BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Etisalat Afghanistan-Huawei Swap Project


Standard Operation Procedure

(SOP of BTS3900A)

V3.0
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Overview
BTS3900A Swap Process

BTS3900A is Huawei 4th Generation BTS and it will be deployed in most of the
future projects. The intension of writing this document is to improve the efficiency of
the delivery service and to setup clear standard procedures. The standardization will
help Huawei co-operators and partners to work independently, yet produce improved delivery
in terms of quality as well as time.
1 - This document intends to standardize the BTS3900A installation process and provides
installation steps for 4 team members.
2 - The swap process is explained with reference to the cold BTS Swap and it is
illustrated that how to complete the swap with minimum service interruption.
Release record

Issue No Prepared By Reviewed By Date

V1.0 WangDi Qulei 2009.11.11

V2.0 WangDi Qulei 2009.11.28

V3 .0 WangDi 2009.12.22
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Before Swap

Issue the Swap Cutover plan and Change Request 72 Hours before
Swap Notice Huawei
to Etisalat Swap
Testing of A interface plan including the CIC testing
72 Hours before
Media implementation Testing of GB interface Huawei/Etisalat
Swap
Testing of Ater interface
Huawei will provide the Contact list of the Engineers
Huawei 72 Hours before
working on each site, BSC , M2000, DT teams & DT Huawei
Swap Nominations Swap
routes
Nominate Engineer for NBR Relations definition on
MSC
Nominate Engineer for MSC cell data configuration
Etisalat Swap 48 Hours before
Nominate Engineer for transmission support in BSC Etisalat
Nominations swap
room
Nominate Engineer for On-site support (Technical,
Power related issues, Access)
48 Hours before
Work Order Approval Approve Work Order Etisalat
Swap
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

During Swap

All Sites are outdoor sites & have not enough space on the BTS Pad to install the
Huawei BTS there in parallel with existing BTS working there. So this kind of swap falls in
HOT swap (first dismantle existing BTS & Power system & then install Huawei BTS &
power system). For this kind of swap where we have single band BTS the outage window
required is 4.5-5hours for the BTS Cabinet & Power System Swap. Details of the Activities
are as follows

Single Band BTS Swap

Outage time:5 hours

Action Activity Description Responsibility Time

Block the Existing DDF port using DDF breaker

Confirm from OMCR the site ID


Existing NEC IDU Abis E1
Huawei BTS Team 20:30-21:20
check Label the E1 if there is no label or information
incorrect

Continue testing the rest E1s

Record the existing BTS status and equipment serial


Existing BTS asset check Huawei BTS Team 21:00-21:20
number
Inform OMCR about the swap Activity & inform them
Inform OMCR Huawei BTS Team 21:30-21:40
to block the site
Huawei OMCR record the existing BTS alarm and Huawei OMCR
Existing BTS OMCR Check 21:20-21:40
traffic Team/Etisalat OMCR
Etisalat OMCR will Block the site Etisalat OMCR 21:40-21:50
OMCR Block the ZTE BTS
Note: If Existing BTS is not locked at 21:50, then do not power OFF, deadline 22:10

Disconnect the Abis E1 in BSC room and Etisalat Team/ Huawei


Transmission Loop Test to connect to Huawei BSC DDF Team
BSC Test the Transmission loop back test from BTS site
21:50-22:00
to the Huawei BSC
22:00-22:10
(Service interruption
Power off existing BTS Power OFF Existing BTS Site Huawei BTS Team
Starts for Swap
Activity)
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Dismantle the exiting BTS & power equipment. For


