Sei sulla pagina 1di 1

ID ID Task Task Name Duration Start Finish Predecessors

Resource Names Overtime


Mode Work
August 2019 September 2019 October 2019 November 2019
10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13
1 1 0 hrs
CTS19019168
2 2 Chhengngoun 0 hrs

3 3 1st Floor 5 days Fri 8/16/19 Thu 8/22/19 0 hrs


4 4 Clumn Shop Drawing 5 days Fri 8/16/19 Thu 8/22/19 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

5 5 2 nd Floor 5 days Mon 8/26/19 Fri 8/30/19 0 hrs


6 6 Column Shop Drawing 5 days Mon 8/26/19 Fri 8/30/19 4 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

7 7 3rd Floor 5 days Mon 9/2/19 Fri 9/6/19 0 hrs


8 8 Column Shop Drawing 5 days Mon 9/2/19 Fri 9/6/19 6 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

9 9 4th Floor 5 days Mon 9/9/19 Fri 9/13/19 0 hrs


10 10 Column Shop Drawing 5 days Mon 9/9/19 Fri 9/13/19 8 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

11 11 5th Floor 5 days Mon 9/16/19 Fri 9/20/19 0 hrs


12 12 Column Shop Drawing 5 days Mon 9/16/19 Fri 9/20/19 10 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

13 13 6th Floor 5 days Mon 9/23/19 Fri 9/27/19 0 hrs


14 14 Column Shop Drawing 5 days Mon 9/23/19 Fri 9/27/19 12 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

15 15 7th Floor 5 days Mon 9/30/19 Fri 10/4/19 0 hrs


16 16 Column Shop Drawing 5 days Mon 9/30/19 Fri 10/4/19 14 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

17 17 8th Floor 32 days Thu 8/29/19 Fri 10/11/19 0 hrs


18 18 Column Shop Drawing 5 days Mon 10/7/19 Fri 10/11/19 16 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

19 19 0 hrs
CTS19019168
20 20 Phase1: Structural Pile and Pile 4.13 days Thu 8/29/19 Wed 9/4/19 0 hrs
Cap Design

21 21 Pile Reaction 0.13 days Thu 8/29/19 Thu 8/29/19 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

22 22 Modeling ( Midas GEN) 3 days Thu 8/29/19 Tue 9/3/19 21 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

23 23 Pile Verify 2 days Thu 8/29/19 Mon 9/2/19 21 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

24 24 Pile Cap verify 2 days Mon 9/2/19 Wed 9/4/19 23 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

25 25 Phase2: Structural Beam and 6 days Wed 9/4/19 Thu 9/12/19 0 hrs
Ground Slab Design

26 26 Ground Beam verify 2 days Wed 9/4/19 Fri 9/6/19 24 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

27 27 Ground Slab verify 4 days Fri 9/6/19 Thu 9/12/19 26 Mr.Chhengnguon 0 hrs Mr.Chhengnguon

Task Project Summary Manual Task Start-only Deadline

Project: Rithea Split Inactive Task Duration-only Finish-only Progress


Date: Wed 8/28/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1

Potrebbero piacerti anche