Sei sulla pagina 1di 64

A

PRACTICAL TRAINING SEMINAR REPORT


ON

“Residential & Hotel Block”


Taken At

CREATIVE PROJECTS & CONTRACTS Pvt. Ltd.

Submitted in partial fulfilment for the award of the degree of

BACHELOR OF TECHNOLOGY
In
Civil Engineering

Guided by: Submitted by:


Mr. Ayush Goyal Aditya Singh
Mr. Vikas Sharma Civil (4th year)

RAJASTHAN TECHNICAL UNIVERSITY, KOTA


DEPARTMENT OF CIVIL ENGINEERING
Poornima Group of Institutions, Sitapura,
Jaipur
September 2019
CERTIFICATE

This is to certify that the Practical Training Seminar report for Practical

Training taken at Creative Projects & Contracts Pvt. Ltd., Jaipur

(Rajasthan) from 18th May 2019 to 18th July 2019 is submitted by Mr.

ADITYA SINGH (16ESDCE003) in partial fulfillment for the award of

degree of Bachelor of Technology in Civil Engineering has been found

satisfactory and is approved for submission.

Mr. Prannath Dadhich Mr. Ayush Goyal


Head of Department Mr. Vikas Sharma
Assistant Professor Coordinators
Assistant Professor
Dept. of Civil Engineering, Dept. of Civil Engineering,
PGI, Jaipur PGI, Jaipur

i
ii
DECLARATION

This is to certify that, Aditya Singh student of B.Tech (Civil)-7th Semester Roll
No.16ESDCE003 has undergone industrial training in "Creative Projects & Contracts
Pvt. Ltd. (CPCPL) " as required by two months industrial training for the award of
degree of B.Tech Civil Engineering, POORNIMA GROUP OF INSTITUTIONS,
Sitapura, Jaipur and prepared the report entitled “Residential and Hotel Block”
which is an authentic record of my work carried out Opposite Jaipur International
Airport, Jaipur. If any discrepancy is found regarding the originality of this project, I
may be held responsible. I have not copied from any report submitted earlier this
university or any other university. This is purely original and authentic work.

ADITYA SINGH
(Civil 4th Year)
(PGI16CV063)
(16ESDCE003)

iii
ABSTRACT

This report is a summer internship report submitted in partial fulfilment of the


requirements for the degree of Bachelor of Technology in Civil Engineering as per
norms of Rajasthan Technical University Kota. The author visited the site for
construction of Residential And hotel block, opposite Jaipur international airport, Jaipur
in his training period and attained technical knowledge during the training, after which
he was able to compile this report. The report consists of brief study and description of
materials, equipments and procedures used at site for construction of a Complex. Author
put his best to elaborate the actual site conditions, and problem faced at site and the
tactics used to deal with them.
The main objective of this report is to present a systematic text on the execution of
construction of a complex based on the Indian Standard codes. The report also covers
the fundamental aspects of practical requirement such as safety, feasibility and economy
at site. In this report the objective was to introduce, wherever necessary,
material which embodies the most recent methodologies.
Chapter 1:-Discusses introduction to organization profile, management structure,
products and the main conclusions.
Chapter 2:-Discusses introduction to Company Infrastructure, Vision and Mission of
company, Network Structure and the main conclusions.
Chapter 3:- Contains description of the process plant/site where practical training was
undertaken including block diagrams for showing process scheme, major operations and
process equipments, stream compositions, site conditions governing the process control.
Chapter 4:- Contains the description of project, roles & responsibilities at site,
Responsibility while testing and the main conclusion.
Chapter 5:- Presents the results obtained after the Internship on site proceeding with
their conclusion.
In spite of every care taken, it is possible that some errors might have been left
unnoticed. The author sincerely welcomes the constructive criticism for improving the
report.

iv
ACKNOWLEDGEMENT

We are very grand to expose our sincere and lovable memorial thanks to our
Management for having on hand the facilities for the triumphant completion of the
project.
We have glad to express our subterranean gratitude to Mr. Dinesh Goyal,
Director (PGI, Jaipur), for his invaluable motivation and encouragement in every thread
of our course.
We cordially thanks to Mr. Prannath Dadhich Head of the Department, Civil
engineering, intended for giving valuable guidance, steady support and encouragement
to inclusive our project lucratively. Also, we are vastly obliged to him as our project
guide, for his breed and valuable support to make our project a successful one.
We are very much thankful to our civil department staff for giving unsurpassed
Suggestions towards successful completion of this new project.

Words are inadequate in offering my thanks to the Project team of CPC for their
guidance and cooperation in carrying out the training work.

Finally, yet importantly, I would like to express my heartfelt thanks to my beloved


parents for their blessings, my friends/classmates for their help and wishes for the
successful completion of this training.

v
TABLE OF CONTENT

Content Page No
Chapter 1: Introduction ........................................................................................ 1-3
1.1 Introduction
1.2 Background of the CPCPL
1.3 Organization Structure
1.4 Nature of the Business
1.5 Market Strength
1.6 Products
1.7 Current Projects
1.8 Conclusion

Chapter 2: CPCPL Infrastructure ....................................................................... 4-5


2.1 Introduction
2.2 Departmental Structure
2.3 Vision & Mission
2.4 Available Plan
2.5 Conclusion

Chapter 3: Attended Training at CPCPL ............................................................. 6-43


3.1 Introduction
3.2 Duration of Training
3.3 Location Detail
3.4 Silent Features of the Project
3.5 Material Used at Our Site
3.5.1 Cement
3.5.2 Aggregate
3.5.3 Steel
3.5.4 Admixture
3.5.5 Bonding Agent
3.5.6 Bricks
3.5.7 Water
3.5.8 Ready Mix Concrete
3.5.9 Miscellaneous Material
3.6 Equipments Used at Our Site
3.6.1 Bar Bending Machine
3.6.2 Bar Cutting Machine
3.6.3 Tower Crane
3.6.4 Excavator
3.6.5 Concrete Pumping Machine
3.6.6 Vibrators
3.6.7 Welding Machine
3.6.8 Grinder
3.6.9 Measuring Tape
3.6.10 Try Square
3.6.11 Plumb Bob
3.6.12 Hammer
3.6.13 Trowel
3.6.14 Hammer Machine

vi
3.6.15 Hoe
3.6.16 Head Pan
3.6.17 Sand Screening
3.6.18 Bump Screed
3.6.19 Wooden Rendering Float
3.6.20 Vacuum Blower
3.6.21 Walkie Talkie
3.7 Safety Equipments Used at Our Site
3.7.1 Safety Helmet
3.7.2 Body Harness
3.7.3 Labour Safety Shoes
3.7.4 Safety Net
3.7.5 Welding Goggles
3.7.6 HVSA
3.8 Information About Test
3.8.1 Slump Test
3.8.2 Compression Test
3.8.3 Mix Design Ratios Used at Site
3.9 Construction Process
3.9.1 Piling
3.9.2 Excavation
3.9.3 Dressing
3.9.4 Levelling
3.9.5 Site Marking
3.9.6 Laying of P.C.C
3.9.7 Column Layout
3.9.8 Foundation & Pedestal
3.9.9 Column Binding, Shuttering & Casting
3.9.10 Shuttering & Bar Binding of Slab & Beam
3.9.11 De-Shuttering
3.9.12 Curing

