Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1
Estimating Work Items Costs
Swell and Compaction Factors
To estimate the cost of excavating and hauling earth, it is
necessary to know the physical properties of earth because
the volume changes during construction operations.
The soil is excavated from its natural state, placed in a hauling
unit and transported to the disposal area, where it is
distributed and compacted.
The soil to be excavated is called bank measure, in its
undisturbed condition.
Any additional requirements to support the excavation
operation should be also added to the cost estimating of an
excavation operation. For example, excavation support,
dewatering, etc.
2
Estimating Work Items Costs
Waste Factors
When estimating the material required for any job,
it is necessary to add a portion for the wastage of
material used
Allowance for waste and spillage of this material
can be made by increasing the takeoff quantities or
by raising the price by the percentage factor
considered necessary
The values of waste factors usually ranges from
one to 10 percent for different materials
3
Estimating Work Items Costs
Example
Operator unit price = LE40/hr;
Labor unit price = 0.5 × 30 = LE15/hr
Backhoe unit price = 670 / 8 = LE83.75/hr
This crew produces 60 m3/day
Labor price/m3 = 55 / 60 = LE0.92/m3
Equipment price/m3 = 83.75 / 60 = LE1.4/m3
Transportation price = 4000 / 3000 = LE1.33/m3
Then price/m3 = LE3.65/m3
23/04/2016 Emad Elbeltagi 7
4
Estimating Work Items Costs
Example 2: calculate number of trucks
Truck capacity = 12 (loose material) / 1.12 = 10.71 m3
(bank measure).
Loading time = 10.71 × 60 / 50 = 12.85 min
Travel time = 16 × 2 × 60 / 20 = 96 min
Cycle time= 12.85 + 96 + 5 = 113.85 min
No. of trucks = 113.85 / 12.85 = 8.86 = 9 trucks
5
Estimating Direct Cost
Preparing the method statement
Work breakdown structure
A schedule of the activities showing the labor and
materials required
Construction method of each work item
List of risks and uncertainties the contractor is going
to carry and responses to deal with them
A detailed program of the work (schedule) showing
the proposed duration of each work item
6
Estimating Direct Cost
Unit rate estimating
There are some disadvantages of using the unit-rate
method for estimating major works:
It does not demand the examination of the
program (schedule) or the method statement or
the risks costs in undertaking the work
Also, the precision and level of detail in pricing an
item can give a false sense of confidence in the
resulting estimate
7
Estimating Direct Cost
Operational estimating
It embraces the total anticipated time that the
construction equipment and labor crew are involved in
the operation including all idle time
The operational estimating involves the following:
Prepare the method statement showing the
sequence, resources, timing, etc.
Prepare the work schedule
Smooth or level the resources
8
Estimating Indirect Cost
Site Overheads
Develop comprehensive checklists for general jobsite
requirements, for example:
Cost of temporary site utilities
Jobsite production facilities (concrete batching plants,
quarry, various shops
Jobsite personnel wages
Field buildings, etc.
It is assumed between 5 -15 % of total direct cost
9
Estimating Mark up
Construction contingences
The amount of money added to cover the unforeseen
conditions, difficulties, or estimating accuracy:
Unpredictable price escalation for materials, labor, and
installed equipment for projects
Unforeseen safety and environmental requirements
Weather changes; construction difficulties; economic
and financial problems; etc.
Estimating Mark up
Profit
The contractor should balance between the profit and
the competition, profit is governed by:
The number of competitors
The need for the work
The project size
Project complexity
Working with a certain type of projects or agency
10
Finalizing a Tender Price
Price
Markup Cost
Financial
Risk allowance Profit Indirect cost Direct cost
charge
11
Finalizing a Tender Price
Balanced Bid (straight-forward method)
The share of each item = (direct cost of this item /
total direct cost) x (total indirect cost + mark up)
Example:
Assume that the direct cost for an item (a) is LE
400,000 and that item is included in a contract whose
price is LE 3,500,000 and its total direct cost is LE
2,800,000. Calculate the price for item (a) considering
a balanced bid
12
Finalizing a Tender Price
Un-Balanced Bid (Loading of rates)
The contract price is said to be unbalanced if the
contractor raises the prices on certain bid items
(usually the early items on the bill of quantities) and
decreases the prices on other items so that the tender
price remain the same
This process is also called the loading of rates
Loading of rates may be risky to both the contractor
and the owner
13
Finalizing a Tender Price
Un-Balanced Bid (Loading of rates)
14
Finalizing a Tender Price
Pricing Policy: Method related charge
Fixed Time-related
Activity / Resource Unit Price
charge charge
Establish site Fixed - Sum
Site overheads - Time-related Month
Bulldozers - Time-related Day
Excavators - Time-related Day
General overheads - Time-related Month
----------------- - - -
----------------- - - -
23/04/2016 Emad Elbeltagi 29
UNIT TOTAL
ITEM DESCRIPTION QUANTITY UNIT
PRICE PRICE
Heath Safety
Lump
Equipment and
Sum
Monitoring.
1
Project Site Lump
Mobilization. Sum
Steel Structure
2
Decontamination.
a) Decontaminate steel Square
1100
structure Meters
b) Load and haul debris
5 Ton
to Landfill in Alexandria
Walls Decontamination
3
and Coating.
Square
a) Support walls 1200
Meters
Square
b) Rolling Scaffold 1200
Meters
15