2016
SUBJECT : PREVENTIVE MAINTENANCE (ACTIVITIES) DAILY: QUARTERLY: EVERY 2 MONTHS:
WEEKLY: SEMI-ANNUALLY: EVERY 5 YEARS:
MONTHLY: ANNUALLY: EVERY 2 YEARS:
PLANNED PERIOD OF COVERAGE RESPONSIBLE
EQUIPMENT ACTIVITIES DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER PARTY
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Checking & cleaning of utility room including electrical parameters (voltages) and (retightening of bolts if necessary) In house
EE/ Aux room Checking & testing of emergency & exit lights and accessories (including discharging of betteries) In house
Meter Center Checking & cleaning of gutters, breakers and (retightening of bolts/ terminals if necessary) In house
Fire hose cabinets & accessories Repositioning of Fire Hose, checking of fire extinguisher, nozzles and valves In house
ACU/ Ventilating Equipments Checking & Cleaning of Jet fan, exhaust fans (utility rooms) propeller and thermo switches In house
Checking of parameters and equipments including pool lights (retightening of terminals if necessary) In house
Declogging/ cleaning of sewer lines per building (FOR MID-RISE BUILDINGS) In house
Drainage and Sewerage Declogging/ cleaning of sewer lines per building (FOR HIGH RISE BUILDINGS) In house
Checking & cleaning of sewage and sump pits per building In house
Conduct visual inspection of Tank Cistern / for sign of cracks and forms of cavitation during general cleaning In house
Inspect storage tanks for sanitary deficiencies / inspect sigght glasses and valves ,fittings and controls In house
Inspect rang ladder for corrosion to prevent accident during performing of general cleaning In house
Overhead / Elevated water tank Inspect coatings and structural condition of tank In house
Inspect tank surfaces determine if there is build up of developing biogrowths or corrosion In house
Check electrode switch and clean build up corossion / inspect setting of high and low of electrode position In house
Sewage Pump
Measure the motor insullation test resisitance In house
Sewage Pump
Check noise impact during cut in / cut off of pumps In house
Conduct cleaning of pit / manholes remove build up greese and debris In house
Lift up pumps to sump pit to inspect impeller to avoid clogging . ( quarterly ) In house
Activate float switches and check pump for proper operation In house
Conduct cleaning of pit / manholes remove build up greese and debris In house
Lift up pumps to sump pit to inspect impeller to avoid clogging . ( quarterly ) In house
Monitor the STP equipment performance every hour of each shift to ensure its optimum performance. Service provider
Detect/Check any unusual level and overflows of tanks and piping system. Investigate immediately and make the Service provider
necessary evaluation and correction on the reason for such abnormalities
lift up pumps to check stock debris at impeller Service provider
Water potability test (bacteriological analysis) Monthly c/o third party Service provider
Checking & cleaning of pumps, blowers, diffusers, valves, compressors, solenoids Service provider
Plumbing/ Valves/ STP Siphoning of sludge digester, SBR and holdng tanks Depending on the volume of sludge on the ASD tank Service provider
De-clogging & Cleaning of Sewer Lines, Canal Drains, Storm Drains (per bldg) Service provider
Visual and recording of PRV-waterline, fire pro, transfer pumps, relief valves In house
Ricardo Cabug-os/ Alexis Quiliza/ Julius Warren Aro/ Jay Panaglima Joseph John Maynigo
Area Facilities Officer/ Specialist DPMC-MEPF Head
DPMC PREVENTIVE MAINTENANCE SCHEDULE
2016
EQUIPMENT DAILY WEEKLY MONTHLY EVERY 2 MONTHS QUARTERLY SEMI-ANNUAL ANNUALLY EVERY 2 YEARS EVERY 5 YEARS
Preventive Preventive
maintenance maintenance
Generator Testing without load Testing with load
(including change oil) (including change oil)
Hi-rise Mid-rise & hybrid
General preventive
Transformer & Checking and record maintenance &
LVSG/ MDP/ ATS of parameters retightening of
terminals
Repositioning of Fire
Fire hose
Hose, checking of fire
cabinets &
extinguisher, nozzles
accessories
and valves
a.) Declogging/
cleaning of sewer
lines, canals, storm
drain per building
a.) General cleaning
Drainage and of drainages
b.)
