WATER SUPPLY & SANITATION DIVISION KAPURTHALA
12. Give name of the officer who prepared the estimates. Sh. Sanjay Arora Xen
Are you aware that the proposed work can be undertaken only
15. when requisite funds are released and technical approval of the Yes
proposal is granted by the Competent Authority.
REPORT
Govt. of Punjab has launched the execution of Sewerage Schemes under Punjab
Rural Water Supply and Sanitation Programme with the objective of improving the
environmental condition with specific reference to water supply and sanitation in selected
villages within the State.
There are basically two parts of the proposed scheme 1) Sewerage network and
Sewage Treatment Plant (STP) 2) Household Connection. Three agencies GPWSC/SLC,
DWSS and Contractor are involved in completing and implementing the scheme. Contractor
has been engaged to complete sewerage network and STP under direct supervision of
GPWSC/SLC and DWSS. In parallel with construction work, GPWSC/SLC and DWSS will
supervise proper household connection work to be constructed by house owner. Cost of
household connection up to premises boundary will be borne by respective house owner.
In all the villages of district Kapurthala, where sewerage schemes are under
execution, majority of households are having septic tanks / intercepting chambers. Only a
few households (as per list attached at Appendix ‘A’) are not having septic tanks /
intercepting chambers constructed in their premises. Village wise data of households without
septic tanks / intercepting chambers was collected and economically weaker households
under various categories such as SC, BPL, Small marginal farmers, households headed by
physically handicapped persons and women were signified. The proposal for constructing
septic tanks / intercepting chambers in economically weaker households by the department
was sent to Punjab Rural Development Board by SPMC, DWSS, Punjab for obtaining funds
as no funds for such purpose were available in PRWSS Project. Punjab Rural Development
Board vide their letter no. PRDB/E-3/413 dated 19/2/2014 released Rs. 12.24 Crore in
SPMC account with some terms and conditions for construction of septic tanks / intercepting
chambers to these economically weaker households which are unable to construct septic
tanks / intercepting chambers.
The cost of septic tanks / intercepting chambers as per specified drawing, comes out
to be Rs. 10244/- as per revised Premium applicable on CSR wef 11/12/2013. (Drawing and
quantity/cost calculation attached.)
Executive Engineer,
W/s & Sanitation Division,
Kapurthala
No. of households without Septic tanks/ IC Chambers in 6 Schemes where sewerage system is to be laid
(As per information received from Circle/ Field offices)
District & Divn. Total: 1023.03 1838 546 105 45 17 334 35 20 8 70 21 186 19.05
Sub Divisional Engineer, Sub Divisional Engineer, Sub Divisional Engineer, Sub Divisional Engineer,
W/s & Sanitation Sub Division, W/s & Sanitation Sub Division, W/s & Sanitation Sub Division, W/s & Sanitation Sub Division No.1,
Phagwara. Bhulath at Kapurthala. Sultanpur Lodhi. Kapurthala.
Executive Engineer,
W/s & Sanitation Division,
Kapurthala.
No. of households without Septic tanks/ IC Chambers in 6 Schemes where sewerage system is to be laid
(As per information received from Circle/ Field offices)
District & Divn. Total: 1023.03 1838 546 81 45 41 334 33 20 7 70 24 186 19.05