QCS 2014 Section 01: General Page 1

Part 18: Other Contractors

18 OTHER CONTRACTORS.............................................................................. 2

18.1 GENERAL ...................................................................................................... 2


18.1.1 Scope 2
18.2 ACCESS FOR OTHER CONTRACTORS ..................................................... 2
18.2.1 Unhindered Access 2
18.3 CO-OPERATION AND CO-ORDINATION WITH OTHER CONTRACTORS 2
18.3.1 Co-operation at Site Level 2
18.4 FACILITIES FOR OTHER CONTRACTORS ................................................. 2
18.4.1 Site Facilities for Other Contractors 2
LQ
H
QCS 2014 Section 01: General Page 2
Part 18: Other Contractors

18 OTHER CONTRACTORS

18.1 GENERAL

18.1.1 Scope

1 This Part specifies the requirements for access to the Site for other contractors, for
co-operation and co-ordination with other contractors and for the provision of facilities with
other contractors.

18.2 ACCESS FOR OTHER CONTRACTORS

18.2.1 Unhindered Access

1 The Contractor shall allow other contractors unhindered access to any part of the Works
when in the opinion of the Engineer those parts are sufficiently completed.

18.3 CO-OPERATION AND CO-ORDINATION WITH OTHER CONTRACTORS

18.3.1 Co-operation at Site Level

1 The Contractor shall carry out his work in a manner that causes the minimum amount of
interference to other contractors working on the Site.
LQ

2 The Contractor shall co-ordinate his operations with the activities of other contractors where
necessary in order to avoid conflicts and ensure orderly progress of the Works.
H

3 Those works associated with existing or future service installation shall only be carried out by
a contractor or sub-contractor approved by the public utility authority concerned. The
Engineer shall require proof of such approval in writing prior to the commencement of works.

18.4 FACILITIES FOR OTHER CONTRACTORS

18.4.1 Site Facilities for Other Contractors

1 If specified in the Contract, the Contractor shall provide site facilities for other contractors.