Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
System
Contents
3 Solution on PSCS
5 Case Study
www.nrec.com 2
Power Stability Challenges
⚫ The power system is “the most complex machine ever
built by human beings”
- large-scale
- time-critical
- dynamic
- non-linear
⚫ The power stability is one of the most challenging
issues faced by electrical engineers
www.nrec.com 3
Power System Blackouts
www.nrec.com 4
Largest Blackouts in History
1st 2012 India Blackout 600 Million North India, and East India 2012-07-31
2009-11-10/2009-
6th 2009 Brazil and Paraguay blackout 87 Million Brazil and Paraguay
11-11
2003-08-14/2003-
7th Northeast Blackout of 2003 55 Million North America, northeastern
08-15
Italy, Switzerland, Austria,
8th 2003 Europe blackout 55Million 2003-09-28
Slovenia, Croatia
www.nrec.com 5
Main Issues Causing Blackouts
www.nrec.com 6
Typical Instability Cases
500kV
220kV 220kV
www.nrec.com 7
Typical Instability Cases
⚫ Weak interconnection
- Sudden change in one grid may cause tie line beyond their
stability limits
Grid A Grid B
Gen.
www.nrec.com 8
Typical Instability Cases
Grid A Grid B
www.nrec.com 9
Typical Instability Cases
High percentage
Grid A
www.nrec.com 10
Typical Instability Cases
Gen.
www.nrec.com 11
Typical Instability Cases
Grid A
Grid B Grid C
www.nrec.com 12
Prevention of Distance Z3 Mal-operation
ZArc
Exaggerated
ZLoad RMS Delta I
R www.nrec.com 13
Possible Solutions to Prevent Blackouts
⚫ Primary System
- Strong primary network with N-1 capability
- Voltage-Oriented and Region-Oriented Management
⚫ Secondary System
- Preventive Control (EMS, AGC/AVC etc)
- Reliable Protection System
- Power Stability Control System with Remedial Actions
- Out-of-Step and Frequency/Voltage Control
www.nrec.com 14
The Most Cost Effective Solution
www.nrec.com 15
Transmit More Energy with PSCSTM
⚫ PSCS could improve the stability margin and help utilities
transfer more power
⚫ Choices to meet transmission stability requirements
- Construct new transmission lines
- Reduce the power flow on tie lines
- Adopt remedial action schemes
⚫ Evaluation of an example project per choices
www.nrec.com 16
Five-stage of Cascading Process
Fast
Oscillation Collapse
Trigger Cascading
Event
www.nrec.com 17
Aug 14, 2003 Blackout, US-Canada
Aug 14, 2003 Northeastern Blackout Example
• Stage 1: slow cascading progress
✓12-14:14pm, several lines and one gen outage
✓15:05-15:41pm, three FE 345KV lines outage
✓15:39-15:59pm, collapse of 138KV system
✓16:05pm, trigger event: outage of Sammis-Star line
✓16:05-16:09pm, two 345KV & 138KV lines outages
www.nrec.com 18
Aug 14, 2003 Blackout, US-Canada
www.nrec.com 19
Lessons from 2003 Blackout
Fast Cascading
Collapse
Oscillation
Slow Cascading
1st
Event 2nd 3rd 4th 5th
Restoration t
62 min 3 2 29 hr
min min
10
sec
www.nrec.com 20
Contents
3 Solution on PSCS
5 Case Study
www.nrec.com 21
Bulk Power Transmission from West
to East
Large-scale, long-distance, large-capacity
power Transmission in China
Northwest
4/5 of the hydropower
resource is located in the
southwest Tibet
Center East
www.nrec.com 22
What Happens for Blackouts in China
⚫ One of the Most Stable Power Grids in the World
250
210
200
150
81
100
50 20
2 0
0
1970-1979 1980-1989 1990-1999 2000-2009 2010-now
www.nrec.com 23
Full-Scheme Strategy to Prevent
Blackout
⚫ Safeguard implemented in EACH STAGE
- Preventive Control (PC): small-disturbance, actions taken by
operators or auto-control devices
- Emergency Control (EC): large-disturbance, actions taken by
PSCS, SPS or WAMS, including slow cascading & fast
cascading stages
- Corrective Control (CC): remedial actions taken by out-of-step
Fast Cascading
relay, F/V control
Collapse
Oscillation
Restoration
Slow Cascading
PC EC CC
www.nrec.com 24
Full-Scheme Strategy to Prevent
Blackout
Well-Proven Three-Defense-Line securely maintain
Chinese power systems
• First Defense Line: Clear faults by protective relays Quickly and
Accurately
www.nrec.com 25
Power system cascading progress
⚫ Need a defense plan in cascading progress
Fast
Oscillation Collapse
Trigger Cascading
Event Slow Cascading
