Sei sulla pagina 1di 6

SPE 69594

Significance of Project Risking Methods on Portfolio Optimization Models


P.A. Tyler, Schlumberger GeoQuest, J.R. McVean, Merak Projects

Copyright 2001, Society of Petroleum Engineers Inc.


process, and selecting the “optimal” portfolio while staying
This paper was prepared for presentation at the SPE Latin American and Caribbean Petroleum within the corporate strategy and constraints can become a
Engineering Conference held in Buenos Aires, Argentina, 25–28 March 2001.
very daunting exercise. The task of matching project selection
This paper was selected for presentation by an SPE Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
to the company strategy and goals is often referred to as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to Portfolio Management. There are many elements that must be
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at taken into account in portfolio management, including.
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
• Maximizing the value of the portfolio.
for commercial purposes without the written consent of the Society of Petroleum Engineers is • Living within the capital spending limits.
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous • Meeting the production requirements.
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O.
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435. • Achieving both short term and long term cash flow
goals.
Abstract • Matching forecasted net income targets.
Efficient frontier theory is gaining acceptance as a part of the • Meeting developmental and/or environmental
portfolio analysis process in the petroleum industry. One of constraints.
the major difficulties companies encounter in creating This is even more complex in our industry where many
corporate efficient frontiers is in representing project level projects have significant amounts of uncertainty, or variation
risks in a corporate consolidation of value. Full stochastic in the possible outcomes. In recent years more and more
evaluations require the management of huge quantities of data. attention has been placed on how to represent these
As a result several current solutions use multiple discrete uncertainties within the portfolio evaluation. These
outcomes to represent any given project, rather then a uncertainties exist in various forms within the investment
complete stochastic distribution. This paper evaluates the projects of a petroleum company, and can include.
differences resulting from using these two approaches to • Existence of hydrocarbons (probability of success).
project risking. By examining the optimized portfolio results • Geological reservoir properties.
and the resultant efficient frontier, we are able to draw direct • Timing and extent of the development program.
conclusions about the added value attributable to detailed • Capital and operating costs.
Monte Carlo based evaluations. Since price is the source of • Oil and gas prices.
most correlation between projects, the investigation was done These uncertainties in the input data required to make an
with and without price as an input variable. It was discovered economic evaluation of E&P projects lead to uncertainties in
that the differences between the stochastic and discrete the economic results. Acknowledging that these uncertainties
outcome evaluations are not significant when price uncertainty exist in the individual projects, naturally leads to the concept
is neglected, but the inclusion of price leads to significant that uncertainties exist in the overall portfolio. In recent years
differences if the resulting correlation is not accounted for. a significant amount of effort has been spent in trying to
define this portfolio risk and to compare portfolio’s by their
Introduction risk vs. reward relationship.
Petroleum managers are constantly faced with the decision In light of the importance of portfolio level risk, this paper
of how to invest limited amounts of capital in order to compares two differing approaches to project evaluation under
maximize shareholder value or return. This is usually done by uncertain conditions, and the effect the differing approaches
evaluating all the available investments, and then selecting a have on the overall portfolio risk measurements. The two
subset in which to invest. This subset is often referred to as approaches compared will be an uncertainty tree approach
the company’s portfolio. Selection of this portfolio is critical where projects are evaluated as distinct outcomes each with a
to a company’s success and therefore it requires significant differing probability of occurrence (referred to here as “simple
consideration. stochastic”), and a full Monte Carlo evaluation approach
The goal of the portfolio selection process is to select the where the projects are evaluated across the full range of input
“optimal” set of projects. However, this is not a simple uncertainties.
2 P.A. TYLER, J.R. MCVEAN SPE 69594

