Progress Report Template

Project Title: ERA SHOPPING PARK ORADEA


Report for Period Ending: 8/4/2008

Task Start Finish


PHASE 1 228 days 27-Mar-08 27-Feb-09 2 days
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09 2 days
Superstructure 68 days 5-May-08 6-Aug-08 0 days
Main frame 55 days 5-May-08 20-Jul-08 2 days
12 - precast columns installation 30 days 5-May-08 13-Jun-08 2 days
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 2 days
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 2 days
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 2 days
Secondary structure 38 days 16-Jun-08 6-Aug-08 0 days
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 248 days
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 0 days
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 0 days
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 0 days
Flooring 56 days 13-Jun-08 5-Sep-08 0 days
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 0 days
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 0 days
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08 0 days
General works 37 days 1-Aug-08 29-Sep-08 0 days
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 0 days
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 0 days
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 0 days
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 0 days
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08 0 days
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 0 days
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 2 days
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 0 days
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08 11 days
42 - Finishes 55 days 16-Sep-08 1-Dec-08 11 days
47 General Works 34 days 15-Jul-08 5-Sep-08 4 days
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 4 days
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 218 days
Carrefour works 21 days 1-Sep-08 29-Sep-08 0 days
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 0 days
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 0 days
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 0 days
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08 31 days
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 53 days
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 53 days
59 - HVAC 45 days 5-Aug-08 13-Oct-08 31 days
60 - Low currents 25 days 30-Sep-08 3-Nov-08 31 days
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 31 days

Task Start Finish


EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 0 days
Exterior M&E works 143 days 12-Jun-08 16-Jan-09 0 days
81 Water tanks 30 days 17-Jul-08 3-Sep-08 8 days
Pumps station 81 days 31-Jul-08 27-Nov-08 57 days
83 - structure 35 days 31-Jul-08 24-Sep-08 57 days
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 57 days
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 57 days
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 38 days
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 38 days
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 38 days
Exterior works distribution 118 days 17-Jul-08 16-Jan-09 8 days
90 - electrical 88 days 17-Jul-08 24-Nov-08 8 days
91 - sewage 88 days 17-Jul-08 24-Nov-08 8 days
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 30 days
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09 0 days
94 - retention walls 30 days 3-Jun-08 14-Jul-08 0 days
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 8 days
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 8 days
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 8 days
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 8 days
99 Finishes 20 days 21-Jan-09 17-Feb-09 8 days
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 8 days
101 Fencing 40 days 3-Jun-08 28-Jul-08 20 days

Task Start Finish


MULTIPLEX 160 days 1-Jul-08 27-Feb-09 0 days
STRUCTURES 103 days 1-Jul-08 27-Nov-08 0 days
107 Foundations 15 days 2-Sep-08 22-Sep-08 0 days
108 Main structure 28 days 16-Sep-08 23-Oct-08 0 days
109 Secondary structures 25 days 24-Oct-08 27-Nov-08 17 days
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08 0 days
114 Installations works 42 days 24-Oct-08 22-Dec-08 0 days
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08 0 days
119 Finishes works 42 days 24-Oct-08 22-Dec-08 0 days

Task Start Finish


MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09 23 days
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 23 days
128 Finishes works 66 days 15-Oct-08 27-Jan-09 23 days
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 23 days
133 Installations works 66 days 10-Sep-08 10-Dec-08 48 days
Task Start Finish
PHASE 2 265 days 26-Jun-08 21-Jul-09 0 days
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09 0 days
STRUCTURES 161 days 26-Jun-08 25-Feb-09 0 days
Infrastructures 50 days 26-Jun-08 10-Sep-08 0 days
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 0 days
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 215 days
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 220 days
Superstructure 161 days 26-Jun-08 25-Feb-09 30 days
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 210 days
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 0 days
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 0 days
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 9 days
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 64 days
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 23 days
Floors 99 days 21-Aug-08 19-Jan-09 93 days
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 210 days
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09 0 days
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 0 days
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 9 days
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 0 days
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 36 days
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 51 days
158 - Dock levellers 20 days 14-Apr-09 11-May-09 51 days
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 36 days
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 0 days
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 64 days
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 45 days
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 0 days
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 30 days
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 30 days
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09 23 days
Water and sewage 113 days 1-Dec-08 19-May-09 23 days
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 89 days
169 - Foul water 50 days 1-Dec-08 19-Feb-09 23 days
170 - Watter supply 40 days 25-Mar-09 19-May-09 45 days
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 79 days
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 29 days
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 49 days
Boiler rooms 65 days 29-Jan-09 29-Apr-09 59 days
175 - Distribution 65 days 29-Jan-09 29-Apr-09 59 days
176 - Equipments 25 days 29-Jan-09 4-Mar-09 99 days
Electrical 70 days 29-Jan-09 6-May-09 9 days
178 - Electrical boards 25 days 2-Apr-09 6-May-09 54 days
179 - Distribution 60 days 29-Jan-09 22-Apr-09 9 days
180 - Lighting 70 days 29-Jan-09 6-May-09 54 days
181 - Supply 65 days 29-Jan-09 29-Apr-09 59 days
Low voltage 45 days 26-Mar-09 27-May-09 9 days
183 - Fire detection system 45 days 26-Mar-09 27-May-09 9 days
184 - Voice and data 45 days 26-Mar-09 27-May-09 39 days
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 39 days
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09 23 days
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 23 days
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 23 days
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 23 days
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 23 days
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 23 days
192 - Landscaping 30 days 8-May-09 18-Jun-09 23 days

Task Start Finish


BRICOSTORE 2-Jul-08 27-Jan-09 23 days
STRUCTURES 1-Jul-08 27-Nov-08 0 days
Infrastructures 26-Jun-08 10-Sep-08 0 days
193 - foundations excavations 26-Jun-08 6-Aug-08 0 days
194 - Concrete works for foundations 3-Jul-08 10-Sep-08 215 days
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 220 days
Superstructure 26-Jun-08 25-Feb-09 30 days
197 - Precast columns production 26-Jun-08 20-Aug-08 210 days
198 - Precast columns installation 7-Aug-08 22-Sep-08 0 days
199 - Precast roof elements production 23-Sep-08 21-Oct-08 0 days
200 - Installation of cladding support structure 22-Oct-08 9-Dec-08 9 days
201 - Installation of internal partitions structure 29-Jan-09 25-Feb-09 64 days
203 Floors 21-Aug-08 19-Jan-09 93 days
204 - Balast and backfill 21-Aug-08 17-Sep-08 210 days
205 - Concrete slabs 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 6-Aug-08 27-Jan-09 23 days
Finishes works 15-Oct-08 27-Jan-09 23 days
M&E INSTALLATIONS 2-Jul-08 10-Dec-08 23 days
206 Water and sewage 1-Dec-08 19-May-09 23 days
207 - Rainwater 29-Jan-09 18-Mar-09 89 days
208 - Foul water 1-Dec-08 19-Feb-09 23 days
209 - Watter supply 25-Mar-09 19-May-09 45 days
210 - Hydrants 29-Jul-09 1-Apr-09 79 days
211 - Sprinklers 30-Jul-09 29-Apr-09 29 days
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 49 days
Boiler rooms 1-Aug-09 29-Aug-09 59 days
214 - Distribution 2-Aug-09 30-Aug-09 59 days
215 - Equipments 3-Aug-09 31-Aug-09 99 days
Electrical 4-Aug-09 1-Sep-09 9 days
217 - Electrical boards 5-Aug-09 2-Sep-09 54 days
218 - Distribution 6-Aug-09 3-Sep-09 9 days
219 - Lighting 7-Aug-09 4-Sep-09 54 days
220 - Supply 8-Aug-09 5-Sep-09 59 days
221 Low voltage 9-Aug-09 6-Sep-09 9 days
222 - Fire detection system 10-Aug-09 7-Sep-09 9 days
223 - Voice and data 11-Aug-09 8-Sep-09 39 days
224 - Sound and CCTV 12-Aug-09 9-Sep-09 39 days
Exterior M&E works 12-Jun-08 10-Sep-09 0 days
225 Water tanks 17-Jul-08 11-Sep-09 8 days
226 Pumps station 31-Jul-08 12-Sep-09 57 days
227 - structure 31-Jul-08 13-Sep-09 57 days
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 57 days
229 - internal distribution 31-Oct-08 15-Sep-09 57 days
230 Transformers and boilers 17-Jul-08 16-Sep-09 38 days
231 - equipment procurement 17-Jul-08 17-Sep-09 38 days
232 - equipment installation 18-Jul-08 18-Sep-09 38 days
Electrical&Low currents 4-Aug-09 1-Sep-09 9 days
219 - Lighting 7-Aug-09 4-Sep-09 54 days
223 - Voice and data 11-Aug-09 8-Sep-09 39 days
224 - Sound and CCTV 12-Aug-09 9-Sep-09 39 days
EXTERIOR WORKS 20-Jul-08 20-Sep-09 23 days
233 - Ballast and backfill 21-Jul-08 21-Sep-09 23 days
234 - Stabilized ballast 22-Jul-08 22-Sep-09 23 days
235 - Asphalt layers 23-Jul-08 23-Sep-09 23 days
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 23 days
237 - Landscaping 25-Jul-08 25-Sep-09 23 days
238 Road Marking and signage 26-Jul-08 26-Sep-09 8 days
239 Fencing 27-Jul-08 27-Sep-09 20 days
ate
PPING PARK ORADEA
8/4/2008

Total Percent
Actual
phisical Complete

33.01
34.35
100 100 72.25
100 100 100.00
100 98 98.00
100 90 90.00
100 1 1.00
0.78
100 0.01 0.01
100 3 3.00
100 0.1 0.10
100 0.01 0.01
30.01
100 60 60.00
100 0.01 0.01
32.67
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
98.00
100 98 98.00
0.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
100 10 13.52
6.77
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
33.79
100 70 70.00
100 3 3.00
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
700 400 57.14

Total Percent
Actual
phisical Complete
100 3 3
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Total Percent
Actual
phisical Complete
1
100 1 1
100 1 1
100 1 1
100 1 1
Total Percent
Actual
phisical Complete

2.01331069
2.19157609
2.18115942
88 6 6.81818182
88 0.01 0.01136364
100 0.01 0.01
0.01041667
88 0.01 0.01136364
88 0.01 0.01136364
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
5.84166667
100 35 35
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
16.0767767
30.77
46.54
118 118 100.00
100 15 15.00
100 15 15.00
100 15 15.00
118 118 100.00
118 83 70.34
100 15 15.00
100 11 11.00
100 0.01 0.01
7.51
100 15 15.00
100 0.01 0.01
1.00
100 1 1.00
17.54
17.51
100 6 6.00
100 0.01 0.01
100 0.01 0.01
100 99 99.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
11.43
100 2 2.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 3 3.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 7, 2008

