6.0 Acceptance
Items RAP Delivery Date Status
Lightning Arrester 3
Hotline Clamp 3
PVC solvent 6
Steel Pole 25 ft. 1 ordered
Cross Arms 3 1/2" x 4 1/2" x 8' 1
Metal flat brace 28" 2
Transformer Pad 1
Anchor Bolts 4
Grounding Rod 1
1/2" x 6" Machine Bolt - 2 with square nut and 5
lock
5/8" washer
x 12" Machine Bolt - 2 with square nut and 5
lock washer
Double Arming Bolt 5/8" x 22" with square nut 3 delivered
and lock washer
1 3/8" diameter 9/16" Hole Round Washer -1 10
2 1/4" x 2 1/4" x 11/16" Square Washer - 1 10
Pole Clamp 3
Cable tie 1 delivered
PVC Electrical Tape Red 2
PVC Electrical Tape Blue 2
PVC Electrical Tape Yellow 2
PVC Electrical Tape Black 2
Rubber Tape 2
50mm2, Bare Copper (Grounding) 39
Hualy Nick Status revision
1) To set-up Transformer Pad ( variation)
ok
3) Control Cables- from Gen Set to control room ( as per site inspection
consolidated with Jomalig & Patnanungan, delivery to Minuyan) ok
Scope of Work:
1) To set-up Transformer Pad ( variation)
Nick
9) Budget Coordination
Mae
Materials: Qnty
Transformer 200 kVA 1
1/0 AWG ACSR Power Conductor 34
14C-Instrumentation Cable 44
3C-Instrumentation Cable 44
50mm2, terminal lugs 3
Ground connector, 50mm2 8
Fuse Cut-out 15kV 3
Fuse Link 10A 3
Lightning Arrester 3
Hotline Clamp 3
PVC solvent 6
Steel Pole 25 ft. 1
Cross Arms 3 1/2" x 4 1/2" x 8' 1
Metal flat brace 28" 2
Transformer Pad 1
Anchor Bolts 4
Grounding Rod 1
1/2" x 6" Machine Bolt - 2 with square nut and lock washer 5
5/8" x 12" Machine Bolt - 2 with square nut and lock washer 5
Double Arming Bolt 5/8" x 22" with square nut and lock washer 3
1 3/8" diameter 9/16" Hole Round Washer -1 10
2 1/4" x 2 1/4" x 11/16" Square Washer - 1 10
Prepared by:(Project Engr:)_________________Date:______ Checked by:(Project Ma
________________
SE ONLY
ng approval)
_Date:________ Approved by: (CTO: Joseph):