This paper will focus on a semi-standard deviation


Theory and Definitions definition of portfolio risk in order to simplify the analysis.
In a 1952 article, Noble laureate Harry Markowitz explained Semi-standard deviation is a popular measure of downside
the theory of portfolio diversification from the perspective of uncertainty or risk, and is commonly used by many who are
minimizing risk. His work completely changed the field of employing portfolio management in the petroleum industry.
portfolio optimization (Markowitz, 1952). There are three The use of simple stochastic data at the project level leads
basic principles that need to be understood prior to any to smooth risk profiles at the portfolio level. As the discrete
discussion of efficient frontier theory. outcomes are combined in larger and larger numbers of
• A rational investor will prefer more value to less value, projects, the discreteness of the outcomes is lost. A portfolio
but will also prefer less risk to more risk. that has ten projects, each with four discrete outcomes,
• A portfolio can be more or less than the sum of its contains slightly more then one million possible outcomes. To
individual projects, depending on how the investments illustrate this, the NPV distribution for one of the mid range
interact with each other. The interaction between portfolios (LV – 1) used in this paper, is shown with both the
investments is as important as the individual investments full Monte Carlo based data (Fig. 2) and the simple stochastic
themselves. data
• There is no single optimal portfolio as it is generally (Fig. 3).
possible to gain more value by accepting more risk.
This last point is essentially an expression of the concept
of efficient portfolios. A portfolio is said to be efficient if it is
the case that no other portfolio has more value while having
the same or less risk, and there is no other portfolio that has
less risk while having the same or more value. In order to
evaluate the “efficiency” of any given portfolio it is typically
plotted on an efficient frontier graph (Fig. 1). This graph is a
plot of several portfolios, each with it’s own value and risk
measurements. Points to the right (higher value) and below
(lower risk) are said to be more efficient portfolios than
portfolios that lie to the left or above. The collection of
portfolios that lie on the lower right edge of this graph are
referred to as the efficient frontier. For the given strategy and
goal, there are no other portfolios that generate the same value
for less risk. Fig. 2—NPV distribution of the portfolio LV – 1 from the full Monte
Carlo based optimization.

Fig. 3—NPV distribution of the portfolio LV – 1 from the simple


Fig. 1—An illustration of the efficient frontier graph. Portfolio A is stochastic based optimization.
dominated by all portfolios in quadrant II (portfolios B and C) and
dominates all portfolios in quadrant IV. Portfolio D is neither Project Generation
dominated nor dominates portfolio E because E is in D’s first
quadrant. Portfolios B, C, D, and E are all efficient because they
In order to evaluate the differences that the project risk
have no portfolios in their second quadrant. evaluation method has on portfolio risk, we needed to start
with a typical group of projects. In our case we used thirty
projects based on real evaluations from differing locations
SPE 69594 SIGNIFICANCE OF PROJECT RISKING METHODS ON PORTFOLIO OPTIMIZATION MODELS 3

around the world. The projects included typical producing the capital development costs were scaled around the
assets, acquisitions and a large proportion of exploration individual outcomes using a historically validated function.
projects (Table 1). The projects do not however represent This leads to a far more robust and complex evaluation of the
any single company or country, and the values have been individual projects. Typical results from four of the
modified slightly to ensure anonymity. exploration projects evaluated are shown in Fig. 5.
Each project was fully evaluated using a probabilistic
reservoir simulator, and the resultant distributions were used Incorporation of Price Uncertainties
as the basis for all evaluations. Deterministic development One of the issues with portfolio risk evaluations is that if
profiles were created for the most likely successful outcomes. you need to include price uncertainty, it usually needs to be
For the exploration projects; failure, low and high fully correlated across all the projects, unlike most technical or
deterministic evaluations were also created, and the reservoir uncertainty. This can be achieved in Monte Carlo
probability of each outcome was derived from the simulator simulations by applying a single price distribution to the entire
results. The combination of these creates a “simple set of projects. This global application of a price uncertainty
stochastic” evaluation of the projects. These can be allows fully correlated prices across multiple projects. This is
represented by multiple branch uncertainty trees (Fig. 4), and easily accomplished in many of today’s Monte Carlo
could have included as many outcomes as required to describe simulating systems, but adds a considerable complexity to
the development options. uncertainty tree analyses.
In order to illustrate the importance of this correlation, a
second set of project data was generated in which the Monte
Carlo evaluated projects used a fully correlated price
distribution, while the simple stochastic evaluations used a
typical 3-branch price uncertainty (Fig. 6).

Fig. 4—An example of the typical simple stochastic evaluation of


an exploration project used in the risked portfolio optimization.
The probabilities are derived from a detailed analysis of the
inherent reservoir uncertainties, and the independent scenarios
came from the development engineering group.
Fig. 6—An example of the typical simple stochastic evaluation
including the uncertainty associated with price. This is a
schematic representation, where price uncertainty effects all end
nodes.

It is possible to account for price-induced inter-project


correlation using a modified simple stochastic approach.
Including the 3-branch uncertainty node, to roughly model
price uncertainty, increases the number of possible outcomes
from four to twelve. When combining projects into portfolios,
perfect price correlation can be achieved by insuring that only
project outcomes of similar price assumptions are combined.
In other words, the high price outcomes of each project can
only be combined with high price outcomes of other projects.
This technique, while requiring more project outcome
evaluations and considerable care in the portfolio generation
stage, may prove to be sufficient to capture the broad affects
of inter-project correlation, provided price is the only
Fig. 5—Four examples of project risk profiles that are markedly significant contributor to this correlation. For the purposes of
different from normal distributions. These risk profile shapes are this paper, this approach was not attempted but further study
typical of exploration projects.
of this topic is clearly warranted.
In the case of the full Monte Carlo evaluations, the same
specific development assumptions were made as in the simple
stochastic evaluations. However, the entire distribution of
outcomes from the reservoir simulator was incorporated, and
4 P.A. TYLER, J.R. MCVEAN SPE 69594