Restoration t
Protection
Out-of-Step Relay,
F/V Control Scheme
www.nrec.com 26
Defense Plan to Protect Powergrid
Restorative Black
Control Start
Take actions
before the
system goes into
instability
www.nrec.com 27
What are 3-Defence-Lines of
Backouts
⚫ Three-Defense-Line to guarantee power system stability
3rd
Defense
2nd Line
Defense Out-of-Step and F/V
control will island
1st Line regional power
Innovative Power networks to save
Defense Stability Control region away from
blackout
Line System will implement
remedial actions to
Reliable protective rebalance active power
relays will clear faults
on duty and immune to
external interruptions
www.nrec.com 28
First Defense Line
⚫ Reliable Protection & Control-----
Faster Tripping, Larger Margin
Sym FD element ≥1
Trip
Distance element
www.nrec.com 29
Second defense line
⚫ Power Stability Control System----
Take remedial actions in slow and
fast cascading prior to oscillation
• Event-based
• Distributed decision-
making
• Real-time-data-based
• Non-reliance on GPS
• Full-IED-Solution without
rotating components
www.nrec.com 30
Actions of Second Defense Line
• Take actions to prevent cascading
Before Instability Starts
- Real time responding to control CB of
generator, transformer, line and others
- Turn on or turn off generators
- Load shedding as per stability tactic
- HVDC modulation
www.nrec.com 31
Third defense line
⚫ Out-of-step and Voltage/Frequency Control---
The last defense against blackouts
Impedance
1 Crossing
Out-of-Step
Detection
Technologies
UCOSφ
2 Crossing
www.nrec.com 32
Three-Defense-Lines cover all stages
Out-of-Step Islanding:
Prevent blackout &
minimize loss of loads
Severity of Disturbance
www.nrec.com 33
Contents
3 Solution on PSCS
5 Case Study
www.nrec.com 34
Power Stability Control System (PSCS)
Loads Generators
Power Grid
Action to
Power stabilize
Instability ? power
system
PSCS
Second Defense Line Calculation of Tactic Table
www.nrec.com 35
PSCS Systematic Structure
www.nrec.com 36
PSCSTM Working Flow
Stability analysis based on system IEDs measure real-time data &
data detect contingencies
www.nrec.com 37
Tactic Table
⚫ Tactic tables are the results of stability study (simulation,
action-design and verification)
…… …… …… …… ……
www.nrec.com 38
Power Stability Control System
⚫ Stability Control Solution based on pre-designed tactic
tables
Master Station Table
Real-time Real-time
Data Data Actions
www.nrec.com 39
Flexible Structure of PSCS
⚫ Flexible Structure Design according SDH network and
stability study results.
Master Station Master Station
64kbit/2 64kbit/2
M Fiber M Fiber
…… ……
Slave Station Slave Station Slave Station Slave Station
64kbit/2 64kbit/2
M Fiber M Fiber
…… ……
Executing Station Executing Station Executing Station Executing Station
www.nrec.com 40
PSCSTM Features
• System-level algorithm, not local algorithm
www.nrec.com 41
Response-based Control
Response-based control
• Definition:
If (parameter A) exceed or below …
then ….
e.g.
If frequency below 49.0 Hz for 200ms
then shed 4-7% of total load.
• Feature:
Slow relatively
www.nrec.com 42
Event-based Control
Event-based control
• Definition:
If (event A) occur when …
then ….e.g.
• Feature:
Faster
www.nrec.com 43
Distributed Tactic Table of PSCSTM
• Centralized Decision-Making Structure
IED IED
www.nrec.com 44
Distributed Tactic Table of PSCSTM
• Distributed Tactic Table for fast decision-making during
emergency
Table
Table
Table Table
X
……
Table
X
Table
……
Table Table
www.nrec.com 45
Time-Critical Stability Control
Source: CIGRE Study Committee 38 and the IEEE Power System Dynamic Performance Committee
www.nrec.com 46
Time-Critical Stability Control
Time From Trigger Event to Instability
Frequency Voltage
Angle Stability
Stability Stability
Steady State
10 to 20 sec
(Small Disturbance)
Several hundred Several
3 to 5 sec
milliseconds to seconds to tens
Transient State several minutes of minutes
10 to 20s in extra
(Large Disturbance)
large system with
interval oscillation
• Stability Control shall be completed in 150-200ms, including breaker
operating time, communication delay etc.
