

The following parameters/ site conditions shall be kept in mind when designing the sewage,

Sludge and storm water drainage system.

 Natural slope of the area.


 Layout of different facility in the complex;
 Possibility of using complete or part of the existing sewage network;
 Sub-soil water table;
 Provision of Sewage lifting station; ( if required)
 Provision of venting arrangement for manholes;
 Construction of manholes & laying of pipes considering ground condition;
 Termination of vent cowl at terrace level;
 Provision of adequate slope for horizontal header in the under slung pipes especially

for public toilets


 Sewage flow starts with fractional capacity and builds up to full capacity in due

course. An operational plan to meet this demand from a low flow to full flow will be

part of the design.

A summary of board design parameters to be adopted for designing Sewage supply system is

given below.

Table 11: Design Parameters for Sewage Collection System

Different Use Norm Used


Type of Collection System Separate System
Design Period -30 years for sewers and
appurtenances -15 years for pumps
and electric equipment’s
Peak Factor 3
Minimum velocity 0.6 m/sec
Maximum velocity 3.0 m/sec
Minimum size of pipe 250 mm (ID)
Minimum depth of Sewer 1.0 m from FGL (0.6 m minimum
cushion)
Hydraulic Formula for calculation Manning’s formula V= 1/n*(R^2/3)
for design of sewer lines (As per *(S^1/2 ) V= Velocity R = Hydraulic
CPHEEO manual 3.4.2.1 page no- mean depth = A/P S = Slope

36)
Flow conditions in pipe up to 400 0.50 full
mm dia
Flow conditions in pipe up to 300 0.67 full
mm dia
Manning’s Co-efficient ‘n’ 0.011
Shape of sewers Circular
Material of sewers HDPE
Manhole Sizes As per manual on sewerage and
sewerage treatment/ IS4111:1985
For depth above 0.9m & up to 900 mm diameter
1.65m
For depth 1.65m & up to 2.3m 1200 mm diameter
For depth 2.3m & up to 9.0m 1500 diameter

Technology Proposed- MBR (Membrane Bio Reactor)


The MBR is a suspended growth-activated sludge system that utilizes micro porous

membranes for solid/liquid separation instead of secondary clarifiers.

An external sewage network shall collect the sewage from all units, and flow by gravity to the

proposed sewage treatment plant.

Following are the benefits of providing the Sewage Treatment Plant in the present

circumstances:

 Reduced net daily water requirements, source for Horticultural purposes by

utilization of the treated wastewater. This shall consequently lead to a lower

withdrawal from the underground aquifer water sources.

 Reduced dependence on the public utilities for water supply and sewerage

systems.

 Sludge generated from the Sewage Treatment Plant shall be rich in organic

content and an excellent fertilizer for horticultural purposes.

The STP is being proposed with state-of-the-art membrane separation technology called as

Membrane Bio-Reactor (MBR) which can produce very good quality with highest possible

bacterial reduction without adding any chemicals. MBR (Membrane Bio Reactor) is the latest

technology in wastewater treatment. MBR has many advantages such as higher quality of

treated water, smaller space for installation and easier operation compared to conventional

activated sludge process.


Designed to produce high quality treated water from wastewater the Membrane Bio Reactor

(MBR) is among the latest technologies in biological treatment.

The characteristic of the MBR process is the use of revolutionary submerged polymeric

hollow fibre membranes in the biological process water tank, so as to produce high quality

permeate from domestic sewage, primary and secondary waste water, cooling tower blow

down etc. The MBR is also ideal for retrofitting/augmenting capacity/quality of existing

wastewater plants.

The hollow fibers are combined into bundles and wound around a carrier cartridge, which

gives the membranes the required strength and allows for high-pressure air scour for

cleaning. The MBR can handle very high sludge concentrations in the aeration tank because

of which the size of the aeration tank reduces four to five folds. As the membrane acts as a

fine filter, it does not require any further treatment using sand filters, activated carbon

filters, etc. The MBR is available in standard and customized modules.

