WCC PROCESS BUILDING - QUANTITY ESTIMATE

TOP BOTTOM
SL No ITEM DESCRIPTION NO D QTY/each TOTAL QTY REF. DWG NO.
L B L1 B1
1 FOUNDATION FOOTING CONCRETE
a PF1 7 2.90 2.90 1.50 1.50 0.70 3.73 26.12 cu.m. 17-AR-00-APE-203
b PF1A 2 2.20 2.20 1.50 1.50 0.70 2.48 4.96 cu.m. 17-AR-00-APE-203
c PF3 2 4.40 4.40 3.00 3.00 0.70 9.93 19.85 cu.m. 17-AR-00-APE-203
d PF4 4 4.40 4.40 3.00 3.00 0.70 9.93 39.70 cu.m. 17-AR-00-APE-203
e PF4A 1 3.00 3.00 3.00 3.00 1.00 9.00 9.00 cu.m. 17-AR-00-APE-204
f PF4B 1 4.40 5.90 3.00 4.50 0.70 13.81 13.81 cu.m. 17-AR-00-APE-204
g PF5 1 5.50 5.50 3.70 3.70 0.90 19.77 19.77 cu.m. 17-AR-00-APE-204
h PF5A 1 3.70 3.70 3.70 3.70 1.20 16.43 16.43 cu.m. 17-AR-00-APE-205
i PF5B 1 3.70 3.70 3.70 3.70 1.20 16.43 16.43 cu.m. 17-AR-00-APE-205
j F1 2 1.50 1.50 1.50 1.50 0.50 1.13 2.25 cu.m. 17-AR-00-APE-205
k MF1 1 5.05 4.90 5.05 4.90 1.00 24.75 24.75 cu.m. 17-AR-00-APE-207
3 sides wall upto slab bottom 10.50 0.30 10.50 0.30 1.70
Vertical wall b/w MF1 and MF2 1 0.75 4.90 0.75 4.90 0.70 7.93 7.93 cu.m.
l MF2(including slab thickness) 10.75 6.30 10.05 4.90 0.70 17-AR-00-APE-207
1 10.75 6.30 10.75 6.30 0.30 61.26 61.26 cu.m.
m XLPE KNEADER, 17-EX-2201 6.01 1.65 6.01 1.65 1.57 17-AR-00-APE-222
1 5.95 3.70 5.95 3.70 1.57 50.13 50.13 cu.m.
n SC KNEADER, 17-EX-2201 4.53 1.52 4.53 1.52 1.57 17-AR-00-APE-223
2.97 3.25 2.97 3.25 1.57
1 2.61 1.75 2.61 1.75 1.57 33.08 33.08 cu.m.
o Emergency Generator Fondtn. 1 4.60 2.20 4.60 2.20 1.62 16.39 16.39 cu.m. 17-AR-00-APE-224
p WF1 1 163.20 2.70 166.00 2.00 0.70 270.42 270.42 cu.m. 17-AR-00-APE-206
q WF2 31.30 2.90 31.30 1.50 0.70 17-AR-00-APE-206
17.75 2.90 17.75 1.50 0.70
1 3.55 2.90 3.55 1.50 0.70 81.00 81.00 cu.m.
r WF3 6.80 1.50 6.50 0.80 0.70 17-AR-00-APE-206
1 5.80 1.50 5.80 0.80 0.70 10.06 10.06 cu.m.
TOTAL QANTITY 723.35 cu.m.