Task Start Finish


PHASE 1 228 days 27-Mar-08 27-Feb-09 2 days
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09 2 days
Superstructure 68 days 5-May-08 6-Aug-08 0 days
Main frame 55 days 5-May-08 20-Jul-08 2 days
12 - precast columns installation 30 days 5-May-08 13-Jun-08 2 days
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 2 days
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 2 days
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 2 days
Secondary structure 38 days 16-Jun-08 6-Aug-08 0 days
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 248 days
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 0 days
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 0 days
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 0 days
Flooring 56 days 13-Jun-08 5-Sep-08 0 days
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 0 days
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 0 days
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08 0 days
General works 37 days 1-Aug-08 29-Sep-08 0 days
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 0 days
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 0 days
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 0 days
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 0 days
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08 0 days
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 0 days
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 2 days
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 0 days
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08 11 days
42 - Finishes 55 days 16-Sep-08 1-Dec-08 11 days
47 General Works 34 days 15-Jul-08 5-Sep-08 4 days
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 4 days
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 218 days
Carrefour works 21 days 1-Sep-08 29-Sep-08 0 days
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 0 days
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 0 days
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 0 days
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08 31 days
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 53 days
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 53 days
59 - HVAC 45 days 5-Aug-08 13-Oct-08 31 days
60 - Low currents 25 days 30-Sep-08 3-Nov-08 31 days
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 31 days

Task Start Finish


EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 0 days
Exterior M&E works 143 days 12-Jun-08 16-Jan-09 0 days
81 Water tanks 30 days 17-Jul-08 3-Sep-08 8 days
Pumps station 81 days 31-Jul-08 27-Nov-08 57 days
83 - structure 35 days 31-Jul-08 24-Sep-08 57 days
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 57 days
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 57 days
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 38 days
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 38 days
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 38 days
Exterior works distribution 118 days 17-Jul-08 16-Jan-09 8 days
90 - electrical 88 days 17-Jul-08 24-Nov-08 8 days
91 - sewage 88 days 17-Jul-08 24-Nov-08 8 days
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 30 days
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09 0 days
94 - retention walls 30 days 3-Jun-08 14-Jul-08 0 days
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 8 days
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 8 days
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 8 days
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 8 days
99 Finishes 20 days 21-Jan-09 17-Feb-09 8 days
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 8 days
101 Fencing 40 days 3-Jun-08 28-Jul-08 20 days

Task Start Finish


MULTIPLEX 160 days 1-Jul-08 27-Feb-09 0 days
STRUCTURES 103 days 1-Jul-08 27-Nov-08 0 days
107 Foundations 15 days 2-Sep-08 22-Sep-08 0 days
108 Main structure 28 days 16-Sep-08 23-Oct-08 0 days
109 Secondary structures 25 days 24-Oct-08 27-Nov-08 17 days
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08 0 days
114 Installations works 42 days 24-Oct-08 22-Dec-08 0 days
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08 0 days
119 Finishes works 42 days 24-Oct-08 22-Dec-08 0 days

Task Start Finish


MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09 23 days
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 23 days
128 Finishes works 66 days 15-Oct-08 27-Jan-09 23 days
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 23 days
133 Installations works 66 days 10-Sep-08 10-Dec-08 48 days
Task Start Finish
PHASE 2 265 days 26-Jun-08 21-Jul-09 0 days
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09 0 days
STRUCTURES 161 days 26-Jun-08 25-Feb-09 0 days
Infrastructures 50 days 26-Jun-08 10-Sep-08 0 days
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 0 days
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 215 days
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 220 days
Superstructure 161 days 26-Jun-08 25-Feb-09 30 days
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 210 days
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 0 days
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 0 days
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 9 days
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 64 days
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 23 days
Floors 99 days 21-Aug-08 19-Jan-09 93 days
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 210 days
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09 0 days
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 0 days
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 9 days
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 0 days
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 36 days
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 51 days
158 - Dock levellers 20 days 14-Apr-09 11-May-09 51 days
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 36 days
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 0 days
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 64 days
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 45 days
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 0 days
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 30 days
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 30 days
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09 23 days
Water and sewage 113 days 1-Dec-08 19-May-09 23 days
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 89 days
169 - Foul water 50 days 1-Dec-08 19-Feb-09 23 days
170 - Watter supply 40 days 25-Mar-09 19-May-09 45 days
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 79 days
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 29 days
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 49 days
Boiler rooms 65 days 29-Jan-09 29-Apr-09 59 days
175 - Distribution 65 days 29-Jan-09 29-Apr-09 59 days
176 - Equipments 25 days 29-Jan-09 4-Mar-09 99 days
Electrical 70 days 29-Jan-09 6-May-09 9 days
178 - Electrical boards 25 days 2-Apr-09 6-May-09 54 days
179 - Distribution 60 days 29-Jan-09 22-Apr-09 9 days
180 - Lighting 70 days 29-Jan-09 6-May-09 54 days
181 - Supply 65 days 29-Jan-09 29-Apr-09 59 days
Low voltage 45 days 26-Mar-09 27-May-09 9 days
183 - Fire detection system 45 days 26-Mar-09 27-May-09 9 days
184 - Voice and data 45 days 26-Mar-09 27-May-09 39 days
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 39 days
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09 23 days
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 23 days
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 23 days
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 23 days
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 23 days
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 23 days
192 - Landscaping 30 days 8-May-09 18-Jun-09 23 days

Task Start Finish


BRICOSTORE 2-Jul-08 27-Jan-09 23 days
STRUCTURES 1-Jul-08 27-Nov-08 0 days
Infrastructures 26-Jun-08 10-Sep-08 0 days
193 - foundations excavations 26-Jun-08 6-Aug-08 0 days
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 215 days
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 220 days
Superstructure 26-Jun-08 25-Feb-09 30 days
197 - Precast columns production 2-May-08 26-Jul-08 210 days
198 - Precast columns installation 3-Jun-08 26-Jul-08 0 days
199 - Precast roof elements production 20-Jun-08 20-Jul-08 30 days
200 - Installation of cladding support structure 22-Oct-08 9-Dec-08 9 days
201 - Installation of internal partitions structure 29-Jan-09 25-Feb-09 64 days
203 Floors 21-Aug-08 19-Jan-09 93 days
204 - Balast and backfill 21-Aug-08 17-Sep-08 210 days
205 - Concrete slabs 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09 23 days
Finishes works 16-Jul-08 30-Oct-08 154days
M&E INSTALLATIONS 2-Jul-08 10-Dec-08 23 days
206 Water and sewage 1-Dec-08 19-May-09 23 days
207 - Rainwater 29-Jan-09 18-Mar-09 89 days
208 - Foul water 1-Dec-08 19-Feb-09 23 days
209 - Watter supply 25-Mar-09 19-May-09 45 days
210 - Hydrants 29-Jul-09 1-Apr-09 79 days
211 - Sprinklers 30-Jul-09 29-Apr-09 29 days
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 49 days
Boiler rooms 1-Aug-09 29-Aug-09 59 days
214 - Distribution 2-Aug-09 30-Aug-09 59 days
215 - Equipments 3-Aug-09 31-Aug-09 99 days
Electrical 4-Aug-09 1-Sep-09 9 days
217 - Electrical boards 3-Aug-09 2-Sep-09 54 days
218 - Distribution 6-Aug-09 3-Sep-09 9 days
219 - Lighting 10-Aug-09 30-Oct-09 54 days
220 - Supply 8-Aug-09 5-Sep-09 59 days
221 Low voltage 10-Aug-09 30-Oct-09 9 days
222 - Fire detection system 10-Aug-09 30-Oct-09 9 days
223 - Voice and data 11-Aug-09 30-Oct-09 39 days
224 - Sound and CCTV 12-Aug-09 30-Oct-09 39 days
Exterior M&E works 12-Jun-08 10-Sep-09 0 days
225 Water tanks 17-Jul-08 11-Sep-09 8 days
226 Pumps station 31-Jul-08 12-Sep-09 57 days
227 - structure 31-Jul-08 13-Sep-09 57 days
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 57 days
229 - internal distribution 31-Oct-08 15-Sep-09 57 days
230 Transformers and boilers 17-Jul-08 16-Sep-09 38 days
231 - equipment procurement 17-Jul-08 17-Sep-09 38 days
232 - equipment installation 18-Jul-08 18-Sep-09 38 days
Electrical&Low currents 4-Aug-09 1-Sep-09 9 days
219 - Lighting 7-Aug-09 4-Sep-09 54 days
223 - Voice and data 11-Aug-09 8-Sep-09 39 days
224 - Sound and CCTV 12-Aug-09 9-Sep-09 39 days
EXTERIOR WORKS 20-Jul-08 20-Oct-09 23 days
233 - Ballast and backfill 21-Jul-08 21-Sep-09 23 days
234 - Stabilized ballast 22-Jul-08 22-Sep-09 23 days
235 - Asphalt layers 23-Jul-08 23-Sep-09 23 days
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 23 days
237 - Landscaping 25-Jul-08 25-Sep-09 23 days
238 Road Marking and signage 26-Jul-08 26-Sep-09 8 days
239 Fencing 27-Jul-08 27-Sep-09 20 days

91 MALL AREA 12'-18' - PHASE 1 Architectural works behind the structural works?
Mobexpert is missing?
ate
PPING PARK ORADEA
July 7, 2008

Total Percent
Actual
phisical Complete

33.05
34.55
100 100 72.25
100 100 100.00
100 98 98.00
100 90 90.00
100 1 1.00
1.38
100 0.01 0.01
100 3.5 3.50
100 2 2.00
100 0.01 0.01
30.01
100 60 60.00
100 0.01 0.01
32.67
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
98.00
100 98 98.00
0.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
100 10 13.52
6.77
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
33.79
100 70 70.00
100 3 3.00
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
700 400 57.14

Total Percent
Actual
phisical Complete
100 3 3
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Total Percent
Actual
phisical Complete
1
100 1 1
100 1 1
100 1 1
100 1 1
Total Percent
Actual
phisical Complete

3.72
6.54
6.53
88 9 10.23
88 9 10.23
100 0.01 0.01
0.01
88 0.01 0.01
88 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
8.34
100 50 50.00
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
22.5807515
56.79
73.27
118 118 100.00
100 100 100.00
100 15 15.00
40.30
118 118 100.00
118 83 70.34
100 15 15.00
100 0.01 0.01
100 0.01 0.01
7.51
100 15 15.00
100 0.01 0.01
1.00
100 1 1.00
17.54
17.51
100 6 6.00
100 0.01 0.01
100 0.01 0.01
100 99 99.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
12.14
100 7 7.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 3 3.00

ks behind the structural works?


Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 8, 2008

Task Start Finish


PHASE 1 228 days 27-Mar-08 27-Feb-09 2 days
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09 2 days
Superstructure 68 days 5-May-08 6-Aug-08 0 days
Main frame 55 days 5-May-08 20-Jul-08 2 days
12 - precast columns installation 30 days 5-May-08 13-Jun-08 2 days
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 2 days
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 2 days
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 2 days
Secondary structure 38 days 16-Jun-08 6-Aug-08 0 days
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 248 days
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 0 days
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 0 days
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 0 days
Flooring 56 days 13-Jun-08 5-Sep-08 0 days
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 0 days
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 0 days
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08 0 days
General works 37 days 1-Aug-08 29-Sep-08 0 days
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 0 days
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 0 days
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 0 days
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 0 days
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08 0 days
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 0 days
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 2 days
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 0 days
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08 11 days
42 - Finishes 55 days 16-Sep-08 1-Dec-08 11 days
47 General Works 34 days 15-Jul-08 5-Sep-08 4 days
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 4 days
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 218 days
Carrefour works 21 days 1-Sep-08 29-Sep-08 0 days
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 0 days
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 0 days
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 0 days
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08 31 days
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 53 days
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 53 days
59 - HVAC 45 days 5-Aug-08 13-Oct-08 31 days
60 - Low currents 25 days 30-Sep-08 3-Nov-08 31 days
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 31 days

Task Start Finish


EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 0 days
Exterior M&E works 143 days 12-Jun-08 16-Jan-09 0 days
81 Water tanks 30 days 17-Jul-08 3-Sep-08 8 days
Pumps station 81 days 31-Jul-08 27-Nov-08 57 days
83 - structure 35 days 31-Jul-08 24-Sep-08 57 days
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 57 days
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 57 days
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 38 days
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 38 days
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 38 days
Exterior works distribution 118 days 17-Jul-08 16-Jan-09 8 days
90 - electrical 88 days 17-Jul-08 24-Nov-08 8 days
91 - sewage 88 days 17-Jul-08 24-Nov-08 8 days
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 30 days
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09 0 days
94 - retention walls 30 days 3-Jun-08 14-Jul-08 0 days
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 8 days
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 8 days
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 8 days
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 8 days
99 Finishes 20 days 21-Jan-09 17-Feb-09 8 days
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 8 days
101 Fencing 40 days 3-Jun-08 28-Jul-08 20 days

Task Start Finish


MULTIPLEX 160 days 1-Jul-08 27-Feb-09 0 days
STRUCTURES 103 days 1-Jul-08 27-Nov-08 0 days
107 Foundations 15 days 2-Sep-08 22-Sep-08 0 days
108 Main structure 28 days 16-Sep-08 23-Oct-08 0 days
109 Secondary structures 25 days 24-Oct-08 27-Nov-08 17 days
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08 0 days
114 Installations works 42 days 24-Oct-08 22-Dec-08 0 days
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08 0 days
119 Finishes works 42 days 24-Oct-08 22-Dec-08 0 days

Task Start Finish


MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09 23 days
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 23 days
128 Finishes works 66 days 15-Oct-08 27-Jan-09 23 days
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 23 days
133 Installations works 66 days 10-Sep-08 10-Dec-08 48 days
Task Start Finish
PHASE 2 265 days 26-Jun-08 21-Jul-09 0 days
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09 0 days
STRUCTURES 161 days 26-Jun-08 25-Feb-09 0 days
Infrastructures 50 days 26-Jun-08 10-Sep-08 0 days
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 0 days
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 215 days
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 220 days
Superstructure 161 days 26-Jun-08 25-Feb-09 30 days
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 210 days
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 0 days
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 0 days
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 9 days
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 64 days
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 23 days
Floors 99 days 21-Aug-08 19-Jan-09 93 days
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 210 days
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09 0 days
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 0 days
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 9 days
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 0 days
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 36 days
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 51 days
158 - Dock levellers 20 days 14-Apr-09 11-May-09 51 days
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 36 days
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 0 days
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 64 days
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 45 days
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 0 days
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 30 days
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 30 days
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09 23 days
Water and sewage 113 days 1-Dec-08 19-May-09 23 days
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 89 days
169 - Foul water 50 days 1-Dec-08 19-Feb-09 23 days
170 - Watter supply 40 days 25-Mar-09 19-May-09 45 days
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 79 days
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 29 days
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 49 days
Boiler rooms 65 days 29-Jan-09 29-Apr-09 59 days
175 - Distribution 65 days 29-Jan-09 29-Apr-09 59 days
176 - Equipments 25 days 29-Jan-09 4-Mar-09 99 days
Electrical 70 days 29-Jan-09 6-May-09 9 days
178 - Electrical boards 25 days 2-Apr-09 6-May-09 54 days
179 - Distribution 60 days 29-Jan-09 22-Apr-09 9 days
180 - Lighting 70 days 29-Jan-09 6-May-09 54 days
181 - Supply 65 days 29-Jan-09 29-Apr-09 59 days
Low voltage 45 days 26-Mar-09 27-May-09 9 days
183 - Fire detection system 45 days 26-Mar-09 27-May-09 9 days
184 - Voice and data 45 days 26-Mar-09 27-May-09 39 days
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 39 days
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09 23 days
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 23 days
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 23 days
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 23 days
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 23 days
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 23 days
192 - Landscaping 30 days 8-May-09 18-Jun-09 23 days

Task Start Finish


BRICOSTORE 2-Jul-08 27-Jan-09 23 days
STRUCTURES 1-Jul-08 27-Nov-08 0 days
Infrastructures 26-Jun-08 10-Sep-08 0 days
193 - foundations excavations 26-Jun-08 6-Aug-08 0 days
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 215 days
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 220 days
Superstructure 26-Jun-08 25-Feb-09 30 days
197 - Precast columns production 2-May-08 26-Jul-08 210 days
198 - Precast columns installation 3-Jun-08 26-Jul-08 0 days
199 - Precast roof elements production 20-Jun-08 20-Jul-08 30 days
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 9 days
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 64 days
203 Floors 21-Aug-08 19-Jan-09 93 days
204 - Balast and backfill 21-Aug-08 17-Sep-08 210 days
205 - Concrete slabs 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09 23 days
Finishes works 16-Jul-08 30-Oct-08 154days
M&E INSTALLATIONS 2-Jul-08 10-Dec-08 23 days
206 Water and sewage 1-Dec-08 19-May-09 23 days
207 - Rainwater 29-Jan-09 18-Mar-09 89 days
208 - Foul water 1-Dec-08 19-Feb-09 23 days
209 - Watter supply 25-Mar-09 19-May-09 45 days
210 - Hydrants 29-Jul-09 1-Apr-09 79 days
211 - Sprinklers 30-Jul-09 29-Apr-09 29 days
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 49 days
Boiler rooms 1-Aug-09 29-Aug-09 59 days
214 - Distribution 2-Aug-09 30-Aug-09 59 days
215 - Equipments 3-Aug-09 31-Aug-09 99 days
Electrical 4-Aug-09 1-Sep-09 9 days
217 - Electrical boards 3-Aug-09 2-Sep-09 54 days
218 - Distribution 6-Aug-09 3-Sep-09 9 days
219 - Lighting 10-Aug-09 30-Oct-09 54 days
220 - Supply 8-Aug-09 5-Sep-09 59 days
221 Low voltage 10-Aug-09 30-Oct-09 9 days
222 - Fire detection system 10-Aug-09 30-Oct-09 9 days
223 - Voice and data 11-Aug-09 30-Oct-09 39 days
224 - Sound and CCTV 12-Aug-09 30-Oct-09 39 days
Exterior M&E works 12-Jun-08 10-Sep-09 0 days
225 Water tanks 17-Jul-08 11-Sep-09 8 days
226 Pumps station 31-Jul-08 12-Sep-09 57 days
227 - structure 31-Jul-08 13-Sep-09 57 days
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 57 days
229 - internal distribution 31-Oct-08 15-Sep-09 57 days
230 Transformers and boilers 17-Jul-08 16-Sep-09 38 days
231 - equipment procurement 17-Jul-08 17-Sep-09 38 days
232 - equipment installation 18-Jul-08 18-Sep-09 38 days
Electrical&Low currents 4-Aug-09 1-Sep-09 9 days
219 - Lighting 7-Aug-09 4-Sep-09 54 days
223 - Voice and data 11-Aug-09 8-Sep-09 39 days
224 - Sound and CCTV 12-Aug-09 9-Sep-09 39 days
EXTERIOR WORKS 20-Jul-08 20-Oct-09 23 days
233 - Ballast and backfill 21-Jul-08 21-Sep-09 23 days
234 - Stabilized ballast 22-Jul-08 22-Sep-09 23 days
235 - Asphalt layers 23-Jul-08 23-Sep-09 23 days
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 23 days
237 - Landscaping 25-Jul-08 25-Sep-09 23 days
238 Road Marking and signage 26-Jul-08 26-Sep-09 8 days
239 Fencing 27-Jul-08 27-Sep-09 20 days

ASA Turda is not working enymore at C


ate
PPING PARK ORADEA
July 8, 2008

Total Percent
Actual
phisical Complete

33.13
34.97
100 100 72.25
100 100 100.00
100 98 98.00
100 90 90.00
100 1 1.00
2.67
100 0.01 0.01
100 3.5 3.50
100 2.5 2.50
38 3 7.89
30.01
100 60 60.00
100 0.01 0.01
32.67
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
98.00
100 98 98.00
0.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
100 10 14.07
7.04
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
35.16
100 79 79.00
100 3.1 3.10
100 0.09 0.09
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
700 410 58.57

Total Percent
Actual
phisical Complete
100 3 3
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Total Percent
Actual
phisical Complete
1
100 1 1
100 1 1
100 1 1
100 1 1
Total Percent
Actual
phisical Complete

5.14
10.52
10.51
88 15 17.05
88 14 15.91
100 0.01 0.01
0.01
88 0.01 0.01
88 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.51
100 1 1.00
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
10.01
100 60 60.00
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
22.8372814
57.81
73.27
118 118 100.00
100 100 100.00
100 15 15.00
42.35
118 118 100.00
118 83 70.34
100 26 26.00
100 0.01 0.01
100 0.01 0.01
7.51
100 15 15.00
100 0.01 0.01
1.00
100 1 1.00
17.54
17.51
100 6 6.00
100 0.01 0.01
100 0.01 0.01
100 99 99.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
12.14
100 7 7.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 3 3.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 9, 2008