Process Description

Figure below shows the principle of the filtration for the flat sheet type submerged

membrane. Activated sludge in the aeration tank is clearly removed by the flat sheet type

submerged membrane. The membrane module consists of housing, aeration diffuser;

permeate water manifold and membrane elements. The membrane element consisting of flat

sheet membranes sandwiching a support panel is set up vertically. Feed water including

activated sludge is filtrated by flat sheet membranes with pore size of 0.1 micron meter. The

air bubbles supplied from the bottom of the membrane elements continuously scour off cake

of activated sludge accumulated on the membrane surface. This is continuous filtration

operation. The air bubbles are also used for the biological reaction to decompose organic

substances included in the raw sewage.


Figure 5: Schematic Diagram of MBR Technology

MBR Module

The material of the membrane is PVDF (Poly vinylidene fluoride). PVDF is fluorine polymer,

which has high stability for chemicals and good physical strength. The form of membrane is

fibre reinforced flat sheet membrane. The membrane has small and uniform pore size.

Therefore, the rejection property of this membrane is excellent. Almost all particles with sizes

more than 0.1 micron meter can be removed effectively using this membrane.

Operation

 Sewage from main drain line is collected through gravity pipes into a screen chamber.

This manually cleaned screen is provided to remove floating and big size particles, which

may choke the pumps and pipe lines.

 Screened sewage is then passed through equalization tank to homogenize the sewage

quality and also even out flow fluctuations and feed sewage of uniform quality at constant

rate to subsequent treatment units. Air mixing is also provided to mix the contents of the

equalization tank. A coarse bubble aeration grid is provided to distribute air uniformly at
the base of the equalization tank.

 After above treatment, raw sewage is fed into aeration basin.

 In aeration tank, MLSS (mixed liquor suspended solids) in the range of 12000 to 15000

mg/l are maintained. The high amount of bacteria gives better and complete removal of

organic matter from the raw sewage in relatively small area. Oxygen required for the

bacteria is supplied through the blower. The air is used both for scouring of membranes

and supplying oxygen to bacteria.

 The filtration is carried out by the suction pump directly sucking permeates water. The

permeate water produced is clear and devoid of bacteria and viruses to the minimum

levels.

 As the membranes are continuously under operation, they are polluted with organic or

inorganic substances. Hence, chemical cleaning is carried out once in two to three

months for removing substances polluting and clogging the membranes. Normal cleaners

used are sodium hypo chloride and citric acid.

Sewer System

The alignment and slope of the sewer line will follow the road network, drains or natural

ground surface and will be connected to the trunk sewers. The discharge point will be a

treatment plant, a pumping station, a water course or an intercepting sewer. Pumping

stations would be provided at places where the natural slope of the terrain is insufficient to

permit gravity flow or the cost of excavation is uneconomical to do the same

Table 12: Wastewater Details

Particulars Quantity
Daily load 2,295KLD
Duration of flow to STP 24 Hours
Temperature 320 C
Inlet Outlet (Treated Wastewater )
pH 6.0 – 9.0 7.0-8.0
T.S.S. (mg/l) 300-400 <10
BOD5 270 C (mg/l) 250-300 <20
COD (mg/l) 400-600 <50
Oil & grease ABS (mg/l) <50 <10

Preventive measures to Avoid Leaching


Treated sewage from Sewage Treatment Plant will be conveyed to Treated Sewage Tank

through pipelines. All the joints from piping system will be checked periodically and carrying
treated wastewater pipes will be laid in conduits wherever road crossings are expected. Thus

no leaching of treated sewage into nearby water courses shall take place. Supervisors will be

employed for overall operation & maintenance of water supply, waste water treatment and

other utility services.

Rainwater Harvesting and Strom Water Drain


A rainwater harvesting system comprises components of various stages -transporting

rainwater through pipes or drains, filtration, and recharging the ground water through

tanks. Percolation structures will be constructed for ground water recharge.

Runoff from the first spell of rain carries a relatively large amount of pollutants from the air

and catchments surface so the system will be provided with a filtration pit consisting of

layers of sand, gravel and pebbles of relevant sizes to remove impurities from the collected

rainwater.

Need for Rainwater Harvesting


Surface water is inadequate to meet the daily demand and we have to depend on ground
water.