Chapter 4: Project Development .......................................................................... 44-44


4.1 Project Description
4.2 Roles & Responsibilities
4.3 Role in Checking Implementation
4.4 Role in Testing
4.5 Conclusion
Chapter 5: Conclusion ........................................................................................... 45-46
5.1 Introduction
5.2 Lessons Learned Skills Developed
5.3 Knowledge Gained
5.4 Conclusion
Chapter 6: Conclusion & Recommendations to the Company ......................... 47-52
6.1 Conclusion
6.2 Recommendations
6.3 Important Drawings related to site
6.4 Problems Faced at Site
CHECK LISTS ................................................................... 60-63
REFERENCES

vii
LIST OF FIGURES
CONTENT PAGE NO
Figure 1 Location Map of site (Golden Sand) 7
Figure 2 Cement 10
Figure 3 Coarse aggregate 11
Figure 4 Fine aggregate 11
Figure 5 Reinforcement bars 14
Figure 6 MS plate 15
Figure 7 Admixture 16
Figure 8 Faircreate SB(L) 16
Figure 9 Rebaring using Hilti re-500 17
Figure 10 Bricks 18
Figure 11 Cover blocks 19
Figure 12 Nails 20
Figure 13 Binding wire 20
Figure 14 BBM (Bar Bending Machine) 21
Figure 15 BCM (Bar Cutting Machine) 21
Figure 16 Tower crane 22
Figure 17 Excavator 22
Figure 18 Concrete pump 23
Figure 19 Needle vibrator 24
Figure 20 Welding machine 24
Figure 21 Grinder 25
Figure 22 Measuring tape 25
Figure 23 Try square 26
Figure 24 Plumb bob 26
Figure 25 Trowel 26
Figure 26 Hammer machine 27
Figure 27 Hoe 27
Figure 28 Head pan 27
Figure 29 Bump screed 28
Figure 30 Wooden rendering float 28
Figure 31 Vacuum blower 28
Figure 32 Walki talki 29
Figure 33 Safety helmet 29
Figure 34 Body harness 30
Figure 35 Labour safety shoes 30
Figure 36 Safety net 31
Figure 37 Welding goggles 31
Figure 38 Slump test 32
Figure 39 Cube test 34
Figure 40 Piling reinforcement 35
Figure 41 Excavation 36
Figure 42 Levelling 37
Figure 43 Site marking 38
Figure 44 Laying of P.C.C 38

ix
Figure 45 Column Layout on Site 39
Figure 46 Column layout plan 39
Figure 47 Bar Binding of Raft 40
Figure 48 Raft casting 40
Figure 49 Column shuttering 41
Figure 50 Main Reinforcement of Column 41
Figure 51 Beam schedule 42
Figure 52 Slab & beam casting 43
Figure 53 Gunny bag method 43
Figure 54 Ponding method 43
Figure 55 Layout plan 49
Figure 56 Column main reinforcement detail 50
Figure 57 Beam main & extra reinforcement detail 51

GRAPHS
Graph-1 Grading Limit of Masonry Sand 12

x
LIST OF TABLES
CONTENT Page No
Table 1 Block wise detail of the number of stories in each block 8
Table 2 Chemical properties of reinforcement bars 13
Table 3 Mechanical properties of reinforcement bars 14
Table 4 Slump test 32
Table 5 Cube test performed at site 33
Table 6 M-35 mix design by weight 34
Table 7 M-30 mix design by weight 34
Table 8 Piling specification 35
Table 9 Foundation & pedestal specification 40
Table 10 Column specification 41
Table 11 Slab & beam specification 42

xi
CHAPTER-1 INTRODUCTION

1.1 INTRODUCTION

CREATIVE PROJECTS & CONTRACTS PVT. LTD. is an organization formed with


the aim of handling large Civil Engineering Projects with quality construction and time-
bound completion of work.

1.2 BACKGROUND OF CPCPL

Creative Projects & Contracts Private Limited is a Private incorporated on 24 April


1995. It is classified as Non-govt. company and is registered at Registrar of Companies,
Jaipur. Its authorized share capital is Rs. 3,500,000 and its paid-up capital is Rs.
3,500,000. It is involved in Real estate activities with own or leased property. This class
includes buying, selling, renting and operating of self-owned or leased real estate such
as apartment building and dwellings, non-residential buildings, developing and
subdividing real estate into lots etc. Also included are development and sale of land and
cemetery lots, operating of apartment hotels and residential mobile home sites
(Development on own account involving construction is classified in class 4520).
Creative Projects And Contracts Private Limited's Annual General Meeting (AGM) was
last held on 29 September 2018 and as per records from Ministry of Corporate Affairs
(MCA), its balance sheet was last filed on 31 March 2018.
Directors of Creative Projects And Contracts Private Limited is Girdhari Singh.
Creative Projects And Contracts Private Limited's registered address is SB-154, 5th
Floor, Ganga Heights, Bapu Nagar, Tonk Road, Jaipur RJ 302015 IN.

1
1.3 ORGANIZATIONAL STRUCTURE
The company has following organizational Structure:
 Administrative
 Engineering
 Finance
 Procurement


1.4 NATURE OF BUSINESS
Company executed the works of building like: -
 Residential
 Hospitals
 Commercial Complex
 Multiplexes, etc.
1.5 MARKET STRENGTH
CPC Pvt. Ltd. is the company with following Gross Turn Over from last few years: -
 2012-13: Rs.41.59 Crore
 2013-14: Rs.49.13 Crore
 2014-15: Rs.61.35 Crore
 2017-18: Rs.76.72 Crore

1.6 PRODUCTS
 Real Estate / Different type of Buildings (Commercial & Residential
Complexes)

1.7 CURRENT PROJECTS


We at CPC believe in quality with precision in commitment of deliverables to achieve
the profound contentment of the community we serve. This is made possible with the
team at CPC which has the right mix of youth, experience, technical and professionals
and preach “Excellence” in every walk of life.
 Golden Sands, TAJ Hotel + Residential Complex
 Horizon Tower
 Extension of Manipal University
 Extension of Mahatma Gandhi hospital etc.

