Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Inspection Department
The training materials contained in this module are the property of the Saudi Arabian Oil Company (Saudi Aramco) and
are intended for the exclusive use of Saudi Aramco employees enrolled in advanced inspection training courses. Any
material contained in this manual which is not already in the public domain, may not be copied, reproduced, sold, given or
disclosed to third parties or otherwise used, in whole or in part, for purposes other than for use in Saudi Aramco’s
Professional Engineering Development Unit courses without the prior written permission of the Chief Engineer of Saudi
Aramco.
PEW-403.02 PARTICIPANT REVISION
i
PEW-403.02 PARTICIPANT OBJECTIVES
OBJECTIVES 1
Terminal Objective 1
Enabling Objectives 1
INTRODUCTION 2
Scope 2
PERFORM PRE-INSPECTION DOCUMENT REVIEW 3
Review Job file 3
WPS/PQR/Weld Map 3
Welder Qualification Record 4
Safety Instruction Sheet (SIS) 4
S. A. Form 7627 (Hot-tap/Stopple & Reinforcement Calculation Request) 6
Project drawings 7
Checklists 8
PERFORM PRE-WELDING FIELD INSPECTION 9
Thickness Measurements (UT) 9
Repair Materials 11
Verification of Line Pressure 11
Proper Fit-Up of Components 12
PERFORM INSPECTION OF HOT TAP INSTALLATION 15
Appearance of the Weld Profile 15
Completed Weld of a Hot-Tap Sticker 16
Weld in Progress-Hot-Tap Reinforcement Pad 16
WITNESS TESTING OF HOT-TAP FIELD WELDS 20
Hydrotest Hot-Tap Sticker and Valve 20
Valve Body and Seat Test 20
Branch Connection Test 20
Reinforcing Pad or Ring Test 21
Tightness Test 21
High Pressure Closure Test 21
Test with Hot-Tap Machine Installed 21
NDT Test of Boss Plug Weld 21
ii
PEW-403.02 PARTICIPANT OBJECTIVES
iii
PEW-403.02 PARTICIPANT OBJECTIVES
OBJECTIVES
Terminal Objective
Upon completion of this module, the Participant will be able to inspect hot tap installation
in accordance with applicable standards.
Enabling Objectives
To achieve the Terminal Objective, the Participant will be able to accomplish the
following:
1
PEW-403.02 PARTICIPANT INFORMATION
INTRODUCTION
This kind of inspection work is performed by Saudi Aramco Inspectors on all types of
piping, vessels, and cross-country pipelines, which contain hydrocarbon or other
products under pressure.
Hot taps present a greater hazard to personnel and adjacent equipment than welds on
equipment that is out of service. Therefore, the Inspector must verify that all people
assigned to the job are properly certified and are well informed of the procedures and
safety requirements.
Scope
The scope of this module will be limited to visual inspection of the preparation and
welding on equipment that is in service (i.e. hot-tap installations). Hot tap is the
technique of attaching a welded branch fitting to piping or equipment in service and
creating an opening in that piping or equipment by drilling or cutting a portion of the
piping or equipment within the attached fitting
An inspector has no direct control over contractor’s crews on the job site. However, he is
responsible to verify the correctness of the preparation and execution of their work. He
must also verify that the safety practices of the work crews meet the minimum standards
established by the company for the type of work being performed.
In order to carry out these responsibilities, the Inspector must understand the work that
will be performed and the Saudi Aramco and industry standards that govern the quality
and safety requirements of such work.
The Inspector must prepare reports and make recommendations based on his
inspection activities. Therefore, he must know where to find the latest company and
industry standards which apply to the work, and he must refer to them when necessary,
to support his conclusions.
2
PEW-403.02 PARTICIPANT INFORMATION
There are many activities to be performed before proceeding to the job site. The
Inspector should locate and examine the job file. The job file contains the information the
Inspector needs to conduct an effective in-service weld inspection.
The Inspector must know where the job file is located and what documents are in the job
file. He must become familiar with the information contained in the job file documents.
The Inspector uses the information contained in the job file to plan and perform an in-
service weld inspection. The information required for the inspection may come from
many sources and the Inspector may have to obtain some items from Saudi Aramco
engineers, supervisors and contractor personnel.