www.nrec.com 47
Time-Critical Stability Control
Fast Cascading
Oscillation
Collapse
Trigger
Event
PC EC RC
CC
www.nrec.com 48
HST Protocol of NR
www.nrec.com 49
PSCSTM Solution
• Real-time-data-based, Event-based, Distributed tactic
table, Non-Reliance on GPS, Full-IED-Solution without
any rotating component
Master Station Table
Real-time Real-time
Data Data Actions
www.nrec.com 50
SPS Solution
• Using the data from RTU
• Centralized decision-making leading to slow operation
• Communication channel delay is not controlled
• All Substations need communication channel to Remote Center
Table
Decision-Maker
www.nrec.com 51
WAMS/WAPS Solution
• Computer-based Solution with rotating components
• Reliance on GPS leading to low reliability (GPS receiver)
• Centralized decision-making leading to slow operation & increased
risks (PDC)
• Response-based
WAMS/WAPS
PDC
GPS
Receiver
www.nrec.com 52
Comparison of PSCS and SPS, WAMS
PSCSTM SPS WAMS (PMU)
Real-time data from data from RTUs or
Data Source Phasor from PMUs
Dedicated IEDs protections
30-90
Sampling Rate 24 samples/cycle 2-5 seconds
samples/second
Response-based or
Decision Mode Event-based Response-based
Event-based
Typical Operating
<90ms >200ms >200ms
time
www.nrec.com 53
Comparison of Stability Controller & PMU
www.nrec.com 54
Fast Operation of PSCSTM
Fast Cascading
Oscillation
Collapse
Trigger
Event
PC EC CC RC
PSCSTM
www.nrec.com 55
Operating Time of PSCSTM
• Typical Operating Time within station <30ms
Master Station Table
<30ms
Table Table
X Table
Real-time Actions
Data
www.nrec.com 56
Operating Time of PSCSTM
• Typical Operating Time within Master and Slave <60ms
X <5ms
<60ms
Real-time Actions
Real-time Actions
Data Data
www.nrec.com 57
Operating Time of PSCSTM
• Typical Operating Time of Master Station + Slave Station
+ Execution Station) <90ms
X <5ms
<10ms <10ms
Slave Station Slave Station <90ms
<5ms <5ms
Real-time Real-time
Data Data Actions
www.nrec.com 58
Contents
3 Solution on PSCS
5 Case Study
www.nrec.com 59
PSCSTM Hierarchical Structure
On-line
Tactic
Data
Manage
Slave Station
✓ SDH or dedicated fiber
✓ Point-to-Point Fiber Slave Station
www.nrec.com 60
Functions of Regional PSCSTM
• Master Station:
- Seek in system-level control tactic tables
- Transmit data to Slave Stations & other Master Stations
- Distribute tactic tables to Slave Stations (If online)
• Sub-Master Station:
- Seek in region-level control tactic tables
- Transmit data to Execution Stations & Master Stations
- Acquire data and drive control outputs
• Slave Station:
- Seek in local-level control tactic tables
- Transmit data to Slave Station
- Acquire data and execute tripping or close commends
www.nrec.com 61
Functions of Regional PSCS
• Implement distributed tactic tables at different stations
• Refresh system monitoring data every 1.389ms/60Hz or
1.667ms/50Hz interval, 24 samples/cycle & data
exchange every 2 samples
• Support point-to-point optical communication between
substations
• Supervise remote control command by local detection
• Use internal clock for synch-timing
www.nrec.com 62
PSCS Stationary Structure
⚫ Stability Controller in Station
Current/Voltage
Binary Inputs
Binary Outputs
www.nrec.com 63
Stability Controller in Station
⚫ 1 MU and up to 6 SUs installed in substation or generation
⚫ Up to 108 current inputs, 108 voltage inputs, 150 binary
inputs, 216 binary outputs available in substation or
generation
RCS-992 Stability Controller
Up to 6 SUs can be
integrated
In one SU:
18 current inputs
