Sei sulla pagina 1di 39

January 21, 2013

January 21, 2013


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TABLE OF CONTENTS

1.0 SCOPE

2.0 DEFINITIONS

3.0 CONFLICTS AND DEVIATIONS

4.0 GENERAL AND SAFETY REQUIREMENTS

4.1 General Requirements


4.2 Safety Requirements

5.0 CODES AND STANDARDS

5.1 Company Standards


5.2 International Standards

6.0 CLEARING SITE AND ROUGH GRADING

6.1 Clearing of Existing Materials and Miscellaneous Fill Materials


6.2 Rough Grading

7.0 EXCAVATION

7.1 General
7.2 Excavation for Buildings and Structures
7.3 Utility Trenching
7.4 Bracing and Shoring

8.0 DEWATERING

8.1 Groundwater
8.2 Surface Runoff

9.0 SELECTION AND TYPES OF CONTROLLED FILL MATERIALS

9.1 Types of Controlled Fill


9.2 Requirements of Controlled Fill Materials
9.3 Acceptance of Controlled Fill Materials

10.0 CONSTRUCTION REQUIREMENTS

10.1 Sub-grade
10.2 Backfill
10.3 Embankments
10.4 Test Section for Embankments

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 2 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

11.0 SLOPE PROTECTION

11.1 Permanent Slopes


11.2 Temporary Slopes

12.0 SABKHAH SOILS

12.1 General
12.2 Improvement of Sabkhah Soils
12.3 Drainage Control

13.0 QUALITY CONTROL, INSPECTION AND REPORTS

13.1 Quality Control and Inspection


13.2 Reports

14.0 FINAL GRADING AND CLEANUP

15.0 BIBLIOGRAPHY

16.0 FIGURES

Figure 1 - Slope Protection for Foundation


Figure 2 - Utility Trench
Figure 3 - Dewatering Scheme
Figure 4 - Gutter Isometric View - Slope Protection
Figure 5 - Gutter Longitudinal Section - Slope Protection
Figure 6 - Gutter Section “A-A” - Slope Protection
Figure 7 - Soil Particles Sizes for Ground Improvement Techniques
Figure 8 - Approximate Correlation Of Soil Ratings Base On CBR Values For
Use In Pavements.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 3 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

1.0 SCOPE

This Transmission Construction Standard covers the mandatory requirements for the
construction of safe and reliable facilities by controlling Earthwork in the system of
National Grid Saudi Arabia. This Standard is applicable for all the works for the
COMPANY including, but not limited to, the following:

a. Clearing site and rough grading

b. Excavation

c. Bracing and shoring

d. Dewatering

e. Selection of fill materials

f. Preparation and compaction of existing sub-grade

g. Backfilling

h. Construction of embankment

i. Slope protection

j. Developing Sabkhah Area

k. Final grading and cleanup

2.0 DEFINITIONS

2.1 Backfill Refers to the construction of earth fill in confined spaces, such as the
refilling operations above concrete structures, or refilling in trenches
around pipes, direct buried cables, etc.

2.2 Base course The layer or layers of specified or selected material of designed
thickness placed on a sub-base or sub-grade to support surface course
such as asphalt concrete, aggregate surfacing or concrete pavement.

2.3 Borrow Pit A site where earth material is removed by mechanical equipment and
transported to an off-site location for use in grading.

2.4 Borrow Pit Boundary:

The boundary for a Borrow Pit is defined in the Borrow Pit permit.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 4 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

2.5 Controlled Fill


This is defined as the placement of earthfill of specified engineering
properties (gradation, plasticity index, California Bearing Ratio
(CBR) thermal conductivity, etc.) and compacted to a required
density.

2.6 Existing grade Existing grade is the grade prior to grading

2.7 Fill Fill is a deposit of earth material placed by artificial means

2.8 Finished grade Finished grade is the final grade of the site, which conforms to the
approved plan by the COMPANY.

2.9 Grade Grade shall mean the vertical location of the ground surface

2.10 Grade Slope Refers to cut and fill side slope as per site requirements or as
indicated in the approved drawings. Standard for Cut = 1:2 (vertical:
horizontal) and for Fill = 1:4. Berming system is also applicable for
cut slope.

2.11 Grading Leveling at site any excavation, filling or a combination thereof

2.12 Rough Grade Refers to grading the construction site to approximate design contours

2.13 Select Fill Materials, obtained from a specified source such as a borrow area, of
acceptable quality having a specified characteristic to be used for a
specific purpose. The material, if not of acceptable quality, shall be
improved by mixing at site with suitable material to meet the
specified characteristics such as gradation, CBR, plasticity index, etc.

2.14 Sub-base The layer or layers of specified or selected material of designed


thickness placed on a sub-grade to support a base course

2.15 Sub-grade The existing underlying ground prepared and compacted for
supporting foundations of structures, embankments, pavements, etc.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 5 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

3.0 CONFLICTS AND DEVIATIONS

3.1 Any conflicts between this Standard and other applicable National Grid Saudi Arabia
Standards, Industry Standards, Codes, and forms shall be resolved in writing by the
COMPANY Representative.

3.2 Any request to deviate from this Standard shall be directed to the Manager,
Standards and Specifications Department

4.0 GENERAL AND SAFETY REQUIREMENTS

4.1 General Requirements

4.1.1 All works performed and all materials furnished shall be in conformity with
the lines, grades, cross-sections, dimensions, and material requirements,
including tolerances, shown on the plans/drawings or indicated in the
specifications.

4.1.2 All materials to be incorporated into the work shall meet or exceed the
appropriate AASHTO, ASTM, or other International Standard and
specifications as required by the plans/drawings and specifications but in no
case shall be less than the requirements of this Standard.

4.1.3 All materials shall be inspected, sampled, tested and accepted by the
COMPANY Representative before incorporation into the work.

4.1.4 Field and laboratory tests required to determine compliance with the
compaction requirements of this Standard shall be done by an Independent
Agency approved by the COMPANY.

4.1.5 No material, regardless of its source, shall be incorporated in the Work until
representative samples taken and tested by the COMPANY approved
Independent Laboratory have been reviewed and approved by the
COMPANY Representative.

4.1.6 Sub-grades or bottom of excavation for structures shall be firm, dense and
thoroughly compacted as specified under Construction Requirements. It shall
be free from mud and muck, and sufficiently stable to remain firm and intact
under the feet of the workmen.

4.1.7 Adequate dewatering equipment to remove and dispose all surface and
groundwater entering the excavations and other parts of the work, shall be
provided at site and maintained properly.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 6 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

4.2 Safety Requirements

4.2.1 The safety provisions of Construction Safety Manual shall be strictly


followed.