2
1.8 CONCLUSION

CPC Pvt. Ltd. is very rapidly developing the company in the field of construction; CPC
is running multiple multi-story projects around Jaipur. The future of this company is
very bright in the field of construction. CPC is trusted for quality and is acknowledged
for an unshakable commitment to excellence in every aspect of construction. CPC is an
organization formed with the aim of handling large Civil Engineering Projects with
quality construction and time-bound completion of work.

3
CHAPTER-2 CPCPL’S INFRASTRUCTURE

2.1 INTRODUCTION
Creative projects & contracts is trusted for quality and is acknowledged for an
unshakable commitment to excellence in every aspect of construction.

2.2 DEPARTMENTAL STRUCTURE


 Proprietor
 Managing Director
 Project Manager
 Project Engineer
 Foreman
 Supervisors

2.3 VISION & MISSION


VISION

To be a world-class construction and infrastructure enterprise committed to quality,


timely completion and customer satisfaction.

MISSION

To deliver high-quality, cost-effective projects on schedule by employing and


supporting motivated, flexible, and focused teams. We value the importance of our
relationships and will continue to remain fair and true in our dealings with all
employees, clients, vendors, and partners. Our clients count on our dependability,
our drive, and our integrity. We take great pride in our accomplishments and build
on them every day.

2.4 AVAILABLE PLAN


 To become the most successful and respected construction company in INDIA.
 Our mission is to grow personally, professionally, emotionally and spiritually by
using our compassion, unique perspective, and our belief in other's inherent
goodness, integrity, and enormous potential.

4
2.5 CONCLUSION
In CPCPL there is very good and very well managed departmental structure.
And CPCPL used to be updated with respect to time and use advanced tools, machines
and software’s related to civil construction work and planning. They also have a future
vision of being most successful and respected construction company in INDIA.

5
CHAPTER-3 TRAINING ATTENDED AT CPCPL

3.1 INTRODUCTION

Industrial Training program provides pre-professional work with specific assignments


and responsibilities. The aim of this Industrial Training is to prepare the student
physically, mentally and emotionally for the rigors of work as executives in real
organization upon graduation. It helps to develop the student's maturity, self-awareness,
and confidence and familiarize the student with some structured practical experience of
the organization, its operations, its customers, and its staff. By providing pre-
professional work experience with specific assignments and responsibilities, it
stimulates personal career interests, serving as a bridge between university and the
world of work. This trains and prepares the student with knowledge and skills required
in current and future Industry environments.

3.2 DURATION OF TRAINING

The construction was already in full swing, at the building, when I started my training at
the site. My training at Creative projects and contracts Pvt. Ltd., Jaipur initiated on
Saturday, 18th May 2019. I had to report to my training Co-Ordinator, Mr. Anil Kr.
Verma premises on every weekday (Monday to Saturday) at 10:00 A.M. and had to
leave before 6:00 P.M. The Training duration was set as 12 weeks training program
which ended on Thursday, 18th July 2019.In this report, all the details regarding various
practices that I saw at the site have been included.

3.3 LOCATION DETAILS

 Located opposite Jaipur International Airport


 100 Meters from Jawahar Circle Garden
 6.2 Kms From Gandhi Nagar Railway Station
 14 Kms From Jaipur Railway Station
 13 Kms From Sindhi Camp Bus Stand

6
Fig-1:-Location Map of Mangalam JKD Radiance

3.4 SILENT FEATURES OF THE PROJECT

 Plot Area: 1000000 sqft.


 Type of Structure: Residential Building and Hotel

Table-1 - Block wise detail of the number of stories in each block:

Block – 1 2B+G+Service Floor+11

Block – 2 2B+G+ Service Floor +11

Block – 3 2B+G+ Service Floor +11

Block – 4 2B+G+ Service Floor +11

Block – 5 2B+G+ Service Floor +11

Hotel Block 2B+G+ Service Floor +07

7
 Client Name: Jaipur Motels and Buildestates Pvt. Ltd.
 Architect: Tushar Sogani Designs Pvt. Ltd.
 Structural Consultant: S.G. Structures
 Contractor: Creative Projects & Contracts Pvt. Ltd.
 Original Contract Duration: 60 Months from the letter of Intent
 Type of Contract: Measurement Rate For Block 1/2/3/4/5/Hotel

8
3.5 MATERIAL USED AT OUR SITE

The various materials used for constructing and supporting the building are termed
cement, sand, and steel are to be tested before using them in building construction. The
materials which are used at our site are as follows: -
3.5.1. CEMENT
A cement is a binder, a substance used in construction that sets, hardens and
adheres to other materials, binding them together. Cement is used with fine
aggregate to produce mortar for masonry, or with sand and gravel aggregates to
produce concrete. The volume of 1 bag of cement was 0.0347 m3.
PPC (Portland Pozzolana Cement). The brand which was used on our site was
MP BIRLA CEMENT & BIRLA CHETAK CEMENT. The percentage of fly
ash in PPC permitted by IS:1489 varies from 15% (in minimum) to 35%
(maximum).

REASONS FOR USE

3.5.1.1 More Durable - Longer Lifespan: -


Constructions using Birla Cement are tougher than other
constructions and immune to environmental changes. The
noxious gases of air pollution have no effect on them. Therefore,
the constructions become more durable and have a longer life.
What's more, it gives freedom from the trouble of regular
maintenance.
3.5.1.2 Anti-Rust: - The unique elements of Birla
Cement prevents the steel bars within concrete reinforcements,
from rusting. Hence, the construction's lasts longer,
comparatively.
3.5.1.3 Minimizes Water Seepage: - Birla Cement is
used to construct roofs, basements, and water tanks, making
them stronger, durable & water resistant. The extra fine grains of
Birla Cement act as deterrents for seepage.
3.5.1.4 Lesser Thermal Cracks: - The Heat of
Hydration count is very low in Birla Cement. This prevents
cracks in RCC and other construction works.

3.5.1.5 More Fineness:- Birla Cement is finer than 53

9
Grade OPC. It has super strength, great adhesive qualities and
creates a more flexible and resilient cement mix for
constructions.
3.5.1.6 Setting Time:- Like Ordinary Portland Cement
(OPC), the shuttering of columns, beams, slabs etc. can be
opened within the specified duration.