 Due to rapid urbanization, infiltration of rain water into the sub-soil has decreased
drastically and recharging of ground water has diminished.
 Rainwater harvesting prevents the flooding of low-lying areas in the site.

Rainwater Harvesting Network


Rain water harvesting structures will be constructed all around the compound wall to collect

rain water. Excess storm water will be allowed to drain into the external storm drain.

Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak

hourly rainfall has been considered as 11 mm/hr. The recharge well of 10 mtr dia and 10

mtr depths and 4 mtrs width will be constructed for recharging the water. The bottom of the

recharge structure will be kept 5 m above this level. At the bottom of the recharge pit, a filter

media is provided to avoid choking of the recharge bore.

The pit will be filled with rounded gravel 5 to 10 mm size. The sectional detail of the

proposed rain water recharge structure is provided in below figure.

The path ways around the harvesting lines will be graded to facilitate drainage into trenches

proposed around the compound. Recharge wells/structures are envisaged along the path of
the storm water drains for rain water recharging & surplus water from the recharge

wells/structures shall be diverted to the storm water drainage network.

The collected storm water will be allowed to percolate to the sub-soil by suitably designed

percolation structures. The structures will be designed based on the soils percolation

capability. The subsoil water table is high in these areas and however harvesting structures

with bores will be provided.

Percolation structures of suitable numbers will be provided for recharge of ground water

potential. A total of 10 rain water harvesting structures will be constructed. The quantity of

storm water load for the proposed construction project is given below.

Table 13: Calculation for Strom Water Load for the Development of IECC

S. Type of Catchment's Area Run Intensity Discharge (Run Total


No. Surface sq. m Ha. off of Off) [Q=10CIA] (m3/hr)
Coff. Rainfall m3/hr [Q]
[C] (mm/hr)
1 Building (Terrace)
(a) Area 1,40,169.75 14.01 0.60 80 10×0.60×80×14 6,720
1,80,482.31 18.04 0.20 80 10×0.20×80×18 2,886.4
1,55,409 15.54 0.75 80 10 ×0.75×80×15 9,000
Total 18,606.4
(b) Considering 15 mins (0.25) retention period 4,651.6
(c) Volume of Rain water Storage Structure 10×4×4 160 m3
(d) Total No. of Rain water Storage Structure required 29.07
Total No. of Rain water Storage Structure Proposed 10
Figure 6: Rainwater Harvesting Structure

Efficacy of Rain Water Harvesting


The area of site has the water table at 3.0 M. It is not advisable to recharge aquifer by rain

water in areas with water table less than 8.0 M. In this case, following is recommended: -

 Use the storm water to recharge lake next to Old Fort, subject to approval by ASI &
additional cost of connectivity. This will automatically mean water harvesting through
percolation.
 Use the storm water to run chillers cooling towers after tertiary treatment during the
monsoons. The treated effluent being received from DJB will not be drawn during this
period. The facility management team must ensure the same.

Parking Details
Adequate provision will be made for car/vehicle parking at the project site. There shall be

adequate parking provisions for visitors so as not to disturb the traffic and allow smooth

movement at the site.


Proposed project will be consists of basement and open parking. The parking space criteria

and area requirement provided are summarized in the table below. Parking details are

designed as per Delhi Building Bye Laws


Table 14: ECS Required

As Per DDA
Parking Required Area (m2) Total (ECS)
For the Site 2 ECS/100 2,28,520.887/ 4,570

m2 of FAR 50

area 2,28,520.887
Total Parking Required 4,570

(ECS)

Table 15: Parking Proposed

Description Area Area (m2) Parking


Required for Proposed
1 ECS ( ECS)
2
In Basement 1 ECS/32 m 1,47,392.5 4,606

of area 2
2
In Open 1 ECS/23 m 1,649.580 72

of area
In podium 1ECS/28 m2 3,584.440 128
Total Parking Proposed 4,806

(ECS)
TWO WHEELER 1000 × 0.5 500ECS
BUSES 52 × 3.5 182 ECS
CARS 4,124 × 1 4,124 ECS

Electrical details
Power Details
The power shall be supplied by BSES Delhi. The total demand load for the project (Retained

Building + Proposed) will be 17.51 MVA. It is proposed to install 2 Electrical subs- Station

named MRS-1 and MRS-2.