Task Start Finish


PHASE 1 228 days 27-Mar-08 27-Feb-09 2 days
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09 2 days
Superstructure 68 days 5-May-08 6-Aug-08 0 days
Main frame 55 days 5-May-08 20-Jul-08 2 days
12 - precast columns installation 30 days 5-May-08 13-Jun-08 2 days
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 2 days
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 2 days
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 2 days
Secondary structure 38 days 16-Jun-08 6-Aug-08 0 days
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 248 days
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 0 days
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 0 days
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 0 days
Flooring 56 days 13-Jun-08 5-Sep-08 0 days
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 0 days
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 0 days
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08 0 days
General works 37 days 1-Aug-08 29-Sep-08 0 days
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 0 days
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 0 days
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 0 days
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 0 days
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08 0 days
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 0 days
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 2 days
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 0 days
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08 11 days
42 - Finishes 55 days 16-Sep-08 1-Dec-08 11 days
47 General Works 34 days 15-Jul-08 5-Sep-08 4 days
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 4 days
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 218 days
Carrefour works 21 days 1-Sep-08 29-Sep-08 0 days
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 0 days
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 0 days
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 0 days
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 0 days
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08 31 days
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 53 days
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 53 days
59 - HVAC 45 days 5-Aug-08 13-Oct-08 31 days
60 - Low currents 25 days 30-Sep-08 3-Nov-08 31 days
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 31 days

Task Start Finish


EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 0 days
Exterior M&E works 143 days 12-Jun-08 16-Jan-09 0 days
81 Water tanks 30 days 17-Jul-08 3-Sep-08 8 days
Pumps station 81 days 31-Jul-08 27-Nov-08 57 days
83 - structure 35 days 31-Jul-08 24-Sep-08 57 days
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 57 days
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 57 days
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 38 days
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 38 days
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 38 days
Exterior works distribution 118 days 17-Jul-08 16-Jan-09 8 days
90 - electrical 88 days 17-Jul-08 24-Nov-08 8 days
91 - sewage 88 days 17-Jul-08 24-Nov-08 8 days
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 30 days
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09 0 days
94 - retention walls 30 days 3-Jun-08 14-Jul-08 0 days
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 8 days
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 8 days
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 8 days
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 8 days
99 Finishes 20 days 21-Jan-09 17-Feb-09 8 days
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 8 days
101 Fencing 40 days 3-Jun-08 28-Jul-08 20 days

Task Start Finish


MULTIPLEX 160 days 1-Jul-08 27-Feb-09 0 days
STRUCTURES 103 days 1-Jul-08 27-Nov-08 0 days
107 Foundations 15 days 2-Sep-08 22-Sep-08 0 days
108 Main structure 28 days 16-Sep-08 23-Oct-08 0 days
109 Secondary structures 25 days 24-Oct-08 27-Nov-08 17 days
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08 0 days
114 Installations works 42 days 24-Oct-08 22-Dec-08 0 days
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08 0 days
119 Finishes works 42 days 24-Oct-08 22-Dec-08 0 days

Task Start Finish


MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09 23 days
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 23 days
128 Finishes works 66 days 15-Oct-08 27-Jan-09 23 days
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 23 days
133 Installations works 66 days 10-Sep-08 10-Dec-08 48 days
Task Start Finish
PHASE 2 265 days 26-Jun-08 21-Jul-09 0 days
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09 0 days
STRUCTURES 161 days 26-Jun-08 25-Feb-09 0 days
Infrastructures 50 days 26-Jun-08 10-Sep-08 0 days
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 0 days
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 215 days
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 220 days
Superstructure 161 days 26-Jun-08 25-Feb-09 30 days
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 210 days
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 0 days
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 0 days
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 9 days
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 64 days
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 23 days
Floors 99 days 21-Aug-08 19-Jan-09 93 days
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 210 days
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09 0 days
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 0 days
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 9 days
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 0 days
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 36 days
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 51 days
158 - Dock levellers 20 days 14-Apr-09 11-May-09 51 days
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 36 days
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 0 days
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 64 days
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 45 days
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 0 days
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 30 days
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 30 days
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09 23 days
Water and sewage 113 days 1-Dec-08 19-May-09 23 days
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 89 days
169 - Foul water 50 days 1-Dec-08 19-Feb-09 23 days
170 - Watter supply 40 days 25-Mar-09 19-May-09 45 days
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 79 days
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 29 days
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 49 days
Boiler rooms 65 days 29-Jan-09 29-Apr-09 59 days
175 - Distribution 65 days 29-Jan-09 29-Apr-09 59 days
176 - Equipments 25 days 29-Jan-09 4-Mar-09 99 days
Electrical 70 days 29-Jan-09 6-May-09 9 days
178 - Electrical boards 25 days 2-Apr-09 6-May-09 54 days
179 - Distribution 60 days 29-Jan-09 22-Apr-09 9 days
180 - Lighting 70 days 29-Jan-09 6-May-09 54 days
181 - Supply 65 days 29-Jan-09 29-Apr-09 59 days
Low voltage 45 days 26-Mar-09 27-May-09 9 days
183 - Fire detection system 45 days 26-Mar-09 27-May-09 9 days
184 - Voice and data 45 days 26-Mar-09 27-May-09 39 days
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 39 days
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09 23 days
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 23 days
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 23 days
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 23 days
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 23 days
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 23 days
192 - Landscaping 30 days 8-May-09 18-Jun-09 23 days

Task Start Finish


BRICOSTORE 2-Jul-08 27-Jan-09 23 days
STRUCTURES 1-Jul-08 27-Nov-08 0 days
Infrastructures 26-Jun-08 10-Sep-08 0 days
193 - foundations excavations 26-Jun-08 6-Aug-08 0 days
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 215 days
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 220 days
Superstructure 26-Jun-08 25-Feb-09 30 days
197 - Precast columns production 2-May-08 26-Jul-08 210 days
198 - Precast columns installation 3-Jun-08 26-Jul-08 0 days
199 - Precast roof elements production 20-Jun-08 20-Jul-08 30 days
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 9 days
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 64 days
203 Floors 21-Aug-08 19-Jan-09 93 days
204 - Balast and backfill 21-Aug-08 17-Sep-08 210 days
205 - Concrete slabs 17-Dec-08 19-Jan-09 9 days
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09 23 days
Finishes works 16-Jul-08 30-Oct-08 154days
M&E INSTALLATIONS 2-Jul-08 10-Dec-08 23 days
206 Water and sewage 1-Dec-08 19-May-09 23 days
207 - Rainwater 29-Jan-09 18-Mar-09 89 days
208 - Foul water 1-Dec-08 19-Feb-09 23 days
209 - Watter supply 25-Mar-09 19-May-09 45 days
210 - Hydrants 29-Jul-09 1-Apr-09 79 days
211 - Sprinklers 30-Jul-09 29-Apr-09 29 days
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 49 days
Boiler rooms 1-Aug-09 29-Aug-09 59 days
214 - Distribution 2-Aug-09 30-Aug-09 59 days
215 - Equipments 3-Aug-09 31-Aug-09 99 days
Electrical 4-Aug-09 1-Sep-09 9 days
217 - Electrical boards 3-Aug-09 2-Sep-09 54 days
218 - Distribution 6-Aug-09 3-Sep-09 9 days
219 - Lighting 10-Aug-09 30-Oct-09 54 days
220 - Supply 8-Aug-09 5-Sep-09 59 days
221 Low voltage 10-Aug-09 30-Oct-09 9 days
222 - Fire detection system 10-Aug-09 30-Oct-09 9 days
223 - Voice and data 11-Aug-09 30-Oct-09 39 days
224 - Sound and CCTV 12-Aug-09 30-Oct-09 39 days
Exterior M&E works 12-Jun-08 10-Sep-09 0 days
225 Water tanks 17-Jul-08 11-Sep-09 8 days
226 Pumps station 31-Jul-08 12-Sep-09 57 days
227 - structure 31-Jul-08 13-Sep-09 57 days
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 57 days
229 - internal distribution 31-Oct-08 15-Sep-09 57 days
230 Transformers and boilers 17-Jul-08 16-Sep-09 38 days
231 - equipment procurement 17-Jul-08 17-Sep-09 38 days
232 - equipment installation 18-Jul-08 18-Sep-09 38 days
Electrical&Low currents 4-Aug-09 1-Sep-09 9 days
219 - Lighting 7-Aug-09 4-Sep-09 54 days
223 - Voice and data 11-Aug-09 8-Sep-09 39 days
224 - Sound and CCTV 12-Aug-09 9-Sep-09 39 days
EXTERIOR WORKS 20-Jul-08 20-Oct-09 23 days
233 - Ballast and backfill 21-Jul-08 21-Sep-09 23 days
234 - Stabilized ballast 22-Jul-08 22-Sep-09 23 days
235 - Asphalt layers 23-Jul-08 23-Sep-09 23 days
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 23 days
237 - Landscaping 25-Jul-08 25-Sep-09 23 days
238 Road Marking and signage 26-Jul-08 26-Sep-09 8 days
239 Fencing 27-Jul-08 27-Sep-09 20 days
ate
PPING PARK ORADEA
July 9, 2008

Total Percent
Actual
phisical Complete

33.14
35.03
100 0 72.25
100 100 100.00
100 98 98.00
100 90 90.00
100 1 1.00
2.83
100 0.01 0.01
100 3.55 3.55
100 3 3.00
38 3 7.89
30.01
100 60 60.00
100 0.01 0.01
32.67
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
98.00
100 98 98.00
0.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
100 10 15.96
7.99
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
39.90
100 85 85.00
100 3.1 3.10
100 0.09 0.09
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
1000 590 59.00

Total Percent
Actual
phisical Complete
100 3 3
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Total Percent
Actual
phisical Complete
1
100 1 1
100 1 1
100 1 1
100 1 1
Total Percent
Actual
physical Complete

6.57
13.42
13.41
88 22 25.00
88 15 17.05
100 0.01 0.01
0.01
88 0.01 0.01
88 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.51
100 1 1.00
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
12.84
100 75 75.00
100 2 2.00
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01

