Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Das
NITK, Surathkal
• Its uniqueness.
Termination
Realisation
Development
Conception
2. It is not of itself a time schedule but it contains all the time based
and other plans for the project. It sets out the ‘What', 'Why',
‘When‘, ‘Who', ‘Where', ‘How' and often the ‘How much' of the
project.
• project progress.
• expenditure.
• costs.
• foreseen possible adverse or beneficial events as documented in the
project risk register.
This structure will affect the way the organisation can respond to
change and the introduction of projects.
Project
Authority
Relative
Functional
Authority
100%
0%
Functional with very Project with very
Matrix authority
Limited Project authority Limited Functional authority
Product Service
Constructed Facility Contract Planning Culture
(Received by End-user) (Received by Owner) Quality Systems
(Received by Client/ Society)
• Most construction projects take many months if not more to complete. This
time factor makes many sites susceptible to disruption and inclement
weather.
• The people involved in each construction project may change from month to
month. No two construction jobs have the same set of designers, advisors,
supervisors or operatives. This invariably leads to variations in quality. There
is, moreover, a certain lack of continuity in construction jobs often resulting
from a change in the workforce composition.
•Materials and components do not necessarily come from the same sources for all
contracts. This tends to lead to greater variations in quality.
•Because of the dichotomy between the designer and contractor indicated above,
architects do not normally tell builders how to erect buildings. In other works, the
client, via the designer, tells the builder what is required – he does not tell the
contractor how to go about it, unless special site or contractual considerations are
present. This may lead to some changes in theconstruction during the contract by the
builder to suit his program.
•Quality control is not consistent from site to site. For instance, standards of
supervision by site agents and clerks of works will depend upon the respective
backgrounds of those involved, their attention to detail and the time spent on site,
etc.
•Feedback between the user or installer and designer is often slow or difficult if not
non-existent. Dr. B. B. Das, NITK Surathkal
Money
Land Materials Manpower Equipment
Management
The Project
Dr. B. B. Das, NITK Surathkal
Incorrect Assumptions
Incorrect Estimation
Work More Difficult than Anticipated
Non-availability of Equipment
Changes in Designs, Budget, Dead line
Land Acquisition
Human Error
Approvals
Conflicts
• tactical plans - which are those made 'when in contact with the
enemy'.
(Short-Term Plan)
Foundation
Super
structure
Finishing Task level
Base Raft Plinth wall
construction construction construction Work package level
Shuttering Reinforcement Concreting Curing Activity level
• Can you accurately estimate how long the activity will take?
• If you have to assign the activity to someone else, are you confident
that he’ll understand exactly what to do?