The job file will normally be located in the Projects Inspector's office. The Inspector
should be aware however, that he may have to locate the necessary documents, and
build up a job file through his own efforts.
The job file, for the purpose of this module, should contain the following:
Welder Qualification Record (plus Welder Performance and Test Record card,
and Welder Job Clearance card)
Project Drawings
Checklists.
WPS/PQR/Weld Map
SAES-W-011 specifies that the contractor shall submit a weld map, table or fabrication
drawing that specifies where each welding procedure will be used. The weld map should
be submitted to Saudi Aramco Inspection along with the WPS and their PQR for each
3
PEW-403.02 PARTICIPANT INFORMATION
job or project. The weld map consists of drawings and/or isometric sketches of the
equipment and piping to be welded.
The weld map is used as a tracking document and as a permanent record to confirm the
location of all welds and the welder who performed them. The welding Inspector takes
the weld map to the job site and checks that the welder has marked his symbol on the
metal next to each weld. In the case of hot tap, it may be isometric drawing showing the
location of hot tap.
After review of WPS along with PQR, the authorized inspection representative will sign
form “Request for welding procedure Approval”. This form is given in SAES-W-011. The
inspector shall confirm the validity of the approval signature.
Note: For more information on WPS and PQR, refer to PEW-402.02 (Welding
Procedures and Welder qualifications).
Saudi Aramco requires a certified welder shall do the job. The welder shall possess
welder qualification card and JCC given by inspector. These welders shall be certified by
third party weld test centers, approved by Saudi Aramco. Inspector shall review these
documents for confirming his suitability.
The purpose of the SIS is to ensure that operating, maintenance, and inspection
personnel have the necessary information concerning safe operating limits, protective
devices, and any special safety precautions for certain pressurized and rotating
equipment in industrial plants and pipelines. The most important part of the SIS, for the
Inspector, is the Operating Limits section, which specifies t m's for designated areas of
pipe and equipment walls.
The SIS is provided by the proponent engineering organization and a copy of it should
be placed in the inspection job file.
4
PEW-403.02 PARTICIPANT INFORMATION
The SIS is used with a UT Gauging Sheet (to determine if actual measured wall
thicknesses and operating procedures fall within the limits specified by the SIS.
5
PEW-403.02 PARTICIPANT INFORMATION
An actual thickness measurement is taken for every test point indicated on the UT
Survey Form (See Figure 2). These actual thickness measurements are recorded in the
column of the Gauging Sheet under the date they were taken.
This form specifies safe design requirements for each hot-tap to be performed. It
contains critical information on field welding safety, job site layout, equipment
configuration and operating data. It also provides space for related inputs from all
organizations involved in the hot-tap project.
The purpose of this form is to specify the allowable pressures and flows, which must be
maintained during the welding and hot-tapping phases of the on-site work. SAEP - 311
specifies the maximum and minimum flow rates permissible during hot-tapping, as
follows:
The form also requires calculations and other inputs from all organizations participating
in the hot-tap job. These calculations should be submitted by representatives of the
following organizations:
The engineer from the engineering organization that is responsible for the hot-tap
or stopple.
Look at the completed S. A. Form 7627-Eng located in the sample job file. This is a
typical operational form from an actual project. It has inputs from the individuals and
organizations who are involved in the project.
The initiating engineer is responsible for Section 1 and for the left hand Summary
Column.
6
PEW-403.02 PARTICIPANT INFORMATION
Note: SAEP -311 provides guidance for completing Saudi Aramco Form 7627-Eng
The completed S. A. Form 7627 should be obtained from the engineering organization
that is responsible for the hot-tap or stopple.
The Inspector uses this information to verify that the actual site conditions are within the
limits specified in S. A. Form 7627.
Project drawings
The drawings for an in-service welding job provide information about the location of the
job with respect to other adjacent equipment (refinery job) or to pipeline reference points
(cross-country job). The weld map is usually such a drawing; however, this information is
not always presented as a drawing. P&IDs can be used to specify the location of a
welding job within the refinery or with respect to other process equipment such as a
GOSP facility.
An isometric sketch (iso), provides more detail as to the location of the weld. For
example, an iso shows the height and position of a weld location with respect to the
ground.
