No Description Qty Unit Unit Price (Rp) Total Price (Rp)

A Preparation work
1 Site Survey 12 Kms 4,080,000 48,960,000
2 Route Map 12 Kms 816,000 9,792,000
3 Pole Position Schedule (Stacking) 300 Poles 54,400 16,320,000
4 Soil Investigation 30 Poles 1,632,000 48,960,000
5 Pole Foundation Schedule 310 Poles 20,400 6,324,000
6 Material Schedule 310 Poles 20,400 6,324,000

B Over Head Conductor and Accessories


Conductor A3C 185 mm2 36000 m 24,000 864,000,000
Joint Sleeve 72 PCS 81,600 5,875,200
Midspan Joint 360 PCS 156,400 56,304,000
Anti Climbing 310 set 115,600 35,836,000
Installation Cost 36 Km 7,480,000 269,280,000

C Pemasangan Cross Arm Tumpu 1800 mm 185 Pole 5,960,000 1,102,600,000


1 Concrette Pole C12 - 350 daN E 1 Pole
2 Cross Arm UNP 10 100.50.5x1800 mm 1 PC
3 U Clamp Type I 50 x 6 mm 1 PC
4 Bolt,nut and 2 washer M16 x 70 mm 4 PC
5 Steel Plate Type I 2 PC
6 Bolt,nut and 2 washer M16 x 148 mm 2 PC
7 Arm Tie Brace 50.50x1270 mm 2 PC
8 Pin/Post Insulator 3 PC
9 Preformed Top Ties 3 PC
10 U Clamp and Plate type II 50 x 6 mm 2 PC
11 Installation Cost 1 set

D Install. Cross Arm Double Supp. for below 5 degree 45 7,517,000 338,265,000
1 Concrette Pole C12 - 350 daN E 1 Pole
2 Cross Arm UNP 10 100.50.5x2000 mm 2 PC
3 U Clamp Type II 50 x 6 mm 4 PC
4 Double Arming Bolt M16x300 mm 2 PC
5 Arm Tie Brace 50.50x1270 mm 2 PC
6 Steel Plate Type I 4 PC
7 Bolt,nut and 2 washer M16 x 148 mm 12 PC
8 Bolt,nut and 2 washer M16 x 70 mm 4 PC
9 Steel Plate Type II 4 PC
10 Pin/Post Insulator 6 PC
11 Preformed Side Tie 6 PC
12 Installation Cost 1 set

E Install. Cross Arm Tension Single Supp. 2000 mm 34 Pole 9,131,000 310,454,000
1 Concrette Pole C13 - 350 daN E 1 Pole
2 Cross Arm UNP 10 100.50.5x2000 mm 2 PC
3 Arm Tie Brace 50.50x1270 mm 2 PC
4 U Clamp Type II 4 PC
5 Double Arming Bolt M16x300 mm 2 PC
6 U Clamp Type II 4 PC
7 Bolt,nut and 2 washer M16 x 148 mm 10 PC
8 Steel Plate Type I 4 PC
9 Steel Plate Type II 4 PC
10 Pin/Post Insulator 1 PC
11 Tension insulator set 6 PC
12 Preform Top Ties 1 PC
13 Parallel Groove Clamp/nobn tension Joint 6 PC
14 Installation Cost 1 set
F Install. Cross Arm Tension Single Support 2200 mm 20 Poles 9,961,000 199,220,000
1 Concrette Pole C13 - 350 daN E 2 Poles
2 Cross Arm UNP 10 100.50.5x2200 mm 2 PCS
3 U Clamp Type II 4 PCS
4 Double Arming Bolt M16x300 mm 4 PCS
5 Steel Plate Type II 6 PCS
6 Bolt,nut and 2 washer M16 x 148 mm 6 PCS
7 Pin/Post Insulator 1 PC
8 Preform Top Ties 1 PC
9 Tension insulator set 6 PCS
10 Parallel Groove Clamp/non tension Joint 6 PCS
11 Installation Cost 1 set