Master Unit (MU)
18 voltage inputs
25 binary inputs
36 binary outputs
Slave Unit (SU) Slave Unit (SU) Slave Unit (SU) Slave Unit (SU)
www.nrec.com 64
Functions of Stability Controller
⚫ Functions of Master Unit:
- Receive data from local SUs
- Receive data from remote MUs
- Calculate and optimize power system control
scheme
- Discriminate system operation mode
- Send control commands to SUs
www.nrec.com 65
Communication of Controller
✓ Dedicated Fiber
✓ G.703 or C37.94 SDH
2M bit/s
Dedicated Fiber Remote MU
Current/Voltage
Binary Inputs
Binary Outputs
www.nrec.com 66
Communication to Control Center
Switch
PCS-9882
Interface
Substation Substation
Interface
Switch
PCS-9882
100M bit/s Network
G.703/C37.94
SDH Network
www.nrec.com 68
Supporting Software Package
……
EMS/SCADA
RCS-992 PSCSTM
www.nrec.com 69
RCS-9012 Stability Data Management
⚫ Monitor IEDs in PSCSTM & Manage stability data
www.nrec.com 70
NRSCP Power Stability Analysis
⚫ Power System Simulation & Stability Calculation
www.nrec.com 71
RCS-9009 On-Line Calculation of
Control Table
⚫ Update Control Table based on online data PSCS & EMS
www.nrec.com 72
Improve Adaptability of Control Table
Fast Cascading
Oscillation
Collapse
Slow Cascading
Tactic Table
calculated Valid Invalid
off-line
Table
www.nrec.com 73
Off-Line Calculation of Tactic
www.nrec.com 74
On-Line Calculation of Control Table
EMS
(SCADA)
SSC Other
www.nrec.com 75
Centralized PSCS with online data
Communication
S1 S2 S3 S4 S5 S5
Interface
Substations
后石电厂 Substation
厦门变电站 Substation Substation
福州变电站
Plant 1 3
Master Stations
RCS-992 1
RCS-992 2 RCS-992
Load Shedding
Exc1 Exc2 Exc3 Exc4 Exc5 Exc6
Executing Station
www.nrec.com 76
Cyber Security in Control Center
Calc Server
Calc Server Calc Server Calc Server Calc Server Calc Server
Steady State Voltage
Control Table N-1 Contingency Section Pwr Limit Preventive Control Off-line Analysis
Stability
Physical
Switch
Isolator
NET A
NET B
Firewall to
Lib Server external
Isolator
Control Table
LAN/WAN
Disc Array
Printer Maintenance WS HMI
Firewall to
EMS Firewall
Firewall WEB Server
Router
EMS
External
LAN/WAN
www.nrec.com 77
Contents
3 Solution on PSCS
5 Case Study
www.nrec.com 78
Typical Customer References
2000+ stability controllers in service worldwide
20+ Stations
Fujian Regional Grid Jun, 2004 500kV & 220 kV
On-line tactic (Dec, 2009)
Beijing-Tianjin Regional Grid Mar, 2006 20+ Stations 500kV & 200kV
Weak Network
Xinjiang Regional Grid Jun, 2006 80+ Stations
220kV & 110kV
www.nrec.com 79
PSCS in China Southern Grid (CSG)
5.8
534.3 532.0 127 530.8
+j4
大方电厂 黔西电厂 6.0 构皮滩
4.1
-j1 529.3
G:1200.0+j152.0 68.8
G:1200.0+j108.6
铜仁
47
G:1800.0+j297.7
L:72.0+j28.0 L:72.0+j28.0 528.1 L:30.0+j9.0
1125.8-j43.8
息烽
2247.2+j67.3 142.0-j1
177
523.5 54.3
6.6 G:3001.2+j77.6
福泉
0.0
+j3 533.6
17
534.1 三峡江陵换流站
+j5
6.1 鲤鱼江
94
66 松桃
6.1
.7+
529.7
j23
纳雍一厂 526.4 G:630.0+j194.8
.4
6.7 525.1
.5
526.3
贵阳 -j245 L:30.0+j16.0
01
G:900.0+j146.9 1074.8+j67.0 7-j9 .8 施秉
+j1
L:54.0+j21.0 371.
8.9
j54.4
533.4
59
535.9
522.2 桥口
3000.0+j0.0
355.6-
+j2
.9 醒狮 荷树园二期
129
529.1 531.0
3.9 G:1300.0+j252.1 G:540.0
9.5
535.1
六盘水 30 27 坪石 海门
-j1
54 522.2 08 L:60.0+j36.0 L:30.0+j16.0
61.5
0.4 .9-j G:500.0+j138.6
+j2 青岩 93 G:1000.0
-j18.5
.0 L:30.0+j20.0
3
8.2 L:120.0+j60.0
1838.7+j24.
524.5
161.7
62.6
529.0
392.1+j15.1 安顺 776.3-j 11 521.8 鹅城换流站
01
黎平
63.8
.2-j 520.8
纳雍二厂 23 470.0 S:-j1482.8
.2-j
G:900.0+j158.3 9.8 +j75.0 232.8
524.5
曲江
509
独山
23
L:54.0+j21.0
879.4-j110.1
20.5
90
S:+j322.2
.8+
2818.8-j100.4
.5-j
525.3 535.8
613.