Total Percent
Actual
phisical Complete
23.1560983
58.34
73.58
118 118 100.00
100 100 100.00
100 16 16.00
43.10
118 118 100.00
118 85 72.03
100 26 26.00
100 2 2.00
100 0.01 0.01
7.51
100 15 15.00
100 0.01 0.01
1.00
100 1 1.00
18.28
18.01
100 7 7.00
100 2 2.00
100 0.01 0.01
100 99 99.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
0.26
100 0.01 0.01
100 1 1.00
100 0.01 0.01
100 0.01 0.01
0.01
100 0.01 0.01
100 0.01 0.01
100 0.01 0.01
15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
12.14
100 7 7.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 15 15.00
100 3 3.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 10, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 1-Dec-08 19-May-09
207 - Rainwater 29-Jan-09 18-Mar-09 100
208 - Foul water 1-Dec-08 19-Feb-09 100
209 - Watter supply 25-Mar-09 19-May-09 100
210 - Hydrants 29-Jul-09 1-Apr-09 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 4-Aug-09 1-Sep-09
217 - Electrical boards 3-Aug-09 2-Sep-09 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-09 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 12-Jun-08 10-Sep-09
225 Water tanks 17-Jul-08 11-Sep-09 100
226 Pumps station 31-Jul-08 12-Sep-09 100
227 - structure 31-Jul-08 13-Sep-09 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 15-Sep-09 100
230 Transformers and boilers 17-Jul-08 16-Sep-09 100
231 - equipment procurement 17-Jul-08 17-Sep-09 100
232 - equipment installation 18-Jul-08 18-Sep-09 100
Electrical&Low currents 4-Aug-09 1-Sep-09 100
219 - Lighting 7-Aug-09 4-Sep-09 100
223 - Voice and data 11-Aug-09 8-Sep-09 100
224 - Sound and CCTV 12-Aug-09 9-Sep-09 100
EXTERIOR WORKS 20-Jul-08 20-Oct-09
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 23-Jul-08 23-Sep-09 100
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 100
237 - Landscaping 25-Jul-08 25-Sep-09 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
10, 2008

Percent Prevoius day


Actual
Complete percent

33.18 33.14
35.20 35.03
72.28 72.28
100 100.00
98.1 98.10 98.00
90 90.00
1 1.00
3.27 2.83
0.01 0.01
3.55 3.55
3.5 3.50 3.00
4 10.53 7.89
30.06
60.1 60.10 60.00
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.03
8.02
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
40.07
85 85.00
3.1 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
593 59.30 59.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.18
14.87
14.86 13.41
25 28.41 25.00
16 18.18 17.05
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
20.8360392
63.47 58.34
73.58 73.58
118 100.00
100 100.00
16 16.00
53.36
118 100.00
86 72.88 72.03
80 80.00 26.00
2 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
1.00
1 1.00
18.77
18.12 18.01
7.5 7.50 7.00
2.2 2.20 2.00
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.63
0.01 0.01
1.5 1.50 1.00
1 1.00 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.54
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
3 3.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 11, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 1-Dec-08 19-May-09
207 - Rainwater 29-Jan-09 18-Mar-09 100
208 - Foul water 1-Dec-08 19-Feb-09 100
209 - Watter supply 25-Mar-09 19-May-09 100
210 - Hydrants 29-Jul-09 1-Apr-09 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 4-Aug-09 1-Sep-09
217 - Electrical boards 3-Aug-09 2-Sep-09 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-09 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 12-Jun-08 10-Sep-09
225 Water tanks 17-Jul-08 11-Sep-09 100
226 Pumps station 31-Jul-08 12-Sep-09 100
227 - structure 31-Jul-08 13-Sep-09 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 15-Sep-09 100
230 Transformers and boilers 17-Jul-08 16-Sep-09 100
231 - equipment procurement 17-Jul-08 17-Sep-09 100
232 - equipment installation 18-Jul-08 18-Sep-09 100
Electrical&Low currents 4-Aug-09 1-Sep-09 100
219 - Lighting 7-Aug-09 4-Sep-09 100
223 - Voice and data 11-Aug-09 8-Sep-09 100
224 - Sound and CCTV 12-Aug-09 9-Sep-09 100
EXTERIOR WORKS 20-Jul-08 20-Oct-09
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 23-Jul-08 23-Sep-09 100
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 100
237 - Landscaping 25-Jul-08 25-Sep-09 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
11, 2008

Percent Prevoius day


Actual
Complete percent

33.20
35.33 33.18
72.30 72.30
100 100.00
98.2 98.20 98.10
90 90.00
1 1.00
3.60 3.27
0.01 0.01
3.55 3.55
3.6 3.60 3.50
5 13.16 10.53
30.08
60.15 60.15 60.10
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.41
8.21
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.01
100 100.00 85.00
3.1 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
594 59.40 59.30

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.31
15.38
15.37 14.86
25.7 29.20 28.41
16.7 18.98 18.18
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.0413564
64.22 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
54.85
118 100.00
87 73.73 72.88
87 87.00 80.00
2 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
1.00
1 1.00
18.85
18.17 18.01
7.6 7.60 7.50
2.4 2.40 2.20
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.50
1 1.00 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 14, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 1-Dec-08 19-May-09
207 - Rainwater 29-Jan-09 18-Mar-09 100
208 - Foul water 1-Dec-08 19-Feb-09 100
209 - Watter supply 25-Mar-09 19-May-09 100
210 - Hydrants 29-Jul-09 1-Apr-09 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 4-Aug-09 1-Sep-09
217 - Electrical boards 3-Aug-09 2-Sep-09 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-09 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 12-Jun-08 10-Sep-09
225 Water tanks 17-Jul-08 11-Sep-09 100
226 Pumps station 31-Jul-08 12-Sep-09 100
227 - structure 31-Jul-08 13-Sep-09 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 15-Sep-09 100
230 Transformers and boilers 17-Jul-08 16-Sep-09 100
231 - equipment procurement 17-Jul-08 17-Sep-09 100
232 - equipment installation 18-Jul-08 18-Sep-09 100
Electrical&Low currents 4-Aug-09 1-Sep-09 100
219 - Lighting 7-Aug-09 4-Sep-09 100
223 - Voice and data 11-Aug-09 8-Sep-09 100
224 - Sound and CCTV 12-Aug-09 9-Sep-09 100
EXTERIOR WORKS 20-Jul-08 20-Oct-09
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 23-Jul-08 23-Sep-09 100
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 100
237 - Landscaping 25-Jul-08 25-Sep-09 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
14, 2008

Percent Prevoius day


Actual
Complete percent

33.20
35.33 33.18
72.30 72.30
100 100.00
98.2 98.20 98.10
90 90.00
1 1.00
3.60 3.27
0.01 0.01
3.55 3.55
3.6 3.60 3.50
5 13.16 10.53
30.08
60.15 60.15 60.10
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.41
8.21
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.01
100 100.00 85.00
3.1 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
594 59.40 59.30

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.31
15.38
15.37 14.86
25.7 29.20 28.41
16.7 18.98 18.18
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.0413564
64.22 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
54.85
118 100.00
87 73.73 72.88
87 87.00 80.00
2 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
1.00
1 1.00
18.85
18.17 18.01
7.6 7.60 7.50
2.4 2.40 2.20
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.50
1 1.00 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 15, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 1-Dec-08 19-May-09
207 - Rainwater 29-Jan-09 18-Mar-09 100
208 - Foul water 1-Dec-08 19-Feb-09 100
209 - Watter supply 25-Mar-09 19-May-09 100
210 - Hydrants 29-Jul-09 1-Apr-09 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 4-Aug-09 1-Sep-09
217 - Electrical boards 3-Aug-09 2-Sep-09 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-09 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 12-Jun-08 10-Sep-09
225 Water tanks 17-Jul-08 11-Sep-09 100
226 Pumps station 31-Jul-08 12-Sep-09 100
227 - structure 31-Jul-08 13-Sep-09 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 15-Sep-09 100
230 Transformers and boilers 17-Jul-08 16-Sep-09 100
231 - equipment procurement 17-Jul-08 17-Sep-09 100
232 - equipment installation 18-Jul-08 18-Sep-09 100
Electrical&Low currents 4-Aug-09 1-Sep-09 100
219 - Lighting 7-Aug-09 4-Sep-09 100
223 - Voice and data 11-Aug-09 8-Sep-09 100
224 - Sound and CCTV 12-Aug-09 9-Sep-09 100
EXTERIOR WORKS 20-Jul-08 20-Oct-09
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 23-Jul-08 23-Sep-09 100
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 100
237 - Landscaping 25-Jul-08 25-Sep-09 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
15, 2008

Percent Prevoius day


Actual
Complete percent

33.25
35.53 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
4.22 3.27
0.01 0.01
3.55 3.55
3.7 3.70 3.60
7 18.42 13.16
30.08
60.15 60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.43
8.22
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.07
100 100.00 100.00
3.1 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
595 59.50 59.40

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.31
15.38
15.37 14.86
25.7 29.20 29.20
16.7 18.98 18.98
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.3379982
64.41 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
55.23
118 100.00
88 74.58 73.73
88 88.00 87.00
2 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
2.00
2 2.00 1.00
18.85
18.17 18.01
7.6 7.60 7.50
2.4 2.40 2.20
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.50
1 1.00 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 16, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 1-Dec-08 19-May-09
207 - Rainwater 29-Jan-09 18-Mar-09 100
208 - Foul water 1-Dec-08 19-Feb-09 100
209 - Watter supply 25-Mar-09 19-May-09 100
210 - Hydrants 29-Jul-09 1-Apr-09 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 4-Aug-09 1-Sep-09
217 - Electrical boards 3-Aug-09 2-Sep-09 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-09 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 12-Jun-08 10-Sep-09
225 Water tanks 17-Jul-08 11-Sep-09 100
226 Pumps station 31-Jul-08 12-Sep-09 100
227 - structure 31-Jul-08 13-Sep-09 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 15-Sep-09 100
230 Transformers and boilers 17-Jul-08 16-Sep-09 100
231 - equipment procurement 17-Jul-08 17-Sep-09 100
232 - equipment installation 18-Jul-08 18-Sep-09 100
Electrical&Low currents 4-Aug-09 1-Sep-09 100
219 - Lighting 7-Aug-09 4-Sep-09 100
223 - Voice and data 11-Aug-09 8-Sep-09 100
224 - Sound and CCTV 12-Aug-09 9-Sep-09 100
EXTERIOR WORKS 20-Jul-08 20-Oct-09
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 23-Jul-08 23-Sep-09 100
236 - Kerbstones and walkways 24-Jul-08 24-Sep-09 100
237 - Landscaping 25-Jul-08 25-Sep-09 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
16, 2008

Percent Prevoius day


Actual
Complete percent

33.26
35.58 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
4.37 3.27
0.01 0.01
3.55 3.55
3.72 3.72 3.70
7.5 19.74 18.42
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.43
8.22
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.07
100 100.00 100.00
3.1 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
595 59.50 59.50

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.31
15.38
15.37 14.86
25.7 29.20 29.20
16.72 19.00 18.98
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.6457656
65.52 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
57.46
118 100.00
88 74.58 73.73
100 100.00 88.00
2 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 1.00
18.86
18.18 18.01
7.65 7.65 7.60
2.42 2.42 2.40
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 17, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
17, 2008

