JOB RISK ASSESSMENT - FRON
1 of ……
Date JOB
6/19/2019
Tanggal PEKERJAAN
Installation / Site CPU - TRF
Instalasi / Lapangan
Buillding maintenance at CPU and
Assessed Overall Risk
Penilaian Resiko Keseluruhan RISK Level 3
Notes
Task Assessment / Safety Critical Tasks:
1. Excavation and backfilling 7. Remove and install roof gutter and ceiling
(Penggalian dan penimbunan kembali) (Pemasangan dan pembongkaran atap,talang dan pla
2. Drive Ulin Pile 8. Painting works
(Pemancangan kayu ulin) (Pengecatan)
3. Carpentry works 9. Plumbing works
(Pekerjaan Pertukangan kayu) (Pekerjaan Pipa)
4. Masonry works
(Pekerjaan Tukang Batu)
5. Hot Works
(Pekerjaan Panas)
6. Demolition works
(Pekerjaan Pembobokan)
Others information:
◎. Use and wear proper PPE in proper way ( Pergunan alat pelindung diri dengan benar )
◎. Use Cold / Hot Work Permit , and follow work permit procedure ( Pergunakan izin kerja yang sesua
◎. Perform safety talk, pre job meeting, last minute risk assessment, and maintain good communicati
( Lakukan persiapan yang meliputi : Pengarahan keamanan,persiapan kerja, penilaian resiko pam
◎. Working on live electricity the use of non Ex equipment and on hazardous area must be started and followed with conti
on surrounding working area by using portable gas detector
( Pekerjaan pada peralatan yang bertegangan dan penggunaan alat yang tidak bersertifikasi khusus harus diiringi denga
Name : Name :
Date : Date :
Name : Name :
Date : Date :
ASSESSMENT - FRONT SHEET
JOB System
PEKERJAAN
Ref. No
ding maintenance at CPU and TRF
Reassessment Required ? Yes / No *)
Notes
ISIT/MEETING PERFORM
Duration
Durasi
ormed by / Penilaian Resiko dilakukan oleh :
Signature Position Signature
service manager
Name :
Nala Y.
Date :
6/19/2019
Name :
Date :
Name :
Date :
PAGE INSTALLATION CPU - TRF SYSTEM -- REF. -- LEADER
JOB DESCRIPTION
REVIEW SHEET
REVIEWER
COMMENTS UPDATED DOC.
NO. NAME ENTITY SIGNATURE DATE
Production < 2K boe ≥ 2K boe ≥ 20K boe ≥ 200K boe ≥ 1M boe ≥10M boe
Shortfall
International press +
Local rumour or no media Regional press + regional TV International press +
Media Reaction consequence
Local rumour / regional press
national rumour
National press + national TV
international TV
international TV for prolonged
period
Severity of Consequence
Production Shortfall Personnel Safety, Environment Impact, Material Loss
Minor Moderate Serious Very Serious Catastrophic Disastrous
(or Gain) & Media Reaction
1 2 3 4 5 6
Ri
Incident probable with
sk
additional factors (or for gain)
Could occur several times during over plant Likely
5 5 10 15 20 25 Le 30
Probability / Likelihood of Occurrence
ve
lifetime 10-1 - 10-2
successful modification
outcome
Ri l
sk 1
Incident possible with
additional factors (or for gain) Could occur once for every 10 to 20 similar Unlikely
4 4 8 12 Le 16 20 24
Some uncertainty of successful plants over 20 to 30 years of plant lifetime
modification outcome
10-2 - 10-3
ve
l2
Ri
Combination of rare factors One time per year for at least 1000 units. One
required to cause an incident time for every 100 to 200 similar plants in the
Very Unlikely
3
sk 6 9 12 15 18
3
Le
(or for gain) High uncertainty of world over 20 to 30 years of plant lifetime.
successful modification Has already occurred in the company but 10-3 - 10-4
outcome corrective action has been taken
ve
l 3
Has already occurred in the industry but
Extremely Unlikely
Freak combination of factors
required to cause an incident
corrective action
has been taken 10-4 - 10-5
2 2 4 6 8 10 12
*1) for more detail on environment definitions, refer to Guidence for Environment Classification Risk Level 1 First priority, risk level to be obligatory reduce to level 2 or 3
(MHK-COMP-RUL-EP-HSE 0102) Major Consequence
Risk Level 2 Tolerable risk level if demonstrated to be ALARP
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE
x
- Untuk menurunkan tingkat kerusakan
Hazard 2 : Damage existing cable and fresh water pipe line (Jalur Kabel dan jalur pipa air rusak)
Material consequences (Akibat terhadap peralatan) 4 4 16 4 2
Damage existing cable
To reduce probability
Untuk menurunkan probabilitas
Soil excavation and backfilling by manual
1 ( Penggalian dan penimbunan tanah secara
manual ) - Provide excavation permit and drawing under ground cable layout
x
- Ijin kerja penggalian dan denah gambar kabel bawah tanah tersedia
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
- Use shovel
- Gunakan Sekop x
High First priority, risk level to be obligatory reduce to level 2 or 3 Medium Tolerable risk level if demonstrated to be ALARP Low
LEADER
DURATION
DESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
12
PT.BJM
PT.BJM
LEADER
DURATION
DESCRIPTION
PT.BJM
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
Hazard 2 : Damage existing underground facilities ( Electrical,telephone & instrument cables, fire & fresh water pipeline ) Kerusakan fasilitas bawah tanah ( Jalur elektrikal
Material consequences (Akibat terhadap peralatan) 4 4 16 3 3
Demage existing underground facilities
To reduce probability
Untuk menurunkan probabilitas
- Identify the existing cables and fresh water pipe line and install marker
- Kenali jalur kabel dan pipa air yang telah ada dan pasang tanda x
Demage existing underground facilities
To reduce severity
Untuk menurunkan tingkat kerusakan
- Always proper PPE
- Selalu menggunakan APD yang tepat x
High First priority, risk level to be obligatory reduce to level 2 or 3 Medium Tolerable risk level if demonstrated to be ALARP Low
DURATION
DESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
fire & fresh water pipeline ) Kerusakan fasilitas bawah tanah ( Jalur elektrikal,telepon,& kabel instrumen,Pipa Api& air )
9
PT.BJM
LEADER
DURATION
DESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
Perfoming Authority
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
To reduce severity
Untuk menurunkan tingkat kerusakan
PAGE INSTALLATION -- SYSTEM -- REF. --
Personnel injury
ATTENDEES SITE VISIT Yes / No *) DATE
JOB DESCRIPTION
DURATION
DESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
PT.BJM
LEADER
DURATION
DESCRIPTION PT.BJM
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
15
PT.BJM
PT.BJM
LEADER
DURATION
DESCRIPTION
PT.BJM
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
Human Consequence 3 4 12 3 3
Respiratory Injury To reduce probability
Personnel Injury Untuk menurunkan probabilitas
To reduce severity
Untuk menurunkan tingkat kerusakan
Hazard 2 : Falling of part being removed, sharp object Kejatuhan benda saat bekerja, benda tajam
Human Consequence 4 5 20 2 5
Hand & Finger Injury
To reduce probability
Personnel injury Untuk menurunkan probabilitas
Instal Baricade
- No body is under working area
- Tidak ada orang di bawah area kerja x
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
Human Consequence 3 3 9 2 2
To reduce probability
Untuk menurunkan probabilitas/kemungkinan
JOB DESCRIPTION
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
10
PT.BJM
LEADER
DURATION
ESCRIPTION
PT.BJM
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
4
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE (electrical hand gloves & full face shield helmet)
x
- Selalu menggunakan APD yang sesuai/lengkap
Hazard 2 : Grinding disk burst/ Mata gerinda pecah meledak
Human Consequence/konsekuensi terhadap manusia 4 4 16 4 2
Personnel injury
To reduce probability
Untuk menurunkan probabilitas
JOB DESCRIPTION
- Wear proper PPE (electrical hand gloves & full face shield helmet)
- Selalu menggunakan APD yang tepat / lengkap x
Hazard 3 : smoke fire, Dust contamination rubbish / asap, api ,Terkontaminasi kotoran debu
Human Consequence 4 4 16 2 3
Skin burns injury To reduce probability
personel injury Untuk menurunkan probabilitas/kemungkinan
To reduce severity
Untuk menurunkan tingkat kerusakan
JOB DESCRIPTION
Human Consequence 3 4 12 2 4
damage/ future on the nearest smoke detector or To reduce probability
gas detector Untuk menurunkan probabilitas/kemungkinan
To reduce severity
Untuk menurunkan tingkat kerusakan
- bypass pendeteksi asap atau gas yang dapat terkena efek pada area krja. x
Hazard 5 : Perapihan dan pembersihan yang kurang / Lack of House keeping, Tersandung dan abstraksi personil / Tripping and abstraction personnel
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
12
PT.BJM
8
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
PT.BJM
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
JOB DESCRIPTION
All material & equipment must arrenged properly and safely / 'Semua
material dan peralatan harus di rencanakan secara tepat dan aman x
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE / Selalu menggunakan APD yang sesuai, (gunakan high
inpact glove untuk barang atau benda tajam) x
JOB DESCRIPTION
-all personel involved within the job must peform last minute risk assesment
during the job / semua orang yang terlibat dalam pekerjaan selalu x
melakukan resiko penilaian akhir ketika bekerja.
To reduce severity
Untuk menurunkan tingkat kerusakan
-splash the material being dismantled with water to prevent dust /material yg
di bongkar dengan air untuk mencegah keluarnya debu. x
- Wear proper PPE ( hand gloves, dask mask & full face shield helmet)
/Selalu menggunakan APD yang tepat / lengkap.
Hazard 3 : lack of haousekeeping,stumble or obstructed by material /kurang menjaga kebersihan, Tersandung atau terhalang oleh material
Human Consequence 4 4 16 2 4
To reduce probability
personel injury Untuk menurunkan probabilitas/kemungkinan
To reduce severity
Untuk menurunkan tingkat kerusakan
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
rsonnel / Penanganan dan pemindahan material, Benda jatuh Tersandung
PT.BJM
6 taja
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
PT.BJM
LEADER
DURATION
ESCRIPTION
PT.BJM
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
All material & equipment must arrenged properly and safely / 'Semua
material dan peralatan harus di rencanakan secara tepat dan aman X
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE / Selalu menggunakan APD yang sesuai, (gunakan high
inpact glove untuk barang atau benda tajam) X
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE ( hand gloves, dask mask & full face shield helmet)
- Selalu menggunakan APD yang tepat / lengkap. x
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
rsonnel / Penanganan dan pemindahan material, Benda jatuh Tersandung
PT.BJM
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
6 taja
PT.BJM
12
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
To reduce severity
Untuk menurunkan tingkat kerusakan
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
er or turpentine / terkontaminasi oleh debu dan larutan kimia (uap cat, cat ,thinner/pengencer cat)
8
PT.BJM
6 taja
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM
10
PT.BJM
PAGE INSTALLATION -- SYSTEM -- REF. --
JOB DESCRIPTION
To reduce severity
Untuk menurunkan tingkat kerusakan
- Wear proper PPE / Selalu menggunakan APD yang sesuai, (gunakan high
Install, replace , repair inpact glove untuk barang atau benda tajam) x
sanitaries and fresh water
9. pipe line.(Pasang Hazard 2 : lack of poor of housekeeping at working area / kurangnya pembersihan dan perapihan pada area
kerja
,mengganti,memperbaiki jalur
Human Consequence/konsekuensi terhadap manusia 3 4 12 2 3
pipa air bersih dan sanitasi)
Personnel injury
To reduce probability
Kontaminasi pencemaran lingkungan / Untuk menurunkan probabilitas
JOB DESCRIPTION
-all personel involved within the job must peform last minute risk assesment
during the job / semua orang yang terlibat dalam pekerjaan selalu x
melakukan resiko penilaian akhir ketika bekerja.
- Wear proper PPE ( hand gloves, dask mask & full face shield helmet)
x
- Selalu menggunakan APD yang tepat / lengkap.
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
structed or blocked/ penanganan & pemindahan material, basah,licin, benda tajam, tersandung menghalangi akses
PT.BJM
6 taja
PT.BJM
LEADER
DURATION
ESCRIPTION
Residual Risk
Action Party Target Date Last Minute Risk Assessment
R
PT.BJM