嘉应
j18
412
安顺电厂 844.2+j
92.6 8+j4
271.7+j58.0
534.9
2.4
4.1 89
韩江
1481.6-j110.5
G:900.0+j211.0 5.3 24 530.6
-j1 64
L:54.0+j21.0 533.3 03 .9-j 上寨
.2
.6 524.0
发耳
456.6-j158
16 518.1 .5
1116 河池 5.1
桂林 -j332
G:1200.0+j155.9 .0-j S:+j406.5 512.9 42.5
13.2 518.0 8.0
L:84.0+j42.0 贤令山 花都 +j9
180
31.8-j361.9 525.2 78.1
2.3
854.9-j10 523.7 9.1 33.1-j84.8
539.5-j67.7
3.8
博罗
-j8
531.1 -j1 2524.0-j242.6
高坡换流站 05.5
3.9
525.3
盘南 534.1 1.5 2088.2-j270.2 535.3
16
528.0 520.9
董箐 S:-j1293.7 龙滩 +j7 柳东 09
.8 586.8 惠蓄 榕江
G:1200.0+j196.3 527.1 4.1 -j1
-j82.3 534.9
139 525.4 525.3 G:600.0+j105.9
L:84.0+j42.0 G:880.0-j11.5 八河 G:4900.0+j1235.5
80
6.0
广蓄A 广蓄B L:24.0+j16.0
S:+j141.0
汕头
157
L:24.0+j8.0 S:+j219.7 2041.3- 535.5
514.7
柘林
.7-j
j159.2 G:1080.0+j254.9 G:1080.0+j257.0
贺州
.6
223
70
L:48.0+j32.0 L:48.0+j32.0
1.6
8.2
1116 241 G:600.0
-j3
.7
.0+j 1.5
23
.2+j12
3.5
26.1 +j6 L:60.0+j30.0
.3-j
2021.6+j127.8
4.1
27
16 517.1+j18.5
65
3.3
1825
87 940.0-j125.1
12
.1-j
.2-j7
18
j47.7
2.1
533.2
1547.0+j131.8
531.1 6.7
531.1 茅湖
1391
0+j9
300
光照 1037.8+ 532.8
1161.0-
小湾 518.8 j0.8 528.2 0.0 522.7 红海湾
513.
1094.4-j55.3 +j0
G:2700.0+j616.4 和平换流站 G:1040.0+j129.0 兴仁换流站 537.1 .0 519.0
横沥
岩滩 521.4 梧州 515.9 G:1000.0
沙塘
S:+j265.8 1425.7-j176.6 罗洞 438.4-j196.0
517.1 L:60.0+j36.0
353.9+j56.7
2690.7-j72.3 G:1102.3+j136.5
增城 115
.7
81
52
531.7 544.8 L:24.0+j8.0 823.3-j119.2 3.2-j144 3.9 222.7
j717.0
-j37.3
-j5
小湾1 S:+j212.1
.0
.0 -j4
永丰 541.4
590.4 524.5
2-j271
5.7
1.7
516.0 99
宣威电厂 东莞
1354.9-j729.5
18
.6
48
G:1400.0+j300.0
2377.0+
218.4
0.7
1093.2+j19.9
.9-j
北郊
404.
22
1395
+j4
536.8 5000.0+j0.0
16
.0-j5
39
516.6
j26.9
5.5
534.1-j143.7
6.2 曲靖电厂
.5-j
穗东
8.0
530.8
165
91
.8
106
487.9+
523.0 0.0-j25 金州
.6+j1
527.1
.0
.3
210.3+j1
113.1 和平
5.0
j78
530.7 186.7 24.1 229.4
大理 816.4-j
+j1
1091
.5+
惠州
39.8
541.2 525.2
35.0
271.0-j434.6
52
525.0
多乐 肇庆换流站
-j1
20
218.5
0.0
砚都
13.6
531.9
-j4
84
182.5
天二
6.0
514.9
1.2
535.9
广州换流站 水乡
j1.7
.7
滇东
-j3
528.4 530.7
-j438
226.9 518.7
97
G:1294.1+j325.1
厂口 S:-j986.0 平海
764.2+
1971.1+j392.4
天二220 530.6 2818.8+j116.2
西江
.3
G:300.0+j15.5 535.8
.3
S:+j418.8
平果
44.3
雨汪 1773.0-j104.9 527.2
j30
531.3 L:30.0+j11.0 3000.0+
漫湾电厂 j0.0 鲲鹏
.9+
524.2 226.3
G:300.0+j16.7
来宾 838.8+j13.8
16
G:1300.0+j165.1 707.0-j416.6 158 116.7+j33.6 513.9
524.9 G:900.0+j135.1
32
L:30.0+j11.0 1351.2-j253.8
.9+ 隆林
169.3
草铺 536.8 莞城
37.3
402.1+j17.8
j79 L:60.0+j30.0
曲靖
.8
.5 S:+j406.7
532.4-j115.3
j74
257.1-j
513.6+j2
0.2
1670.6-j141 26
412.2-j50.3
4.8
.8+
溯河
66
4.8 沧江
269.