Standard drawings for valves and other piping implements provide information about the
exact dimensions of the equipment to be used in the job. These drawings are most likely
to be provided when the weld is for hot-tap preparation.
7
PEW-403.02 PARTICIPANT INFORMATION
Checklists
The welding Inspector will be particularly concerned with four types of checklists. The In-
Process Welding Checklist and the Final Weld Inspection Checklist must be developed
by the Inspector. The Hot-tap Data & Checklist (Saudi Aramco Form 7235-Eng), and
Hot-tap Checklist (Appendix II, SAEP - 311, Saudi Aramco Form 7627-Eng) are available
in printed form.
The Inspector can develop his own inspection checklist with information that he obtains
from the contract documents.
The sample In-Process, Final Weld, and Hot-tap Inspection Checklists show many of the
areas you will need to check during a welding inspection. These lists are based on
typical jobs and are not complete for every kind of inspection. However, they provide
some general guidelines for checking procedures and welding variables.
Each Inspector must develop his own checklist based on the project that the supervisor
assigns. You must compare the welding conditions with the specifications throughout the
inspection process. The Inspector must constantly ask himself, 'Do the on-site conditions
match the specifications in the WPS?"
8
PEW-403.02 PARTICIPANT INFORMATION
The following activities outline the activities of the Inspector at the job site but prior to the
start of welding.
The contractor shall inspect and determine the minimum pipe wall thickness at the tie-in
weld areas by a continuous UT scan along the lines to be welded. The UT record shall
be entered in the form shown in Figure 2. The area to be scanned shall include the weld
zone and 50 mm each of it. The minimum remaining wall thickness at the weld
connection area shall not be below minimum thickness tm and in all cases, no less than
5 mm.
The Inspector verifies that the thickness of the pipe is greater than the minimum allowed
for safe welding.
9
PEW-403.02 PARTICIPANT INFORMATION
HEADER MEASUREMENTS
(CONTINUOUS SCANNING)
Point A Min:__________ Max.:_________
Circle B Min:__________ Max:__________
Circle C Min:__________ Max:__________
Line D-D Min:__________ Max:__________
Line E-E Min:__________ Max:__________
180 deg. from Pt. A Min:__________ Max:__________
STICKER MEASUREMENT
Min:__________ Max.:__________
D E LOCATION-------DESCRIPTION
D E
10
PEW-403.02 PARTICIPANT INFORMATION
Repair Materials
The Inspector verifies that the base metals, welding filler metals and welding gases are
properly identified and conform to the WPS requirements. He inspects the base metal to
ensure that there are no discontinuities near the weld end preparation. The remainder of
the base metal is inspected for discontinuities during the final inspection.The Inspector
verifies that the contractor has provided materials that apply to the specified type of
weld.
The contract or job order specifications and the WPS specify the manufacturing, quality
and performance standards that apply to the job.
For hot-tap jobs, Saudi Aramco Form 7627 (Hot-tap/Stopple & Reinforcement
Calculation Request) and Saudi Aramco Drawing AB-36719 contain additional materials
standards.
The Inspector must verify line pressure/flow before the contractor begins the tapping
operation. This is a critical safety factor.
Serious damage and injury may result from burn through, explosion and fire if line
pressure is not within specified limits when welding is in progress.
The Inspector must obtain existing pressure readings at the equipment location where
the hot-tap will be performed. He must compare these readings with the pressure/flow
limits specified in Saudi Aramco Form 7627.
Look in Section 4 of Saudi Aramco Form 7627-Eng, for the critical values that the
Inspector must verify. A separate form must be completed for each hot-tap performed.
Notice that the allowable pressures and flows are given for the following situations:
11
PEW-403.02 PARTICIPANT INFORMATION
Note: SAEP -311 provides additional information about pressure and flow limits for
welding and hot-tapping of pipe and equipment
The Inspector must compare actual field pressures and flows with those specified in
section 4 of SAF 7627-Eng.
He must check the weld end preparation to verify that it meets all of the requirements
specified by the welding procedure.
The Inspector must check cleanliness of the base metal on both sides of the joint to
verify that it meets procedure and specification requirements. Check for moisture,
contaminants such as grease, oil, and paint, scale, and corrosion products such as rust.