Fig-2:-Cement

3.5.2. AGGREGATE
Aggregate occupies most of the volume of the concrete. It is the stuff that the
cement paste coats and binds together. The composition, shape, and size of the
aggregate all have a significant impact on the workability, durability, strength,
weight, and shrinkage of the concrete. IS: 383-1970 is preferred for aggregate
testing. Aggregates, which account for 60 to 75 percent of the total volume of
concrete, are divided into two distinct categories are as follows: -

10
COARSE AGGREGATE
o SIZE- 10-20mm
o SPECIFIC GRAVITY – 1.6-1.88
o WATER ABSORPTION- 0.23
Fig-3:-Coarse Aggregate (20 to 10 mm)

Fig-4:-Fine Aggregates

11
FINE AGGREGATE (ZONE2)
Sand is basically consisting of small grains of silica which is formed by the
decomposition of sandstones due to various effects of weather. The sand which is
used at sites coming from Banas River whose Specific Gravity lies Between
1.44 to 1.6. There is one factor which affects batching i.e. Bulking of sand. The
presence of moisture in sand increases the volume of sand. This is due to the fact
that moisture causes a film of water around sand particles which result in the
increase in the volume of sand.
GRADING LIMIT

The particle size distribution of sand for use in masonry mortar should be within
the limits as given in the following table.

Particle Size Percentage of Passing


4.75 mm 100
2.36 mm 90 – 100
1.18 mm 70 – 100
600 micron 40 – 100
300 micron 5 – 70
150 micron 0 – 15

Graph:-1 Grading Limit of Masonry Sand

If the sand does not conform to grading limit as specified above, then by combining it
with other sand we can get the desired grading.

12
3.5.3. STEEL
Steel is most commonly used as reinforcing material as a tension member
because is satisfying all characteristics required for an ideal reinforcing material.
The grade which is used at the site is 500D of sizes 8mm, 12mm, 16mm, 20mm,
25mm& 32mm.The size of 8mm is used in slab and 16mm,20mm,25mm &
32mmwas used in beam and column. Due to ribs present on steel bars, it
develops a good bond with the concrete.IS:1786 give specifications for HYSD
bars on site.

Steel

Reinforcement Bars M.S Plates

a) Reinforcement Bar
BRAND - TATA TISCON
GRADE – Fe 500D
Diameter of bars used (in mm)- 8,12,16,20,25,32

Table 2:- Chemical Properties of Reinforcement Bars


Chemical Properties
Constituents Maximum Percentage
FE 500 FE 500D
Carbon 0.30 0.25
Sulphur 0.55 0.40
Phosphorus 0.55 0.40
Sulphur & Phosphorus 0.105 0.075

13
Table 3:- Mechanical Properties of Reinforcement Bars
Mechanical Properties
Properties Minimum Value
FE 500 FE 500D
Yield Stress (N/mm2)-YS 500 500
Ultimate Tensile Stress (N/mm2)-UTS 545 565
UTS/YS Ratio 1.08 1.1
% Elongation 12 16

Fe 500 & Fe 500D the term “Fe” denotes Iron, “500” stands for the minimum
yield stress in N/mm2 and the letter “D” denotes that such bars have higher values of
ductility (higher UTS/YS & % Elongation).

Fig-5:-Reinforcement Bars

14
b) M.S Plates
BRAND- SAIL
GRADE- Fe 500

REASON FOR USING MS PLATE

Reinforced concrete coupled shear walls in tall buildings are known as efficient
structural systems to provide lateral resistance to wind and earthquake. The coupling
beams connecting two shear walls are normally subjected to very high bending and shear
stresses. In the design of coupled shear walls, structural engineers have to face a problem
that the conventional reinforced concrete coupling beams cannot provide enough shear
capacity, which is independent of the amount of transverse reinforcement, to resist such
high shear stresses due to the limitation of beam sizes from both architectural and
structural considerations.

Fig-6:-MS Plate (Mild Steel Plate)

15
3.5.4. ADMIXTURE
The admixture is the materials which are used to improve the quality of concrete.
The admixture which is used at the site is coming from Chembond Chemicals
Ltd. And Admixture is known as Kemsuplast 340J (Type: Poly-Carboxylic
Ether). The capacity of one drum is 225 Kg. This admixture helps to increase the
setting time and maintain the strength of concrete.

Fig-7:-Admixture
3.5.5. BONDING AGENTS
 FAIRCRETE
The bonding agent is a high solid, water-based emulsion admixture suitable for
modifying Portland cement compositions. It is also designed for use as a bonding
agent between new and hardened concrete. It is a milky white, non-yellowing liquid
ready for use and requires no on-site dilution. The Bonding Agent used at our site
was a product of Fairmate Pvt. Ltd. And Bonding Agent were Faircrete whose
main work was to prepare a bond between new and hardened concrete.

Fig-8:-FaircreteSB(L)

16
 HILTI RE500
It is an epoxy adhesive chemical for rebar connections and heavy anchoring
works. Structural connections with post-installed rebar (e.g. extension/connection
to walls, slabs, stairs, columns, foundations, etc.). It can take 30% higher load
with Re 500.
Key Technical Details
 Material composition: Epoxy adhesive
 Tested/approved for diamond drilling: Yes
 In-service temperature range-40 - 70 °C
 Storage and transportation temperature- 5°C-25°C
Features
 European Technical Approval covering automatic cleaning of holes drilled
using TE-CD or TE-YD drill bits and Hilti vacuum cleaners.
 Especially suitable for large-diameter elements and/or deep embedment
depths.
 Virtually odorless, hence pleasant to work with
 Suitable for anchoring in diamond-cored holes
Applications
 Structural connections with post-installed rebar (e.g. extension/connection to
walls, slabs, stairs, columns, foundations, etc.)
 Anchoring structural steel connections (e.g. steel columns, beams, etc.)
 Anchoring crash barriers, noise barriers, etc.
 Suitable for underwater applications in hammer-drilled holes

Fig-9:-Rebaring Using Hilti Re-500

17
3.5.6. BRICKS
Bricks are used as siding in the building industry due in part to its important
characteristics and just because it can be a good affordable option. Below we
summarize the benefits and applications of the most commonly used type of
bricks.2nd Class brick was used at our site was according to Indian standard(IS:
1077: 1992). Whose water absorption was less than 20%
There are various types of bricks used in masonry.
o Common Burnt Clay Bricks
o Sand Lime Bricks (Calcium Silicate Bricks)
o Engineering Bricks
o Concrete Bricks
o Fly ash Bricks
The brick which was used at our site was Common Burnt Clay Bricks.