Percent Prevoius day


Actual
Complete percent

33.27
35.64 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
4.53 3.27
0.01 0.01
3.55 3.55
3.75 3.75 3.72
8 21.05 19.74
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.48
8.25
0.01 0.01
0.01
0.01 1.00 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.19
100 100.00 100.00
3.1 3.10 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
597 59.70 59.50

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.33
15.46
15.45 14.86
25.9 29.43 29.20
16.72 19.00 19.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.6807469
65.66 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
57.74
118 100.00
89 75.42 74.58
100 100.00 88.00
2.5 2.50 2.00
0.01 0.01
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 1.00
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 18, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
18, 2008

Percent Prevoius day


Actual
Complete percent

33.29
35.74 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
4.83 3.27
0.01 0.01
3.55 3.55
3.77 3.77 3.75
9 23.68 21.05
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.54
8.36
0.01 0.01
0.51
1.5 1.50 1.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.25
100 100.00 100.00
3.15 3.15 3.10
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
598 59.80 59.70

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

7.34
15.51
15.50 14.86
25.99 29.53 29.43
16.77 19.06 19.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7224913
65.83 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.08
118 100.00
89.7 76.02 75.42
100 100.00 100.00
2.6 2.60 2.00
1 1.00 0.01
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 1.00
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 21, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
21, 2008

Percent Prevoius day


Actual
Complete percent

33.30
35.79 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
4.99 3.27
0.01 0.01
3.55 3.55
3.8 3.80 3.77
9.5 25.00 23.68
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.54
8.36
0.01 0.01
0.52
1.55 1.55 1.50
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.25
100 100.00 100.00
3.16 3.16 3.15
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
598 59.80 59.70

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

8.25
19.14
19.13 14.86
36 40.91 29.53
16.79 19.08 19.06
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7294876
65.86 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.13
118 100.00
90 76.27 76.02
100 100.00 100.00
2.6 2.60 2.00
1 1.00 0.01
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 22, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
22, 2008

Percent Prevoius day


Actual
Complete percent

33.41
36.35 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.66 3.27
0.01 0.01
3.55 3.55
3.95 3.95 3.80
15 39.47 25.00
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.60
8.41
0.01 0.01
0.67
2 2.00 1.55
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.37
100 100.00 100.00
3.17 3.17 3.16
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
600 60.00 59.80

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

10.52
28.24
28.22 14.86
61 69.32 40.91
16.89 19.19 19.08
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7294876
65.86 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.13
118 100.00
90 76.27 76.02
100 100.00 100.00
2.6 2.60 2.60
1 1.00 1.00
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 23, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
23, 2008

Percent Prevoius day


Actual
Complete percent

33.41
36.35 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.66 3.27
0.01 0.01
3.55 3.55
3.95 3.95 3.95
15 39.47 39.47
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.60
8.41
0.01 0.01
0.67
2 2.00 2.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.37
100 100.00 100.00
3.17 3.17 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
600 60.00 60.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

10.52
28.24
28.22 14.86
61 69.32 69.32
16.89 19.19 19.08
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7294876
65.86 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.13
118 100.00
90 76.27 76.27
100 100.00 100.00
2.6 2.60 2.60
1 1.00 1.00
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 24, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
24, 2008

Percent Prevoius day


Actual
Complete percent

33.41
36.35 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.67 3.27
0.01 0.01
3.55 3.55
3.97 3.97 3.95
15 39.47 39.47
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.60
8.41
0.01 0.01
0.67
2 2.00 2.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.37
100 100.00 100.00
3.17 3.17 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
600 60.00 60.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

10.52
28.24
28.22 14.86
61 69.32 69.32
16.89 19.19 19.08
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7528085
65.95 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.32
118 100.00
91 77.12 76.27
100 100.00 100.00
2.6 2.60 2.60
1 1.00 1.00
7.51
15 15.00
0.01 0.01
2.10
2.1 2.10 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 25, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
25, 2008

Percent Prevoius day


Actual
Complete percent

33.41
36.35 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.67 3.27
0.01 0.01
3.55 3.55 3.55
3.98 3.98 3.95
15 39.47 39.47
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 16.60
8.41
0.01 0.01
0.67
2 2.00 2.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
41.37
100 100.00 100.00
3.17 3.17 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
600 60.00 60.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

10.57
28.42
28.41 14.86
61.5 69.89 69.32
16.89 19.19 19.08
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7769689
66.00 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.41
118 100.00
91.5 77.54 77.12
100 100.00 100.00
2.6 2.60 2.60
1 1.00 1.00
7.51
15 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 28, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
28, 2008

Percent Prevoius day


Actual
Complete percent

33.42
36.40 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.82 3.27
0.01 0.01
3.55 3.55 3.55
3.99 3.99 3.98
15.5 40.79 39.47
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.07
8.66
0.01 0.01
0.71
2.1 2.10 2.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
42.55
100 100.00 100.00
3.17 3.17 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
620 62.00 60.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

10.58
28.45
28.44 14.86
61.6 70.00 69.89
16.89 19.19 19.19
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
21.7944596
66.07 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
58.55
118 100.00
92 77.97 77.54
100 100.00 100.00
2.6 2.60 2.60
1.25 1.25 1.00
7.51
15 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.25
7 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 29, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
29, 2008

Percent Prevoius day


Actual
Complete percent

33.42
36.40 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.82 3.27
0.01 0.01
3.55 3.55 3.55
4 4.00 3.99
15.5 40.79 39.47
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.21
8.78
0.01 0.01
1.01
3 3.00 2.10
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
42.84
100 100.00 100.00
3.17 3.17 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
625 62.50 62.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.24
35.12
35.11 14.86
80 90.91 70.00
16.89 19.19 19.19
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.3716518
68.38 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.17
118 100.00
116 98.31 77.97
100 100.00 100.00
2.6 2.60 2.60
2 2.00 1.25
7.51
15 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.32
7.5 7.50 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 30, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
30, 2008

Percent Prevoius day


Actual
Complete percent

33.42
36.40 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.82 3.27
0.01 0.01
3.55 3.55 3.55
4 4.00 3.99
15.5 40.79 40.79
30.08
60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.28
8.87
0.01 0.01
1.34
4 4.00 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
42.96
100 100.00 100.00
3.18 3.18 3.17
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
627 62.70 62.50

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.34
35.48
35.47 14.86
81 92.05 90.91
16.89 19.19 19.19
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.3973047
68.48 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.38
118 100.00
117 99.15 98.31
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.01
16 16.00 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.32
7.5 7.50 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: July 31, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 21-Aug-08 19-Jan-09
204 - Balast and backfill 21-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 16-Jul-08 30-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 10-Dec-08
206 Water and sewage 11-Jun-08 29-Jul-08
207 - Rainwater 11-Jul-08 29-Jul-08 100
208 - Foul water 25-Jun-08 29-Jul-08 100
209 - Watter supply 10-Jun-08 28-Jul-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 30-Jul-09 29-Apr-09 100
212 - Heating, ventilation & cooling 31-Jul-09 13-May-09 100
Boiler rooms 1-Aug-09 29-Aug-09
214 - Distribution 2-Aug-09 30-Aug-09 100
215 - Equipments 3-Aug-09 31-Aug-09 100
Electrical 27-Jul-09 30-Oct-08
217 - Electrical boards 3-Aug-09 30-Oct-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 30-Oct-09 100
220 - Supply 8-Aug-09 5-Sep-09 100
221 Low voltage 10-Aug-09 30-Oct-09
222 - Fire detection system 10-Aug-09 30-Oct-09 100
223 - Voice and data 11-Aug-09 30-Oct-09 100
224 - Sound and CCTV 12-Aug-09 30-Oct-09 100
Exterior M&E works 16-Jun-08 10-Sep-09
225 Water tanks 16-Jun-08 31-Jul-08 100
226 Pumps station 17-Jun-08 31-Jul-08 100
227 - structure 17-Jun-08 31-Jul-08 100
228 - equipments (procurmenent and installation) 31-Jul-08 14-Sep-09 100
229 - internal distribution 31-Oct-08 31-Oct-08 100
230 Transformers and boilers 17-Jul-08 31-Oct-08 100
231 - equipment procurement 17-Jul-08 31-Oct-08 100
232 - equipment installation 17-Jul-08 31-Oct-08 100
Electrical&Low currents 17-Jul-08 31-Oct-08 100
219 - Lighting 17-Jul-08 31-Oct-08 100
223 - Voice and data 17-Jul-08 31-Oct-08 100
224 - Sound and CCTV 17-Jul-08 31-Oct-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-09 100
234 - Stabilized ballast 22-Jul-08 22-Sep-09 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-09 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
31, 2008

Percent Prevoius day


Actual
Complete percent

33.42
36.40 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.82 3.27
0.01 0.01
3.55 3.55 3.55
4 4.00 3.99
15.5 40.79 40.79
30.08
60.15 60.15 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.30
8.88
0.01 0.01
1.34
4 4.00 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
43.02
100 100.00 100.00
3.19 3.19 3.18
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
628 62.80 62.70

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.43
35.84
35.83 14.86
82 93.18 92.05
16.89 19.19 19.19
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.3973047
68.48 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.38
118 100.00
117 99.15 98.31
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.01
16 16.00 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.34
7.6 7.60 7.00
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 1, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 1, 2008

Percent Prevoius day


Actual
Complete percent

33.42
36.41 33.18
72.30 72.30
100 100.00
98.2 98.20 98.20
90 90.00
1 1.00
6.82 3.27
0.01 0.01
3.55 3.55 3.55
4 4.00 3.99
15.5 40.79 40.79
30.10
60.18 60.18 60.15
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.33
8.89
0.01 0.01
1.34
4 4.00 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
43.08
100 100.00 100.00
3.19 3.19 3.18
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
629 62.90 62.80

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.43
35.84
35.83 14.86
82 93.18 92.05
16.89 19.19 19.19
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.3973047
68.48 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.38
118 100.00
117 99.15 98.31
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.01
16 16.00 15.00
0.01 0.01
2.15
2.15 2.15 2.10
18.86
18.18 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.46
7.6 7.60 7.00
0.15 0.15
0.15 0.15
1 1.00 0.15
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 4, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 4, 2008

Percent Prevoius day


Actual
Complete percent

33.47
36.57 33.18
72.75 72.75
100 100.00
100 100.00 98.20
90 90.00
1 1.00
6.85 3.27
0.01 0.01
3.55 3.55 3.55
4.1 4.10 4.00
15.5 40.79 40.79
30.10
60.18 60.18 60.18
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.11
0.5 0.50 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.82
9.14
0.01 0.01
1.34
4 4.00 4.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
44.31
100 100.00 100.00
3.19 3.19 3.18
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
650 65.00 62.90

