LIST OF CHECKLISTS

SL. NO. CHECKLIST NO. CHECKLIST FOR NO. OF SHEETS


1 EW - CL - 01 Earthworks ( Site Clearance ) 1
2 EW - CL - 02 Earthworks ( Excavation in Cut ) 1
3 EW - CL - 03 Earthworks ( Replacement For Unisuitable Material ) 1
4 EW - CL - 04 Earthworks ( Filling of Pond ) 1
5 EW - CL - 05 Earthworks ( Filling For Embankment ) 1
6 EW - CL - 06 Earthworks ( Approval for Embankment Fill ) 1
7 EW - CL - 07 Earthworks ( Final Trimming To Formation Level ) 1
8 PC - CL - 08 Subbases / Bases ( Non-Bituminous ) Laying 1
9 PC - CL - 09 DLC Laying 1
10 PC - CL - 10 Pavement Quality Control 3
11 PC - CL - 11 Wet Mix Macadam ( WMM ) Laying 1
12 PC - CL - 12 Prime Coating / Tack coating 1
13 PC - CL - 13 - 1 Bituminous Course ( Pre - Laying ) 2
14 PC - CL - 13 - 2 Bituminous Course ( Post Laying ) 1
15 PC - CL - 14 - I Mastic Asphalt ( Pre - Laying ) 1
16 PC - CL - 14 - 2 Mastic Asphalt Laying ( Post - Laying ) 1
17 RW - CL - 15 Construction of Toe Wall 1
18 RW - CL - 16 Brick Masonery Work 1
19 RW- CL - 17 Kerb Casting Work 1
20 RW- CL - 18 Guardrail Works 1
21 RW- CL - 19 Kilometer Stone 1
22 RW- CL - 20 Road line Marking 1
23 RW- CL - 21 Kerb Painting 1
24 RW- CL - 22 Signboard Installation 1
25 SW - CL- 23 RCC Works ( Before Placing Of Concrete ) 1
26 SW - CL- 24 RCC Works ( After Placing Of Concrete / striking of Formworks ) 1
27 SW - CL - 25 Pre-cast Concrete Work 1
28 SW - CL - 26 RC Pipe Culvert 1
29 SW - CL - 27 Construction Of Precast Box Culvert 1
30 SW - CL - 28 Pilling Works ( Displacement Pile ) 1
31 SW - CL - 29 Pilling Works ( Bored Pile ) 1
32 SW - CL - 30 Post- Tensioned Concrete Works ( Before Casting) 1
33 SW - CL - 31 Post- Tensioned Concrete Works ( After Casting) 1
34 SW - CL - 32 PSC Girder (Before Concreting) 2
35 SW - CL - 33 Prestressing of Girder 1
36 SW - CL - 34 Grouting Record 1
37 SW - CL - 35 Fabrication of steel Girders (before drilling of holes) 2
38 SW - CL - 36 Fabrication of steel Girders (after drilling of holes) 1
39 SW - CL - 37 Fabrication of Steel Girder ( Before painting and assembling at site ) 1
40 SW - CL - 38 Fabrication of Steel Girder ( After painting and assembling at site ) 1
41 SW - CL - 39 Box Girder (Before Placing of Concrete) 1
42 SW - CL - 40 Box Girder (Cable Layout) 1
43 SW - CL - 41 Random Checking of RE Wall Panel 1
44 SW - CL - 42 R.E Wall Installation 1
45 SW - CL - 43 Load Test 1
46 MW - CL - 44 Dismantling Of Structure / Pavements 1
47 MW - CL - 45 Street Lighting 1
48 MW - CL - 46 Watermains Relocations 1
49 MW - CL - 47 Electrical Services Relocations 1
50 MW - CL - 48 Material & Batching Plant (RCC work) 2
51 MMI - CL - 49 Identification of Source for Manufactured Material 1
52 MMT - CL - 50 Inspection & Testing of Source for Manufactured Material 1
53 MMP - CL - 51 Procurement of Manufactured Material 1