Fig-10:-Bricks

3.5.7. WATER
Water is one of the most important elements in construction, but people still
ignore the quality aspect of this element. The water is required for preparation of
mortar, mixing of cement concrete and for curing work etc. during construction
work. The quality and quantity of water have much effect on the strength of
mortar and cement concrete in construction work.
Quality of Water
The water used for mixing and curing should be clean and free from injurious
quantities of alkalis, acids, oils, salt, sugar, organic materials, vegetable growth

18
and other substances that may be deleterious to bricks, stone, concrete or steel.
Potable water is generally considered satisfactory for mixing. The pH value of
water should be not less than 6.

3.5.8. READY MIX CONCRETE (RMC)


Ready-mix concrete is a type of concrete that is manufactured in a factory or
batching plant, according to a set recipe, and then delivered to a work site, by
truck mounted transit mixers. This results in a precise mixture, allowing specialty
concrete mixtures to be developed and implemented on construction sites.
Concrete itself is a mixture of Portland cement, water, and aggregates comprising
sand and gravel or crushed stone. In traditional work sites, each of these materials
is procured separately and mixed in specified proportions at the site to make
concrete. Ready Mixed Concrete is bought and sold by volume - usually
expressed in cubic meters. RMC can be custom-made to suit different
applications.
3.5.9. MISCELLANEOUS MATERIAL
a) Cover Blocks: -A cover block is essentially a spacer that is used to lift the bar
matrix off the ground so that concrete may flow underneath the bar. In order to
prevent corrosion of the bar& exposure to the environment, it needs to be fully
encased in concrete. By code, it usually needs about 2 to 3 inches of coverage on
all sides.

Fig-11:-Cover Blocks
b) Nails:- Nails are used to making unit assembly of shuttering panels.These are
made up of Iron, these are pointed at one end and flat headed from another.

19
Fig-12:-Nails
c) Binding Wire:- Binding wire is used for binding reinforcement construction. It is
made of mild steel inker, which takes place in the form of thermal processing
annealing. Binding wire is also called annealed wire. Binding wires play a
significant role in holding the rebars during construction. Binding wires are used
for tying rebars to hold the structure intact. The main and distributional
reinforcement rebars are held together using annealed wire made of mild steel.
Binding wires are prepared by the process of annealing which provides them
flexibility, softness and required strength. The diameters range from 0.61 mm to
1.22 mm.At our site, 0.8mm diameter wire was used.

Fig-13:-Binding Wire

d) Shuttering oil:- Oil that is mainly used in the process of greasing inner areas of
molds is commonly known as Shuttering Oil. Such kind of oils is also used for
construction work.

20
3.6. EQUIPMENT AND TOOLS USED AT SITE

3.6.1. BBM {Bar Bending Machine}:-Apparatus used to bend and shape steel rod,
especially used in the preparation of steel reinforced concrete structures.

Fig-14:-Bar Bending Machine

3.6.2. BCM {Bar Cutting Machine}:-Highly sophisticated bar cutting machines work with
hydraulics, which makes them very accurate in their cutting. With fast and efficient
bar cutting machines are capable of cutting multiple rods at the same time.

Fig-15:-Bar Cutting Machine


3.6.3. Tower Crane:-A rotatable cantilever jib on top of a steelwork tower used on building
sites where the operator needs to command a good view of the site. Fixed to the ground
on a concrete slab, tower cranes often give the best combination of height and lifting capacity
and are used in the construction of tall buildings. The base is then attached to the mast which
gives the crane its height.

21
Fig-16:-Tower Crane
3.6.4. Excavator: -an excavator, also called a rear actor or back actor, is a piece of
excavating equipment or digger consisting of a digging bucket on the end of a two-
part articulated arm. They are typically mounted on the back of a tractor or front
loader.

Fig-17:-Excavator

3.6.5. Concrete Pumping Machine: - A concrete pump is a machine used for transferring
liquid concrete by pumping. There are two types of concrete pumps. With Maximum
Pump 24/14 Strokes Per Minute.
Pumps are used in most of the larger construction projects as they are capable of
pumping at very high volumes.

22
Fig-18:-Concrete Pump

3.6.6. Vibrator: - A concrete vibrator is a construction tool typically used on concrete


pouring sites. These machines and an assortment of attachments are designed for
multiple applications built by a variety of manufacturers. The vibrators are used to
ensure that the pour is free of air bubbles and are even. This is so that the concrete
remains strong and has a smooth finish even after removal of the formwork. It is not
exactly necessary for small jobs but it can be essential for large load bearing project
on our site needle vibrator was used. Specifications: Needle Size: 60 Mm. Needle
Length: 4 Meters Long. Capacity: 12000 To 15000 Cm3.

23
Fig-19:-Needle Vibrator
3.6.7. Welding Machine:-Welding is a fabrication or sculptural process that joins metals by
causing fusion, which is distinct from lower temperature metal-joining techniques
such as soldering, which does not melt the base metal. In addition to melting the base
metal, a filler material is typically added to the joint to form a pool of molten material
that cools to form a joint that is usually stronger than the base material. Welding
electrode is coated with Cellulose Potassium Titania sodium, Titania potassium,
Iron Powder Titania, Low hydrogen sodium, Low hydrogen potassium, Iron
powder iron oxide, Iron powder low hydrogen.

Fig-20:-Welding Machine
3.6.8. Grinder: - Grinding is used for finishing of workpieces that must show high surface
24
quality and high accuracy of shape and dimension. It Rotates at the speed of 6600-
7700 RPM.

Fig-21:-Grinder

3.6.9. Measuring tape (Steel): -A measuring tape is a flexible ruler. It consists of a metal
strip with linear-measurement markings. It is a common measuring tool. The
measuring tape was of different-different sizes like- 30m, 5m.

Fig-22:-Measuring Tape
3.6.10. Try Square: - The engineers try-square is composed of two parts, the stock, and the
blade. The try-square is used to test that a 90-degree angle exists across the edge of
the steel. Although a burr exists on the edge of the steel it fits into the slot and does not
affect the way the try-square is used.

25
Fig-23:-Try square
3.6.11. Plumb Bob: -A plumb bob is a weight, usually with a pointed tip on the bottom,
suspended from a string and used as a vertical reference line, or plumb-line. It is used
on site to transfer point exactly vertically upward or downward for marking points.

Fig-24:-Plumb Bob

3.6.12. Hammer: -A hammer is a tool that delivers a blow to an object. Hammers are hand
tools used to drive nails and break apart objects. Hammers which was used on our site
was a claw hammer.
3.6.13. Trowels:-Trowels also help smooth concrete surfaces for their finish coats before
being left to dry. Hand-troweling is common for smaller tasks on the site.

