Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
The anchor span held by the end tie provided the necessary
stability for the cantilever construction. A temporary tie was also
used at top chord level at the junction of the cantilever and
suspended span for cantilever construction of the suspended span.
ADVERTISEMENTS:
By this process, the cantilever span as well as the half length of the
suspended span were erected from both tower ends and the central
gap was closed. Thereafter, the suspenders were hung from the
nodal points of the bottom chord of the truss and the deck was
constructed over longitudinal girders and cross-girders supported
on suspenders.
A temporary tie is used over the pier at top chord level for this
purpose. To construct some portion of the truss over the pier in
order to have a platform for the two working cranes, temporary
struts at bottom chords are used from wells or piers. This method
is similar to the cantilever construction of PSC bridges as shown in
Fig. 24.2.
(iii) Spinning of the main cables and fixing them with the
anchorages and towers.
The spinning wheels are pulled along the catwalk and over the
towers to the opposite anchorages. The wires are then attached to
the anchorages and this procedure is repeated till all the wires of
the strand are carried over the towers to the anchorages.
After the first span girders were launched, the rail track was
extended over the already launched girders and the launching truss
having a balancing tail truss with water tanks at the end was moved
to the next span.
The balancing truss maintained the stability of the launching truss
during its shifting to the next span. After the launching truss was
moved to the next span and fixed, the process of launching the
girders carried from the casting yard was repeated as before till all
girders of all spans were launched and side shifted in position.
The portion of the deck between the inclined struts B to C was cast
in place to provide a for the erection of the precast box-girder
sections in the portions A to B and C to D. The precast box-girder
sections were cast in casting yard against each other for proper
matching.
The segments were floated to the site by barges, lifted by a crane,
placed on top of the already completed deck, placed against the
previously erected deck and prestressed. Each unit of the bridge
deck, i.e., C to D is supported by two sets of stay cables in each
cantilever span, i.e., eight sets for the entire unit considering both
towers.
In addition, four sets of temporary cables, though of smaller
strands, had to be used in each cantilever from each tower for the
facility of erection by cantilever construction method.
The Second Hooghly Bridge now under construction at Calcutta is
a cable-stayed bridge and the general arrangement of the bridge.
Similar to Howrah Bridge, the shore spans have been completed
over false-work in this bridge also (Fig. 24.6c).
Thereafter, the concrete deck slab was Cast while the shore spans
were still supported over false-work. After the completion of the
towers and the shore spans, two pairs of inclined cables are fixed
from the tower to the shore and the main span simultaneously
starting from tower side cables.
While the cables are fixed to the shore spans which have been
completed over false-work, the main span cables support only the
main and cross-girders of one panel length which is lifted from the
floating barges by the deck erection cranes placed over completed
deck.