Verify that the weld joint fit-up meets procedure and specification requirements. Check
the root opening and the amount of mismatch (e.g., high-low).
Not cracked.
The inspector applies the following regulatory documents and drawings to inspect fit-up
for welding of Saudi Aramco hot-tap projects:
SAES-L-052,
SAEP -311
Examples of fit-up problems are many and varied since each repair or installation project
has its own unique set of requirements. Requirements for welding operations that are
performed on a recurring basis are specified by Saudi Aramco General Instructions and
Standard Drawings.
12
PEW-403.02 PARTICIPANT INFORMATION
To ensure that the proper fit-up is in progress for the hot-tap connection (See also Figure
3), the Inspector must:
Verify that the fitting is the proper size to accommodate the hot-tap machine.
Verify that the welded branch or split tee is accurately positioned so that the axis
of the cutter will intersect the axis of the pipe or vessel being tapped, at a 90-
degree angle.
Re-verify the branch position before welding (See Figure 4), including
Header/Branch root gap.
Prior to any welding the Inspector must verify the thickness of the weld area by
ultrasonic examination at 1- inch intervals along the line to be welded. The inspection
area should be marked for future reference and identification.
Note: When performing ultrasonic examination, enter the necessary data in the form
titled "Ultrasonic Thickness Measurements for Hot-Tap Connections,"
Appendix I, SAEP- 311.
The connection through which a hot-tap will be made must be inspected in accordance
with the following references:
13
PEW-403.02 PARTICIPANT INFORMATION
The Inspector calculates a specified preheat temperature from data contained in tables
located in Saudi Aramco Standard Drawing AE-036451. This drawing is titled, Preheat
Levels for Welding Carbon Steels, Including Low Hydrogen Processes. These tables
specify values for calculating the correct preheat levels for given materials.
SAES-W-011 & 12 provide a quick reference to the necessary procedures and preheat
values.
Look at the WPS located in the job folder. Note the following points:
SAES-W-011 and SAES-W-012 should be included with the WPS because they
contain the information needed to determine the required welding preheat values
for the base metals which are specified in the WPS.
The WPS specifies the type of base metal and the thickness range of that base
metal.
The welding Inspector compares the type and maximum wall thickness of the
base metal specified in the procedure with the data in AE036451, SAES-W-O11,
and SAES-W-012. The information in these documents gives him the required
preheat temperatures for pipe or fittings.
Figure 4
14
PEW-403.02 PARTICIPANT INFORMATION
In almost all hot-tapping jobs, the main problem areas are related to welding the branch
connection fitting on the pipeline. The branch connection is usually referred to as the
hot-tap sticker or as simply the sticker.
The welding Inspector must check for the following deficiencies in welding methods
while welding of the hot-tap sticker is in progress:
Blow through.
Low current.
High current
These deficiencies can cause common weld defects such as lack of fusion,
undercut, and porosity, if not corrected quickly.
The Inspector must visually inspect the weld bead for the desired characteristics as the
work progresses.
He checks all completed welds for overall profile, weld dimensions, unusual coloration
and discontinuities.
15
PEW-403.02 PARTICIPANT INFORMATION
When a radiography test of the weld is required, the welding Inspector must prepare the
request. Upon completion of the test, the Inspector will analyze the result. Welds that
contain deficiencies must be repaired. After repairs, the Inspector must perform another
visual and radiographic inspection of the weld.
Lack of fusion.
Undercut.
Porosity.
The hot-tap procedure should commence only after the sticker weld has been thoroughly
inspected and approved.
Installation without a reinforcement pad is specified for some hot-tap stickers and
installation with a reinforcement pad is specified for others. The reinforcing pad must be
welded separately and the welding procedures are similar to those for the weld of the
hot-tap sticker.
In most Saudi Aramco applications, the reinforcing pad is slipped down over the hot-tap
sticker until it seats on the exterior wall of the header pipe or vessel. Reinforcing pads
are fabricated specifically for a given job.
16
PEW-403.02 PARTICIPANT INFORMATION
Verify correct root gap where the pad rings the base of the sticker.
Verify that the welder meets all WPS weld requirements as he progresses with
the welding.
Figure 5C shows a welded branch connection with a reinforcement pad. Notice that the
reinforcement pad requires a vent hole to allow gases to escape during the welding
process.