4.2.2 Excavation by the use of explosives shall be with prior written approval from
the COMPANY.

4.2.3 The stability of adjacent structures or facilities including public safety shall
not be impaired or endangered by excavation works.

4.2.4 All existing underground utilities, which may be uncovered or otherwise be


affected by the excavation work shall be properly protected, by shoring,
bracing, and supporting, etc., as needed.

5.0 CODES AND STANDARDS

The latest revisions/amendments of the following Standard and specifications are intended
as guidance in providing an acceptable level of quality and practice. In case of conflict
between these Standards and the text of this Standard, the latter shall govern:

5.1 COMPANY Standards

5.1.1 TCS-P-104 Underground Cable Construction Standards

5.1.2 TCS-Q-113.01 Asphalt Concrete Paving

5.1.3 TCS-Q-113.03 Cast-In-Place Concrete

5.1.4 TCS-T-111.12 Mini Trenching

5.1.5 TES-P-122.11 Access Roads and Structure Pads

5.1.6 TES-P-119.21 Fire & Loss Prevention and Security Requirements

5.1.7 Construction Safety: Special Manual Chapter No. 6: Excavation.

5.1.8 Construction Safety: Special Manual Chapter No. 14: Electrical Hazards.

5.2 International Standards

5.2.1 ASTM C 127 Test Method for Density, Relative Density (Specific
Gravity) and Absorption of Coarse Aggregates

5.2.2 ASTM D 421 Practice for Dry Preparation of Soil Samples for
Particle-Size Analysis and Determination of Soil
Constants

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 7 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

5.2.3 ASTM D 422 Test Method for Particle-Size Analysis of Soils

5.2.4 ASTM D 698 Test Methods for Laboratory Compaction


Characteristics of Soil Using Standard Effort (12,400
ft-lbf/ft3 (600 kN-m/m3))

5.2.5 ASTM D 854 Test Methods for Specific Gravity of Soil Solids by
Water Pycnometer

5.2.6 ASTM D 1194 Test Method for Bearing Capacity of Soil for Static
Load and Spread Footings

5.2.7 ASTM D 1556 Test Method for Density and Unit Weight of Soil in
place by the Sand-Cone Method

5.2.8 ASTM D 1557 Test Method for Laboratory Compaction


Characteristics of Soil Using Modified Effort (56,000
ft-lbf/ft3 (2,700 kN-m/m3))

5.2.9 ASTM D 1558 Test Method for Moisture Content Penetration


Resistance Relationships of Fine-Grained Soils

5.2.10 ASTM D 1586 Test Method for Standard Penetration Test (SPT) and
Split-Barrel Sampling of Soils

5.2.11 ASTM D 1632 Practice for Making and Curing Soil-Cement


Compression and Flexure Test Specimens in the
Laboratory

5.2.12 ASTM D 1633 Test Method for Compressive Strength of Moulded


Soil-Cement Cylinders

5.2.13 ASTM D 1739 Test Method for Collection and Measurement of


Dustfall (Settleable Particulate Matter)

5.2.14 ASTM D 1883 Test Method for CBR (California Bearing Ratio) of
Laboratory-Compacted Soils

5.2.15 ASTM D 2216 Test Method for Laboratory Determination of Water


(Moisture) Content of Soil and Rock by Mass

5.2.16 ASTM D 2922 Test Methods for Density of Soil and Soil-Aggregate
in Place by Nuclear Methods (Shallow Depth)

5.2.17 ASTM D 4253 Test Methods for Maximum Index Density and Unit
Weight of Soils Using a Vibratory Table

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 8 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

5.2.18 ASTM D 4254 Test Methods for Minimum Index Density and Unit
Weight of Soils and Calculation of Relative Density

5.2.19 ASTM D 4318 Test Methods for Liquid Limit, Plastic Limit, and
Plasticity Index of Soils

5.2.20 ASTM D 4791 Test Method for Flat Particles, Elongated Particles, or
Flat Particles and Elongated Particles in Coarse
Aggregate

5.2.21 AASHTO T-180 Test Method for Moisture-Density Relations of Soils


Using a 4.54 kg (10-lb) Rammer and 457 mm (18-in.)
Drop

6.0 CLEARING SITE AND ROUGH GRADING

6.1 Clearing of Existing Materials and Miscellaneous Fill Materials

6.1.1 The site shall be cleared of all boulders, debris, decomposable materials such
as wood, grass, plants, tree stumps, etc., to the satisfaction of COMPANY
Representative.

6.1.2 All existing miscellaneous fill, broken building materials, or damaged


concrete shall be removed from the area.

6.1.3 Where structural support is required, the soil that softens due to rainfall,
groundwater, disturbance, exposure or any other cause shall be excavated and
replaced with controlled fill.

6.1.4 Burning of rubbish and organic materials, resulting from the site clearing
operations, shall not be permitted on the site or adjacent property.

6.1.5 All surplus materials, resulting from the site clearing operations, shall be
transported to and dumped in municipal approved dump areas, with prior
approval from the COMPANY Representative

6.1.6 Care shall be taken to protect existing utilities, site improvement works and
existing structures.

6.2 Rough Grading

Rough grading shall be done to the approximate finished lines and grades shown on
approved drawings. This area shall then be inspected and approved by the
COMPANY Representative before commencing any work.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 9 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

7.0 EXCAVATION

7.1 General

7.1.1 Prior to excavation, information about all existing underground services such
as gas, water, telephone lines, sewage lines, electric cables, etc., shall be
obtained from ministries, municipalities, utility companies and other affected
agencies. Excavation shall be carried out with special care and with proper
permissions to avoid any interference with these systems. Only manual
excavation shall be employed in locations where underground utilities are
present. Any damage caused shall be repaired expeditiously and restoration
of services shall be made without delay.

7.1.2 Safe working distances and overhead clearances shall be maintained at all
times when working near or under energized overhead lines or substation
structures to ensure safety of personnel and avoid accidental disruption of
power. Safe working distance shall be in accordance with Chapter 14 of
Construction Safety Manual.

Work permits shall be secured prior to excavation in locations classified as


restricted areas such as inside substations, power plants, and near or under
overhead power lines.

7.1.3 Subject to permission from concerned agency of Saudi Arabian Government,


any blasting in the proximity of facilities shall be approved by the
COMPANY as per TES-P-119.21, Fire & Loss Prevention and Security
Requirements. The danger of damage to existing structures shall be
minimized by limiting velocity, induced in any structure due to ground
motions created by blasting to a maximum of 50 mm/sec. No blasting shall
be permitted in the vicinity of concrete within 7 days of its placement.