Fig-25:-Trowel
3.6.14. Hammer Machine: -A drilling machine is used to cut holes into or through metal or
any other materials. Drilling machines use a drilling tool that has cutting edges at its
point.

26
Fig-26:-Hammer Machine

3.6.15. Hoe:-This tool is used to digging and to place concrete, cement mortar in the head
pan.

Fig-27:-Hoe

3.6.16. Head Pan: -This one is used to transport materials.

Fig-28:-Head pan

3.6.17. Sand screening: -This tool is used to sieve sand at the site.

3.6.18. Bump Screed: -This tool is used to level fresh concrete surface especially in slab
concrete.

Fig-29:-Bump Screed

27
3.6.19. Wooden Rendering Float:-This tool is used to give a smooth finish to the plastered
area.

Fig-30:-Wooden Rendering Float


3.6.20. Vacuum Blower:-These tools are used to clean the surface area from impurities Slab
concrete. And also used during rebaring work. Blower used at our site was having the
speed of 620 to 750 RPM.

Fig-31:-Vacuum Blower

3.6.21. Walkie Talkie:- It was used to communicate with site staff on the site without going
to them and wasting time. Its range was nearly 2.99 Miles.

28
Fig-32:-Walkie Talkie

3.7. SAFETY EQUIPMENT USED AT SITE


3.7.1. Safety helmets: -Safety helmets are one of the most frequently used forms of PPE.
Safety Helmets will protect the user’s head against:
 The impact of objects falling from above, by resisting and deflecting blows to the
head.
 Hitting fixed dangerous objects at the workplace,

Fig-33:-Safety Helmet
3.7.2. Body Harness: -Body harnesses are designed to minimize stress forces on labor’s
body in the event of a fall while providing sufficient freedom of movement to allow
work to be performed.

Fig-34:-Body harnesses

3.7.3. Labour Safety Shoes: -Wellington boots are waterproof and are most often made
from rubber or polyvinyl chloride (PVC), a halogenated polymer. They are usually
worn when walking on the concrete or muddy ground, or to protect the wearer from
heavy showers and puddles.
29
Fig-35:-Labour Safety Shoes
3.7.4. Safety Net:-Safety Net Systems consist of nets installed as close as possible under the
work area. Perimeter nets are personal or debris nets that are erected around the
perimeter of a building to protect workers from overboard falls or to catch
construction debris.

Fig-36:-Safety Net

3.7.5. Welding goggles: - Welding goggles provide a degree of eye protection while some
forms of welding and cutting are being done. They are intended to protect the eyes not
only from the heat and optical radiation produced by the welding, such as the intense
ultraviolet light produced by an electric arc but also from sparks or debris.

30
Fig:-37 Welding Goggles
3.7.6. HVSA: - High-visibility safety apparel (HVSA) is clothing that workers can wear to
improve how well other people see them (their visibility). Most often, high- visibility
clothing is worn to alert drivers and other vehicle operators of a worker's presence,
especially in low light and dark conditions.

31
3.8. INFORMATION ABOUT TEST
There are number of tests which are performed at the site on different material. The tests
which we have performed at the site are below:-
3.8.1. Slump Test: - This test is used to check the workability of concrete at the site. Steel
mould is used which is in the form of a frustum of a cone whose dimensions are
300mm at bottom dia., 200mm at top dia. and height is 100mm.

Observation and calculations: -


 Proportion of sample = M30/M35
 Slump Value = 105-120 mm

Table:-4 -Value of slump test obtained on site


S. No Slump Value of Slump Value
1) Pumpable Concrete 105 to 125 mm
2) Normal Concrete 80 to 100 mm

Fig-38:-Slump Test

32
3.8.2. Compression Test: - The compressive strength of a cube is an indication of the
strength of concrete. With the help of this, we can check the characteristics strength of
concrete. The size of the cube is taken as 15cm3. At least three specimens should be
made for testing which is to be performed at 7 & 28 days.
Observation and calculations: -
 Proportion of concrete = M30 & M35
 Cross-section Area = 150x150=22500mm2

TABLE-5:- Cube Test Performed at Site


S. No Weight (Kg) Load (N) Compressive Strength (N/mm2)
7 Day Cubes (M-35)
1 8.278 800000 35.56
2 8.292 1101000 48.93
3 8.274 1320000 58.67
4 8.246 1207000 53.64
5 8.356 1122000 49.86
6 8.278 1034000 45.96
28 Day Cubes (M-30)
7 8.246 1059000 47.06
8 8.174 988000 43.91
9 8.166 886000 39.37
7 Day Cubes (M-35) (Slab)
10 8.308 1458000 64.80
11 8.390 1208000 53.68
12 8.494 1425000 63.33
13 8.410 1310000 58.22
14 8.404 1322000 58.75
15 8.424 1429000 63.51

Result:- Compressive Strength of concrete sample after 28 days is (average)


43.45 N/mm2. Whereas strength designed for is 30 N/mm2, hence tested sample is safe.

33
Fig-39:-CUBE TEST

3.8.3. Mix Design Ratios Used at Our Site

Table 6:- M-35 Mix Design By Weight (For 3 Bags) .34Cum


S.no Water Cement Aggregate Admixture
(litre) (kg) Fine (kg) Coarse (kg) (litre)
20 mm 10mm

61.5 150 213 230 153 1.75


Ratio 0.41 1 1.42 2.55

Table 7:- M-30 Mix Design By Weight (For 3 Bags) .38Cum


S.no Water Cement Aggregate Admixture
(litre) (kg) Fine (kg) Coarse (kg) (litre)
20 mm 10mm
61.5 150 265 260 173 1.30
Ratio 0.43 1 1.766 2.89

34
3.9. CONSTRUCTION PROCESS

3.9.1. Piling:- Piling forms the very basis of construction; the essential support needed for
any kind of structure. It is a technique that sets deep foundations for any form of
construction work, such as buildings. On our site piling was done as the depth of
excavation was 40ft from the ground so to resist soil from failure. And piling consists
of following specifications at our site:-

Table8:-PILING SPECIFICATIONS
a) Depth of Piling 40feet
b) Diameter of pile 2.5 feet
c) Spacing between two pile c/c 3 Feet
d) Main bar Diameter 16 mm
e) Diameter of helical 8 mm
f) Clear Cover 50 mm
g) Grade of Concrete M-25
h) Grade of Steel Fe 500 D

Fig-40:-Piling Reinforcement & Piling

35
3.9.2. Excavation: - Excavation is the process of moving earth, rock or other materials with
tools, equipment or explosives. It includes earthwork, trenching, wall shafts,
tunneling, and underground. Excavation is used in construction to create building
foundations, reservoirs, and roads. Some of the different processes used in excavation
include trenching, digging, and dredging and site development. Each of these
processes requires unique techniques, tools, and machinery to get the job done right.
The processes used will depend upon the structure that will result from the
construction process. At our Construction site excavation was done by Pock lane. Up
to the depth of 46 feet after completion of piling.

