FLOWCHART FOR ECC APPLICATION PROCESS

SCOPING
(OPTIONAL)

1. SCREENING
(FORM----- ANNEX A)

YES Has the proponent submitted NO


complete requirements?
REJECT APPLICATION
AND/OR REQUIRE
PROPONENT TO
SUBMIT AI/COMMITMENT

Has the
proponent submitted NO
YES the required AI ?
Is the project
NO covered by EIS? YES

CNC
ECP Non ECP w/in APPLICATION IS
ECA DROPPED
a. EIS b. IEER/EPRMP/IEE Checklist

YES Is the project existing NO


and operational?

NOV/NOM
2. ACKNOWLEDGEMENT
(FORM ANNEX B)

PAYMENT OF PENALTY/
COMMITMENT TO PAY 3. RECEIVING OF DOCUMENTS 1 DAY

CASHIER
4. CASHIER

MONITOR IF THE
PROPONENT HAS 5. LOGGING OF DOCUMENTS
PAID

6. ROUTING OF DOCUMENTS
APPLY FOR ECC
1 DAY
7. REVIEW /
EVALUATION / INSPECTION

9 DAYS

Note:
NOV – Notice of Violation a. PREPARATION OF SITE
NOM – Notice of Meeting INSPECTION REPORT/
- - - - Processing Days EVALUATION
(FORM ANNEXC)
1 DAY
8. FINALIZATION OF ECC

a. RECOMMENDATION FROM CASE HANDLER


b. RECOMMENDATION FROM EIAD CHIEF
8 DAYS
Time Frame of ECC Processing: c. SIGNATURE OF THE REGIONAL DIRECTOR
20 working days