Dismantle ZTE BTS &
detailed process please refer to the Dismantling Huawei/Etisalat 22:10-23:20
Power equipment
SOP.
Install Huawei BTS Huawei Team will install the BTS & APM30, BBC Huawei BTS team 23:20-00-10
Shift the MW IDU to the Huawei APM30 Cabinet
Shift MW IDU
Make OT terminals for NEC power cable Huawei BTS team 00:10-00:40
Huawei will connect the PGND cables with Huawei
PGND Cables Huawei BTS team 00:40-00:50
equipment through the existing BUS bar installed.
Huawei team will connect the APM30 power cables
Connect the AC power
to ACDB (32A is the first option, otherwise use the Huawei BTS team 00:50-01:00
Cables
existing BTS AC breaker)
Connect the DC Power Huawei team will lay & connect the DC power cable
Huawei BTS team 01:00-01:10
Cables between BBC & APM30

Connect the feeder cable Connect new feeder jumper cable to HUAWEI BTS,
Huawei BTS team 01:10-01:40
Jumpers and connect the feeder jumper to existing feeder.

Power test Test the external input AC power Huawei

Connect the Power cables of IDU Huawei

Power on the IDU Huawei

Report the result to BSC Connect the E1 cable to UELP board. Huawei 01:40-02:00
engineer Power on BTS fan Huawei
Power on BBU frame, check the BBU board is
working normally or not and make sure the Huawei
transmission is ok according to the LIU status
Power on the DRFU board after the corresponding
Power on the Complete BTS Huawei BTS team 02:00-02:10
feeder jumpers are properly connected.
Software Upgrade Download the software Huawei BTS team 02:10-02:30
Check the indicators of GTMU
RUN: Slow flash (1 s on, 1 s off)
ALM:OFF
Huawei
ACT: ON
LIU(0-3):OFF
CPRI(0~5):ON(Green)
BTS Status Confirmation Check the indicators of DRFU: 02:30-02:40
RUN: Slow flash (1 s on, 1 s off)
ACT: ON
ALM: OFF Huawei
VSWR: OFF
CPRI0:ON(Green)
CPRI1:ON(Green)

Basic service test Call test Huawei 02:40-03:00(Service


Restored)
Deadline:04:00 SMS test Huawei
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

External Alarm SWAP


Deadline:02:40-03:10 Before leaving the
Connect the external alarm cables on DDF Huawei
Coordinate with BSC Site
engineer
Inform the RF team to perform the DT
DT test Huawei
DT test
Clear up tools, clean up the spot and report the site
Huawei
status to the post swap BSS Team
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Dual Band BTS Swap

Outage time:8 hours

Action Activity Description Responsibility Time

Block the Existing DDF port using DDF breaker


Confirm from OMCR the site ID
Existing NEC IDU Abis E1
Label the E1 if there is no label or information Huawei BTS Team 20:30-21:20
check
incorrect
Continue testing the rest E1s
Record the existing BTS status and equipment serial
Existing BTS asset check Huawei BTS Team 21:00-21:20
Number
Inform OMCR about the swap Activity & inform them
Inform OMCR Huawei BTS Team 21:30-21:40
to block the site
Etisalat OMCR will Block the site Etisalat OMCR 21:40-21:50
OMCR Block the ZTE BTS
Note: If Existing BTS is not locked at 21:50, then do not power OFF, deadline 22:10

Disconnect the Abis E1 in BSC room and Etisalat Team/ Huawei


Transmission Loop Test to connect to Huawei BSC DDF Team
21:50-22:00
BSC Test the Transmission loop back test from BTS site
to the Huawei BSC
22:00-22:10
(Service interruption
Power off existing BTS Power OFF Existing BTS Site Huawei BTS Team
Starts for Swap
Activity)
Dismantle the exiting BTS & power equipment. For
Dismantle ZTE BTS &
detailed process please refer to the Dismantling Huawei/Etisalat 22:10-23:50
Power equipment
SOP.
Install Huawei Master BTS & Huawei Team will install the Master BTS Cabinet &
Huawei BTS team 23:50-00:40
APM30 APM30
Shift MW IDU Shift the MW IDU to the Huawei APM30 Cabinet Huawei BTS team 00:40-01:20
Huawei will connect the PGND cables with Huawei
PGND Cables Huawei BTS team 01:20-01:30
equipment through the existing BUS bar installed.
Connect the AC power Huawei team will connect the APM30 power cables
Huawei BTS team 00:30-01:40
Cables to ACDB (32A Existing Ac breaker in the ACDB)
Connect the DC Power Huawei team will lay & connect the DC power cable
Huawei BTS team 01:40-01:50
Cables between APM30 & BTS Cabinet

Connect the feeder cable Connect new feeder jumper cable to HUAWEI BTS,
Huawei BTS team 01:50-02:20
Jumpers and connect the feeder jumper to existing feeder.