Figure 6 shows the various types of reinforcing pads used in Saudi Aramco.
17
PEW-403.02 PARTICIPANT INFORMATION
18
PEW-403.02 PARTICIPANT INFORMATION
19
PEW-403.02 PARTICIPANT INFORMATION
The branch connection must be hydrotested, if required in the job specifications, before
cutting into the main line. A separate pressure test of the branch connection avoids the
need to test the entire system.
The welding Inspector must witness and approve the following hydrostatic pressure
tests:
The purpose of the valve body and seat test is to verify a positive seal between the gate
and seat.
The Inspector must verify that a hydrostatic pressure test was performed. A tag must be
attached to the valve indicating the test date, the test pressure and the name of the
Inspector who performed the test.
The purpose of the branch connection hydrostatic test is to verify the integrity of the
connection weld. In order to perform this test the open end of the branch connection
must be sealed with a blind flange. Verify that a boss is installed in the branch
connection as shown on Standard Drawing AB-036719.
Verify that the hydrostatic test pressure applied to the branch connection is the lower
value shown in 4.4c or 4.4e on Saudi Aramco Form 7627-Eng.
20
PEW-403.02 PARTICIPANT INFORMATION
SAEP-311 specifies that a pneumatic strength test of 25 psig must be applied to the
reinforcing pad or ring after installation.
Tightness Test
The pneumatic pressure for the reinforcing pad or ring test must then be reduced to 3-5
psig after strength test for a tightness test using a soap solution.
The Inspector must verify, in both of the preceding pneumatic pressure tests that
specified pressures were applied and that leakage did not occur during either test.
The high-pressure closure test must be applied with the hot-tap valve in place on the
branch connection.
The Inspector must verify that the pressure applied in this test is the lower value shown
in 4.4c or 4.4d on Saudi Aramco Form 7627. Pressure must be applied in this test,
through a branch connection boss which is field installed.
The hot-tap machine must be mounted onto the hot-tap valve, with the valve in the open
position and a full pressure hydrostatic test must be applied. The Inspector must verify
that the test pressure applied is the lower value shown in 4.4c or 4.4e on Saudi Aramco
Form 7627.
Note: When the foregoing tests are complete the Inspector must witness installation
of a bar stock plug in the branch connection boss, and seal welding of the
plug.
After completion of all tests, a bar stock plug that is installed in the branch connection
boss shall be seal welded. The Inspector, at his option, may call for a NDT test to be
applied to the branch connection plug weld to verify the integrity of the boss plug weld.
21
PEW-403.02 PARTICIPANT INFORMATION
Confirmation of the internal condition of the header and verification of actual header wall
thickness can be determined after a hot-tap procedure has been completed and the
cutout coupon has been removed.
22
PEW-403.02 PARTICIPANT EXERCISES
This exercise will familiarize you with the information contained in a typical Inspection
Job File.
Use the documents in the sample job file, the Information Sheet, and Work Aids 1 and 2
to answer the following questions.
1. When the welding Inspector is assigned to inspect a project, what is his first
duty?
2. What documents should the Inspector make sure are available for initial review?
3. When the welding Inspector is assigned an inspection project he may find a job
file assembled and ready for him, or he may be required to assemble the
necessary documents and make up his own job file.
True ___________
False __________
23
PEW-403.02 PARTICIPANT EXERCISES
5. The welding Inspector checks the "Request for a Welding Procedure Approval" in
the job file. What is the main thing he is looking for?
6. How can the welding Inspector verify that the signature on a "Request for A
Welding Procedure Approval" form is an authorized signature?
7. What is the identification number of the WPS included in the sample job file?
8. Do the welding procedures specified by the WPS provide the requirements for
welding a particular joint?
9. What items of information does the WPS specify for a particular weld?
24
PEW-403.02 PARTICIPANT EXERCISES
True _________
False ________
25
PEW-403.02 PARTICIPANT EXERCISES
This exercise will familiarize you with two specific documents that should be in the
typical inspection job file: the Safety Instruction Sheet (SIS) and Welding Procedure
Specifications (WPS).
Use the SIS and WPS in the sample job file, the Information Sheet, and Work Aid 3 to
answer the following.