Fig-41:-Excavation
3.9.3. Dressing: - Spread the soil using something flat, like the back side of a heavy garden
rake, working it into aeration holes and covering low spots. After Completion Of
excavation proper soil dressing was made and the unwanted soil was removed.

36
3.9.4. Leveling: -A level surface is defined as a curved surface which at each point is
perpendicular to the direction of gravity at the point. The surface of a still water is a
truly level surface. Any surface parallel to the mean spheroidal surface of the earth is,
therefore, a level surface. At Our, Site Levelling Was done using a surveying
instrument called Auto Level.

Fig-42:-Levelling

3.9.5. Site Marking: -


 Site marking is one of the starting point of your construction.
 In this activity, your Engineer and Maestri will identify pillar placements.
 Once pillars placement is identified based on soil condition earthwork will start.
 The engineer will mark the area around the pillar. Earth workers will dig marked
area.
 Depending on soil condition pillar depth will vary.
 Some people perform puja before starting this marking.

37
Fig-43:-Site Marking

3.9.6. Laying of PCC: -To level the unevenness of ground surface for laying of
reinforcement and protecting it from contact with the ground, it also improves firm
base to foundation increase bearing capacity of the soil. After leveling PCC was laid
out With M-10 Grade of Concrete to a Thickness of 4 inches.

Fig-44:-Laying Of PCC

38
3.9.7. Column Layout:- At our Site Column Marking was done using TOTAL STATION
to Plot Important Points and column marking.

Fig-45:-Column Layout on Site

Fig-46:-Column Layout Plan

39
3.9.8. Foundation & Pedestal:- A concrete pedestal is a compression element provided to
carry the loads from supported elements like columns, statues etc. to footing below
the ground. It is generally provided below the metal columns. In general pedestal
width is greater than its height. At our site raft & Isolated footing was used.

Table 9:-FOUNDATION & PEDESTAL SPECIFICATIONS


1 Depth of Raft 4feet
2 Clear Cover 50 mm
3 Grade of Concrete M-30
4 Grade of Steel Fe 500 D

Fig-47:-Bar Binding of Raft Fig-48:-Raft Casting

While Casting Footing we have checked the proper spacing between all
main bars, extra reinforcement, Bars of extra/ main reinforcement, lap
length, clear cover.

3.9.9. Column binding, shuttering& Casting: -At our site Rectangular/Square Column
was used, Columns were a short column in nature. In the case of long Column
pedestal was used, hence eff. length of Column gets reduced and column turns short.

40
Table 10:-COLUMN SPECIFICATIONS
a) Dimension Varying as per drawing
b) Main bar Diameter 12,16,20,25 & 32 mm
c) Diameter of Tie bars 8 mm
d) Clear Cover 40 mm
e) Grade of Concrete M-35
f) Grade of Steel Fe 500 D

Fig-49:-Column Shuttering

Fig-50:-Main Reinforcement Plan of column

While Casting Column we have checked the proper spacing between all tie
bars, check for reinforcement, Number of the bar, checked alternate laps are
provided, lap length, clear cover.

41
3.9.10. Shuttering &Bar Binding of Slab and Beam:-For shuttering at our site
panels(steel/plywood), support, walers, Tie &
Clip Clamp, etc. were used.

Table 11:-SLAB & BEAM SPECIFICATION


a) Dimension Varying as per drawing
b) Main bar Diameter (Slab) 8 mm
c) Main bar Diameter (Beam) 12,16,20,25 & 32 mm
d) Diameter of stirrups 8 mm
e) Diameter of bar (Chair) 10 mm
f) Clear Cover (Slab) 20 mm
g) Clear Cover (beam) 25 mm
h) Grade of Concrete M-30
i) Grade of Steel Fe 500 D

Fig-51:-Beam Schedule

42
Fig-52:-Slab & Beam Casting
3.9.11. De-shuttering: - It is the process of removing formwork after the concrete gains its
proper strength, after this process of curing starts which is discussed below.

3.9.12. Curing: -Curing was done for reducing crack due to evolving of thermal heat and to
do so at our site Gunny bag & Ponding method of curing was used.

Fig-53:-Gunny Bag

Fig-54:-Ponding Method

43
CHAPTER-4 Project Development

4.1 INTRODUCTION
As we have already discussed project detail, Type of Project, Process of working in
previous Sections.

4.2 PROJECT DESCRIPTION


Golden Sands is a residential and commercial complex in which ground floor of
tower 3 is meant for commercial purpose and all above floors are meant for
residential purpose and all two basements are provided for parking facility and in
this project service floor is also provided to provide one stop facility for all
maintenance work of Sanitary, water fitting and electricity connections.

4.3 ROLES & RESPONSIBILITIES


Here during my training period I have been made responsible for executing several
tasks at site as per guidance of engineers and Project Manager like- Checking
Reinforcement of different members, Casting work of different members, To check
Testing done on site, To Check Quality of material coming on site (like:- RMC), Etc.

4.4 RESPONSIBILITIES WHILE TESTING


While performing Several tests like- Slump Test, Compression value test I was held
responsible to check proper method to perform testing as per IS code and to evaluate
test results and to comment on them weather the material can be used or not.

4.5 CONCLUSION
Here during my internship, I’ve learned a lot of things as discussed in previous few
sections above.

44
CHAPTER-5 CONCLUSION & RECOMMENDATIONS

5.1 OVERVIEW OF TRAINING


At Last, I want to say that it was a very knowledgeable site here I have learned several
things for 60 days period of my internship. When I’ve joined a site, I was completely
raw and don’t know anything about how to work to be executed on site and when after
60days I left the site I was able to do lots of work and also learned how to execute work
on site.

5.2 LESSONS LEARNED SKILLS DEVELOPED


 Here I’ve learned how to execute work on site.
 I’ve observed the difference between studying any concept in the book and
applying it to the field there was lots of difference as we can say that theoretical
concept is mutually perpendicular to practical concepts.
 I’ve also learned how to make labour understand our point of view and
communicate with them.

5.3 KNOWLEDGE GAINED


1. I’ve learned how to read drawing given on site like: -
 Main Column Reinforcement Detail.
 Main & Extra Reinforcement Details of Raft.
 Column Stirrup Details.
 Main & Extra Reinforcement Details of Beam.
 Schedule for Shuttering.
 Column Layout Plan.
 Main Layout Plan, Etc.
2. I’ve also learned how tests are performed on site to test properties of concrete.
3. I’ve also learned how to execute work on site, Etc.