Blasting shall be controlled to avoid injury to human beings, damage to


adjacent structures and shattering or weakening of the rock below foundation
level. All blasting shall conform to the local and government regulations.

7.1.4 Excavation in all types of soil and rock shall be treated as unclassified
excavation.

7.2 Excavation for Buildings and Structures

7.2.1 Excavation Limits for Structures

Pits and trenches shall be excavated to grades and depths shown on the
approved drawings. Trenches and pits in loose earth shall be at least 300 mm
bigger in both plan dimensions than the size of foundations. Trenches and
pits for footings in stiff cohesive material or rock shall not be wider than
necessary for formwork and bracing.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 10 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

Machine excavation shall be controlled to prevent undercutting the proper


sub-grade elevations and shall not be used within 1.50 m of permanent
structures and facilities. In an existing COMPANY facility, top 1.50 m
excavation shall be done manually. Only hand tools shall be used for
excavation around permanent structures and facilities.

7.2.2 Excavation below Elevations Shown on the Drawings

If foundation is designed for being supported on rock, excess excavation


below foundation level shall be filled with concrete having a minimum
compressive strength of the excavated rock. If there is no data about the
compressive strength of the underlying rock, or, if the rock strength is greater
than 5500 psi (38 MPa), then, use concrete specified for severe exposure
condition.

Excess excavation below foundation level, when foundation is supported on


soil, shall be filled with selected fill materials (as specified in this Standard)
compacted to 85% relative density (ASTM D 4253 and D 4254) for
cohesionless, free draining soils containing less than 15% non-plastic
material passing 75 micron sieve, or 95% of the maximum density as
determined by ASTM D 1557 for soils containing more than 15% material
passing the 75 micron sieve.

7.2.3 Bottoms of Foundation Excavations

Bottoms of excavations shall be smooth and free of loose earth or sand. Any
soft or loose spots of insufficient bearing shall be compacted to the density as
stipulated in Section 7.2.2 or they may be removed and replaced with
concrete or with compacted Select Fill materials (as specified). Excavation
bottoms for support of foundations shall be level or stepped and shall not be
sloped.

7.2.4 Protection of Adjacent Buildings and Existing Structures

Excavation shall not be extended below the elevation of adjacent existing


foundations unless underpinning and shoring requirements have been fully
established and complied with or the slope of the excavation in soil is such
that the closest edge of the existing footing to the excavation is at least 1.0 m
away from the line that leads up at an angle of 30° to the horizontal from the
bottom of excavation (See Figure 1).

Excavation slope (as shown in Figure 1) must be checked for stability. This is
applicable to all types of foundations.

7.3 Utility Trenching

7.3.1 Applicable provisions of COMPANY Underground High Voltage Cable


Construction Standard TCS-P-104 “Trenches” shall be followed.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 11 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

Also, special trenching and backfilling requirements of the Government


agencies (Ministries, Municipalities), having jurisdiction, shall apply.

7.3.2 Utility trenching shall follow strictly the approved alignment requirements.
Care shall be taken such that pipes, cables, and duct runs shall be made as
straight as possible, both horizontally and vertically, and if a deflection must
be made, it shall be along a smooth and gradual curve to avoid stressing the
ducts, cables or pipes.

7.3.3 All excavations shall be extended at least 150 mm below the bottom of pipe
or power cable to provide an all around 150 mm minimum clean sand
bedding (See Figure 2). The gradation of clean sand shall conform to Section
9.1.3. The thermal conductivity of sand around power cables shall comply
with design requirements.

7.3.4 Trenches shall be excavated to the grade shown on the profile with a
minimum of 1000 mm and 500 mm earth cover over the top of the service
line in traffic areas and non-traffic areas, respectively (See Figure 2). Excess
excavation below required level shall be backfilled with selected fill
materials compacted to 95% of the maximum density as determined by
ASTM D 1557 for soils containing more than 15% material passing the 75-
micron sieve or 85% relative density (ASTM D 4253 and ASTM D 4254) for
free draining cohesionless soils containing less than 15% non-plastic material
passing 75-micron sieve.

7.3.5 Soft or loose spots in the trench shall be compacted to the density as per
Section 7.3.4 or the soft materials shall be removed and replaced with
selected fill materials that is compacted to the density per Section 7.3.4.

7.3.6 The trench bottom shall be continuous, smooth and free of loose debris
and/or sharp rocks which could damage the service line/power cable.

7.4 Bracing and Shoring

7.4.1 The sides of pits and trenches shall be sloped back to the natural angle of
repose of the soil to avoid caving. Sides which cannot be sloped, because of
space limitation due to adjacent structures, or unrestrained sand masses
(loose sand) shall be shored adequately to resist earth movement, protect
workers, and protect on-going work and existing property.

7.4.2 Shoring shall not be braced against forms. Forms shall be properly braced
and tied together, independent of shoring.

7.4.3 Excavated soils, construction materials, or heavy machineries shall not be


placed at the top of excavations or embankments unless they are set back at a
previously established safe distance from the top of excavation.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 12 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

8.0 DEWATERING

8.1 Groundwater

When it is required to excavate below Ground Water Table (GWT), a suitable


dewatering system shall be provided to keep the excavated area dry. Sheet piling
may be required for deep excavations. It will be important to maintain the bottom
stability of excavations by sheeting and dewatering. Appropriate shoring shall be
installed and dewatering done to lower the GWT to a depth of approximately 1.0 m
below the maximum depth of excavation (See Figure 3).

In order to obtain a stable bottom of the excavation, dewatering should be carried out
in advance of excavation. Dewatering shall be performed by carefully installed well
point system which should be properly designed, having sufficient knowledge of
local condition. The problem of bottom “heave” can be anticipated by adopting a
designed dewatering system. A typical dewatering procedure could be as follows:

Excavate to near the anticipated ground level. The sides may be supported by sheet
piles.

Install well points around the perimeter of the area to be excavated.

The well points could be jetted or drilled into position. The well points should extend
below the excavation to a depth of at least about 1.5 times the excavation depth
below the ground water level. The well points should be spaced about two meters
center to center (other depth-spacing criteria may be adopted to suit the field
conditions).

Dewatering should be accomplished by pumping from the well points. After


dewatering, excavate the remaining soils to the final grade. Supplemental well points
may be necessary to lower ground water levels below the bottom of the interior of
the excavation.

Typical grain size distribution range of the soils encountered at the study area or
from the gradation charts shall be obtained. This should assist in the design of a well
point system, the size of the screening, the sand filter and the size of the vacuum
pump, if necessary.