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.43
35.85
35.84 14.86
82 93.18 92.05
16.9 19.19 19.19
0.01 0.01
0.01
0.01 0.01 Is it start?
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.4385547
68.48 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.38
118 100.00
117 99.15 99.15
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.01
16 16.00 16.00
0.01 0.01
2.15
2.15 2.15 2.10
19.02
18.35 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
1 1.00 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.48
7.65 7.65 7.60
0.15 0.15
0.15 0.15
1.1 1.10 1.00
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 5, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 5, 2008

Percent Prevoius day


Actual
Complete percent

33.47
36.57 33.18
72.75 72.75
100 100.00
100 100.00 98.20
90 90.00
1 1.00
6.86 3.27
0.01 0.01
3.55 3.55 3.55
4.12 4.12 4.10
15.5 40.79 40.79
30.10
60.18 60.18 60.18
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.11
0.52 0.52 0.50
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 17.82
9.14
0.01 0.01
1.34
4 4.00 4.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
44.31
100 100.00 100.00
3.2 3.20 3.19
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
650 65.00 62.90

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.43
35.85
35.84 14.86
82 93.18 92.05
16.9 19.19 19.19
0.01 0.01
0.01
0.01 0.01 Is it start?
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.4385547
68.48 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.38
118 100.00
117 99.15 99.15
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.06
16.1 16.10 16.00
0.01 0.01
2.15
2.15 2.15 2.10
19.02
18.35 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
1 1.00 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1.48
7.66 7.66 7.65
0.15 0.15
0.15 0.15
1.1 1.10 1.00
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 6, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 6, 2008

Percent Prevoius day


Actual
Complete percent

33.47
36.57 33.18
72.75 72.75
100 100.00
100 100.00 98.20
90 90.00
1 1.00
6.86 3.27
0.01 0.01
3.55 3.55 3.55
4.13 4.13 4.12
15.5 40.79 40.79
30.10
60.18 60.18 60.18
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.11
0.53 0.53 0.52
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 19.00
9.72
0.01 0.01
1.34
4 4.00 4.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
47.25
100 100.00 100.00
3.2 3.20 3.19
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
700 70.00 65.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.71
36.97
36.96 14.86
82 93.18 92.05
20 22.73 19.19
0.01 0.01
0.01
0.01 0.01 Is it start?
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.4737973
68.54 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.49
118 100.00
117.6 99.66 99.15
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.06
16.1 16.10 16.10
0.01 0.01
2.16
2.16 2.16 2.15
19.02
18.35 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
1 1.00 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.18
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1 1.00 0.10
0.1 0.10
0.1 0.10
1.48
7.67 7.67 7.66
0.15 0.15
0.15 0.15
1.1 1.10 1.00
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 7, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 7, 2008

Percent Prevoius day


Actual
Complete percent

33.48
36.58 33.18
72.50 72.50
100 100.00
100 100.00 98.20
90 90.00
0.01 0.01
7.16 3.27
1 1.00 0.01
3.55 3.55 3.55
4.14 4.14 4.13
15.5 40.79 40.79
30.10
60.18 60.18 60.18
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.12
0.54 0.54 0.53
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 19.00
9.72
0.01 0.01
1.34
4 4.00 4.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
47.25
100 100.00 100.00
3.2 3.20 3.20
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
700 70.00 70.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

12.80
37.33
37.32 14.86
82 93.18 93.18
21 23.86 22.73
0.01 0.01
0.01
0.01 0.01 Is it start?
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.4737973
68.54 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.49
118 100.00
117.6 99.66 99.15
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.11
16.2 16.20 16.10
0.01 0.01
2.16
2.16 2.16 2.15
19.02
18.35 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
1 1.00 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.18
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1 1.00 0.10
0.1 0.10
0.1 0.10
1.48
7.68 7.68 7.67
0.15 0.15
0.15 0.15
1.1 1.10 1.00
0.15 0.15
0.15 0.15
1 1.00
Progress Report Template
Project Title: ERA SHOPPING PARK ORADEA
Report for Period Ending: August 8, 2008

Total
Task Start Finish
phisical
PHASE 1 228 days 27-Mar-08 27-Feb-09
CARREFOUR, GALLERY MEDIA GALAXY 228 days 27-Mar-08 27-Feb-09
Superstructure 68 days 5-May-08 6-Aug-08
Main frame 55 days 5-May-08 20-Jul-08 100
12 - precast columns installation 30 days 5-May-08 13-Jun-08 100
13 - installation of precast beams 25 days 19-May-08 20-Jun-08 100
14 - complete roof structure with windbrass15 days 23-Jun-08 11-Jul-08 100
15 - Mezzanine floor slabs 20 days 23-Jun-08 20-Jul-08 100
Secondary structure 38 days 16-Jun-08 6-Aug-08
17 - Perimeter concrete beam (precast) - su25 days 16-Jun-08 20-Jul-08 100
18 Secondary structure foundations 15 days 26-Jun-08 16-Jul-08 100
19 - Internal Concrete walls 20 days 7-Jul-08 1-Aug-08 100
20 - Support structure for cladding 20 days 10-Jul-08 6-Aug-08 38
Flooring 56 days 13-Jun-08 5-Sep-08
25 - Balast and backfil 15 days 21-Jul-08 8-Aug-08 100
26 - Concrete floor 20 days 4-Aug-08 5-Sep-08 100
ARCHITECTURAL FINISHES 101 days 7-Jul-08 1-Dec-08
General works 37 days 1-Aug-08 29-Sep-08
32 - Roof deck 36 days 4-Aug-08 29-Sep-08 100
33 - roof insulation 37 days 1-Aug-08 29-Sep-08 100
34 - Skylights and roof tops 37 days 1-Aug-08 29-Sep-08 100
35 - External (side) cladding 25 days 7-Aug-08 17-Sep-08 100
Carrefour Finishes 21 days 1-Sep-08 29-Sep-08
37 - Sectional and over head doors 14 days 10-Sep-08 29-Sep-08 100
38 - Exterior doors and windows 10 days 15-Sep-08 26-Sep-08 100
39 - Internal walls 15 days 1-Sep-08 19-Sep-08 100
40 - Internal doors 10 days 16-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy finishes 55 days 16-Sep-08 1-Dec-08
42 - Finishes 55 days 16-Sep-08 1-Dec-08 100
47 General Works 34 days 15-Jul-08 5-Sep-08
48 - Under slab conduits 15 days 15-Jul-08 4-Aug-08 100
49 - Rain water (geberit system) 20 days 4-Aug-08 5-Sep-08 100
Carrefour works 21 days 1-Sep-08 29-Sep-08
51 - Sewage and potable water networks 21 days 1-Sep-08 29-Sep-08 100
52 - Fire fighting (sprinklers and hydrants) 21 days 1-Sep-08 29-Sep-08 100
53 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
54 - Low currents (fire detection) 21 days 1-Sep-08 29-Sep-08 100
55 - Power distribution 21 days 1-Sep-08 29-Sep-08 100
Gallery and Media Gallaxy 60 days 5-Aug-08 3-Nov-08
57 - Sewage and potable water networks 25 days 5-Aug-08 15-Sep-08 100
58 - Fire fighting (sprinklers and hydrants) 25 days 5-Aug-08 15-Sep-08 100
59 - HVAC 45 days 5-Aug-08 13-Oct-08 100
60 - Low currents 25 days 30-Sep-08 3-Nov-08 100
61 - Power distribution 25 days 30-Sep-08 3-Nov-08 100

Total
Task Start Finish
phisical
EXTERIOR WORKS FOR PHASE 1 172 days 3-Jun-08 17-Feb-09 100
Exterior M&E works 143 days 12-Jun-08 16-Jan-09
81 Water tanks 30 days 17-Jul-08 3-Sep-08 100
Pumps station 81 days 31-Jul-08 27-Nov-08
83 - structure 35 days 31-Jul-08 24-Sep-08 100
84 - equipments (procurmenent and install 66 days 31-Jul-08 6-Nov-08 100
85 - internal distribution 20 days 31-Oct-08 27-Nov-08 100
Transformers and boilers 110 days 17-Jul-08 6-Jan-09 100
87 - equipment procurement 90 days 17-Jul-08 26-Nov-08 100
88 - equipment installation 20 days 27-Nov-08 6-Jan-09 100
Exterior works distribution 118 days 17-Jul-08 16-Jan-09
90 - electrical 88 days 17-Jul-08 24-Nov-08 100
91 - sewage 88 days 17-Jul-08 24-Nov-08 100
92 - utilities connections 30 days 25-Nov-08 16-Jan-09 100
Exterior civil works (roads and platforms) 172 days 3-Jun-08 17-Feb-09
94 - retention walls 30 days 3-Jun-08 14-Jul-08 100
95 - balast and backfill 30 days 21-Aug-08 1-Oct-08 100
96 - kerbstones and walkways 30 days 18-Sep-08 29-Oct-08 100
97 - stabilized ballast 30 days 30-Oct-08 10-Dec-08 100
98 - heavy traphic asphalt 30 days 11-Dec-08 3-Feb-09 100
99 Finishes 20 days 21-Jan-09 17-Feb-09 100
100 Road Marking and signage 10 days 4-Feb-09 17-Feb-09 100
101 Fencing 40 days 3-Jun-08 28-Jul-08 1000

Total
Task Start Finish
phisical
MULTIPLEX 160 days 1-Jul-08 27-Feb-09 100
STRUCTURES 103 days 1-Jul-08 27-Nov-08
107 Foundations 15 days 2-Sep-08 22-Sep-08
108 Main structure 28 days 16-Sep-08 23-Oct-08
109 Secondary structures 25 days 24-Oct-08 27-Nov-08
M&E INSTALLATIONS 100 days 29-Jul-08 22-Dec-08
114 Installations works 42 days 24-Oct-08 22-Dec-08
ARCHITECTURAL FINISHES 85 days 26-Aug-08 22-Dec-08
119 Finishes works 42 days 24-Oct-08 22-Dec-08