Sewerage b.)
Checking & cleaning
Septic tank siphoning
of sewage and sump
pits per building
c.) general
cleaning of drainages
Booster Pump
Sewage Pump
Sump Pump
Sewage treatment
plant
WEEKLY ACTIVITIES
1.) Genset testing without load (every 1st Monday of the week)
2.) General cleaning of pool and checking of PH (depending on the schedule of weekly pool maintenance)
3.) Checking of parameters and equipments including pool lights (retightening of terminals if necessary)
4.) Check all pumps control panel for any loose screw or termination of wires.
5.) Check running current vs to rated capacity of pumps to ensure the efficiency of pumps.
6.) Conduct inspection of float switch if available in equipment.
7.) Check functionality of all selector knobs in control panel.
8.) Ensure all indicating lamps are working .
9.) Observed noise vibration during running of pumps .
10.) Observed check valves for noise vibration during cut in and cut off of pumps.
11.) Conduct cleaning of pit , removed debris presence inside the pit .
12.) Checking & cleaning of pump motors
13.) Checking & cleaning of pumps, blowers, diffusers, valves, compressors, solenoids
MONTHLY ACTIVITIES
1.) Elevator general preventive maintenance
2.) Transformer & LVSG/ MDP/ ATS checking and recording of parameters (every 3rd week of the month)
3.) Checking & cleaning of utility room including electrical parameters (voltages) and (retightening of bolts if necessary) (every 3rd week)
4.) Checking & testing of emergency & exit lights and accessories (including discharging of betteries) (every 4th week)
5.) Checking & cleaning of gutters, breakers and (retightening of bolts/ terminals if necessary) (every 3rd week)
6.) Smoke Detectors testing per building (every 1st week)
7.) Checking and cleaning of FDAS panels, supervisory and flow switches and accessories (every 1st week)
8.) Fire pump, Jockey pump dry run testing (every 2nd week)
9.) Repositioning of Fire Hose, checking of fire extinguisher, nozzles and valves (every 3rd week)
10.) Water station potability test (bacteriological analysis) every 3rd week
11.) Checking water station filter cartridge and equipments, etc. (every 3rd week)
12.) Checking & Cleaning of filters for ACU (every 3rd week)
13.) Checking & Cleaning of Jet fan, exhaust fans (utility rooms) propeller and thermo switches (every 3rd week)
14.) Declogging/ cleaning of sewer lines, canals, storm drain per building (every 4th week)
15.) Checking & cleaning of sewage and sump pits per building (every 1st week)
16.) Transfer pump, Sump pump, Booster pump, Sewage pump insulation test monthly (every 3rd week)
17.) General cleaning of final tank (every 4th week)
18.) Visual and recording of PRV-waterline, fire pro, transfer pumps, surge relief valves (every 4th week)
EVERY 2 MONTHS
1.) Water station replacement of filter block. (January, March, May, July, September, November) in house maintenance
QUARTERLY
1.) Genset testing with load (every January, April, July, September)
2.) Lift up pumps to sump pit to inspect impeller to avoid clogging . (every January, April, July, September)
SEMI ANNUALLY
1.) Genset general preventive maintenance (including change oil) Hi-rise (Every March and September)
2.) Water station physico-chemical analysis (every April and November)
3.) General cleaning of cistern tank & elevated tank (every April and November)
ANNUALLY
1.) Elevator no load and full load test (every August)
2.) Genset Preventive maintenance (including change oil) Mid-rise & hybrid (every May)
3.) Transformers, MDP, ATS general preventive maintenance & retightening of terminals (every May-August)
4.) Replacement of emergency & exit lights batteries (every April)
5.) Refiling of fire extinguishers (every January)
6.) General cleaning of drainages (every February)
7) Septic tank siphoning (every May - June)
8.) General cleaning of all ACU (every December)
EVERY 5 YEARS
1.) Draining & filing of pool water (January - February)
EVERY 2 YEARS
1.) Siphoning of sludge digester, SBR and holdng tanks (May - June) as per recommendations of service provider (every May - June)