Portfolio Optimization Process evaluations were selected. They are labeled on Fig. 7, and
In order to evaluate the effect that these two approaches had their characteristics are listed in Table 1. The same portfolios
on the portfolio risk measurement, an efficient frontier was (groups of projects) were then identified in the simple
developed for each of the four project evaluations. stochastic efficient frontier graph (Fig. 8). As can be seen
• Full Monte Carlo evaluations without price most of the portfolios remained efficient or did not shift
uncertainty. markedly from the efficient frontier in the simple stochastic
• Simple stochastic evaluations without price optimizations. This indicates the differences in the evaluation
uncertainty. detail did not significantly effect the portfolio selection or
• Full Monte Carlo evaluations with fully correlated portfolio risk comparisons, when price uncertainty was
price uncertainty. ignored.
• Simple stochastic evaluations with price uncertainty
without correlation.
This was accomplished by defining a strategy that
consisted of the following requirements.
• A minimum annual produced oil volume and gas
volume was required from year 2003 to 2010.
• Annual exploration capital and production capital
expenditure was limited for all years
• Cumulative reserve replacement over the first five
years and over the first ten years were specified.
Only portfolios that met all of the above goals were
included in the efficient frontier graph. In this case, the
projects could either be included or not. The model was not
permitted to vary the percent working interest in any of the
projects. This was representative of the majority of projects Fig. 7—The optimized efficient frontier graph based on the full
we were working with, and is often how some companies Monte Carlo based project evaluations without price uncertainty.
The highlighted efficient portfolios were chosen for comparison
evaluate portfolio selection. with the simple stochastic based efficient frontier.
The optimizer objective value was set to maximize NPV at
a 10% discount rate, or to minimize the semi-standard
deviation of NPV at a 10% discount rate, our risk measure.
By varying the minimum required NPV for a given
optimization, and optimizing on minimum possible risk,
specific portfolios from the set of the most efficient portfolios
found were noted. Randomly generated portfolios were used
to supplement the efficient portfolios, in order to populate the
efficient frontier graph. In total over fifteen optimizations
were run for each graph.
The exact same optimization procedure was performed for
all sets of input data (Figs. 7 to 10), and the efficient frontiers
were compared for both project selection and overall risk
measures.

Results Fig. 8—The efficient frontier graph based on the simple stochastic
project evaluations, without price uncertainty. Note that most of
Using the full Monte Carlo evaluations, the resultant portfolio the portfolios identified as efficient in Fig. 7 are efficient or close
NPV’s ranged from MM$1,510 to MM$3,070, while the to efficient here.
associated risk ranged from MM$225 to MM$660 (Fig. 7).
While using the simple stochastic evaluations, the resultant
portfolio NPV’s ranged from MM$1,510 to MM$3,070, and The same procedure was carried out using the projects
the associated risk ranged from MM$200 to MM$490 (Fig. 8). evaluated with price uncertainty. Using the full Monte Carlo
The identical NPV values are no surprise as the expected evaluations with correlated price uncertainty, the resultant
values of the simple stochastic evaluations matched the mean portfolio NPV’s ranged from MM$1,565 to MM$3,040, while
values (expected) from the full Monte Carlo evaluations the associated risk ranged from MM$610 to MM$1,000 (Fig.
(Table 2). 9). Using the simple stochastic evaluations with non
In order to compare the optimized project selection correlated price uncertainty, the resultant portfolio NPV’s
between the two project risking methods, fourteen of the most ranged from MM$1,560 to MM$3,040, and the associated risk
efficient portfolios found based on the full Monte Carlo ranged from MM$310 to MM$590 (Fig. 10).
SPE 69594 SIGNIFICANCE OF PROJECT RISKING METHODS ON PORTFOLIO OPTIMIZATION MODELS 5