14.9
439.
-j9
524.0
j112.3
517.3
9.8
岭澳
90.8+j82.3
宝安
2368.3-j421.5
26
.9
500.0+j30.9
134.1+
522.8 G:1960.0+j322.7
42.3+j38
488.4-j12.5
533.8 贵港电厂
.0
L:70.0+j40.0
大朝山
-j0
528.4 j295.3
宝峰 1078.9-
-0.0
3.2
1281.9-j274.4 534.6 14.1
百色
-j232.1
363.3+j38.9
.9+j36
233.5
罗平
119.8
1309.4
528. 525.6 0.0
2400
1334.7-j219.8 529.0 S:+j622.2 533.4
8-j5
合山新厂 .0+j
233.5 永安
232.3-j
9.8 1352 1800 423.6
1364.9-j210.0
230.7
七甸 鲁布革 534.
.5-j2.
4 523.9 222.9
G:600.0+j160.9 1+j4 9.5 523.8
-j7 521.9 526.7
广南 517.3
顺德
23.7
S:+j138.1 2.7
530.3 27
0.7 1344 518.3 茂名 蝶岭 2914.3-j450.9 84.7-j79.6 916.3-j142.6 374.1+j253.5 深圳 426.0
527.3 .9+j76 玉林 1826.5-j40.1 1449.1+j12.2
.7-j2
德宏 玉溪 -j117
.8 533.3 .4 525.9
122.0 大亚湾
1076
228.6 马窝 526.9
1691.3-j18.7 2469.3-j277.4 1950.2-j284.2 524.2 521.9 522.0
957.1-j160.8 481.7+j45.6
天一 S:+j111.4
南宁 五邑 江门 沙角C
226.7 G:1960.0+j315.8
216.0-j334.2
564.0-j62.1
3.6
1743.5-j150.8
517.5
.7
G:1200.0+j547.1 1200.0+j376.3 L:70.0+j40.0
.2
1-j192
鹏城
.4-j36
17 227.5 G:2340.0+j260.8
81
52 528.5
-j1
红河
873.7+j91.2
.3
2.7
526.5
1494
868.
83.9-j104.8
33 马窝换流站 526.4
.5
港城
.5+
54
93
5.0 3094.2-j212.7 S:+j634.3 230.7
桂山
53.8
-j2
55
3-j2 525.1
6.9
10
1465 S:-j704.2
699.6-j4.1
921. 香山
11
.2-j40 528.2
1726.4-j253.7 3150.2-j549.3 建水串补 0.0
0.1+j8.2
3.7
533.4 527.2
-j6
8.1 阳西 1093.5-j235.7 522.1
454.4-j26.6
博尚 墨江 G:600.0+j14.6 沙角B
378.4-j190.4
529.8 529.9
久隆 422.9
35
4.7
L:36.0+j10.8 423.0
邕州 G:393.7+j126.0
大埔
1.2
元朗
0-j7
0.2-j374.5 0.1-j360.4
4.5
532.2 526.7
2.1
2
175.8+j28.9
L:30.0+j14.0
-j1
101.
奥里油
+j1
南岭 L:472.0+j74.0
-j11
267.
