Sei sulla pagina 1di 16

1

FIDIC at a Glance

Project Management Mini Series

FIDIC at a Glance
FIDIC stands for ‘Fédération
Internationale des Ingénieurs
- Conseils’, which is best
translated from French as
The International
Federation of Consulting
Engineers. FIDIC represents
What does the consulting engineering
FIDIC mean? indus-try both globally and
What do they domestically
do?
FIDIC at a Glance 2
Choice of FIDIC form of contract

FIDIC at a Glance 3
Employer

Engineer

Contractor

Design/Planning

Dispute
Adjustment Board
Build/Construction

FIDIC at a Glance 4
Choice of FIDIC form of contract

The choice of form depends on the type of project being


contemplated.
In summary:
▪ straight forward, quick or cheap project - Green Book
▪ employer design (traditional project) - Red Book
▪ employer design (Multilateral Development Banks providing
finance) - Pink Book
▪ contractor design (traditional project) - Yellow Book
▪ design, build, operate project - Gold Book
▪ EPC/Turnkey project - Silver Book

FIDIC at a Glance 5
Which FIDIC contract should I use?

FIDIC at a Glance 6
The Construction Contract (Red Book)
is based on design provided by the
Employer and payment is made on a
re-measurement basis.
The Plant Contract (Yellow Book), the
Design, Build & Operate Contract (Gold
Book) and the EPC/Turnkey Contract
(Silver Book) are based on design by
the Contractor and payment is made
on a lump-sum basis.

Summary
FIDIC at a Glance 7
Yellow/Silver Book: Key differences

Key Issue Yellow Book (Design & Build) Silver Book (EPCT)
Typical Use Recommended for the Suitable for a process or power
provision of electrical and/or plant, a factory or similar facility,
mechanical plant and for or an infrastructure project, or
building and engineering other type of development, if:
works if most (or all) of the • a higher degree of certainty of
works are to be designed by final price and time is
(or on behalf of ) the required; and
Contractor. • the Contractor takes total
responsibility for the design
and execution of the project
(including responsibility for
Employer design).
Payment Interim and final payments Interim and final payments are
are certified by the Engineer. made without certification;
typically determined by
reference to a Schedule of
Payments.
FIDIC at a Glance 8
Yellow/Silver Book: Key differences

Key Issue Yellow Book (Design & Build) Silver Book (EPCT)
General risk Risks are allocated on a fair A majority of risks is allocated to
profile and equitable basis taking the Contractor under the
account of such matters as Contract, including any errors in
insurability, and each party’s the Setting Out Data (SubClause
ability to foresee, and 4.7), Site data (Sub-Clause 4.10)
mitigate the affect of, the and unforeseeable difficulties or
circumstances relevant to costs (Sub-Clause 4.12).
each risk.

There are a number of key risks The Contractor is expected to:


that the Employer retains, for • price these risks; and/or
example errors • carry out extensive due diligence to
in the Setting Out data (Sub- mitigate risks.
Clause 4.7) Site data (Sub-Clause
4.10) and “Unforeseeable” Site
risks (Sub-Clause 4.12).

FIDIC at a Glance 9
Yellow/Silver Book: Key differences

Key Issue Yellow Book (Design & Build) Silver Book (EPCT)
Design The Contractor is not The Contractor is deemed to
responsible for any error, fault have scrutinized the Employer’s
or other defect found Requirements and is responsible
in the Employer’s for the accuracy of the
Requirements to the Employer’s Requirements
extent that “an experienced (including design criteria and
contractor exercising due calculations), except
care” would not have for the matters identified in sub-
discovered the error, fault or paragraphs (a) to (d) in Sub-
defect before submitting its Clause 5.1
tender (SubClause 5.1).

FIDIC at a Glance 10
Yellow/Silver Book: Key differences

Key Issue Yellow Book (Design & Build) Silver Book (EPCT)
Contractor’s Various rights for the Limited rights for claim the
rights to claim Contractor to claim additional Contractor to claim additional
additional time time/money under time/money under
/ money the Contract, including in the Contract. Sub-Clause 8.4
respect of those risks borne [Extension of Time for
by the Employer in respect of Completion] does not include
errors in the Setting Out data the right to an extension of time
(Sub-Clause 4.7), errors in the in the event of exceptionally
Site data (Sub-Clause 4.10) adverse climatic conditions or
and unforeseen Site risks unforeseeable shortages.
(Sub-Clause 4.12).

FIDIC at a Glance 11
EPC under Silver Book - EPCT

Employer

Contractor

▪ Fixed Price
▪ Time certainty

▪ More Risk
▪ No Engineer
▪ Less Claims

FIDIC at a Glance 12
Typical Sequence of Principal Event

FIDIC at a Glance 13
Typical Sequence of Payment

FIDIC at a Glance 14
Typical Sequence of Dispute Event

FIDIC at a Glance 15
Thank you

FIDIC at a Glance 16

Potrebbero piacerti anche