1. What documents are used in connection with the Safety Instruction Sheet (SIS)
in the job file to determine if actual measured wall thicknesses are within
specified limits?
Refer to WPS to answer questions 2 through 10. 2. What welding rod is specified for
the root weld?
26
PEW-403.02 PARTICIPANT EXERCISES
8. What standard is specified as the reference standard for preheat? Indicate page
number.
10. Why is electrode E-7010 specified for a root bead instead of E-6010?
11. Name the various types of inspection checklists that should be utilized by the
welding inspector to make sure that no items are overlooked in performing a
complete inspection.
27
PEW-403.02 PARTICIPANT EXERCISES
At this point, the Inspector is on the job site but welding has not commenced. This
exercise will familiarize you with how to locate specific information and how to analyze
specific documents in order to perform the pre-welding procedures required by Saudi
Aramco.
Answer the following questions using the documents in the sample job file, the
Information Sheet, and Work Aids 4 and 5.
3. What are the minimum and maximum flow rates specified by SAF-7627 for
header flow during welding (or cutting the coupon)?
28
PEW-403.02 PARTICIPANT EXERCISES
5. Given the welder qualification card, answer the following questions: (Please
provide welder qualification card)
6. If a welder has not welded with any welding process for a period of 3 months or
more, is his welding qualification card still valid?
7. What must any welder do to re-validate his welder qualification card if it lapses?
10. What must the welding inspector verify according to SAES-L-052, Para. 4.1 ?
29
PEW-403.02 PARTICIPANT EXERCISES
This exercise continues to familiarize you with how to locate specific information and
how to analyze specific documents in order to perform the pre-welding procedures
required by Saudi Aramco.
Answer the following questions using the documents in the sample job file, the
Information Sheet, and Work Aid 6.
True ________
False _______
4. What calculation can the Inspector make using the data contained in Saudi
Aramco Standard Drawing #AE-036451?
5. Given: WPS and attached SAES-W-012, Table 2. The base metal is API
Specification 5L GR X 60 pipe, 1.00 Inch thick. Materials and conditions are as
specified in SAES-W-012, including the Notes section. The hot pass will be made
within 5 minutes of completing the root pass. The weld is pipe-to-pipe. What is
the required minimum preheat in degrees Fahrenheit for:
a. Root pass?
b. Balance of weld?
30
PEW-403.02 PARTICIPANT EXERCISES
6. Is it your job as welding Inspector to specify the correct electrodes for a particular
job?
8. Referring to WPS, what type of shielding gas is required in the welding procedure
specifications?
9. Referring to WPS, does the specification for a hot pass electrode agree with the
classification in ASME Sec.ll, Part C?
31
PEW-403.02 PARTICIPANT EXERCISES
This exercise reinforces your ability to perform inspection procedures related to welds in
progress and completed welds of pipelines, hot-tap stickers, and hot tap reinforcement
pads.
Answer the following questions using the documents in the sample job file, the Information
Sheet, and Work Aid 6.
1. While welding is in progress, how will the Inspector check the voltage and
amperage actually produced by the welding machine?
4. Who should check to make sure that the welder maintains the correct interpass
temperature during multiple-pass welds?
5. Who is responsible for controlling the interpass temperature during the welding
process?
32
PEW-403.02 PARTICIPANT EXERCISES
8. Name two devices that the welding Inspector can use to verify that the correct
interpass temperature is being maintained.
33
PEW-403.02 PARTICIPANT EXERCISES
Answer the following questions using the documents in the sample job file, the
Information Sheet, and Work Aid 6 as needed.
4. What is the type of current and the polarity specified in the WPS?
Current _________
Polarity _________
6. What is the welding Inspector looking for while visually inspecting the in-process
weld?
34
PEW-403.02 PARTICIPANT EXERCISES
8. A weld rejected by the Inspector after radiography has now been repaired by the
welder and the Inspector has performed a visual inspection of the repair. Will it
be necessary to perform another radiographic inspection of the repaired weld?
9. When the welding Inspector desires a radiography test who prepares the
request?
10. What evidence should the inspector look for while analyzing a hot-tap coupon?
35
PEW-403.02 PARTICIPANT EXERCISES
Answer the following questions using SAEP-311, the Information Sheet, and Work Aid as
needed.