03
L:432.0-j12.0
575.0-j12.0
1596.5+j9.5
5.6
536.7 .0
.9
514.6
.9-j
527.4
-j5
9.0
砚山
27
崇左 5.8 国安
1108
167
60
S:+j199.6 532.1
539.7+j52.9
533.3 528.7
大盈江 通宝 531.3 林诗岛
G:700.0+j66.2 海港
.5
531.8 529.9
95
529.5
景洪 巡检司
.0-j
530.8
小龙潭 钦州
00
G:1750.0+j81.9 G:300.0+j50.2
12
531.4
L:24.0+j10.0 G:200.0+j49.6 G:1200.0+j205.4
防城港 529.5
L:24.0+j10.0 L:55.0+j6.0 福山 526.6
铜鼓B厂
528.7
G:1200.0+j53.0 珠海B厂
G:1200.0+j41.0 G:600.0+j120.0 潮流图 (单位: kV、MW、MVar)
L:90.0+j54.0 L:60.0+j36.0
Power Direction
www.nrec.com 81
Transferred Energy
pingguo
TSQ2
laibin wuzhou
pingguo GD
TSQ luodong ZONE
1800 MW
luoping zhaoqing
YN
Converter
zone baise
lbg tsq1 station
nanning jiangmen
yulin
maoming
www.nrec.com 82
Stability Controller in MM Station
MM Station Luodong Station
G.703 SDH
2M bit/s Fiber
www.nrec.com 84
Stability Control Example
• Example:
- 8th May, 2006 ,Blocking of GAOP-ZHAOQ HVDC line (3000MW)
• If no PSCS
- Power will be transferred to 500kV HVAC lines
- Cause oscillation of GZ & GD & under frequency in GD
Three-Gorge-DC
QINGY HECHI
AN
ANSH X LONGT3000 MW LIUD
GAO
PANNAN
UN HEZ
PU GZ-DC
YANT
SHA
T
XREN WUZ
TIANER LAIB LUO
D BHD
GD
MAWO
YN
XIJIAN
LPING ZHAOQ G
YIFENG
LBG TIANYI BAISHE JIANGM
NANNING YUL
MAOM
AOLY GANGC www.nrec.com 85
Stability Control Example
• PSCS:
- Generation tripping in GZ Jinbei power plant & Pannan power plant
- Load shedding in GD load center, Successful prevent instability
- Responding time: 78ms
Three-Gorge-DC
QINGYAN
HECHI
LIUD
ANSHUN
LONGT
GAOPU 3000 MW
PANNAN
X HEZ
XREN
WUZ LUOD GD
TIANER LAIB
BHD
MAWO
YN
XIJIANG
LPING
ZHAOQ
YIFENG
NANNING YUL
MAOM
AOLY GANGC www.nrec.com 86
PSCS in CSG
• NR PSCS Solution
- Master Stations
- Slave Stations
- Execution Stations
- On-line Calculation of Tactic
- Three Defense Lines for Power Stability
• Largest PSCS in the World
www.nrec.com 87
Case 2: Xinjiang Power Grid
• Power network in Xinjiang
Transmission voltage level: 220kV
Distance : >=3000km
Install generation
capability : 8500 MW
www.nrec.com 88
Xinjiang Power Grid Development
⚫ Small-scale power grid stage(1949-1988)
Before 1988, 14 local independent power grids were respectively
developed, operation economy was also very poor.
www.nrec.com 89
Stability Challenge in Development
⚫ Stability problem becomes challenging due to the
increasing power transfer
⚫ The construction of PSCS began in 2007 and completed
in June 2008.
www.nrec.com 90
Capacity of Xinjiang PSCS
• Configuration
- 75 Control Stations installed in different substations and power
plants
- 1 management workstation installed in load dispatch center
• Communication channel
- Optical cable
- Power line carrier
• Sub Systems
- Southern XINJIANG Power stability control system
- Northern XINJIANG Power stability control system
- Eastern XINJIANG Power stability control system
www.nrec.com 91
Grid of South Xinjiang
Northern
Grid
KASHI
AKESU1 KUCHE 192km
P
P
172km 217km
BAZHOU
229km
KUCHE
HETIAN
www.nrec.com 92
Stability Problems
• Transient instability
Generators in KUCHE are the key support of the Southern XJ
grid, if one generator shutdowns, the voltage will drop quickly
and the angle between the Southern grid and Northern grid
will become out of step.
• Slow voltage instability
If the loads of Southern grid increase, the voltage of the
Southern grid will decay slowly. When the power flow of tie-
line exceeds the acceptance level, the voltage collapse will
happen
• Frequency instability
If the tie-line or tie-transformer trips in some condition,
Frequency collapse will happen in some areas
www.nrec.com 93
Solutions to Stability Problems
⚫ Control method for various stability problems
- Design control strategies for diverse operation scenarios
⚫ Workflow:
- Step by Step: South system->East system->North system
- Both the equipment supplier and the owner took part in the
research.
- Combined simulation with experience
www.nrec.com 94
Solutions to Stability Problems
Main grid
URUMQI
KASHI
KELB
AKESU1 AKESU2
BAZHOU
KSB
AKSB QCB
KUCHE
HETIAN
www.nrec.com 95
Solutions to Stability Problems
• Solve stability problems from generator trip in KUCHE
plant
If the PSCS detects that the generator in KUCHE plant is tripped,
accompanying with the under-voltage, PSCS will shed some
loads in AKESU, KASHI and BAZHOU.
