1.1. INTRODUCTION
Paku Field is located in Block PM6 Offshore Terengganu, Malaysia in Malay Basin.
PM6 block is at the southern part of Malay Basin. Paku Field is located south of
Meranti, south-west of Dulang, north of Beranang and north-west of Ketumbar. The
water depth is 76 metres. Paku Field consists of 5 main wells which are Paku-1, Paku-2
(005º36’59.6411’’N, 103º53’54.997’’E), Paku-3 (000º0’0.0977’’N, 100º30’40.582’’E),
Paku-4 (005º35’36.9’’N, 103º56’55.5’’E) and Paku-NW (005º36’25.6901’’N,
103º52’5.6’’E).
1.2. OBJECTIVES
The objective of Field Development Plan (FDP) is to perform a technical and economic
study of Paku Field by focusing on the latest technologies, economics, environmental
and political conditions and implementing knowledge gained from Oil and Gas
Engineering courses.
This project involves development of oil and gas reservoirs in Paku field within 18
weeks. Focus will be given to oil development. The disciplines involved in this FDP are
Geology and Geophysics, Petrophysics, Reservoir Engineering, Drilling Engineering,
1
Production Technology, Facilities Engineering, Economics and Health, Safety and
Environment.
1.3.1. Deliverables
The deliverables from each discipline are shown in the Table 1.1 below.
Disciplines Deliverables
Geology and To interpret the seismic data and identify the petroleum
Geophysics system, stratigraphy and depositional environment of
given field.
Perform GRV and HIP calculation and determine the
uncertainties.
Petrophysics To derive petrophysical parameters and perform full log
interpretation
Reservoir To identify reservoir type and drive mechanism
Engineering To perform static and dynamic reservoir simulation
Drilling To prepare drilling program
Engineering To identify proper drilling waste management, drilling
risk and mitigation plan
Production To perform well performance analysis and design the
Technology completion string
To predict production problems and provide mitigation
measures
Facilities To design the most suitable platform together with
Engineering processing facilities
Economics To carry out economic assumptions
To perform economic sensitivity analysis
Health, Safety To come out with suitable HSE planning and procedures
and Environment
2
1.4.2. Project Management Team
1.4.4. Vision
3
1.4.6. Organization Chart
4
1.5. GANTT CHART
5