8.2 Surface Runoff

Grading in the vicinity of excavations shall be controlled to prevent surface water


running into excavated areas. Any water accumulated in the excavations shall be
removed by pumping or by other means as approved by the COMPANY
Representative.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 13 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

9.0 SELECTION AND TYPES OF CONTROLLED FILL MATERIALS

Controlled fill shall be free of organic matters, rubbles, cobbles and boulders, and other
deleterious substances.

9.1 Types of Controlled Fill

The following four (4) types of controlled fills are classified for earthworks.

9.1.1 General Fill (Class D) shall meet the following gradation requirements:

a. Maximum particle size = 100 mm

b. Between 80% and 40% by weight passing the 2.0 mm mesh sieve

c. Not more than 15% by weight passing the 75 micron mesh sieve; less
than 4 plasticity index. Where binding effect is required between soil
particles as in uncontained embankments, a maximum of 20% by
weight material passing the 75 micron mesh sieve shall be provided.

9.1.2 Select Fill shall be a well graded granular material as shown in Table-I.

Table-I

USA Standard Percent Passing


Sieve Size (mm)

50 100

19.0 95 to 80

2.0 80 to 50

0.250 50 to 25

0.075 20 to 5

Where free draining properties of the controlled fill are essential, such as
groundwater table being within 1.5 m depth below the bottom of foundations
or pavements, the material passing the 75 micron mesh sieve shall be
between 5% and 10% by weight. Where groundwater is not a problem and
binding effect is required between soil particles, as in uncontained
embankments and surfaces exposed to erosion, near maximum limit of 20%
by weight material passing the 75 micron mesh sieve shall be provided.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 14 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

9.1.3 Clean sand satisfying the following USA Standard sieve size gradation shall
be used for bedding around utilities as shown in Table II.

Table II

USA Standard Sieve Size (mm) Percent Passing


4.75 100

2.00 95 to 80

0.425 80 to 40

0.250 60 to 20

0.075 Less than 10

9.1.4 Aggregate sub-base and base course materials shall meet the following
gradation as shown on Table III and physical properties as shown on Table
IV.

Table III GRADATION

Sub-base Material Classes Base Course Material Classes


CLASS A CLASS B CLASS C CLASS A CLASS B
Sieve Well graded Uniform mixture of Well Mixture of all Uniform
Size gravel with gravel and/ or stone graded aggregate mixture of
(mm) sand & silt fragments with sand gravel uniformly graded crushed rock or
sand, silt and clay from coarse to fine crushed gravel
101.6 - - - - -
63.5 100 - - 100 -
50.8 90 - 100 100 - 90 - 100 -
38.1 - 70 - 100 100 60 - 90 100
25.4 - 55 - 85 - 42 - 77 60 - 100
19.0 * - 50 - 80 - 35 - 70 55 - 85
12.7 - - - 25 - 60 -
9.51 - 40 - 70 - - -
4.76 35 - 70 30 - 60 - 15 - 40 35 - 60
2.00 - 20 - 50 80 max. 10 - 26 25 - 50
0.425 - 10 - 30 - 5 - 15 15 - 30
0.250 - - - - -
0.075 0 - 15 5 - 15 15 max. 2-9 8 - 15

* If less than 30% of the sample is retained on a 19 mm sieve, Moisture-Density Relations of


soils shall be tested in accordance with ASTM D1557, Method C. If the retained sample on a
19 mm sieve is 30% or more, tests shall be as per AASHTO T-180, Method D

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 15 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TABLE IV PHYSICAL PROPERTIES

Sub-base Material Base Course Material


PHYSICAL CLASS CLASS CLASS CLASS CLASS
REQUIREMENTS A B C A B

Liquid Limit (Max %) - 25 25 - 25

Plasticity Index (Max %) - 6 6 6 4-8

Sand Equivalent (Min %) 25 25 25 30 50

Loss by abrasion (Max %) 50 50 50 40 40


Thin and elongated pieces, by
weight (larger than 25 mm,
thickness less than 1/5 length) - - - 5 5
as per ASTM D 4791
(Max %)

Friable Particles (Max %) - - - 0.25 0.25


Soundness Test using MgSO4
(Max. %)
Coarse Aggregate 18 18 18 18 18

Fine Aggregate 20 20 20 20 20

9.2 Requirements of Controlled Fill Materials

The COMPANY Representative shall approve the depth of the fill after the
availability of soil reports. Aggregate sub-base and base courses, if specified, shall
be used as fill material for access roads, substation yards, designated roadways,
parking lots, and material yards where heavy traffic load is expected.

Controlled Fill materials shall be required up to 1.0 m of the bottom elevation of


foundations, concrete sidewalks/pavements, slabs on grade, and asphalt concrete
surface/binder courses depending on the existing sub-grade soil condition.

Minimum depth of filling shall be 600 mm if the bottom of excavation reveals good
soil/ hard surface.

Sand shall be used for bedding around service lines such as pipes, conduits, and
cables. In all other instances, “General Fill” shall be used as sub-base unless
otherwise specified.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 16 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

9.3 Acceptance of Controlled Fill Materials

Fifty kilogram bag samples of each material to be used as controlled fill shall be
collected in the presence of COMPANY Representative and submitted for testing to
an independent soil testing laboratory, approved by the COMPANY, at least ten
(10) days prior to commencing controlled fill operations. The testing laboratory shall
perform at least one of each of the following tests on fill samples and submit the test
results to the COMPANY.

i. Mechanical analysis (Gradation), ASTM D 422

ii. Plasticity Index, ASTM D 4318

If the results from the above tests meet the specification requirements, the testing
laboratory shall determine the CBR, Sulfate and Chloride content including the
compaction characteristic of the fill material by conducting one of the following tests
(item a or b below) that is applicable to the gradation, plasticity and drainage
characteristics of the fill material:

a. Modified Compaction, ASTM D 1557, Method D, Minimum of Five


Moisture Density Determinations per Test for soils containing more than
15% materials passing the 75 micron sieve; or

b. Maximum and Minimum Index Density of Soils and Calculation of Relative


Density, ASTM D 4253 and D 4254 for free draining soil containing less
than 15% non-plastic materials passing the 75 micron sieve.

c. The California Bearing Ratio (CBR) for each class of fill materials
compacted in the laboratory after four (4) days soaking as determined by
ASTM D 1883 shall be as follows:
Table V

Material Class CBR Values

Class A, B, C Not less than 50


Sub-base
Class D (General Fill) Not less than 15

Base Course Class A & B Not less than 100

Note 1: In Transmission Access Roads and Structure Pads, CBR Value for
Base course (which is used as Surface Course) shall be not less than
75.

Note 2: The correlation of the soil ratings based on CBR values is given in
Figure 8.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 17 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

d. The Sulfate and chloride contents of controlled fill for each class of fill
materials shall also be determined. Borrowed fill with greater Sulfate or
chloride content than the existing soil in the site shall not be used as
controlled fill for improvement of existing facility.