G Install. 2 x 1/2 Tension Support 2000 mm, 90 degree 14 Poles 10,683,000 149,562,000
1 Concrette Pole C12 - 500 daN E 1 Pole
2 Cross Arm UNP 10 100.50.5x2000 mm 4 PCS
3 Double Arming Bolt M16x300 mm 4 PCS
4 U Clamp Type II 50 x 6 mm 4 PCS
5 Steel Plate Type I 4 PCS
6 Steel Plate Type II 8 PCS
7 Bolt,nut and 2 washer M16 x 148 mm 16 PCS
8 Arm Tie Brace 50.50x1270 mm 4 PCS
9 Pin/Post Insulator 1 PCS
10 Performed Side Ties 1 PCS
11 Tension insulator set 6 PCS
12 Parallel Groove Clamp/non tension Joint 8 PCS
13 Installation Cost 1 set

H Pemasangan Cross Arm T - OFF Suspension 1 Pole 40,650,000 40,650,000


1 Concrette Pole C12 - 500 daN E 1 Pole
2 Cross Arm UNP 10 100.50.5x2000 mm 2 PCS
3 Cross Arm UNP 10 100.50.5x1800 mm 1 PC

4 U Clamp Type II 2 PCS


5 Double Arming Bolt M16x300 mm 2 PCS
6 U Clamp Type I 2 PCS
7 Bolt,nut and 2 washer M16 x 70 mm 6 PCS
8 Bolt,nut and 2 washer M16 x 148 mm 10 PCS
9 Steel Plate Type I 4 PCS
10 Arm Tie Brace 50.50x1270 mm 4 PCS
11 Steel Plate Type II 4 PCS
12 Pin/Post Insulator 5 PCS
13 Loadbreak switch includ. Steel support 1 PC
14 Lightning Arrester 10 KA 3 PCS
15 Tension insulator set 3 PCS
16 H Connector 8 PCS
17 Performed Top Ties 5 PCS
18 Installation Cost 1 set

I Install. Cross Arm Dead End Pole Double Support 1 Pole 14,560,000 14,560,000
1 Concrette Pole C12 - 500 daN E 2 Poles
2 Cross Arm UNP 10 100.50.5x2000 mm 2 PCS
3 U Clamp Type II 4 PCS
4 Double Arming Bolt M16x300 mm 4 PCS
5 Steel Plate Type II 6 PCS
6 Bolt,nut and 2 washer M16 x 148 mm 6 PCS
7 Tension insulator set 3 PCS
8 Arrester 20 kV 10 kA 3 PCS
9 Parallel Groove Clamp/non tension Joint 6 PCS
Installation Cost 1 set

J Down Guy 30 Sets 2,522,000 75,660,000


1 Single Guy wire Band 1 set
2 Bolt,nuts and washer 2 PCS

3 Turnbuckle 5/8 inch 1 PC


4 Wire Clips 8 PCS
5 Guy Insulator Dia. 105 mm 1 PC
6 Galv.Steel Wire 2 x 16 mm 12 m
7 Galv.Steel Wire 1 x 16 mm 8 m
8 Guy Rod 2 mtr 1 PC
9 Expanding Anchor 1 PC
10 Installation Cost 1 set

K Grounding Poles : 100 Point 639,000 63,900,000


1 Rod Ground Steel 1 1/4" x 3 1 Poles
2 Clamp Ground Rod 1 PC
3 Connector as req./parallel Groove Clamp 1 PC
4 Grounding Terminal 2 PC
5 Grounding Wire CU 50 mm2 1.5 m
Installation Cost 1 set

L Grounding for Guy Wire : 30 Poles 262,000 7,860,000


1 Connector as require 1 PC
2 Ground Wire Solid copper 1 m
3 Grounding Terminal 1 PC
4 Installation Cost 1 set

M Pole Foundation : 120 Poles 2,992,000 359,040,000


Estimated Pole Foundation 120 Poles

N Testing ,Commissioning and Certificate for


Laik Operation by Third Party 1 lot 115,600,000 115,600,000

O Danger Plate two Face 300 Sheets 122,400 36,720,000


1 Danger Plate 1 sheet
2 Installation Cost 1 set

P Number Plate 300 Sheets 108,800 32,640,000


1 Number Plate 1 sheet
2 Installation Cost 1 set

Q MOB/DEMOB
Mobilisasi Material 1 lot 380,800,000 380,800,000
Worker 1 lot 54,400,000 54,400,000
Tools & Equipment 1 lot 18,496,000 18,496,000

Grand Total A to Q 4,668,402,200