MRS-1 shall receive 2 Nos. 33KV supplies from BSES and feed electrical power at 11KV to

Hall A1, A2, A3, A4a, A4b, A5 and A6 by providing 2 Nos. 7.5 MVA 33/11KV and it shall be

located near Hall A5

MRS-2 shall receive 1 No. 33KV supply from BSES and feed electrical power at 11KV to

Convention Center and Admin Block by providing 1 Nos. 6 MVA 33/11KV and it shall be

located near Hall A6. 2 Nos. 33kV meter room shall be located for MRS-1 (near Hall A5) and

1 No. 33KV meter room for MRS-2 shall be near Hall Admin Block at the Ground Level.

For the MRS I, 2 numbers of (7.5 MVA), 33/11 kV, oil types outdoor transformers has been

selected. For MRS II, 1 number of (6 MVA), 33/11 kV, oil types outdoor transformers has

been selected

D. G. Sets Details

In case of power failure, there are 2 Nos. 11 KV DG rooms with corresponding 2 Nos. MRS .it

provides the 100% power back up for the development. The location of DG rooms shall be

either at the ground or in Basement. D.G. sets location and their description is given below.

Table 16: D.G. sets location and their description

S.No. Description Feed


1. DG Room-1 (For Hall A1, A2, A3, A4a, 6 Nos. 2MVA & 2Nos.

A4b, A5 and A6) 2.5MVA, 11KV DG Sets


2. 4 Nos. 2MVA, 11KV DG
DG Room-2 (For Hall A6 and Admin Block)
Sets

Lighting system
Lighting systems with green features to be used for this project are:

 Solar Street Lightings.


 LED lights over T5 or T8 Fluorescent lightings.

Lighting Control through day lighting and sensor Motion

It is proposed to use Presence/Occupancy sensors in common areas like corridor, Lift Lobby,
Toilets etc. which will result in considerable saving of energy.

 Two way programmable High performance, compact presence detectors /occupancy

sensors will be used which provide automatic control for lighting loads.
 It detects human presence and automatically turns the lights ‘ON’. When the area is

vacated, the lights turn ‘OFF’ after a preset time period.


 The sensor has advanced presence detection by passive infrared (PIR) technology along

with Sensitivity level adjustments. The sensor has Adjustable off delay timing 10 sec –

99 min which can be programmed & changed using a remote control.


 The sensor has a Passive photocell that holds lights OFF in extremely bright ambient

conditions.
 The occupancy cum day light sensors will be used which are used for switching off the

luminaries when the areas are unoccupied & also used for dimming the luminaries

when there is day light coming inside the building & thus help to reduce the power

consumption.
 This sensor is basically used in the areas along the building façade where the day

light contribution is high. Along with presence detection, this sensor has built-in

adjustable photocell which regulates the lighting level as per availability of natural

daylight in an area, thus maintaining uniform illumination.

Integrated Fire Detection System


This will comprise of below mentioned components.

 Intelligent addressable Fire Detection system with communication, notification &

Interface capability.
 Manual call points for activation of fire alarm system manually.
 Integrated Emergency Voice Evacuation System.
 Interlocking with other equipments likes Elevators, Air-conditioning Units, Smoke

Extraction system etc.

Solid Waste Details


During Construction Phase of the Proposed Building

The solid waste expected to be generated during the construction phase will comprise of

excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following

steps are proposed to be followed for the management solid waste:

 Construction yards are proposed for storage of construction materials.


 The excavated material such as topsoil and stones will be stacked for reuse during

later stages of construction.


 Excavated top soil will be stored in temporary constructed soil bank and will be reused

for landscaping during operational phase of the project.


 Remaining soil shall be utilized for refilling / road work / rising of site level at

locations/ selling to outside agency for construction of roads etc.