No material shall be used as a controlled fill until it is tested, as above, by the


soil testing laboratory, and approved by the COMPANY Representative.

Changes in the controlled fill material may be made when characteristics of


materials, job conditions, weather, test results or other circumstances warrant.
Each time, a change in fill material has to take place, the new material shall
be tested as above and test results submitted to COMPANY Representative
for approval and acceptance before using in the work. A change in controlled
fill material and related tests shall be planned so as to avoid construction
delays.

Final acceptance of controlled fill material rests with the COMPANY


Representative, whose decision shall be final and binding.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 18 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

10.0 CONSTRUCTION REQUIREMENTS

10.1 Sub-grade

10.1.1 The existing ground surface shall be proof-rolled by the same equipment that
will be used to compact the controlled fill materials prior to the placement of
first lift of controlled fill (sub-base). Compaction of the sub-grade may be
facilitated by maintaining its moisture content at or slightly wet or dry (±2 %)
of the optimum moisture content determined from laboratory tests.
Depending on the type of structure supported, sub-grade shall be compacted
to develop the following degrees of compaction to about 300 mm below the
ground surface:

Table-VI Compacted Density Requirements of Soils for Different Works

Type of Supported Structure Degree of Compaction Required


Service Lines, Concrete Slabs, Minimum of 75% Relative density (ASTM D 4253 and
and parking areas ASTM D 4254) for free draining soils containing less
than 15% by weight finer than 75 micron sieve non
plastic material or 90% of the maximum density as
determined by ASTM D 1557 for soils containing more
than 15% material passing the 75 micron sieve.

Light Traffic Road, e.g., Plant Minimum of 80% relative density (ASTM D 4253 and
roads for operations and ASTM D 4254) for free draining soils containing less
maintenance only and not than 15% by weight finer than 75 micron sieve non
frequently subjected to traffic. plastic material or 92% of the maximum density as
service lines/ power cables determined by ASTM D 1557 for soils containing more
below these roads than 15% materials passing the 75 micron sieve.

Foundations of all facilities Minimum of 85% relative density (ASTM D 4253 and
including buildings, ASTM D 4254) for free draining soils containing less
transformers, circuit breakers, than 15% by weight finer than 75 micron sieve non
etc, heavy traffic roads carrying plastic material or 95% of the maximum density as
high density of heavy trucks determined by ASTM D 1557 for soils containing more
and equipment. than 15% material passing the 75 micron sieve

Service lines or power cables In addition to above, technical requirements of the


below ministry and concerned Ministry or Municipality shall govern.
municipality roads

Note: ASTM D 2922 can be used for testing the compaction of the soil at site if permitted
by the COMPANY Representative, provided the soil is uniform.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 19 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

The compaction of the sub-grade or excavation shall be checked and


approved by the COMPANY Representative before the sub-grade is covered
up with further construction such as sub-base/base course or concrete
foundation.

Where soft or otherwise unacceptable zones are disclosed, they shall be


removed and replaced with approved controlled fill materials compacted as
discussed above.

10.1.2 In case of filling Sabkhah or areas of high water table, the requirements for
proof-rolling the ground surface may be waived by the COMPANY
Representative if proof-rolling is not feasible. For modification to Sabkhahs,
refer Section 12.0. Dewatering shall be done for areas of high water table.

10.1.3 Hand or mechanical tampers shall be used in places inaccessible to rollers.

10.2 Backfill

10.2.1 All formworks shall be completely removed but in no case less than 24 hours
after placing concrete. All debris shall be cleaned out and permission to
backfill shall be secured from the COMPANY Representative.

10.2.2 Trenches, pits and other excavations shall be backfilled with materials
described in Section 9.1. The location of each type of fill shall be governed
by Section 9.2. As far as possible, excavated materials shall be used as
backfill provided they meet the requirements of controlled fill specified in
this Standard.

10.2.3 Unless directed otherwise by COMPANY Representative, backfill adjacent


to or against any structural concrete shall not be placed until the concrete in
the adjacent structure has attained a minimum of 75% of its design strength
and is coated with coal tar epoxy.

10.2.4 Backfill materials shall be placed in uniform layers not exceeding 300 mm of
uncompacted thickness. Increased thickness may be permitted for non-
cohesive materials by the COMPANY representative if the specified
compacted density can be obtained.

10.2.5 Unless specified otherwise, backfill shall be compacted to densities indicated


in Table VI at or slightly wet or dry (± 2 %) of optimum moisture content.

10.2.6 Where controlled fill is placed adjacent to walls, which are not designed as
retaining walls, either the difference in elevation of the top of the controlled
fill on both sides of the wall shall not be more than 300 mm, or the wall is to
be adequately braced.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 20 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

10.2.7 All utility lines shall be laid on a clean sand bed compacted to the density
criteria of Table VI. Sand shall conform to Section 9.1.3 and thermal
resistivity of sand around power cables shall comply with design
requirements. After utility lines have been laid, clean sand shall be carefully
placed and compacted beneath the bottom half of the service lines to assure
firm support. Careful backfilling and compaction by tamping or inundation
with water shall continue above the service lines.

10.2.8 Finished grades adjacent to structures shall slope away from the structures to
minimize ingress of precipitation and quickly drain away the surface runoff.

10.3 Embankments

10.3.1 Prior to placing the first layer of controlled fill, sub-grade shall be leveled, if
necessary moistened, compacted, tested and then scarified so that the surface
material of the sub-grade is as compact and well bonded with the first layer
of controlled fill as is specified for succeeding layers of controlled fill. Test
criteria for the sub-grade shall be as per Section 9.3. Bond between a sloping
sub-grade and controlled fill shall be improved by benching the sub-grade.

10.3.2 Unless otherwise specified, all controlled fill shall conform to soil gradation
specified in Section 9.1. The location of use of each type of controlled fill
shall be determined by provisions of Section 9.2.

10.3.3 Unless specified otherwise, all controlled fill shall be compacted to densities
indicated in Table VI.

10.3.4 Moisture content shall be uniform throughout the layer to be compacted and
it shall be as close as practicable to the optimum moisture content from
laboratory compaction tests, which will result in the maximum densification
of the material to be compacted.