Total
Task Start Finish
phisical
MALL AREA 12'-18' - PHASE 1 136 days 2-Jul-08 27-Jan-09
ARCHITECTURAL FINISHES 111 days 6-Aug-08 27-Jan-09 100
128 Finishes works 66 days 15-Oct-08 27-Jan-09 100
M&E INSTALLATIONS 111 days 2-Jul-08 10-Dec-08 100
133 Installations works 66 days 10-Sep-08 10-Dec-08 100
Total
Task Start Finish
physical
PHASE 2 265 days 26-Jun-08 21-Jul-09
Shopping Mall & Gallery (Prior tenant handover) 265 days 26-Jun-08 21-Jul-09
STRUCTURES 161 days 26-Jun-08 25-Feb-09
Infrastructures 50 days 26-Jun-08 10-Sep-08
139 - foundations excavations 30 days 26-Jun-08 6-Aug-08 88
140 - Concrete works for foundations 45 days 3-Jul-08 10-Sep-08 88
141 - Dock leveleres concrete works 35 days 10-Jul-08 3-Sep-08 100
Superstructure 161 days 26-Jun-08 25-Feb-09
143 - Precast columns production 35 days 26-Jun-08 20-Aug-08 88
144 - Precast columns installation 28 days 7-Aug-08 22-Sep-08 88
145 - Precast roof elements production 21 days 23-Sep-08 21-Oct-08 100
146 - Installation of cladding support structu 35 days 22-Oct-08 9-Dec-08 100
147 - Installation of internal partitions struct 20 days 29-Jan-09 25-Feb-09 100
148 - Mezzanine floor slabs 28 days 22-Oct-08 28-Nov-08 100
Floors 99 days 21-Aug-08 19-Jan-09
150 - Balast and backfill 20 days 21-Aug-08 17-Sep-08 100
151 - Concrete slabs 15 days 17-Dec-08 19-Jan-09 100
ARCHITECTURAL FINISHES 156 days 22-Oct-08 9-Jun-09
153 - Roof Deck 25 days 22-Oct-08 25-Nov-08 100
154 - Roof insulation 50 days 5-Nov-08 26-Jan-09 100
155 - Skylights and roof tops 40 days 26-Nov-08 2-Feb-09 100
156 - Internal partitions 50 days 3-Feb-09 13-Apr-09 100
157 - Sectional and overhead doors 20 days 14-Apr-09 11-May-09 100
158 - Dock levellers 20 days 14-Apr-09 11-May-09 100
159 - External doors and windows 35 days 14-Apr-09 1-Jun-09 100
160 - Internal partitions and specific structu 56 days 3-Feb-09 21-Apr-09 100
161 - Special finishes and glazing at the inte40 days 26-Feb-09 22-Apr-09 100
162 - Internal doors and windows 20 days 22-Apr-09 19-May-09 100
163 - wall and ceiling finishes 45 days 8-Apr-09 9-Jun-09 100
164 - roof skylights, ceiling special finishes 45 days 8-Apr-09 9-Jun-09 100
165 - flooring finishes 45 days 8-Apr-09 9-Jun-09 100
M&E INSTALLATIONS 119 days 1-Dec-08 27-May-09
Water and sewage 113 days 1-Dec-08 19-May-09
168 - Rainwater 35 days 29-Jan-09 18-Mar-09 100
169 - Foul water 50 days 1-Dec-08 19-Feb-09 100
170 - Watter supply 40 days 25-Mar-09 19-May-09 100
171 - Hydrants 45 days 29-Jan-09 1-Apr-09 100
172 - Sprinklers 65 days 29-Jan-09 29-Apr-09 100
173 - Heating, ventilation & cooling 75 days 29-Jan-09 13-May-09 100
Boiler rooms 65 days 29-Jan-09 29-Apr-09
175 - Distribution 65 days 29-Jan-09 29-Apr-09 100
176 - Equipments 25 days 29-Jan-09 4-Mar-09 100
Electrical 70 days 29-Jan-09 6-May-09
178 - Electrical boards 25 days 2-Apr-09 6-May-09 100
179 - Distribution 60 days 29-Jan-09 22-Apr-09 100
180 - Lighting 70 days 29-Jan-09 6-May-09 100
181 - Supply 65 days 29-Jan-09 29-Apr-09 100
Low voltage 45 days 26-Mar-09 27-May-09
183 - Fire detection system 45 days 26-Mar-09 27-May-09 100
184 - Voice and data 45 days 26-Mar-09 27-May-09 100
185 - Sound and CCTV 30 days 16-Apr-09 27-May-09 100
EXTERIOR WORKS 135 days 1-Dec-08 18-Jun-09
187 - Retention walls 30 days 1-Dec-08 22-Jan-09 100
188 - Ballast and backfill 15 days 23-Jan-09 12-Feb-09 100
189 - Stabilized ballast 15 days 13-Feb-09 5-Mar-09 100
190 - Asphalt layers 35 days 20-Mar-09 7-May-09 100
191 - Kerbstones and walkways 30 days 6-Mar-09 16-Apr-09 100
192 - Landscaping 30 days 8-May-09 18-Jun-09 100

Total
Task Start Finish
phisical
BRICOSTORE 2-Jul-08 27-Jan-09
STRUCTURES 1-Jul-08 27-Nov-08
Infrastructures 26-Jun-08 10-Sep-08
193 - foundations excavations 26-Jun-08 6-Aug-08 118
194 - Concrete works for foundations 3-Jul-08 20-Jun-08 100
195 - Dock leveleres concrete works 10-Jul-08 3-Sep-08 100
Superstructure 26-Jun-08 25-Feb-09
197 - Precast columns production 2-May-08 26-Jul-08 118
198 - Precast columns installation 3-Jun-08 26-Jul-08 118
199 - Precast roof elements production 20-Jun-08 20-Jul-08 100
200 - Installation of cladding support structure 21-Jul-08 22-Jul-08 100
201 - Installation of internal partitions structure 22-Jul-08 23-Jul-08 100
203 Floors 31-Aug-08 21-Sep-08
204 - Balast and backfill 31-Aug-08 17-Sep-08 100
205 - Concrete slabs 17-Dec-08 21-Sep-08 100
ARCHITECTURAL FINISHES 16-Jul-08 27-Jan-09
Finishes works 14-Sep-08 26-Oct-08 100
M&E INSTALLATIONS 2-Jul-08 2-Nov-08
206 Water and sewage 11-Jun-08 5-Oct-08
207 - Rainwater 11-Jul-08 5-Oct-08 100
208 - Foul water 25-Jun-08 5-Oct-08 100
209 - Watter supply 10-Aug-08 5-Oct-08 100
210 - Hydrants 29-Jul-09 1-Jul-08 100
211 - Sprinklers 10-Aug-08 5-Oct-08 100
212 - Heating, ventilation & cooling 10-Aug-08 28-Sep-08 100
Boiler rooms 31-Aug-08 28-Sep-08
214 - Distribution 31-Aug-08 28-Sep-08 100
215 - Equipments 31-Aug-08 28-Sep-08 100
Electrical 1-Sep-08 11-Nov-08
217 - Electrical boards 31-Aug-08 2-Nov-08 100
218 - Distribution 6-Aug-09 3-Sep-09 100
219 - Lighting 10-Aug-08 2-Nov-08 100
220 - Supply 10-Aug-08 2-Nov-08 100
221 Low voltage 10-Aug-08 2-Nov-08
222 - Fire detection system 10-Aug-08 2-Nov-08 100
223 - Voice and data 10-Aug-08 2-Nov-08 100
224 - Sound and CCTV 10-Aug-08 2-Nov-09 100
Exterior M&E works 16-Jun-08 2-Nov-08
225 Water tanks 10-Aug-08 2-Nov-08 100
226 Pumps station 10-Aug-08 2-Nov-08 100
227 - structure 10-Aug-08 2-Nov-08 100
228 - equipments (procurmenent and installation) 10-Aug-08 2-Nov-08 100
229 - internal distribution 10-Aug-08 2-Nov-08 100
230 Transformers and boilers 31-Aug-08 31-Oct-08 100
231 - equipment procurement 31-Aug-08 31-Oct-08 100
232 - equipment installation 31-Aug-08 31-Oct-08 100
Electrical&Low currents 31-Aug-08 2-Nov-08 100
219 - Lighting 31-Aug-08 2-Nov-08 100
223 - Voice and data 31-Aug-08 2-Nov-08 100
224 - Sound and CCTV 31-Aug-08 2-Nov-08 100
EXTERIOR WORKS 11-Apr-08 3-Oct-08
233 - Ballast and backfill 21-Jul-08 21-Sep-08 100
234 - Stabilized ballast 22-Jul-08 22-Sep-08 100
235 - Asphalt layers 19-Aug-08 18-Sep-08 100
236 - Kerbstones and walkways 25-Aug-08 24-Sep-08 100
237 - Landscaping 21-Aug-08 9-Sep-08 100
238 Road Marking and signage 26-Jul-08 26-Sep-09 100
239 Fencing 27-Jul-08 27-Sep-09 100
G PARK ORADEA
st 8, 2008

Percent Prevoius day


Actual
Complete percent

33.50
36.68 33.18
72.50 72.50
100 100.00
100 100.00 98.20
90 90.00
0.01 0.01
7.46 3.27
2 2.00 1.00
3.55 3.55 3.55
4.15 4.15 4.14
15.5 40.79 40.79
30.10
60.18 60.18 60.18
0.01 0.01
32.67
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
98.00
98 98.00
0.00
0.01 0.01
0.01 0.01
0.12
0.56 0.56 0.54
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
10 19.00
9.73
0.01 0.01
1.34
4 4.00 4.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
47.26
100 100.00 100.00
3.25 3.25 3.20
0.09 0.09
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
700 70.00 70.00

Percent Prevoius day


Actual
Complete percent
3 3 100
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!

Percent Prevoius day


Actual
Complete percent
1
1 1
1 1
1 1
1 1
Percent Prevoius day
Actual
Complete percent

13.07
38.42
38.41 14.86
84 95.45 93.18
22 25.00 23.86
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.51
1 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
13.84
80 80.00
3 3.00
0.01 0.01
0.01 0.01
0.01 0.01
0.01 0.01

Percent Prevoius day


Actual
Complete percent
22.4784615
68.56 63.47
73.58 73.58
118 100.00
100 100.00
16 16.00
63.53
118 100.00
117.8 99.83 99.66
100 100.00 100.00
2.6 2.60 2.60
2.1 2.10 2.00
8.11
16.2 16.20 16.20
0.01 0.01
2.16
2.16 2.16 2.15
19.02
18.35 18.01
7.65 7.65 7.65
2.42 2.42 2.42
0.01 0.01
99 99.00 99.00
0.01 0.01
1 1.00 0.01
0.01
0.01 0.01
0.01 0.01
0.66
0.01 0.01
1.6 1.60 1.60
1 1.00 1.00
0.01 0.01
0.01
0.01 0.01
0.01 0.01
0.01 0.01
0.18
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
0.1 0.10
1 1.00 0.10
0.1 0.10
0.1 0.10
1.48
7.69 7.69 7.68
0.15 0.15
0.15 0.15
1.1 1.10 1.00
0.15 0.15
0.15 0.15
1 1.00