2. According to SAEP-311, how shall the Inspector confirm that the hydrostatic test
pressure for a hot-tap connection is correct at the time of the test?
3. How many hydrostatic tests must be performed on a hot-tap valve prior to the
hot-tap procedure?
4. The welding Inspector must witness and approve the hydrostatic test(s) of the
equipment and connection of hot-taps in new project construction. (See SAEP-
311)
True ________
False _______
5. You notice that the test pressures specified in SAEP-311 for a hot-tap
reinforcement pad differ from the test pressures specified in SAES-L-052. Which
specifications should you follow?
36
PEW-403.02 PARTICIPANT EXERCISES
Prepare a Final Inspection Report using the hypothetical information provided below.
This hypothetical information represents observations recorded in the welding
Inspector's field notes. Use the example final inspection report located in the sample job
file as a guide.
BI 3115, CN-37261/00.
10" JUBAIUFG.
10" pipeline bringing fuel gas from Jubail Gas Plant to Ju'aymah Pwr Station.
Distance - 30km.
Materials used - 10" dia. FBE coated 0.500 wt. API-5L Grade 60 pipe.
Number of welds rejected and repaired - 2 (One weld was cut out).
37
PEW-403.02 PARTICIPANT EXERCISES
38
PEW-403.02 PARTICIPANT EXERCISES
Supervisor
Projects Inspection Div.,
Description of Job
Procedures Used
39
PEW-403.02 PARTICIPANT EXERCISES
Hydrostatic Testing
Contractor Cooperation
Final Evaluation
40
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to identify the documents for the job file and to determine who is
responsible to provide each document.
41
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to find the materials standards that are specified in the project
documents located in the job file.
3. Check the WPS, the SAF-7627, and Saudi Aramco Standard Drawing AB-36719.
42
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to locate information in the WPS that relates to the inspection of in-
service welds and welding in progress.
Note: The specifications listed below are derived from a typical WPS from an actual
project. Compare the specifications below with the information contained in WPS
located in the Handout Package.
SECTION
INSPECTION ITEM SPECIFICATION
OF W P S
43
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to locate thickness information as presented on an SIS and to make
the correct comparisons with thickness measurement data from corresponding UT
Survey and Gauging Sheets.
1. Check to ensure that the following documents are in your job file.
SIS
UT SURVEY SHEET
44
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to help you select the required information from among the various
sections of Saudi Aramco Form 7627, "Hot-tap/Stopple & Reinforcement Calculation
Sheet". This information allows the Inspector to compare actual line pressure and
temperature with the specified pressure and temperature, during a hot-tap.
3. Note the specified operating pressure and temperature. For example, SAF-7627-
Eng for job number 81274 specifies that the operating pressure should be 850
psig and the temperature should be 120 °F
4. Check the actual operating pressure and temperature or obtain readings from the
job site contractor or operations personnel.
45
PEW-403.02 PARTICIPANT WORKAIDS
Use this Work Aid to select information from the WPS and SAES-W-011 and 012, and
determine preheat/interpass temperature requirements.
4. Note measured actual base metal thickness (Measured at the job site).
8. Note that material specifications of SAES-W-012, call for carbon steel materials
up through Grade X60. This corresponds to WPS (QW403).
Approved electrodes
11. Move horizontally under the column headed by the specified fit-up, e.g. Pipe-to-
pipe or fittings.
46
PEW-403.02 PARTICIPANT GLOSSARY
GLOSSARY
Interpass temperature The temperature at which the weld area must be before
the next weld pass is started. This may be stated as either
a minimum or a maximum.
47
PEW-403.02 PARTICIPANT GLOSSARY
Nominal pipe size (NPS) Normally, pipe is specified in terms of NPS. Nominal pipe
size (in inches) is somewhat different from the actual size
up to 12” NPS; it represents internal diameter and 14” and
above it represents outside diameter.
PSIG Pounds per square inch gauge. i.e. pressure in pounds per
square inch above existing atmospheric pressure.
48
PEW-403.02 PARTICIPANT GLOSSARY
system product The type of fluid that is being carried and processed in the
piping system of a petroleum processing facility.
to Thickness, original
49