Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Case 16-F-0328
May 2018
1 Project Information
Number Three Wind LLC (NTW) proposes installation of the Number Three Wind Farm (the Project) in
Lewis County, New York. The Project will consist of up to 43 wind turbine generators (WTG) and
associated improvements, including buried electric cables, pad-mount transformers, access roads, an
electrical substation, overhead electric lines, permanent meteorological towers, and an operations and
maintenance building.
2 Introduction
This plan will apply to work, inspections, and testing activities performed under the terms of the BOP
contracts, including work performed by subcontractors, fabricators, and suppliers. It includes control
measures for verifying the quality of equipment and materials, processing submittals, monitoring
construction activities and testing.
During construction, NTW will have a Construction Site Manager and assistant on-site. They will work
with a Chicago-based project manager to oversee daily construction activities and ensure the BOP
contractors construct the Project in accordance with the terms of the BOP contracts and industry
1
standards, including implementation of the QA/QC Plan. NTW’s Construction Site Manager will have at
least five years of experience with construction of heavy industry and commercial power generation
projects. Each BOP Contractor will also have a designated site manager on-site daily during the period
when that contractor is providing services.
3 Quality Control
The Project Manager (PM) shall serve as the single point of contact for coordination with the Project. As
the chief contract representative, the PM technically and administratively manages the contract and has
authority and is responsible for the following activities:
• Issue and authorize, in conjunction with the Quality Assurance Manager, stop-work orders when
necessary
• Ensure that relevant portions of the work plan are implemented through audits and observations
of project activities.
• Interface directly with the owner to maintain an awareness in planning and scheduling processes
The Vice President of Environmental, Safety, and Quality (ESQ) will ensure the necessary independence
required for unbiased and objective assessments. The responsibilities of the Vice President of
Environmental, Safety, and Quality or designee include the following activities:
• Review and approve the project-specific QA/QC Plan and subsequent revisions
2
• Periodically evaluate the effectiveness of the project-specific QA/QC Plan through observations,
audits, or independent assessments
The Site Quality Assurance Manager (QAM), responsibilities include, but are not limited to, the following:
• Establish a document management system for project quality records that ensures detail,
accessibility, and ensure document security.
• Ensure instruments, tools, and testing equipment that require calibrations are current and
documented.
• Issue Non-Conformance Reports (NCR), review, and verify corrective actions as defined in
section 6
The PM or designee is responsible for the preparation and maintenance of the required project
submittals. Submittals will be listed in the project submittal log. The date of submittal distribution and
approval will be recorded in the submittal log. The log will be updated and distributed periodically by the
PM or designee.
3
5 Procedures for Inspections and Acceptance Testing
5.1 General
Procedures contained in this QA/QC Plan define requirements for planning and performing quality control
activities for each definable feature of work. The procedures establish control of inspections and tests.
Implementation of the three phase inspection process (preparatory, initial, follow-up) allows for the PM
and QAM to plan work to ensure that actions have been completed, work is understood by project
personnel, submittal obligations are fulfilled and required materials and test equipment are available. The
three phase inspections will be performed for each definable feature of work. To ensure compliance with
technical specifications and contract requirements specific activities associated with the work may warrant
additional inspection or testing. Inspection and testing shall be performed as necessary to ensure the
appropriate level of project quality.
• Environmental Controls
• Road Construction
• WTG Foundations
• WTG Erection
• Collection System
4
• Reviewing of required control inspections and test requirements
• Verifying previous hold points required to begin the feature of work a complete and conforms to
approved drawings and submittal data
• Verifying that the required materials and equipment for commencement of the work are on hand
or available for use on the feature of work and that equipment is properly calibrated and in proper
working condition
• Establishing acceptable levels of workmanship required to meet contract requirements for the
definable features of work
The preparatory inspection meeting results will be documented by the QAM using a preparatory
inspection checklist. Additional inspections will be conducted if the project staff change, if problems
develop, or if work resumes after a substantial stoppage.
The initial inspections will include the participation of the QAM, Construction Manager, Foreman,
responsible construction and testing personnel, and any applicable subcontractor involved with the work.
The initial inspection results will be documented by the QAM using the initial inspection checklist.
Additional inspections will be conducted if the project staff change, if problems develop, or if work
resumes after a substantial stoppage.
5
currently certified/calibrated, maintained, and used in accordance with specifications and applicable
standards. The certified/accredited testing results generated by the laboratory will be used by the BOP
contractors to verify compliance. Performance and results of acceptance tests will be continuously
monitored and reviewed by the Construction Manager, QAM, and PMs. Nonconforming materials or
conditions shall be immediately addressed.
6 Job Books
6.1 General
The QAM shall review the contract, specifications, and drawings to identify the required documentation
and develop an organizational system for maintaining such documentation. Hard copy documentation
including material certifications, receiving inspections, inspection checklists, and test reports shall be
maintained continuously throughout the duration of the project. The QAM or designee shall be
responsible for reviewing and maintaining test reports, certifications, inspection reports and other
documentation throughout the duration of the project. Documentation will be continuously populated in
the job books, which will be available digitally to authorized persons.
7.1 General
Quality control is the primary responsibility of those performing the work and not the sole domain of a
single quality control group or person. Anyone can and should report non-conforming components,
materials, or conditions to the QAM. Early identification of components, materials, or conditions not
conforming to the specifications or contract requirements may not require official disposition but will be
reported to the QAM. Any non-conformance discovered during inspection or testing shall be reported to
the QAM. Best practice will dictate if conditions necessitate a Non-Conformance Report (NCR).
If the non-conformance is severe or the approved corrective action will cause a schedule impact or design
change PM will notify the owner in accordance with the contract. The NCR will remain open until the
nonconforming condition has been resolved and verified by QAM, or designated person. The QAM will
maintain a NCR log including date created, brief description of the condition, level of severity, and date
closed.