10.3.5 Compaction of cohesionless soils by saturation and vibration shall be


acceptable, provided, it can be demonstrated to the satisfaction of the
COMPANY Representative that required densities can be achieved by this
method.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 21 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

10.4 Test Section for Embankments

10.4.1 On large earthwork projects, the COMPANY Representative shall direct for
the construction of a test section using the material and equipment to be used
on the project. This shall provide the basis for the most practicable
processing and placing procedures for representative soils under job
conditions. By varying the placement procedure within certain limits, by
exercising rigid control over the relatively small volume of the section, and
by keeping complete records of the tests, the most applicable procedures shall
be determined during the initial stages of construction. Results of field
density tests made on the test section shall provide the necessary information
for establishing construction control procedures consistent with design
requirements. This is to establish the moisture content of the borrow material;
methods for correcting borrow material’s moisture content if too wet or too
dry; roller characteristics; number of roller passes; thickness of layers; and
effectiveness of power tamping in places inaccessible or undesirable for
roller operation.

If the size of the project does not warrant a test section, then experience from
the initial placing operations shall be used to determine the above
characteristics.

10.4.2 Characteristics determined above shall be used to facilitate construction


control. Compliance with estimated number of passes of a particular roller
over a predetermined layer thickness shall not, however, be considered as
meeting the density requirements. Acceptance or rejection of earthwork shall
depend on field density test results.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 22 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

11.0 SLOPE PROTECTION

11.1 Permanent Slopes

All permanent slopes shall be designed based on the stability considerations of the
embankment and foundation materials.

Based on feasibility and economic considerations, permanent slopes shall be


protected against erosion by one of the following measures:

a. Provide a minimum of 200 mm thick rip-rap of 150-200 mm size stones over


a 100 mm thick layer of 40 mm size crushed stone on compacted slope. Rip-
rap and crushed stones shall be continued over the level ground beyond the
toe, and over the top embankment beyond the top edge, for a minimum
distance of 1.0 meter or to the edge of pavement, if any, whichever is less.
Riprap shall be tightly hand packed with least possible void space. Riprap
and crushed stone materials shall be hard and durable.

b. A layer of hot asphalt concrete mix, conforming to surface course per


Asphalt Concrete Paving Standard, TCS-Q-113.01, shall be placed on clean,
compacted and primed embankment slope to provide a 50 mm minimum
compacted asphalt pavement thickness.

If the top surface of the embankment is paved, the increased runoff from
precipitation shall be collected by provision of curbing around edges of the
pavement and directing the flow of water down the slope through cement
grouted rip-rap gutters. Typical sections of curbs and gutters arrangement are
shown in the attached drawings (Figures 4, 5 and 6). Precast concrete gutter
units may be used if approved by COMPANY Representative.

c. Protection wire-mesh designed as slope protection blanket to intercept rock-


fall shall be provided around the structure pads. The mesh shall be flexible
hot-dip galvanized wire mesh.

d. Rock-fall protection netting

e. High resistance rock-fall netting

f. Galvanized box gabions

g. Lined Concrete of minimum 150 mm thick with reinforcing wire mesh.


Compressive strength f’c of concrete shall be minimum of 21 MPa.

11.2 Temporary Slopes

The temporary slopes, when constructed, shall be maintained in a stable and firm
condition including proper surface drainage and control of erosion.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 23 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

12.0 SABKHAH SOILS

12.1 General

Sabkhah is an expression used to describe salt-encrusted, evaporative flats that are


underlain by sand, silt or clay. These are usually formed under hot, arid climates, and
are associated with a shallow, saline groundwater.

These soils are either situated along the coasts (Coastal Sabkhahs) or farther inland
(Continental Sabkhahs).

The bearing capacity and compressibility characteristics of these soils in the virgin
state rarely meet routine design requirements. Therefore, before any construction
activity, the soil has to be either treated, or replaced, or the foundation loads must be
transferred through end bearing piles to the underlying dense soil or rock.

12.2 Improvement of Sabkhah Soils

Measures to enhance the properties of Sabkhah must be taken before any


construction takes place on the soil. Control of groundwater rise is a vital corrective
measure, in conjunction with soil densification. If various densification and drainage
control techniques fail to improve the soil properties, i.e., the required bearing
capacity and warranted settlement, pile foundations shall be used, if Sabkhah site
cannot be abandoned altogether.

Selection of an improvement method, as appropriate to the structure type; its loading


and settlement sensitivity; thickness of Sabkhah; its location with respect to other
strata; its type (clayey or sandy), etc., is largely case dependent. This shall be based
on the soil investigation report for the proposed site. One of the techniques of
determination of type of improvement is shown as a function of Particle size (Fig. 7).

The detailed report about the Sabkhah soil and the recommended methods of
improvement shall be submitted to The COMPANY. The selection of the type of
improvement shall be done by the COMPANY Representative.

Steel casing shall be used in the following cases:

1. Piling in Sabkhah areas


2. Piling in valleys (Wadi) subjected to flooding
3. Chimney in case of Pad and Chimney type of foundations

12.2.1 Shallow Soil Densification

On small scale construction projects, such as small equipment foundations,


service roads, single storied buildings or equivalent, shallow soil
modification techniques, such as those mentioned below, are adequate to
improve the soil properties in sustaining the required design loads for the
application in question.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 24 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

a. Excavation and Replacement:

This scheme is suited to modification of shallow Sabkhah soils, i.e., if


the Sabkhah layer is of shallow depth. The fill of appropriated soil to
replace the Sabkhah layer shall be as classified in Sec. 9.1, and
compacted to the required density as suggested in Table VI.

b. Displacement, Excavation and Replacement:

This procedure is used for access roads and pavements, and when
subsurface conditions favor displacement. Filling proceeds from one
end of the area to be developed, by building a rolling surcharge fill,
which penetrates and displaces the Sabkhah soil to a certain depth.
The Sabkhah in front of the surcharge fill is excavated to a firm base
and the rolling surcharge is pushed forward to displace any Sabkhah
material that may have squeezed in after excavation. This is
continued until the entire filling procedure is completed.

c. Surficial Chemical Stabilization:

Sabkhah soils stabilized with cement, lime, etc., have numerous


applications such as in backfilling, paving slopes, embankment
protection, lining ditches, access roads, etc. Properly chemically-
stabilized soils gain higher strength, more erosion resistance,
markedly high volume change stability against swelling and
shrinkage. It is essential to assess the performance of chemically-
stabilized Sabkhahs upon wetting, as related to the type of
construction.

12.2.2 Deep Soil Densification

Deep soil modification techniques have to be adopted, as suited to the case in


question, on large scale construction projects.