 Construction waste management is shown in below figure.
H
C
R
E
T
D
m
x
o
e
a
s
f
t
d
a
c
p
m
n
t
i
y
v
s
o
d
r
M
a
o
l
e
u
l
C
a
t
i
d
c
i
k
e
l
s
t
n
m
i
d
h
o
i
g
e
n
c
v
,
n
g
S
o
w
e
R
t
o
n
a
r
a
i
s
n
w
s
i
a
B
l
r
e
t
D
s
i
g
v
e
o
t
n
s
e
m
e
g
d
G
,
o
l
B
S
f
v
r
i
o
t
o
t
r
i
k
e
.
o
n
e
L
a
l
e
n
a
W
b
v
d
p
a
r
e
s
p
s
i
l
c
r
t
c
a
o
e
k
p
v
s
i
e
,
n
d
W
g
s
a
t
n
g
d
e
n
p
r
c
l
e
y
a
f
s
i
f
t
l
o
e
l
r
r
n
i
g
f
i
t
h
n
e
a
l
s
i
d
e
t
i
s
p
o
s
a
l

Figure 7: Solid Waste Management for Construction Phase

C & D waste of Existing Buildings

 Construction and demolition waste of the site shall be keep within the premises.
 The waste shall be deposited at collection centre so made by the local body or
handover it to the authorized processing facilities for further process or disposal.
 As inert it shall be used to fill material for low -lying areas, landscaping, Road Making
etc.
 Finer grade can be molded into blocks and slabs with appropriate binder.

During Operational Phase

The project will adopt a systematic approach for solid waste collection and disposal. Solid

waste generated from the project will be collected properly and will be managed as per MSW

Rules, 2000 amended in 2016.

 Waste shall be mainly categories in two classes. 1. Bio degradable Waste 2 Non-

biodegradable Waste. The biodegradable portion dominates the bulk of MSW. This is

mainly due to food and yard waste.


 These solid wastes will be collected separately by putting three types of separate bins

at the source of generation. For the biodegradable waste yellow bins will be provided,

for the recyclable waste black bins and for the non-recyclable waste red bins will be

provided.
 It is estimated that maximum solid waste generation would be about 26,835.26 kg/day;
Following are the solid waste generation rate has been considered as is given table.
Table 17: Calculation of Solid Waste Generation of Retained and Proposed Building

S.No. Category Counts Weste Waste


(heads) generation Generated
(p/kg/day) (kg/day)
For the Retained and Proposed
Building
1. Staff 671.75
 Support 343 41.50
Facilities
 Management 15
44.25
Office
 VIP Lounges 25 3.75
 Café 235 6.25
 Reception 572 @ 0.25 58.75
 Business Centre 20 kg/day 143.00
 First Aid Rooms 4 5.00
 Cloak rooms 6 1.00
 Amphitheatre 38
1.50
Green Rooms
 Other staff 383 9.50
 Business Centre 217 95.75
 Admin Building 829 207.25
2. Visitors
26,154.60
 Exhibition Halls 1,18,894
(A1-A13)
17,834.10

 G-G Plenary 5,410


Hall (Axial & 811.50
Radial Partition)
 Pre- Function 5,390
@ 0.15 808.50
 Circulation 3,200 kg/day 480.00
 B-B Function 9,158
1,373.70
Hall
 Pre- Function 2,133 319.95
 Meeting Spaces 25,050 3,757.50
 F& B 2,789 418.35
 Amphitheatre 2,340
Visitors 351.00

Total Domestic 26,826.35


Waste (1+2)
11. Landscape waste @ 0.2 8.91
(44.59 Acre) kg/acre/da
y

Total Waste 26,835.26


generated (1-3) kg/day
(Source:http://cpheeo.nic.in/WriteReadData/Cpheeo_SolidWasteManagement/chap3.pdf )

Following arrangements will be made at the site in accordance to Municipal Solid Wastes
(Management and Handling) Rules, 2000 and amended Rules; 2016.

Collection and Segregation of waste

For Domestic Waste

 A door to door collection system will be provided for collection of domestic waste in

colored bins from every unit.


 The local vendors will be hired to provide separate colored bins for dry recyclables and

Bio-Degradable waste.
 For waste collection, adequate number of colored bins (Green and Blue & dark grey

bins– separate for Bio-degradable and Non Bio-degradable) are proposed to be

provided at the strategic locations of the area.


 Litter bin will also be provided in open areas like parks etc.