The difference in the risk measurement is a significant


factor in this case. Including correlated price uncertainty in the
full Monte Carlo based project evaluations leads to a
significant increase in the range of possible values for
resulting portfolios. This increase in the width of the portfolio
risk profiles manifests itself as larger semi-standard
deviations. In the case of the simple stochastic approach with
price uncertainty, the lack of price correlation means that this
affect is not observed.
In order to compare the optimized project selection and the
effect of price correlation, 14 of the most efficient portfolios
found based on the full Monte Carlo with correlated price
evaluations were selected. They are labeled on Fig. 9. The
same portfolios (groups of projects) were then identified in the
Fig. 10—The efficient frontier graph based on the simple
simple stochastic efficient frontier graph with non correlated stochastic project evaluations, including non correlated price
price uncertainty (Fig. 10). In this case only four of the uncertainty. Note location of the Portfolios, from Fig. 9, which
fourteen portfolios are still efficient using the simple were efficient in the full Monte Carlo efficient frontier with
stochastic project data with non correlated prices. The correlated price uncertainty.
portfolios are close to the efficient frontier, indicating that the
reduced evaluation detail still has some value. Conclusions
The method of describing risk at the individual project level, is
a factor in the portfolio optimization and analysis process.
Using full Monte Carlo based evaluations does lead to
improved risk measurement and more accurate portfolio
analysis.
Using a relatively simple uncertainty tree approach to
evaluate the projects will lead to similar portfolio optimization
results when using risk measures as the main selection criteria,
with significantly less effort in the creation of the project
evaluations.
The incorporation of price uncertainty leads to large
differences in the two approaches due to the effects of the
correlation. The authors feel more investigation is warranted
in the effects of incorporating correlated prices in the simple
Fig. 9—The optimized efficient frontier graph based on the full stochastic evaluations.
Monte Carlo based project evaluations, including fully correlated
price uncertainty. The highlighted efficient portfolios were
This paper firmly demonstrates that companies can start
chosen for comparison with the simple stochastic based efficient down the road of risked based portfolio optimization and
frontier. analysis without having to put together detailed Monte Carlo
based evaluations for every project. A mix of the approaches
The simple stochastic approach to project evaluation can be used to perform risk based portfolio optimization and
inevitably leads to the loss of inter-project correlations. analysis, allowing companies to use the detailed data where
However, in many cases there is little cause for inter-project available, without having to force everyone into long and
correlation, with the notable exception of price. As we have detailed analysis of every project.
seen, the loss of this correlation can significantly affect the
understanding of the level of risk involved with the resulting References
portfolios, although the selection of optimal portfolios may not 1. Markowitz, H.: “Portfolio Selection”, The Journal of Finance,
be affected as significantly Vol. VII, No. 1, (1952) 77-91.
2. McVean, J.R..: “The Significance of Risk Definition on Portfolio
Selection”, SPE 62966, 2000 SPE annual technical conference
and exhibition in Dallas, Texas, 1-4 Oct, 2000.
6 P.A. TYLER, J.R. MCVEAN SPE 69594

Appendix A—Project Characteristics Appendix B—Portfolio Properties

TABLE 1— Expected Value Project Characteristics TABLE 2— Portfolio Properties, w/o price uncertainty
Semi-Standard Semi-Standard
AT Cash Capital Oil Prod. Probability deviation based deviation based
Name NPV 10% Undisc. Type of Success Number
AT Cash on Full on Simple
(MM$) (MM$) (MMSTB) (%) Name of
NPV 10% Monte Carlo Stochastic
Projects
EP 1 127 142 56 Acq. - Inputs Inputs
(MM$) (MM$) (MM$)
EP 2 102 62 50 Dev. - Max V 3,070 660 25 490
EP 3 200 133 182 Dev. - HV - 1 2,860 639 22 477
EP 4 251 119 212 Dev. - HV – 2 2,796 611 23 485
EP 5 367 345 47 Acq. - HV – 3 2,690 565 23 442
EP 6 68 75 57 Del. 90 HV – 4 2,613 540 25 378
EP 7 90 137 88 Expl. 72 AV – 1 2,552 523 21 377
EP 8 77 28 48 Expl. 35 AV – 2 2,420 460 24 350
EP 9 125 88 44 Expl. 41 AV – 3 2,352 430 24 315
EP 10 128 204 111 Expl. 17 AV – 4 2,240 403 23 310
EP 11 80 71 80 Del. 94 LV – 1 2,186 380 22 285
EP 12 85 121 85 Expl. 30 LV – 2 2,034 362 20 276
EP 13 30 86 38 Expl. 27 LV – 3 1,889 337 21 255
EP 14 92 95 66 Dev. - LV – 4 1,771 311 19 225
EP 15 51 31 21 Dev. - Min R 1,510 225 19 200
EP 16 47 96 47 Expl. 40
EP 17 8 21 11 Expl. 30
EP 18 7 20 10 Expl. 20
EP 19 5 9 7 Del. 95
EP 20 6 5 6 Del. 90
EP 21 106 452 182 Expl. 30
EP 22 38 182 79 Expl. 60
EP 23 110 352 138 Expl. 23
EP 24 148 42 28 Expl. 43
EP 25 184 387 237 Dev. -
EP 26 50 73 46 Expl. 80
EP 27 118 143 103 Del. 90
EP 28 187 82 32 Expl. 15
EP 29 283 69 39 Del. 90
EP 30 23 51 39 Expl. 25

Potrebbero piacerti anche