The suitability of these improvement techniques is dependent on the required


depth and degree of compaction, type of Sabkhah soil (clayey or sandy), its
clay and organic contents, gradation, contents of fines, degree of saturation,
location of groundwater table, risks involved, available equipment and time,
local experience and economic feasibility of the structure.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 25 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

a. Vibration Methods

i. Vibroflotation:

This is a traditional deep compaction method, employed for


granular soils. In this method, 0.3 m to 0.45 m diameter poker
vibrators (vibroflots) are used to transmit vibrations to the soil
along the whole length of the vibrator or at the tip. The
vibrators are provided with water jets/ compressed air at top
and bottom to improve the penetration rate and to stabilize the
borehole. The vibrators are also provided with fins to increase
the efficiency and to reduce the twisting during compaction. A
cutting ring is used to widen the hole when there are cemented
layers or seams in the soil.

While employing this method, care shall be taken to ensure


that the flush water does not cause leaching of salt in the
Sabkhah soil, and that the fines (smaller than 75 micron sieve)
in the Sabkhah soil are not excessive. Vibroflotation is
preferred for Sabkhahs containing mainly gravel and coarse
sand because of the lateral displacement of the vibrator during
compaction as they are more difficult to compact.

ii. Vibro-compaction:

This method is used for deep compaction of saturated granular


soils. A vibratory hammer, which is attached to a pipe or a
probe, is used and vibrated down into the soil. In contrast to
vibroflotation, the vibrations are in the vertical direction only.
The shaft is pulled out slowly as the soil is vibrated. The
required spacing of the compaction points depends on the
depth, permeability, gradation and fines’ content of the soil.
Sabkhahs containing medium to fine sand are generally
compacted by this method.

iii. Vibro-replacement:

This method is employed in Sabkhahs containing mainly soft,


relatively impervious and cohesive soils. These soils are
penetrated with low pressure, large volume bottom jets with
the displaced material brought to surface through the water
flow. Resistant layers are overcome by direct impact of the
machine. On reaching the desired depth, gravel backfill is
tipped around the machine to fall down the annulus against
continuing upward flow of water from the bottom jet. Gravel
accumulates at the base of the column building upwards, with
diameters at each level depending upon the soil resistance and
the shearing and flushing action.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 26 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

iv. Blasting:

This method is used for granular soils to reduce liquefaction


potential and settlements. Explosive charges are placed in
suitably spaced, jetted or drilled boreholes at elevations
corresponding to 50% to 75% of the required depth of the
compaction. The efficiency of the method depends mainly on
the pore water pressures generated by blasting and the time to
dissipation, and the size of the liquefied zone around the
detonation point.

Test blasting is recommended for large jobs in order to


determine the optimum spacing of the boreholes, the size of
the charges, and the intervals and sequence of blasting.

b. Displacement Methods

i. Stone, Gravel and Sand Columns:

This method involves the formation of compacted “columns,”


or pillars, within fine grained or stable, insensitive, cohesive
soils and cohesionless soils using poker vibrators. The
machine penetrates a thick-walled, steel casing initially closed
at the bottom by a gravel plug, both by vibratory impact (drop
hammer) and by its own weight. There is no removal of soil,
which is displaced laterally involving local shearing as in
driven piling. Compressed air is used through the bottom jet
during penetration.

On reaching the requisite depth, the gravel plug is extruded


and new material is added as the casing is withdrawn. The
machine is lowered on top acting to displace the backfill
laterally and downwards like a vibratory hammer. The
procedure is repeated at each measured lift until the column is
completed. The columns are placed in a triangular or
rectangular grid pattern at spacing as determined by soil
conditions and approval of the COMPANY.

A blanket of sand or gravel, 0.6 m or more in thickness, is


usually placed over the top of the stone columns. This
blanket, along with the columns serves both as a drainage
layer and large diameter drains. Also, it distributes the stresses
from the structures above and reduces settlement.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 27 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

ii. Compaction Piles:

This method is economical for relatively small areas compared


with other soil improvement methods for fine-grained soils.
The compaction is partly caused by the vibrations from
driving the piles and partly by displacement of the soil caused
by the piles. A relatively large spacing is normally chosen for
the first few piles. Additional piles are then driven if the
required penetration resistance and relative density have not
been reached.

iii. Dynamic Compaction (Heavy Tamping):

This method involves the compaction of granular soils, using


heavy tamping, where pore water pressure variation becomes
virtually instantaneous and used to densify loose granular fills.

iv. Dynamic Consolidation:

This is similar, in essence, to dynamic compaction; however,


it deals with the improvement of fine grained soils, using
several phases of heavy tamping, with time intervals dictated
by pore water pressure response and dissipation. This method
does not work properly if the low permeability Sabkhah layer
exceeds 3 to 4m in thickness. A 1m thick layer of free
draining material is normally placed over the area before the
tamping to improve the transfer of energy to the soil.

v. Squeeze and Compaction Grouting:

Granular soils can be improved by squeeze and compaction


grouting.

At squeeze grouting, relatively thin cement slurry is used,


where the grout penetrates into the soil. Relatively thick slurry
is employed at a relatively high grout pressure in compaction
or consolidation grouting. This method is mainly applied in
Sabkhahs containing soft compressible silts and sandy silts
below the groundwater table. The boreholes are vertical and
grouted from the top downwards. Penetration grouting using
cement, silica or different chemicals is employed to reduce the
permeability of the soil, rather than to reduce the
compressibility or to increase the shear strength and the
bearing capacity of the foundation soils.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 28 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

12.2.3 Loading Methods:

Preloading:

Preloading followed by complete or partial unloading is used to reduce the


settlements in Sabkhahs containing granular soils. Bonding between soil
particles is not destroyed during the loading, and compressibility is greatly
reduced. Vertical sand wicks at uniform spacing can be used to accelerate the
consolidation.

12.3 Drainage Control

In order to protect the Sabkhah itself (against salt dissolution), as well as the
embedded substructures against brine saturation due to capillarity, it is vital to
implement effective drainage control measures in conjunction with soil densification
techniques.

Radial and horizontal sand/gravel drains are effective means of controlling drainage
in Sabkhah. However, these drains may become clogged if the Sabkhah contains a
large proportion of fines.

Geotextiles are versatile, cost-effective and multi-functional (reinforcement,


separation, drainage, etc.) materials that are used in drainage control of Sabkhah
soils intercepting the capillary fringe. The use of Geotextiles significantly improves
the inferior properties of Sabkhah sub-grade, particularly when the natural Sabkhah
Fabric Aggregate (SFA) system is saturated.

Other methods generally used for Drainage control are:

a. Well Point system, (See Section 8.0)

b. Two-Way Subsoil Drainage system

c. Cofferdams

d. Electro-osmosis

e. Electrolysis

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 29 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

13.0 QUALITY CONTROL, INSPECTION, AND REPORTS

13.1 Quality Control and Inspection

The quality of construction shall be determined by visual examination, by


measurements, and by testing. The extent to which each of these procedures is
employed shall depend on local conditions, on the importance and value of the work
being inspected. The frequency of each type of inspection shall vary as the work
progresses. During the entire construction stages, testing shall be conducted at
frequent intervals.