Treatment of Waste

Domestic Waste

Bio degradable Waste

 Bio-degradable waste will be subjected to the compost/resultant will be used as

manure.
 STP sludge is proposed to be used for horticultural purposes as manure.
 Horticultural Waste is proposed to be composted and will be used for gardening

purposes.

Recyclable Waste

The cropped grass will be spread on the green area. It will act as manure after
decomposition.
 Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.

Disposal

Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.

Hence, the Municipal Solid Waste Management t will be conducted as per the guidelines of
Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2016.

Solid waste management Scheme is depicted in the following figure.

M
S
R
N
D
t
B
G
C
ile
r
o
a
l
c
u
r
o
e
m
n
i
y
G
-
k
g
d
e
p
u
d
B
c
R
e
n
o
r
li
b
G
v
g
s
e
w
o
ia
c
r
b
t
d
b
n
.y
ia
e
le
s
c
y
d
n
r
t
g
le
a
s
e
r
a
B
p
b
a
ib
lp
ld
n
r
e
a
e
s
o
b
v
W
la
e
e
d
s
t
e
W
V
a
a
e
g
s
n
e
n
t
d
e
o
c
r
y

Figure 8: Solid Waste Management Scheme -Domestic Waste

Landscape Details
 Total green area measures 2,55,955.675m2 (51.20 % of Plot Area)
 A diverse variety of indigenous evergreen and ornamental trees would be planted. As

the project site for construction consists of trees, herbs and shrubs it will require

cutting of trees for construction purpose.


 Total number of trees planted will be 6,713. However nos of trees retained will be 913.
 The plant species will be selected on the basis of Urban Standard Plantation norms

and CPCB guidelines.


 Landscape Details are given in below table

Table 18: Landscape Area Details

Particulars Details
Plot area 4,99,829.28 m2
Open area 3,75,255.895 m2
Landscape area Proposed 2,55,955.675m2 (51.20 % of Plot Area)
As Per MoEF Guidelines One tree per 80 m2 of total area out of which
minimum 50 % to be in the category of
evergreen trees.
Trees Required 4,99,829.28/80= 6,247.866 Trees
Number Of Trees Proposed To 6,713 Trees (Existing Trees Retained= 913)
Be Planted

Table 19: Plantation List

Energy

Conservation Measures
 CFC free equipment, chillers with CFC-free environmentally friendly refrigerant will be
installed to protect the ozone layer.
 The Building envelope details has been followed as per ECBC to reduce heat intake
from outside. Walls, roofs and glass U values will be less than the ASHRAE Standard
90.1 2007 to save energy compared to baseline building energy consumption.
 Lighting power densities are expected to be less than the ASHRAE Standard 90.1 2007
base line to save energy compared to baseline building criteria.
 Provision and space allocation for energy metering will be provided for the following
system loads for continuous monitoring:
 Air conditioning
 Internal lighting
 External lighting
 Treated Effluent water pumping
 Landscape water pumping

 Solar water supply shall be restricted to kitchens.


 The DG set will be ISI rated and certified by the central pollution control board (CPCB)
for emission and noise.
 Level controllers in water tanks will be provided to avoid overflow of water and waste of
energy
 All pumps will be ISI rated with a minimum 60% efficiency
 LED lamps will be provided in all display/exit sign boards to save energy
 Movement sensors for lighting control will be provided in toilets, study rooms,
staircases, cabins, corridors, garbage rooms, balconies, washing and storage areas
 Provision of 50% solar PV panel with LED Street lighting for the external area with
50% based on conventional LED Street lighting to be subjected to GRIHA Consultant
advice.
 Provision of LED lighting over T5 fluorescent lighting.

List of the construction Material Used


List of building materials being used at site:

1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
9. ACC Blocks
10. Crazy (white marble) in grey cement P.V.C. conduit
11. MDS, MCBs
12. PVC overhead water tanks
13. 2 1/2'’ thick red colour paver tiles
14. PPR (ISI marked)
15. PVC waste water lines
16. S.W. sewer line up to main sewer
17. PVC rain water down take
18. Stainless steel sink in kitchen

Potrebbero piacerti anche