Test the external input AC power Huawei


02:20-02:40
Power on GTMU board Power on the PSU modules Huawei
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Report the result to BSC


Connect the Power cables of IDU Huawei
engineer
Power on the IDU Huawei
Connect the E1 cable to UELP board. Huawei
Power on BTS fan Huawei
Power on BBU frame, check the GTMU board is
working normally or not and make sure the Huawei
transmission is ok according to the LIU status
Power on the Master BTS Power on the DRFU board after the corresponding
Huawei BTS team 02:40-02:50
Cabinet feeder jumpers are properly connected.
Software Upgrade Download the software Huawei BTS team 02:50-03:10
Check the indicators of GTMU:
RUN: Slow flash (1 s on, 1 s off)
ALM:OFF
Huawei
ACT: ON
LIU(0-3):OFF
CPRI(0~5):ON(Green)
BTS Status Confirmation Check the indicators of DRFU: 03:10-03:20
RUN: Slow flash (1 s on, 1 s off)
ACT: ON
ALM: OFF Huawei
VSWR: OFF
CPRI0:ON(Green)
CPRI1:ON(Green)

Basic service test Call test Huawei 03:20-03:30 (Partial


Service Restored)
Deadline:04:00 SMS test Huawei
Install the Slave Cabinet &
Install the Slave BTS Cabinet , BBC & batteries Huawei 03:30-04:20
Battery Cabinet
Lay & Connect the PGND Cable with the existing
Connect the PGND & Power
Bus Bar & Lay & connect the power cables between Huawei 04:20-04:30
Cables
ACDB & APM30
Connect the feeder jumpers
of slave cabinet & the Cable Lay & connect the Jumpers with the existing Feeder
Huawei 04:30-04:50
between Master & Slave cable & Slave BTS Cabinet
Cabinet
Power ON the Slave BTS
Power ON the slave Cabinet & download the BTS
Cabinet & Download the Huawei 04:50-05:20
software
software
Power OFF The both Power OFF both Master & Slave BTS cabinet & then
cabinets & connect the Connect the DC Power cable between BBC & Huawei 05:20-05:30
Batteries with APM30 APM30
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Use multi meter to test the BBC power cable positive


and negative
05:30-05:40
Power ON the complete site Power ON the complete site Huawei (Complete Site
service restored)
Basic Testing Perform the Basic Call testing on complete site Huawei 05:40-06:00
External Alarm SWAP
Deadline:02:40-03:10 Before leaving the
Connect the external alarm cables on DDF Huawei
Coordinate with BSC Site
engineer
Inform the RF team to perform the DT
DT test Huawei
DT test
Clear up tools, clean up the spot and report the site
Huawei
status to the post swap BSS Team
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Tools for installation


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

1. Unpacking and site installation material check

2. Install the Base for RF Cabinet


BTS SOP for Etisalat Afghanistan-Huawei Swap Project
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

3. Fix the cabinet


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

4. Install power cable

4.1 Install power cable

4.2 Prepare the OT terminals for cables

3.2.2 Power Cable Connection


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Connect jumper from feeder to BTS


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

E1 connect and testing


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Connect Battery cabinet power cable and test the Voltage


BTS SOP for Etisalat Afghanistan-Huawei Swap Project

Power on BTS
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

NEC IDU Power connect

NEC IDU Power cable should be connected with those two pair of terminals
BTS SOP for Etisalat Afghanistan-Huawei Swap Project

After Swap
1- Clean the sites environment
2- Cover the existing BTS with water-proof material