The inspection operation shall determine whether requirements of the approved


plans/drawings and specifications are being satisfied. Testing shall be sufficient to
provide adequate quality control and to furnish the necessary permanent records.
Testing shall be performed on selected samples of work or materials, which are
representative of some unit of work or material. More specifically, inspection shall
determine whether the material meets the gradation requirements, whether
compaction equipment complies with specification and is maintained in working
order, whether the thickness of lifts and the number of passes produce adequate
compaction, and whether moisture is at optimum limit and uniformly distributed
within the layer. Inspection shall be supported with field tests to determine the
degree of compaction and conformance of the supplied material.

Mechanical tamping when used around structures, along abutments, and in areas not
accessible to the rolling equipment, shall be checked by frequent density tests.

The areas of low density, and any other faults, shall be identified by ascertaining the
causes and shall be rectified on instructions from COMPANY Representative by
sprinkling, scarifying, removal, or re-rolling, as required. As a minimum, one field
density test (ASTM D 1556 or ASTM D 2922) shall be made as follows:

a. In areas where degree of compaction is doubtful

b. In localized areas of concentrated controlled fill operations

c. For every 100 square meters of controlled fill when no doubtful or


concentrated areas occur on large earthwork projects

d. For every 25 linear meters of controlled fill when no doubtful or concentrated


areas occur on small earthwork projects, such as backfilling utility trench
excavations

e. In areas subjected to structural loads, such as foundations for buildings,


transformers, circuit breakers, etc.

f. During each shift involving placing of earth materials

g. For each layer of controlled fill placed

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 30 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

13.2 Reports

A record shall be maintained throughout the construction operations. Reports shall


be made of every test performed in the laboratory and in the field by the approved
independent testing agency and shall be submitted directly to the COMPANY.
COMPANY Representative shall make daily reports concerning adequacy, progress
and the comments on decisions.

14.0 FINAL GRADING AND CLEANUP

14.1 At the end of all construction work, all holes, ruts, settlements and depressions shall
be filled and the whole area graded to final design elevations. All areas disturbed by
construction shall be restored to their original condition to the satisfaction of the
COMPANY Representative.

14.2 All debris, waste, excavated spoils and surplus articles and materials shall be
transported and/or discarded in a manner approved by the COMPANY
Representative.

15.0 BIBLIOGRAPHY

1. Soil Dynamics, Deep Stabilization and Special geotechnical construction by


NAVFAC Dept. Navy, U.S.A. April 83

2. Geological Survey (Drilling in Sabkhahs of Dhahran Area) by Ministry of Petroleum


and Mineral Resources, Jeddah, K.S.A.

3. Geotechnical Investigation for New Generation Projects at Ghazlan by OEO, K.S.A.

4. Pile foundation (Second Edition), Robert D. Chellis

5. Soil Survey for Engineering by ABA Brink, TC Partridge & AAB Williams

6. Design and Construction of Foundations, by Cement and Concrete Association

7. Developments in Soil Mechanics, by C.R. Scott

8. Indian Practical Civil Engineer’s Handbook, by P.N. Khanna

9. Specialists Ground Treatment by Vibrating and Dynamic methods, by D.A.


Greenwood, K. Kirsh & G.K.N. Keller Limited

10. Geotechnical Properties of Soils, by Dr. Saad A Aiban, K.F.U.P. M.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 31 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

11. Soil Stabilization and Ground Improvement “Overview” by Dr. Saad A Aiban,
K.F.U.P.M.

12. Chemical Stabilization of Soils Using Cement and Lime, by Dr. Omer Sayeed
Baghbara Al-Amoudi, K.F.U.P.M.

13. Principles of Geotechnical Engineering, by Brajer M Das, P W S Engineering,


Boston, U.S.A.

14. Soil Stabilization and Grouting, by Hans F Winterkorn, Sibel Pamuken Ph.D.,
Princeston Univ, U.S. A.

15. Symposium on Maintenance System and Application of Materials in the Saudi


Arabian Environment, by Research Institute, K.F.U.P.M.

16. Foundation Analysis and Design, by Joseph E. Bowles McGraw Hills Co., Inc,.
U.S.A.

17. General Specifications for Building Construction in Kingdom of Saudi Arabia-


Latest Edition.

16.0 FIGURES

Figure 1 - Slope Protection for Foundation


Figure 2 - Utility Trench
Figure 3 - Dewatering Scheme
Figure 4 - Gutter Isometric View - Slope Protection
Figure 5 - Gutter Longitudinal Section - Slope Protection
Figure 6 - Gutter Section “A-A” - Slope Protection
Figure 7 - Soil Particles Sizes for Ground Improvement Techniques
Figure 8 - Approximate correlation of soil ratings base on CBR values for use in
pavements.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 32 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

Minimum B or 1.0 m
whichever is greater
Excavation Slope (Slope
stability must be analyzed /
Existing B checked)
footing
30°

FIGURE # 1- SLOPE PROTECTION FOR FOUNDATION


(N.T.S)

FINISHED GRADE

Minimum Earth
cover (See Compacted backfill conforming
Section 7.3.4 ) to local municipal requirements
and/ or this standard

Service Line/
Power Cable Minimum 150 mm clean
sand bedding on all sides

FIGURE # 2- UTILITY TRENCHING


(N.T.S)

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 33 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

WELL POINTS
Header

FIGURE # 3 - DE-WATERING SCHEME


Minimum 1.0 m
Excavation

Lowered Ground level

(N.T.S)

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 34 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 35 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 36 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 37 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 38 OF 39


TRANSMISSION CONSTRUCTION STANDARD TCS-Q-113.02, Rev. 01

California Bearing Ration (CBR)

2 3 4 5 6 7 8 9 10 15 20 30 40 50 60 70 80 90 100

AASHTO SOIL CLASSIFICATION


A-1-b A-1-a
A-2-7 A-2-6 A-2-5 A-2-4
A-3
A-4
A-5
A-6
A-7-6 A-7-5

UNIFIED SOIL CLASSIFICATION

GW
OH CH GM-u GM-d
MH OL GC
CL SW
ML SM-d
SC
SM-u GP
SP

General soil rating as subgrade, subbase or base

Subgrade Poor Medium Good Excellent

Subbase Unacceptable Acceptable Good Excellent

Base Acceptable

Fig- 8 Approximate correlation of soil ratings based on CBR values for use in pavements.

TCSQ11302R01/SZA Date of Approval: January 21, 2013 PAGE 39 OF 39

Potrebbero piacerti anche