Main grid
URUMQI
KASHI
KELB
AKESU1 AKESU2
BAZHOU
KSB
AKSB QCB
HETIAN KUCHE
Detect the fault,
calculate the amount of
load should be sheded
www.nrec.com 97
Real Records in Xinjiang PSCS
• 1# generator shut down, 2008.08.17
The voltage of post-fault was below 209kV, PSCS sheded 80MW
load, the voltage recovered to 225kV, the system maintained stability.
www.nrec.com 98
Economic Benefits in Xinjiang PSCS
⚫ South power system: The capacity of power transmission
is increased to 280MW, the power transmission capacity
is doubled.
⚫ East power system: The capacity of power transmission is
increased to 330MW, which is enhanced 1.3 million than
before.
⚫ North power system: The capacity of power transmission
is increased to 490MW, which is enhanced 100MW than
before.
⚫ Economic benefit exceeds $30 million per year.
www.nrec.com 99
Case 3: Ecuador
www.nrec.com 100
Power Network in Ecuador
• Voltage level 230kV (ring network), 138kV & 69kV
www.nrec.com 101
Power Network in Ecuador
• Ring network of 230kV transmission system
www.nrec.com 102
Challenges in Ecuadorian Power System
• Some of 230 kV transmission lines in operations with
heavy loads
• More heavy-load lines when power transfers from
Colombia to Ecuador reduced
• Double contingencies may cause total or partial collapses
of Ecuadorian Power System
- Angle Instability
- Voltage Instability
www.nrec.com 103
Power Stability Control System in Ecuador
• Redundant
Stability
Controllers in
Substations
• Redundant
Control
Centers
• Optical Fiber
Communicati
ons between
stations
www.nrec.com 104
System Structure
www.nrec.com 105
Redundant Design
www.nrec.com 106
PSCS Functions
• N-2 contingencies considered, PSCS detects the
abnormal conditions and executes predefined
mitigation actions.
Ref Contingency, 230 kV ring Type of Problem Type of Solution
Generation to trip MW
Load to trip
MW (up to)
SPS (Event based) (up to)
Gen trip Load trip
(+) Polynomial based with multiple (+) Over 500 of
1 1)Angular instability with Colombia 2) Overload, 3) solutions based on measurements. Polyno Over 350 MW in
Santa Rosa-Totoras double generation in three
Low voltages mi al different load
contingency. different sites
based centers
Angular instability with Colombia, particularly (+)
2 Santo Domingo- Santa when the generation plants in San Francisco and Step wise, armed with Over 150 MW in a Over 150 MW in
(+)
Rosa double contingency Agoyan are out of service. 2)Low voltages flows higher than 110 in generation site different load
Sto Domingo – Sta. Rosa centers
(+)
3 Santo Domingo - Quevedo Angular instability with Colombia Step wise, armed with (+) Over 100 MW in a Over 50 MW in
and Quevedo Baba flows higher than 100 MW Quevedo to generation site different load
contingency. Santo Domingo centers
Angular instability with Colombia, particularly (+) Step wise, armed with flows
4 higher than 165 in Quevedo Over 100 MW in a Over 50 MW in
Quevedo –Pascuales when the generation plants in San Francisco and (+)
Pascuales generation site different load
double contingency. Agoyan are out of service. 2)Low voltages
centers
(+)
5 Totoras-Molino and Molino - Angular instability with Colombia Over 100 MW in a Over 50 MW in
Step wise, armed with flows higher
Rio Bamba contingency. than 290 in generation site different load
Totoras Molino- Molino centers
Riobamba
www.nrec.com 107
Scope of Supply
• Central Management Software
• Disturbance Management Sofware
• Network Management Software
• 14 Data Servers
• 5 Workstations
• 2 Routers
• 2 Firewalls
• 58 PCS-992M Central Units
• 66 PCS-992S Bay Units
• 27 PCS-9785 GPS Receiver
• 60 PCS-9882 Switch
• 25 Help9000 Tester
• 4 PCS-931 Current Differential Relay
www.nrec.com 108
Operation Time Design
• All actions can be completed in 170ms
(Including breaker time)
Fault inception 0
Relay operating time (not part of SPS
scope of supply)
40 ms 40 ms
www.nrec.com 109
Example : Solution for Anger
Instability
Scenario 1: Angle Instability
Objective of PSCS:
• Deaccelerate machines
• Maintain balance between generations and loads
• Reduce power transfers
www.nrec.com 110
Example: Solution for Voltage
Instability
Scenario 2: Voltage Instability
Objective of PSCS:
www.nrec.com 111
Conclusion
⚫ Design philosophy is well and systematically designed
⚫ Logic and system is tested and verified by the site with abundant
project experience
www.nrec.com 112
Thanks.
www.nrec.com
Version 2017
Copyright 2017 All Copyrights Reserved by NR Electric Co., Ltd.