F0 33: SAFETY ORGANIZATION

JOB SAFE PRACTICE (5.19.3)

DEPARTMENT Electrical EMPLOYEE JOB TITLE Technician


JOB/TASK TITLE Cable Laying
STEPS HAZARDS
IN EACH STEP , WHAT
CONTROLS REQUIRED TO
COULD CAUSE
LIST ALL STEPS IN PERFORMING THIS MINIMIZE /ELEMINATE OBSERVATION
STEP# INJURY,LOSS DAMAGE
TASK HAZARD
INTERUPTION OR
POLUTION?
Sharp edges from existing Extra care to be taken while
cable tray, Damaged pulling the cable on cable
1 Cable laying in cable tray existing cable, Slip, Trip tray/ladders. Use hand gloves.
and Fall from height.

Cables have been hit with Barricading required and


other live panels while additional manpower required.
Segregate the cable as per requirement segregate. Manual
2
handling.

1. Back pain 1. Trained technician required.


3 Lay the cable inside to panel through through. 2. Asset damage. 2. TBT

COMPILED BY DATE

MANAGER MANAGER

Prepared by: Approved by: Element 5.19 Page No: Page 1 of 1 Revision No: 00
Reference No: