Project Title : RESIDENTIAL INTERIOR RENOVATION

Location : St. Jude Village, Candaba, Pampanga


Owner : Mr. & Mrs. Jose Guinto
Title : BILL OF MATERIALS

ITEM
DESCRIPTION QTY. UNIT
NO.
1 Demolition of Existing Beam and Column
2 Clearing and disposal of waste materials
3 Carpentry
a. 4'x8' Fiber cement Board 20 pcs
a. Double Metal Furring 75 pcs
a. Carrying Channel 35 pcs
a. Wall Angle 20 pcs
a. W-clip 150 pcs
a. Blind Rivets 4 boxes
a. Concret e Nails 2 kls
a. H-frame 10 pcs

4 Masonry
a. Retouch plastering 1 lot
b. Stone Slate/Cladding 8 boxes

5 Electrical Works
a. Lighting/Rough-ins 26 sets
b. Outlet/Rough-ins 8 sets
c. Transfer of Panel Board 1 lot

6 Painting Works
a. Ceiling 1 lot
e. Wall 1 lot

7 Bar Counter
a. Granite Slab 6 lm
b. 4'x8'x1/2" thk. Plyboard 5 pcs
c. Assorted Nails 3 kls
d. 2"x2"x20ft. Kilned Dried Lumber pcs lot
d. QDE 1 tin

Prepared by:

Ar. Arriane Mae C. Velasco


Architect

Reg. No: 38186


Ptr No: 5966391
Issued On: 01-24-2017
Issued At: City of San Fernando, Pampanga
TIN No.: 489-747-340
MATL'S UNIT LABOR UNIT
MATL'S COST LABOR COST AMOUNT
COST COST
PHP 7,500.00
PHP 3,500.00

450.00 9,000.00 300.00 6,000.00 PHP 15,000.00


110.00 8,250.00 40.00 3,000.00 PHP 11,250.00
110.00 3,850.00 40.00 1,400.00 PHP 5,250.00
80.00 1,600.00 32.00 640.00 PHP 2,240.00
5.00 750.00 2.00 300.00 PHP 1,050.00
300.00 1,200.00 120.00 480.00 PHP 1,680.00
110.00 220.00 40.00 80.00 PHP 300.00
300.00 3,000.00 30.00 300.00 PHP 3,300.00
(Sub-total) PHP 40,070.00

1,500.00 1,500.00 600.00 600.00 PHP 2,100.00


1,650.00 13,200.00 600.00 4,800.00 PHP 18,000.00
(Sub-total) PHP 20,100.00

1,550.00 40,300.00 500.00 13,000.00 PHP 53,300.00


1,250.00 10,000.00 500.00 4,000.00 PHP 14,000.00
10,000.00 PHP 10,000.00
(Sub-total) PHP 77,300.00

18,000.00 PHP 18,000.00


24,850.00 PHP 24,850.00
(Sub-total) PHP 42,850.00

as per supplier PHP 39,000.00


1,250.00 6,250.00 300.00 1,500.00 PHP 7,750.00
200.00 600.00 50.00 150.00 PHP 750.00

(Sub-total) PHP 47,500.00


TOTAL AMOUNT PHP 238,820.00
DESIGN AND SUPERVISION PHP 35,823.00
TOTAL PROJECT COST PHP 274,643.00