45
5.4 CONCLUSION
Our “DESIGNING OF RESIDENTIAL AND COMMERCIAL COMPLEX” was
designed with a spacious and easy way of making their purchase. The entire functional
requirements such as lighting, ventilation, emergency exit, etc., were considered in
planning.
The structural elements such as foundation, lintel, column, footing, beam, and slab were
designed as per IS 456:2000 in limit state method using M-10, M-25, M-30 & M-35
Grade of concrete and HYSD bars of Grade Fe 500 D.

By performing this project, we learned about the steps involved in planning and
designing of a building. We learned about designing both manually by limit state
method and by using software Auto CAD &STAAD pro. By finishing this project, we
got confidence for designing a framed structure.

46
CHAPTER 6 CONCLUSION AND RECOMMENDATION
TO THE COMPANY

6.1 CONCLUSIONS

The internship is a connection between the theoretical knowledge and the practical or
the field work during construction or civil engineering work. We all who attended the
internship class by going to companies that already working either as a consultant or a
contractor. The responsibilities of the hosting company are to teach trainees and shape
them in the two months as a real site workers. My hosting company is a contracting
company and they help me in acquiring different knowledge in different positions.
This program played an important role in learning field works that can be implemented
by the person who hold a degree or people who have an experience in building
construction. We were able to acquire a high level of confidence to deal with problems
that arise in a building construction.
Since I took my internship session in the CPC Pvt. Ltd., I get an opportunity to work at
the different types of the construction work which helps me to gain more knowledge by
seeing what they work on site and what are their main responsibilities to the client and
each other. Working with CPCPL team made me acquire more knowledge work
includes the duty of the site engineers.
From the design team especially from the structural designers I got some clues about
how to design and the phases and different procedure in the designing of any structure
starting from the roof to the footing. The architects also help me to know every symbol
used in any drawing and room orientations, how each room of the specified space can
be together without being disturbed by one another. In the sanitary and electrical
engineers also help us by teaching us about the riser diagram and installation of each
junction in place for a building.
However, this internship program was not free from challenges. But they come up with
the challenges and teach us how we must gown to be in the field after the graduation.
Overall the internship program laid sound foundation for us to start our career. We are
proud to be able to contribute towards nation building during the country's extremely
critical period of the history. It will be sensible to scale this practice up and to replicate
in other disciplines as well.

47
6.2 RECOMMENDATIONS
Most works in the site needs careful attention and successive supervision of works but
the in some case the site works goes improperly due to different causes. This kind of
carelessness is not good for ether the consultant or the contractor. Therefore, I suggest
supervisors and site engineers to take a care full look after the work executed on the site
and the work that will be executed.

At the site there are works which are performed in the way that not to be performed.
Such works lids to safety problem, loose of human power if its degree is high and
economy if it is ordered to demolish it.
Thus, I recommend for the company the following:

 It is better to use steel form work than wood (plywood) formwork as it is very
repetitively used, stiff, not flammable easily and removed easily without
damaging the concrete structure.
 Use thicker eucalyptus false work in order to avoid the bulging of concrete
 Bar staggering around support also need a special attention or re designing
because of that it hard to compact using vibrator through it.
 The soil blended at the site must be as it is specified in the laboratory result and
the equipment used for blinding must be effective in the mixing process.
 Compacting of the soil more than 20cm in pit and other excavation is improper
and it doesn't full fill the needed density. So, compaction must be in each20cm
layer as specified.
 Formwork should remove easily without damaging the concrete surface.
 Addition of water for concrete casting should be known and shouldn’t a
guessing work.
 Use modern machinery or equipment for high productivity and to finish works
on time.
Ignoring the student suggestion also the problem in the site which is Unreasonable and
illogical. The sources of this kind of ignorance mainly arise from under estimating of
the student it must also avoid unless and otherwise it has a reason.

48
6.3 IMPORTANT DRAWINGS RELATED TO SITE

Fig-55:- Layout Plan

49
Fig-56:- Column Main Reinforcement Detail

50
Fig-57:- Beam Main & Extra Reinforcement Schedule

51
6.4 PROBLEMS FACED AT SITE

6.4.1 Communication with Labour: - Later with help of a foreman


working there, they told me about general terms used by Labour at
the site and also helped in communicating with them. Like- Water-
Level is called Pansaal which is a roman word meaning plummet in
English.

6.4.2 Exposure of reinforcement: - In rare cases, it happened that


columns were not getting proper cover & get exposed to atmosphere
than at that place jackal was provided.

6.4.3 While Casting of the slab in several days: - Due to long span, it
was not possible to cast complete slab or foundation in one batch so
to make proper bonding between old and new concrete Faircrete
SB(L) was used.

6.4.4 Rebaring Problem after casting: - It happened that after casting


structural engineer changed the reinforcement detail of lift, but it is
not possible to demolish concrete and again bind bar as per new
drawing so to satisfy this problem without demolishing concrete a
rebaring agent called Hilti RE 500 was used which increase strength
30 % more and good bonding also in two reinforcement bars.

6.4.5 Weather condition of the site: - In between several times rain


occurred due to which problem in working and casting work was
there.

52
REFERENCES
[1] Encyclopedia

[2] Official website of CREATIVE PROJECTS & CONTRACTS: -


www.cpcpl.co.in/

[3] Official website of Fair mate for specifications of Fair Crete SB (L)
Bonding Agent: -http://www.fairmate.com/media/video/12

[4] Official website of Tata Tiscon for specifications of Fe 500D Steel


Bars:- www.tatatiscon.co.in/
[5] Official website of Chembond Chemicals for specifications of
Admixture: -www.chembondindia.com/

[6] Official website of Hilti RE 500 for specifications of Rebaring Agent


:-www.hilti.in/anchor-systems/injectable-adhesive-anchors/r4929903

[7] IS Codes as per requirement such as:-


IS 456:2000 for concrete.
IS 1077:1992 for Brick.
IS 1489 for cement.
IS 1789 for HYSD steel bars.
IS 516:1959 for concrete cube testing.
IS: 1199:1959 to determine slump value.
IS 383:1970 for aggregates etc.
[8] Structural Drawings like:-
Column Main reinforcement Details
Beam Main/Extra reinforcement Details
Raft Main/ Extra reinforcement Details
Shuttering Layout Plan
Slab Reinforcement detailing & Etc.…
53

Potrebbero piacerti anche